SlideShare a Scribd company logo
Estimation And Quantity Surveying
Presented ByAWANISH SHUKLA
Roll No 271303
Branch- ACM
Section- IV

NATIONAL INSTITUTE OF CONSTRUCTION
MANAGEMENT AND RESEARCH
CONTENTS
DADO
Brief Specification
 Detailed Specification
 Rate Analysis

FLY OVER
 Approximate Estimate
Brief Specification for Dado

Provide dado on 12 mm thick rough cement plaster (1:3)
base and jointed with alkali resisted cement as per IS: 4457
completed as per the direction of Engineer-In-Charge.
Detailed Specification for Dado
1. Materials
2. Preparation of surface & laying
3. Mortar and bedding
4. Fixing tiles for dado
5. Cleaning
6. Pointing and finishing
7. Mode of measurement
MATERIALS
 White Glazed Tiles : The tiles shall be of approved and shall







generally conform to IS : 777.
They shall be flat and true to shape and free from cracks,
blisters, welts, crawling, crazing spots, chipped edges,
corners or other imperfections detracting from their
appearance.
The tiles shall be of square or rectangular of nominal sizes
such as 300x200mm, 150x150mm, 100x100mm.
Samples of tiles shall be got approved by the Engineer-incharge before use on the work.
Top surface of tile shall be glossy or matt as specified.
PREPARATION OF SURFACE & LAYING
 Sub grade concrete or RCC slab or side brick wall/ or







plastered surfaces on which tiles are to be laid shall be
cleaned, wetted and mopped.
The bedding/backing for the tile shall be of C.M. 1.3 or as
specified and shall be applied and allowed to harden.
The mortar shall be roughened with wire brushes or by
scratching diagonal lines 1.5mm. deep at 7.5mm.
dado shall be truly horizontal and joints truly vertical.
After the tiles have been laid, surplus cement grout shall be
cleaned off.
MORTAR AND BEDDING
 Cement mortar shall conform to the specification for

materials, preparations etc. as specified under cement
mortar.
 The amount of water added while preparing mortar shall be
the minimum necessary to give sufficient plasticity for
laying.
 Care shall be taken in preparation of the mortar to ensure
that there are no hard lumps that would interfere with even
bedding of the tiles.
 The mortar of specified proportion and thickness shall then
be even and smoothly spread over the base by use of screed
battens to proper level or slope.
FIXING TILES FOR DADO
 The dado work, shall be done only after fixing the tiles/slabs







on the floor.
The approved white glazed tiles before laying shall be soaked
in water for at least 2 hours.
Tiles shall be fixed when the cushioning mortar is still plastic
and before it gets very stiff.
The back of the tile shall be covered with this layer of cement
mortar 1:2 using fine sand (table III, zone IV, I.S. 383-1963)
and the edge of the tile smeared with neat white cement
slurry.
The tile shall then be pressed in the mortar and gently tapped
against the wall with a wooden mallet.
 The fixing shall be done from bottom of wall upwards without any








hollows in the bed of joints.
Each tile shall be as close as possible to one adjoining.
The tiles shall be jointed with white cement slurry.
Any thickness difference in the thickness of the tiles shall be
arranged out in cushioning mortar so that all tiles faces are in one
vertical plane.
The top of the dado shall be touched up neatly with the rest of the
plaster above.
After fixing the dado/skirting etc. they shall be kept continuously
wet for 7 days.
If doors, windows or other openings are located within the dado
area, the corners, sills, jambs etc. shall be provided with true right
angles without any specials.
CLEANING
 After the tiles have been laid in a room or the days fixing






work is completed, the surplus cement grout that may have
come out of the joints shall be cleaned off before it sets.
After the complete curing, the dado or skirting over shall be
washed thoroughly clean.
In the case of flooring, once the floor has set, the floor shall
be carefully washed clean and dried.
When dry, the floor shall be covered with oil free dry saw
dust.
It shall be removed only after completion of the construction
work and just before the floor is used.
MODE OF MEASUREMENT
 Dado/flooring/skirting shall be measured in sqm.

correct to two places of decimal.
 Length and breadth shall be measured correct to 1 cm.
 Between the exposed surfaces of skirting or dado. No
deductions shall be made nor extra paid for any opening
of area up to 0.1 sqm.
 The rate shall include all the cost of labour and materials
involved.
Rate Analysis for Dado
Rate Analysis for 10 sq-m
The quantity of white-glazed tile is worked out by assuming 1 mm on
either side for thickness in joint & tolerance in size of tiles. Thus, no of
white-gazed tiles
= 10/(0.152X0.152)
= ~ 432 tiles
Particulars

Quantity
Or
Numbers

Rate

Per

Amounts

White Gazed Tiles

432 Nos

Rs. 8.00

no

Rs. 3456.00

Wastage o white
gazed tiles @ 5%

Rs. 172.00

C.M. (1:3) for
rough plaster,
bedding & wastage

0.18 cu m

Rs. 2510.00

Cu m

Rs. 451.80

White Cement
Sundries

0.25 bags

Rs. 950.00

bag

Rs. 237.50
Rs. 6.90

Material Cost =

Rs. 4325.00

Sq m

Rs. 1000.00

Labour:
Labour for fixing,
making rough coat
of plaster, filling
joints etc

10.00 sq m

Rs. 100.00
Labour Cost
Add Material Cost

=
=

Rs. 1000.00
Rs. 4325.00
------------------Total
=
Rs 5325.00
10% Contractors’ Profit =
Rs. 532.50
1.5% Water and electric
consumption charges
=
Rate per 10 sq m
Rate per sq m
Say

Rs. 79.88
-------------------=
Rs. 5937.38
=
Rs. 593.74
=
Rs. 595.00
Approximate Estimate of FLY OVER
Examples:
National ProjectAt Mohan Nagar Junction in Ghaziabad, India.

At Kampthee, Nagpur on NH-7, India
At Sirmaur Chauraha Rewa, M.P., India
International ProjectAt Junction of Che Kung Road and Hung Mui Road, Honkong.
At Mohan Nagar Junction in Ghaziabad, India
 Name of Project
 Detail of Client
 Details of Contractor

:
:
:

 Scope of Work

:






Cost of Work
:
Duration of Work
:
Details, Project Progress:
Resources Used
:

 New Technology

control
 Per meter cost

Construction of Fly Over
National Capital Region Planning Board
Asian Development Bank and
Wilbur Smith Associates
Fly Over with 2 lanes on existing road for
700 meters
Rs. 539,160,413.00
2 Years (work started on July 2008)
Completed on July 2010
Manpower, Equipments, Machineries

:

Paver Finisher Hydrostatic with sensor

:

Rs. 7,70,229
At Kampthee, Nagpur on NH-7, India
 Name of Project
 Detail of Client
 Details of Contractor

 Scope of Work








:
:
:

:
Cost of Work
:
Duration of Work
:
Details, Project Progress:
Resources Used
:
New Technology
:
Per meter cost
:

Construction of Fly Over
NHAI
Oriental Construction Company Pvt. Ltd
Backbone Enterprises
Fly Over on 850 Meter 2 lane road
Rs. 721,122,350.00
2 Years (work started on July 2010)
Completed on July 2012
Manpower, Equipments, Machineries
Fly Ash was used, Pile foundation was done
Rs. 8,48,379.00
At Sirmaur Chauraha Rewa, M.P., India
 Name of Project

 Detail of Client









:

:
Details of Contractor :
Scope of Work
:
lane
Cost of Work
:
Duration of Work
:
Project Progress
:
Resources Used
:
Per meter cost

Construction of Flyover Bridge at
Sirmour Chouraha Rewa on VaranasiNagpur Road, Rewa, MP
Public Works Department M.P.
Abhay Mishra Comstruction company
Fly Over with 750 meters long two
Rs. 25 Crors
2 Years (Started on 2012)
Under Process
Manpower, Equipments, Machineries
:
Rs. 3,33,333
At Junction of Che Kung Road & Hung Mui Road, Honkong.
 Name of Project

 Detail of Client

:
:

 Details of Contractor :
 Scope of Work
 Cost of Work






:

:
Duration of Work
:
Details, Project Progress:
Resources Used
:
Per meter cost
:

Construction of Fly Over
Government of the Hong Kong
Special Administrative Region
HKSAR
Construction of approximate 600
metres long dual 2-lane
Rs. 537,140,479.00
December 2007
Completion January 2013
Manpower, Equipments, Machineries
RS. 8,98,600
Average cost per meter
=

Rs. 5,37,635
THANK YOU

More Related Content

What's hot

Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
sonali parashar
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
Raj Shah
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
Shariful Haque Robin
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
Sakshi Kirar
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
AB MAKASANA
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
gayu pandian
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Aabid Ansar
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
A Makwana
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
Anchit Agrawal
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
akashpadole
 

What's hot (20)

Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Construction contract
Construction contract Construction contract
Construction contract
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 

Viewers also liked

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
ALI HYDER GADHI
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answers
mitchellparker911
 
Table of specification
Table of specificationTable of specification
Table of specification
Abigail Sapico
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
Felix Vong
 
SPECIFICATIONS
SPECIFICATIONSSPECIFICATIONS
SPECIFICATIONS
Joedy Mae Mangampo
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
diasawada12345
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
Simarpreet Singh
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 

Viewers also liked (11)

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answers
 
Table of specification
Table of specificationTable of specification
Table of specification
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
SPECIFICATIONS
SPECIFICATIONSSPECIFICATIONS
SPECIFICATIONS
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Similar to Estimation and quantity surveying

Finishing of cement
Finishing of cementFinishing of cement
Finishing of cement
Prabhat chhirolya
 
Kajaria tiles installtion
Kajaria tiles installtionKajaria tiles installtion
Kajaria tiles installtion
Chuchu Beera
 
02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx
PAVITRA GOYAL
 
QSCM.pptx
QSCM.pptxQSCM.pptx
QSCM.pptx
harishg6783
 
cereamic
cereamiccereamic
cereamic
Neha Bajpayee
 
Building specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptxBuilding specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptx
SanskritiJindal4
 
Specifications for rcc
Specifications for rcc Specifications for rcc
Specifications for rcc
Prabhat chhirolya
 
plaster.pptx
plaster.pptxplaster.pptx
plaster.pptx
SanskritiJindal4
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
swethasekhar5
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
Prabhat chhirolya
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
Prabhat chhirolya
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdf
Rahul Chandra Deb Nath
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
Prabhat chhirolya
 
Kota stone
Kota stoneKota stone
Kota stone
Nss Akhil
 
Finishing works Part 1.pptx
Finishing works Part 1.pptxFinishing works Part 1.pptx
Finishing works Part 1.pptx
SandipPaul46
 
Flooring.ppt
Flooring.pptFlooring.ppt
Flooring.ppt
DhruvTiwari50
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC Blockwork
Civil 4M
 
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
Priyanka Dange
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
Mkh Nantu
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ErLavKushPrasad
 

Similar to Estimation and quantity surveying (20)

Finishing of cement
Finishing of cementFinishing of cement
Finishing of cement
 
Kajaria tiles installtion
Kajaria tiles installtionKajaria tiles installtion
Kajaria tiles installtion
 
02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx
 
QSCM.pptx
QSCM.pptxQSCM.pptx
QSCM.pptx
 
cereamic
cereamiccereamic
cereamic
 
Building specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptxBuilding specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptx
 
Specifications for rcc
Specifications for rcc Specifications for rcc
Specifications for rcc
 
plaster.pptx
plaster.pptxplaster.pptx
plaster.pptx
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdf
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
 
Kota stone
Kota stoneKota stone
Kota stone
 
Finishing works Part 1.pptx
Finishing works Part 1.pptxFinishing works Part 1.pptx
Finishing works Part 1.pptx
 
Flooring.ppt
Flooring.pptFlooring.ppt
Flooring.ppt
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC Blockwork
 
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
Types of flooring-Terazzo flooring, cork flooring. linolium flooring.PVC floo...
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 

More from Awanish Shukla

Case study on small firm
Case study on small firmCase study on small firm
Case study on small firm
Awanish Shukla
 
Green building challenges
Green building challengesGreen building challenges
Green building challengesAwanish Shukla
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneAwanish Shukla
 
Concrete bag selling consept....
Concrete bag selling consept....Concrete bag selling consept....
Concrete bag selling consept....Awanish Shukla
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1Awanish Shukla
 

More from Awanish Shukla (10)

Case study on small firm
Case study on small firmCase study on small firm
Case study on small firm
 
Mass housing
Mass housingMass housing
Mass housing
 
Green building challenges
Green building challengesGreen building challenges
Green building challenges
 
Metro project
Metro projectMetro project
Metro project
 
Water auditing
Water auditingWater auditing
Water auditing
 
Kuwait oil field
Kuwait oil fieldKuwait oil field
Kuwait oil field
 
Global warming
Global warmingGlobal warming
Global warming
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourne
 
Concrete bag selling consept....
Concrete bag selling consept....Concrete bag selling consept....
Concrete bag selling consept....
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1
 

Recently uploaded

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 

Recently uploaded (20)

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 

Estimation and quantity surveying

  • 1. Estimation And Quantity Surveying Presented ByAWANISH SHUKLA Roll No 271303 Branch- ACM Section- IV NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH
  • 2. CONTENTS DADO Brief Specification  Detailed Specification  Rate Analysis FLY OVER  Approximate Estimate
  • 3. Brief Specification for Dado Provide dado on 12 mm thick rough cement plaster (1:3) base and jointed with alkali resisted cement as per IS: 4457 completed as per the direction of Engineer-In-Charge.
  • 4. Detailed Specification for Dado 1. Materials 2. Preparation of surface & laying 3. Mortar and bedding 4. Fixing tiles for dado 5. Cleaning 6. Pointing and finishing 7. Mode of measurement
  • 5. MATERIALS  White Glazed Tiles : The tiles shall be of approved and shall     generally conform to IS : 777. They shall be flat and true to shape and free from cracks, blisters, welts, crawling, crazing spots, chipped edges, corners or other imperfections detracting from their appearance. The tiles shall be of square or rectangular of nominal sizes such as 300x200mm, 150x150mm, 100x100mm. Samples of tiles shall be got approved by the Engineer-incharge before use on the work. Top surface of tile shall be glossy or matt as specified.
  • 6. PREPARATION OF SURFACE & LAYING  Sub grade concrete or RCC slab or side brick wall/ or     plastered surfaces on which tiles are to be laid shall be cleaned, wetted and mopped. The bedding/backing for the tile shall be of C.M. 1.3 or as specified and shall be applied and allowed to harden. The mortar shall be roughened with wire brushes or by scratching diagonal lines 1.5mm. deep at 7.5mm. dado shall be truly horizontal and joints truly vertical. After the tiles have been laid, surplus cement grout shall be cleaned off.
  • 7. MORTAR AND BEDDING  Cement mortar shall conform to the specification for materials, preparations etc. as specified under cement mortar.  The amount of water added while preparing mortar shall be the minimum necessary to give sufficient plasticity for laying.  Care shall be taken in preparation of the mortar to ensure that there are no hard lumps that would interfere with even bedding of the tiles.  The mortar of specified proportion and thickness shall then be even and smoothly spread over the base by use of screed battens to proper level or slope.
  • 8. FIXING TILES FOR DADO  The dado work, shall be done only after fixing the tiles/slabs     on the floor. The approved white glazed tiles before laying shall be soaked in water for at least 2 hours. Tiles shall be fixed when the cushioning mortar is still plastic and before it gets very stiff. The back of the tile shall be covered with this layer of cement mortar 1:2 using fine sand (table III, zone IV, I.S. 383-1963) and the edge of the tile smeared with neat white cement slurry. The tile shall then be pressed in the mortar and gently tapped against the wall with a wooden mallet.
  • 9.  The fixing shall be done from bottom of wall upwards without any       hollows in the bed of joints. Each tile shall be as close as possible to one adjoining. The tiles shall be jointed with white cement slurry. Any thickness difference in the thickness of the tiles shall be arranged out in cushioning mortar so that all tiles faces are in one vertical plane. The top of the dado shall be touched up neatly with the rest of the plaster above. After fixing the dado/skirting etc. they shall be kept continuously wet for 7 days. If doors, windows or other openings are located within the dado area, the corners, sills, jambs etc. shall be provided with true right angles without any specials.
  • 10. CLEANING  After the tiles have been laid in a room or the days fixing     work is completed, the surplus cement grout that may have come out of the joints shall be cleaned off before it sets. After the complete curing, the dado or skirting over shall be washed thoroughly clean. In the case of flooring, once the floor has set, the floor shall be carefully washed clean and dried. When dry, the floor shall be covered with oil free dry saw dust. It shall be removed only after completion of the construction work and just before the floor is used.
  • 11. MODE OF MEASUREMENT  Dado/flooring/skirting shall be measured in sqm. correct to two places of decimal.  Length and breadth shall be measured correct to 1 cm.  Between the exposed surfaces of skirting or dado. No deductions shall be made nor extra paid for any opening of area up to 0.1 sqm.  The rate shall include all the cost of labour and materials involved.
  • 12. Rate Analysis for Dado Rate Analysis for 10 sq-m The quantity of white-glazed tile is worked out by assuming 1 mm on either side for thickness in joint & tolerance in size of tiles. Thus, no of white-gazed tiles = 10/(0.152X0.152) = ~ 432 tiles
  • 13. Particulars Quantity Or Numbers Rate Per Amounts White Gazed Tiles 432 Nos Rs. 8.00 no Rs. 3456.00 Wastage o white gazed tiles @ 5% Rs. 172.00 C.M. (1:3) for rough plaster, bedding & wastage 0.18 cu m Rs. 2510.00 Cu m Rs. 451.80 White Cement Sundries 0.25 bags Rs. 950.00 bag Rs. 237.50 Rs. 6.90 Material Cost = Rs. 4325.00 Sq m Rs. 1000.00 Labour: Labour for fixing, making rough coat of plaster, filling joints etc 10.00 sq m Rs. 100.00
  • 14. Labour Cost Add Material Cost = = Rs. 1000.00 Rs. 4325.00 ------------------Total = Rs 5325.00 10% Contractors’ Profit = Rs. 532.50 1.5% Water and electric consumption charges = Rate per 10 sq m Rate per sq m Say Rs. 79.88 -------------------= Rs. 5937.38 = Rs. 593.74 = Rs. 595.00
  • 15. Approximate Estimate of FLY OVER Examples: National ProjectAt Mohan Nagar Junction in Ghaziabad, India. At Kampthee, Nagpur on NH-7, India At Sirmaur Chauraha Rewa, M.P., India International ProjectAt Junction of Che Kung Road and Hung Mui Road, Honkong.
  • 16. At Mohan Nagar Junction in Ghaziabad, India  Name of Project  Detail of Client  Details of Contractor : : :  Scope of Work :     Cost of Work : Duration of Work : Details, Project Progress: Resources Used :  New Technology control  Per meter cost Construction of Fly Over National Capital Region Planning Board Asian Development Bank and Wilbur Smith Associates Fly Over with 2 lanes on existing road for 700 meters Rs. 539,160,413.00 2 Years (work started on July 2008) Completed on July 2010 Manpower, Equipments, Machineries : Paver Finisher Hydrostatic with sensor : Rs. 7,70,229
  • 17. At Kampthee, Nagpur on NH-7, India  Name of Project  Detail of Client  Details of Contractor  Scope of Work       : : : : Cost of Work : Duration of Work : Details, Project Progress: Resources Used : New Technology : Per meter cost : Construction of Fly Over NHAI Oriental Construction Company Pvt. Ltd Backbone Enterprises Fly Over on 850 Meter 2 lane road Rs. 721,122,350.00 2 Years (work started on July 2010) Completed on July 2012 Manpower, Equipments, Machineries Fly Ash was used, Pile foundation was done Rs. 8,48,379.00
  • 18. At Sirmaur Chauraha Rewa, M.P., India  Name of Project  Detail of Client        : : Details of Contractor : Scope of Work : lane Cost of Work : Duration of Work : Project Progress : Resources Used : Per meter cost Construction of Flyover Bridge at Sirmour Chouraha Rewa on VaranasiNagpur Road, Rewa, MP Public Works Department M.P. Abhay Mishra Comstruction company Fly Over with 750 meters long two Rs. 25 Crors 2 Years (Started on 2012) Under Process Manpower, Equipments, Machineries : Rs. 3,33,333
  • 19. At Junction of Che Kung Road & Hung Mui Road, Honkong.  Name of Project  Detail of Client : :  Details of Contractor :  Scope of Work  Cost of Work     : : Duration of Work : Details, Project Progress: Resources Used : Per meter cost : Construction of Fly Over Government of the Hong Kong Special Administrative Region HKSAR Construction of approximate 600 metres long dual 2-lane Rs. 537,140,479.00 December 2007 Completion January 2013 Manpower, Equipments, Machineries RS. 8,98,600
  • 20. Average cost per meter = Rs. 5,37,635