SlideShare a Scribd company logo
Project Coordinator
HOUSING DEVELOPMENT DEPARTMENT, Ministry of
Development
Architect
ARCHITECT SECTION
Housing Development Department, Ministry of Development
Structural Engineers
STRUCTURE SECTION
Housing Development Department, Ministry of Development
Infrastructure Engineer Phase 1
PETAR PERUNDING SDN BHD
Infrastructure Engineer Phase 2
SEPAKAT SETIA PERUNDING SDN BHD
Quantity Surveyor
SY Consultant Sdn Bhd
Project Title:
PROPOSED 1 CORNER UNIT TERRACE HOUSE FOR NATIONAL HOUSING
SCHEME COMPLETE WITH EXTERNAL WORKS AT KG. TANAH JAMBU,
NEGARA BRUNEI DARUSSALAM
SY Consultant Sdn Bhd
Address:
SY Consultant Sdn Bhd
B-06-01, Menara Bata, PJ Trade Centre,
No 8, Jalan PJU 8/8A,
Bandar Damansara Perdana,
47820 Petaling Jaya, Selangor, Malaysia
Founded: 15th November 1997
Principal: Stephanie Yeoh
Organisational Chart
Project Title:
PROPOSED 1 CORNER UNIT TERRACE HOUSE FOR NATIONAL HOUSING
SCHEME COMPLETE WITH EXTERNAL WORKS AT KG. TANAH JAMBU,
NEGARA BRUNEI DARUSSALAM
• Public sector tendering
• PAM Contract 2006 (with quantities)
• Two Storey Terrace House (Corner Unit)
Type of tender:
Open Tender
Invitation to Tender
Restriction
• Surrounded by dense forest – Heavy site
clearance needed
• Soil condition – muddy soil so filling with sand
is essential
• Long distance to transport construction
materials
Ground Floor Plan
GFA: 58.20m2
1st Floor Plan
GFA: 69.58m2
Total GFA: 127.78m2
Estimated Price & Construction Period
• Estimated Price: RM 153,336.00
(Price is estimated by using the cost per m2 of a 2 storey corner
link house)
• Projected Construction Period: 8 months
Bills of Quantities
- Section A (Main Building Works)
- Section B (External Works)
Section A (Main Building Works)
• Piling
• Work Below Lowest Floor Finish
• Frames
• Upper Floors
• Roof
• Stairs and Staircase Finishes
• External Walls
• Internal Walls & Partitions
• Windows
• Doors
• Internal Wall Finishes
• Internal Floor Finishes
• Internal Ceiling Finishes
• External Finishes
• Sanitary Fittings
• P.C. & Provisional Sums
• External Work within Lot Boundary
Particular
Specifications
Schedule of Finishes
List of PC and Provisional Sums
Section B (External Works)
• Surface Water Drainage
• Sewer Drainage
• Water Reticulation
• Road and Walkway
Surface Water Drainage Plan
Surface Water Drain
Pipe Culvert
Sump
Sewage Drainage Plan
2 nos. Manhole
150mm
diameter pipe
Sewage Drain
Water Reticulation
200mm diameter
pipe
Fire Hydrant
Road Layout Plan6m wide
Main Road
4m wide
Driveway
1.25m wide
footpath
Preliminaries
Earnest Money
• It shall be a condition of this tender that the Contractor shall submit an
Earnest Money of RM 5,000.00 together with his tender submission,
failing which his tender will be disqualified.
• Earnest Money shall be in the approved form of Banker's Guarantee
attached herein or Bank Draft from approved Banks operating in Malaysia.
Company cheque and Insurance Guarantee will not be accepted.
• If the Contractor shall:-
• 1. withdraw his offer after he has been awarded the tender, and/or
2. withdraw his tender before the expiry of the Tender Validity Period
then in any of such event(s), the Employer shall without prejudice to his
any other rights that he may possess, forfeit the Earnest Money.
• The Earnest Money shall be returned to all unsuccessful Contractors upon
award of the tender. The Earnest Money of the successful Contractor shall
only be returned after the submission of the Performance Bond.
Performance Bond
• The Contractor shall provide Performance Bond Guarantee from a
bank operating in Malaysia, to the Employer in a sum equal to five
(5%) percent of the Contract Sum, for the due observance and due
performance of the Contract under the terms of the Bond. The
bank and the terms of the Bond shall be such as shall be approved
by the Employer, and the cost of obtaining the Bond shall be at the
expense of the Contractor and shall be included in the Contract
Sum. The original of the Bond shall be deposited with the Employer
as a condition precedent to the commencement of the Works, and
shall remain with the Employer and be valid for the full duration of
the Contract or the last delivery/shipment/consignment of the
Goods whichever is the later, and in the case of the Contract being
determined, one calendar year after the date of the determination.
• Defects Liability Period : 24 months
• Insurances cover for accidental bodily injury : Refer to insurance policies that has been taken up by
to or illness of third parties (whether fatal the Employer
or not), accidental loss of or damage to
property belonging to third parties (the
aggregate liability of the insurers shall be
limited by twice the limit of indemnity caused
by any one occurrence
• Insurance deductible amount : Refer to insurance policies that has been taken up by
the Employer
• Percentage to Cover Professional fees : Refer to insurance policies for reinstatement that has
been taken up by the Employer
• Amount for removal of Debris : Refer to insurance policies that has been taken up by
the Employer
• Value of existing structure together with : Not applicable
all the contents owned by the Employer
or for which he is responsible
Tender Details
• Date of Commencement : To be as stipulated on the Letter of Award
• Date for Completion : To be as stipulated on the Letter of Award
• Liquidated and Ascertained Damages : At the rate of RM 700.00 per day
• Sectional Completion : To be as stipulated on the Letter of Award
• Period of Delay : Three (3) months
• Interim Claim Interval : One (1) month
• Period of Honouring of Certificates : Thirty (30) days from the date of the Certificate
• Percentage of the value of materials : 75%
• and goods included in the Certificate
• Percentage of Certified Value Retained : Ten percent (10%)
• Limit of Retention Fund : Five percent (5%) of the Contract Sum
• Period to complete the Final Account : Twelve (12) months
• Amount of Performance Bond : 5% of the Contract Sum
Timeline
GROUP MEMBERS
Name ID
Cassandra Wong Xin Yue 0313365
Cheong Kha Man 0319456
Kevin Hii Ting Kui 0319223
Low Chee Ying 0319126
Ng Ding Boon 0319243
Stephanie Yeoh Sze Wei 0318954
Haziq Zariful 0314131

More Related Content

What's hot

Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment reportSyafiq Zariful
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Business plan for construction solutions company
Business plan  for construction solutions companyBusiness plan  for construction solutions company
Business plan for construction solutions companyCochin University
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Managementscienceassignment final
Managementscienceassignment finalManagementscienceassignment final
Managementscienceassignment finalArissa Loh
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesArissa Loh
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1tfkc1212
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 

What's hot (20)

Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment report
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Purpose
PurposePurpose
Purpose
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 Submitted
 
Business plan for construction solutions company
Business plan  for construction solutions companyBusiness plan  for construction solutions company
Business plan for construction solutions company
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Managementscienceassignment final
Managementscienceassignment finalManagementscienceassignment final
Managementscienceassignment final
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation Slides
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 

Viewers also liked

PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment ReportMelvin Lim
 
Estimating letters
Estimating lettersEstimating letters
Estimating lettersZIyeeTan
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompaHasif Alias
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group AssignmentHaziq1511
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.lucaschinsheng
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareKai Yun Pang
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationkohwenqi
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientPang Khai Shuen
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationHasif Alias
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Lee Pei Gie
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationShze Hwa Lee
 
Assignment - Tender Submission Part 2
Assignment - Tender Submission Part 2Assignment - Tender Submission Part 2
Assignment - Tender Submission Part 2Kai Yun Pang
 
Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Kai Yun Pang
 

Viewers also liked (20)

PM Final Assignment Report
PM Final Assignment ReportPM Final Assignment Report
PM Final Assignment Report
 
Estimating letters
Estimating lettersEstimating letters
Estimating letters
 
Group Component
Group ComponentGroup Component
Group Component
 
Measurement 4 ooompa loompa
Measurement 4   ooompa loompaMeasurement 4   ooompa loompa
Measurement 4 ooompa loompa
 
Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group Assignment
 
Management science assignment report.
Management science assignment report.Management science assignment report.
Management science assignment report.
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Estimating
EstimatingEstimating
Estimating
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Assignment - Tender Submission Part 2
Assignment - Tender Submission Part 2Assignment - Tender Submission Part 2
Assignment - Tender Submission Part 2
 
Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1Assignment - Tender Submission Part 1
Assignment - Tender Submission Part 1
 

Similar to Measurement 4 Assignment Presentation

project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentHaziq1511
 
Presentation on Exclusive Reality Investment Opportunity
Presentation on Exclusive Reality Investment Opportunity Presentation on Exclusive Reality Investment Opportunity
Presentation on Exclusive Reality Investment Opportunity Amit Goon
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 
Framework for foreign direct investment in residential projects
Framework for foreign direct investment in residential projectsFramework for foreign direct investment in residential projects
Framework for foreign direct investment in residential projectsGirish Singh
 
Project management final report
Project management final reportProject management final report
Project management final reportSANKET SENAPATI
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfYeshiharegAlemu
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract managementVISHAKA BOTHRA
 
Resume 08--Earl Victor -
Resume 08--Earl Victor -Resume 08--Earl Victor -
Resume 08--Earl Victor -Earlvic Torcino
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02jitendra kumar biswas
 
Component 4 project iniation process.pdf
Component 4 project iniation process.pdfComponent 4 project iniation process.pdf
Component 4 project iniation process.pdfAnatole9
 
Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13jpeabody
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lin Hui
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016Sanjeewa Mahawedage
 

Similar to Measurement 4 Assignment Presentation (20)

project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample document
 
M4ppt
M4pptM4ppt
M4ppt
 
Presentation on Exclusive Reality Investment Opportunity
Presentation on Exclusive Reality Investment Opportunity Presentation on Exclusive Reality Investment Opportunity
Presentation on Exclusive Reality Investment Opportunity
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Framework for foreign direct investment in residential projects
Framework for foreign direct investment in residential projectsFramework for foreign direct investment in residential projects
Framework for foreign direct investment in residential projects
 
Project management final report
Project management final reportProject management final report
Project management final report
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract management
 
Resume 08--Earl Victor -
Resume 08--Earl Victor -Resume 08--Earl Victor -
Resume 08--Earl Victor -
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Component 4 project iniation process.pdf
Component 4 project iniation process.pdfComponent 4 project iniation process.pdf
Component 4 project iniation process.pdf
 
Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
 

More from Haziq1511

IBS Factory Report Assignment
IBS Factory Report AssignmentIBS Factory Report Assignment
IBS Factory Report AssignmentHaziq1511
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...Haziq1511
 
Management Science Assignment
Management Science AssignmentManagement Science Assignment
Management Science AssignmentHaziq1511
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Haziq1511
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Haziq1511
 
Building Material Assignment 2
Building Material Assignment 2Building Material Assignment 2
Building Material Assignment 2Haziq1511
 
Psychology Research Proposal
Psychology Research ProposalPsychology Research Proposal
Psychology Research ProposalHaziq1511
 
Psychology Journal 2
Psychology Journal 2Psychology Journal 2
Psychology Journal 2Haziq1511
 
Psychology Journal 1
Psychology Journal 1Psychology Journal 1
Psychology Journal 1Haziq1511
 
Economics assignment (Analysis of Two business)
Economics assignment (Analysis of Two business)Economics assignment (Analysis of Two business)
Economics assignment (Analysis of Two business)Haziq1511
 
Business studies - charity report
Business studies - charity reportBusiness studies - charity report
Business studies - charity reportHaziq1511
 
Accounting project - Financial Ratio Analysis
Accounting project - Financial Ratio AnalysisAccounting project - Financial Ratio Analysis
Accounting project - Financial Ratio AnalysisHaziq1511
 
English 2 - Report of 3 businesses
English 2 - Report of 3 businessesEnglish 2 - Report of 3 businesses
English 2 - Report of 3 businessesHaziq1511
 
English 2 Compare/Contrast Essay Assignment
English 2 Compare/Contrast Essay AssignmentEnglish 2 Compare/Contrast Essay Assignment
English 2 Compare/Contrast Essay AssignmentHaziq1511
 
English 2 Descriptive Essay
English 2 Descriptive EssayEnglish 2 Descriptive Essay
English 2 Descriptive EssayHaziq1511
 
November Penang Trip - Short Journal
November Penang Trip - Short JournalNovember Penang Trip - Short Journal
November Penang Trip - Short JournalHaziq1511
 
City model (updated)
City model (updated)City model (updated)
City model (updated)Haziq1511
 
The Journal 1
The Journal 1The Journal 1
The Journal 1Haziq1511
 

More from Haziq1511 (20)

IBS Factory Report Assignment
IBS Factory Report AssignmentIBS Factory Report Assignment
IBS Factory Report Assignment
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
Management Science Assignment
Management Science AssignmentManagement Science Assignment
Management Science Assignment
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)
 
Building Material Assignment 2
Building Material Assignment 2Building Material Assignment 2
Building Material Assignment 2
 
Psychology Research Proposal
Psychology Research ProposalPsychology Research Proposal
Psychology Research Proposal
 
Psychology Journal 2
Psychology Journal 2Psychology Journal 2
Psychology Journal 2
 
Psychology Journal 1
Psychology Journal 1Psychology Journal 1
Psychology Journal 1
 
Economics assignment (Analysis of Two business)
Economics assignment (Analysis of Two business)Economics assignment (Analysis of Two business)
Economics assignment (Analysis of Two business)
 
Business studies - charity report
Business studies - charity reportBusiness studies - charity report
Business studies - charity report
 
Accounting project - Financial Ratio Analysis
Accounting project - Financial Ratio AnalysisAccounting project - Financial Ratio Analysis
Accounting project - Financial Ratio Analysis
 
English 2 - Report of 3 businesses
English 2 - Report of 3 businessesEnglish 2 - Report of 3 businesses
English 2 - Report of 3 businesses
 
English 2 Compare/Contrast Essay Assignment
English 2 Compare/Contrast Essay AssignmentEnglish 2 Compare/Contrast Essay Assignment
English 2 Compare/Contrast Essay Assignment
 
English 2 Descriptive Essay
English 2 Descriptive EssayEnglish 2 Descriptive Essay
English 2 Descriptive Essay
 
November Penang Trip - Short Journal
November Penang Trip - Short JournalNovember Penang Trip - Short Journal
November Penang Trip - Short Journal
 
Tj3
Tj3Tj3
Tj3
 
City model (updated)
City model (updated)City model (updated)
City model (updated)
 
Tj2
Tj2Tj2
Tj2
 
The Journal 1
The Journal 1The Journal 1
The Journal 1
 

Recently uploaded

Art Nouveau Movement Presentation for Art History.
Art Nouveau Movement Presentation for Art History.Art Nouveau Movement Presentation for Art History.
Art Nouveau Movement Presentation for Art History.rrimika1
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsFinzo Kitchens
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersConfidence Ago
 
The Design Code Google Developer Student Club.pptx
The Design Code Google Developer Student Club.pptxThe Design Code Google Developer Student Club.pptx
The Design Code Google Developer Student Club.pptxadityakushalsaha
 
National-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptxNational-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptxAlecAnidul
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themmadhavlakhanpal29
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfSudhanshuMandlik
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesResDraft
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdffabianavillanib
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitabilityaaryangarg12
 
The Evolution of Fashion Trends: History to Fashion
The Evolution of Fashion Trends: History to FashionThe Evolution of Fashion Trends: History to Fashion
The Evolution of Fashion Trends: History to FashionPixel poets
 

Recently uploaded (11)

Art Nouveau Movement Presentation for Art History.
Art Nouveau Movement Presentation for Art History.Art Nouveau Movement Presentation for Art History.
Art Nouveau Movement Presentation for Art History.
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
The Design Code Google Developer Student Club.pptx
The Design Code Google Developer Student Club.pptxThe Design Code Google Developer Student Club.pptx
The Design Code Google Developer Student Club.pptx
 
National-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptxNational-Learning-Camp 2024 deped....pptx
National-Learning-Camp 2024 deped....pptx
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
The Evolution of Fashion Trends: History to Fashion
The Evolution of Fashion Trends: History to FashionThe Evolution of Fashion Trends: History to Fashion
The Evolution of Fashion Trends: History to Fashion
 

Measurement 4 Assignment Presentation

  • 1. Project Coordinator HOUSING DEVELOPMENT DEPARTMENT, Ministry of Development Architect ARCHITECT SECTION Housing Development Department, Ministry of Development Structural Engineers STRUCTURE SECTION Housing Development Department, Ministry of Development Infrastructure Engineer Phase 1 PETAR PERUNDING SDN BHD Infrastructure Engineer Phase 2 SEPAKAT SETIA PERUNDING SDN BHD Quantity Surveyor SY Consultant Sdn Bhd Project Title: PROPOSED 1 CORNER UNIT TERRACE HOUSE FOR NATIONAL HOUSING SCHEME COMPLETE WITH EXTERNAL WORKS AT KG. TANAH JAMBU, NEGARA BRUNEI DARUSSALAM
  • 2. SY Consultant Sdn Bhd Address: SY Consultant Sdn Bhd B-06-01, Menara Bata, PJ Trade Centre, No 8, Jalan PJU 8/8A, Bandar Damansara Perdana, 47820 Petaling Jaya, Selangor, Malaysia Founded: 15th November 1997 Principal: Stephanie Yeoh
  • 4. Project Title: PROPOSED 1 CORNER UNIT TERRACE HOUSE FOR NATIONAL HOUSING SCHEME COMPLETE WITH EXTERNAL WORKS AT KG. TANAH JAMBU, NEGARA BRUNEI DARUSSALAM
  • 5.
  • 6. • Public sector tendering • PAM Contract 2006 (with quantities) • Two Storey Terrace House (Corner Unit)
  • 7. Type of tender: Open Tender Invitation to Tender
  • 8. Restriction • Surrounded by dense forest – Heavy site clearance needed • Soil condition – muddy soil so filling with sand is essential • Long distance to transport construction materials
  • 10. 1st Floor Plan GFA: 69.58m2 Total GFA: 127.78m2
  • 11. Estimated Price & Construction Period • Estimated Price: RM 153,336.00 (Price is estimated by using the cost per m2 of a 2 storey corner link house) • Projected Construction Period: 8 months
  • 12. Bills of Quantities - Section A (Main Building Works) - Section B (External Works)
  • 13. Section A (Main Building Works) • Piling • Work Below Lowest Floor Finish • Frames • Upper Floors • Roof • Stairs and Staircase Finishes • External Walls • Internal Walls & Partitions • Windows • Doors • Internal Wall Finishes • Internal Floor Finishes • Internal Ceiling Finishes • External Finishes • Sanitary Fittings • P.C. & Provisional Sums • External Work within Lot Boundary
  • 16. List of PC and Provisional Sums
  • 17. Section B (External Works) • Surface Water Drainage • Sewer Drainage • Water Reticulation • Road and Walkway
  • 18. Surface Water Drainage Plan Surface Water Drain Pipe Culvert Sump
  • 19. Sewage Drainage Plan 2 nos. Manhole 150mm diameter pipe Sewage Drain
  • 21. Road Layout Plan6m wide Main Road 4m wide Driveway 1.25m wide footpath
  • 23. Earnest Money • It shall be a condition of this tender that the Contractor shall submit an Earnest Money of RM 5,000.00 together with his tender submission, failing which his tender will be disqualified. • Earnest Money shall be in the approved form of Banker's Guarantee attached herein or Bank Draft from approved Banks operating in Malaysia. Company cheque and Insurance Guarantee will not be accepted. • If the Contractor shall:- • 1. withdraw his offer after he has been awarded the tender, and/or 2. withdraw his tender before the expiry of the Tender Validity Period then in any of such event(s), the Employer shall without prejudice to his any other rights that he may possess, forfeit the Earnest Money. • The Earnest Money shall be returned to all unsuccessful Contractors upon award of the tender. The Earnest Money of the successful Contractor shall only be returned after the submission of the Performance Bond.
  • 24. Performance Bond • The Contractor shall provide Performance Bond Guarantee from a bank operating in Malaysia, to the Employer in a sum equal to five (5%) percent of the Contract Sum, for the due observance and due performance of the Contract under the terms of the Bond. The bank and the terms of the Bond shall be such as shall be approved by the Employer, and the cost of obtaining the Bond shall be at the expense of the Contractor and shall be included in the Contract Sum. The original of the Bond shall be deposited with the Employer as a condition precedent to the commencement of the Works, and shall remain with the Employer and be valid for the full duration of the Contract or the last delivery/shipment/consignment of the Goods whichever is the later, and in the case of the Contract being determined, one calendar year after the date of the determination.
  • 25. • Defects Liability Period : 24 months • Insurances cover for accidental bodily injury : Refer to insurance policies that has been taken up by to or illness of third parties (whether fatal the Employer or not), accidental loss of or damage to property belonging to third parties (the aggregate liability of the insurers shall be limited by twice the limit of indemnity caused by any one occurrence • Insurance deductible amount : Refer to insurance policies that has been taken up by the Employer • Percentage to Cover Professional fees : Refer to insurance policies for reinstatement that has been taken up by the Employer • Amount for removal of Debris : Refer to insurance policies that has been taken up by the Employer • Value of existing structure together with : Not applicable all the contents owned by the Employer or for which he is responsible Tender Details
  • 26. • Date of Commencement : To be as stipulated on the Letter of Award • Date for Completion : To be as stipulated on the Letter of Award • Liquidated and Ascertained Damages : At the rate of RM 700.00 per day • Sectional Completion : To be as stipulated on the Letter of Award • Period of Delay : Three (3) months • Interim Claim Interval : One (1) month • Period of Honouring of Certificates : Thirty (30) days from the date of the Certificate • Percentage of the value of materials : 75% • and goods included in the Certificate • Percentage of Certified Value Retained : Ten percent (10%) • Limit of Retention Fund : Five percent (5%) of the Contract Sum • Period to complete the Final Account : Twelve (12) months • Amount of Performance Bond : 5% of the Contract Sum
  • 28. GROUP MEMBERS Name ID Cassandra Wong Xin Yue 0313365 Cheong Kha Man 0319456 Kevin Hii Ting Kui 0319223 Low Chee Ying 0319126 Ng Ding Boon 0319243 Stephanie Yeoh Sze Wei 0318954 Haziq Zariful 0314131

Editor's Notes

  1. 1st Person Starts - Speak about Architect (Ministry of Development)
  2. Speak about bolded parts
  3. Speak about main director & Registered QS - All QS are Registered Chartered Surveyors by RICS
  4. 2nd Person Start - Say,”this is the Architect model..blabla”
  5. “The terrace house is part of a housing development”
  6. Speak about the bold parts
  7. Simply point out the invitation & Type of tender
  8. 3rd Person Starts - Talk about everything
  9. Talk about the GFA for the PC, Provisional & Contigiency Sum
  10. Talk about total GFA
  11. “The estimated price is….” “The projected construction period is…”
  12. 4th Person
  13. Just point it out, no need to say everything
  14. Just point it out, no need to say everything
  15. “PC sum consists of….” “While the Provisional sum consists of…” In case teacher asks how we find: M&E Works – RM30/m2 Sanitary – RM35/m2
  16. 5th Person List down everything
  17. Speak about the locations of elements
  18. Speak about the locations of elements
  19. Speak about the locations of elements
  20. 6th Person Starts Speak about the locations of elements
  21. “Now I would like to talk about…”
  22. Speak about red parts
  23. Speak about red parts
  24. 7th Person Starts - Speak About DLP
  25. LAD Interim Claim Interval Limit of Retention Fund Period to Complete Final Acoount