PLANNING, SCHEDULING, RESOURCE ALLOCATING AND TRACKING OF
RESIDENTIAL (G+2) VILLA USING PRIMAVERA P6
MOHD ILYAS AHMED1, BRIJBHUSHAN S2, MANEETH P.D3
1M.Tech Student Department of Construction Technology, Visvesvaraya Technological University, PG Studies,
Regional Office, Kalaburagi-585105 Karnataka, India
2, 3 Assistant Professor, Department of Construction Technology, Visvesvaraya Technological University, PG Studies,
Regional Office,Kalaburagi-585105 Karnataka ,India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Planning, scheduling and required quantity of
resources with regular tracking is very important any
construction projects to reduce delays of the project. Due to
improper scheduling, irregular monitoring and controlling of
ongoing activities substantial amount of time andresourcesis
wasted with this desired goal is not achieved. In the present
work, study is carried out on residential (G+2) villa. This study
covers the process of planning, scheduling, tracking and
controlling of activities. The software used for this study is
primavera p6, this tool is utilized throughout from planning
phase to tracking and controlling of a project, it reduced huge
amount of paperwork. Only development of schedule doesn’t
make a successful project in construction, it further need tobe
tracked regularly, for this, baseline have been managed for
comparison betweentheplannedprogressandactualprogress
by primavera software for proper recognition of problem
which cause deviation. Many uncertainties occur in practical
work leads to delay. By using software techniques, applying
resource dependency, rescheduling of the project by crashing
and fast tracking of critical activities overcome the delay
duration.
Key Words: Planning, Scheduling, Monitoring, Crashing,
Fast Tracking.
1. INTRODUCTION
In this present scenario, construction is being
increased day by day and now it is at higher demand.
Constructional companies deals with these many kinds of
projects daily. Different worldwide organizations manage
the constructions each day and which has turnedintoa most
imperative piece of business.
In the older days the software were not used in
construction projects. No planning or scheduling was done
constructional activities as it was directly executed by
contractor and planning was done manually Now a days,
architectural planning is done with the help of many
software but for the execution no proper management was
done which leads to the delay for the completion of work.
Thus this attempt is made to achievepropermethodoverthe
construction activities with the utilization of software.
Primavera is an advance computer integrated
enterprise project management tool. As we know India is
booming in construction industry so we should be familiar
with tools like primavera which is highly advance
management tool with recorded data base ORACLE this tool
is web assessable for modification in an any situation in
management activities .this tool work simultaneously for
multi project at a time can be monitor and control all the
project.so proper management is required with
documentation and this can be possible if we know
primavera tool completely and properly.
2. OBJECTIVES
 To recognize planning procedure utilized in
creating planning and scheduling.
 Creating work breakdown structure (WBS) in
which single large project into small
portions/pieces for planning and control
purpose.
 To find out the stepwise preparation of
activities of construction for a residential
building.
 Scheduling of critical path by keeping duration
of activities as constraints.
 Allocating required estimated and type of
resources to individual activities to perform
each events.
 To know the significance of providing baseline
during tracking of execution of constructional
work.
 Importance of monitoring on regular basis to
progress of villa and distinguish on actual and
planned schedule.
 Effective rescheduling in plan during negative
float to sort within given target.
 Overcome the delay in program by analysing
compression of critical plan.
 Implementation of method and enhancing the
schedule by various relationships, duration,
man power, calendars for effective
management for completion on time.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 968
3. METHODOLOGY
3.1 PLANNING
Venture arranging is the capacity in which venture and
development administrators and their key staff individuals
readies the ground breaking strategy. At that point this all-
inclusive strategy is put into time plan by planning
responsible which is called extendbooking.Aventuredesign
is generally in charge of the achievement or disappointment
of a venture. Plan is first step of venture administration
reasoning of arranging, sorting out and controlling the
execution of the planned setup.
It is a most important and challenging activity in
management as well as execution of projects. It involves the
choice of technology, the definition of effort task, the
estimation of required durations andresourcesofindividual
activity, and identifies the connections in between different
work tasks. A plan is the base for evolving the schedule,
development of the constructional plan is an acute task in
construction management.Firstlya plannermustkeepa goal
which is required to achieve.
In this project, primary importance is given to duration of
activities, which means duration of all the events in
construction are kept as constraints and based on the
productivity of resources, the amount of required
resources(labor, non-labor) are estimated and assigned to
particular activities.
3.2 SCHEDULING
It displays the duration and order of various construction
activities. Scheduling can be also well-defined as the
comprehensive0plot of the project work tasks
through0reverence to time. Without schedule it is hard to
clarify so system, logic, and manpower requirements means
of building a project. The project schedule serves as a
primary means of relaying construction plans, The
construction schedule also communicates means and
methods, as well as planned sequences and timing for a
project. itis the lay out of the project activities with a time
sequence in which they have to be perform, the start and
finish dates are assigned to each activity, relationship with
each other of these events are to be provided with logic and
common sense with a proper lag of duration if required.
Scheduling is completed when all activities in project after
providing duration and necessary relation to it. Enteringthe
start date of project on data date will automatically provide
the all the start and finish date of every activities.
3.3 RESOURCE ALLOCATION
Resource allocation is a method use to assign the required
resources to the activities. In project management, resource
allocation is supply required by those activities while
considering both resource availability and project time.
Resources include such as man, machinery and material.
Before assigning, they have to createdandcategorizedbased
on the labor and non-labor, and their units. Amount of
resources to be assigned depend on the duration of a
particular activity. These sources are calculated by their
productivity of it per day.
3.4 TRACKING
Supervising the activities of the progress so astoensurethat
they are on-schedule and meeting the required goals and
objectives . It is nothing but the updating the project as per
schedule and recording the progress of individual activities
performed based on specified time and resource.Itissecond
major stage in project management. Monitoring is like a
cautionary mechanism, it is the procedure of collecting,
recording and reportthedata regardingprojectperformance
that the project manager. Monitoringincludesinspection the
advance of in contradiction of time, performanceschedule in
addition to resources thru actual effecting of project and it
identified the laggingregions whichrequirejudiciousactions
besides attention.
In the progress of project some activities will complete
within provided duration and some delays due to various
reasons. Properly monitoring will be helpful in identifying
the difference between actual work and original plan. After
scheduling it is very vital to monitor the practical operation
of work onsite based on the data collected further
rescheduling is performed. During theproceedingofproject,
monitoring is done by comparing the baseline provided
indicated by yellow color, monitoring regularly shows
whether the construction is behind or workingasplanned.If
the project progress is behind schedule, it shows total floats
negative values of delayed number of days.Itshouldbedone
on regular within short gap of time in order to implement
some methods if any delay took place to make the upcoming
schedule parallel with the baseline.
3.5 COMPRESSION
When there is a delay during the execution of construction
activities, which can occur due to any many uncertainties,
delays are the extension of time beyond planned dates of
completion. It is the late completion of construction work
compared to the contract schedule. This canbereducedonly
when the reason for delay is identified.. There are various
reasons delay occur due to client, contactor, consultant,
designer, materials, equipment’s, labor and weather causes
etc. The delay which occurred in critical path of project will
have effect on the completion date of project causes to
generate slack in minus value, if the delay of such activity
occurs which are at the non-critical pathhavingconsiderable
total float it will not have effect on the completion of project
duration. When there is situation happens that caused the
deviation of schedule from its baseline generating
undesirable float. To overcome this compressiontechniques
can be utilized to reduce the duration of activities and
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 969
overcome the effect of delays. This technique can only be
applied to activities that befall on critical path because
applying to non-critical will not be advantageous rather it
would be disadvantage as goal is not achieved. Compression
can be subdivided further into crashing and fast tracking.
Crashing is a schedule compressiontechniquein whichextra
resources are added to reduce completion time of activity.
Initially the critical path should be analyzed and select the
desirable event for which crashing should be performed.
While using crash procedure it is important to have tab on
another path as it has risk that duration of any other path
may become critical. Examples for applying crash such as
increasing the resources,providingovertimeshifts,inspiring
the team by financial/bonus rewards. Fast tracking is also a
compression method by using parallel or partially parallel
performance of activities can done. This also must be used
on critical path by evaluating the schedule, however there is
increase on risk as events will be on parallel which were in
the sequence when planned in the beginning. It helps in
reducing the time to a certain limits it may lead to high risk
and undesirable outcome may be resulted.
4. DATA ANALYSIS
It is the project based on the G+2 residential building which
is being constructed in the kalaburagi city. All the necessary
data required have been extracted from the documents
provided by client and contractor for the purpose of
producing the schedule of activities based on the duration
which is involved in construction, providing necessary
resources to each one of them. Site is located in a congested
area so to practically make the construction is quite tough.
This house consists of 8 bed rooms, 3 halls and 6 bathrooms.
All the quantities have been taken from the BOQ provided.
Duration for each activity is given by contractor based on it
scheduling is done.
Table 4.1 project details
Project name RB villa
Type G+2 residential
Client Jameel ahmed
Contractor Nitin Chauhan
Site location Hagarga road, kalaburagi
Size of plot 40 x 60
Built up area 4250sqft
No of footing Total 18, isolated type
Commencement date 25-mar-2017
Finish date 22-dec-2017
Project Duration 234 days
Fig 4.1 ground floor plan
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 970
Fig -4.2 first floor plan
Fig -4.3 second floor plan
Table 4.2: Activities Delayed Details
Reasons for above mentioned delay
1. Improper coordination between contractor and labour
leads to late start of excavation at original date.
2. There was a conflict as payment was not done caused
labours strike and effect schedule.
3. Bricks which were procured was not of desired quality,
hence it was returned and exchanged.
ID NAME
SCHEDULE
D
DURATION
DURATION
AFTER
CRASHING
TOTAL
FLOAT
ILS1
060
footing
shuttering &
rebar
5 days 3 days (2-3)= -
1
ILS1
100
plinth beam
shuttering &
rebar(gf)
6 days 3 days (3-4)= -
1
ILS1
296
brick work
above
lintel(gf)
5 days 4 days (1-1)=0
Table 4. Fast Tracked Activities
ID Name Scheduled
start date to
finish date
Actual
start date
to finish
date
Total
float
ILS1040 footing
excavation
27/march/17
to 4/April/17
30/mar/17
to
7/April/17
-3
ILS1110 backfilling 24/April/17
to
27/April/17
28/April/17
to
02/may/17
-4
ILS1290 Brickwork
up to lintel
(gf)
18/may/17 to
29/may/17
20/may/17
to
30/may/17
-2
Id Name Original
Relation
with
predecessor
Changed
relationship
Total
float
ILS1070 Footing
concrete
FS=0 d lag SS=2 d lag
FF= 1d lag
(1-1)=
0
ILS1140 Column
concrete
FS=0 d lag FF=0 d lag (1-1)=
0
ILS1142 Lintel
concrete
FS=0 d lag FF=0 d lag (1-2)=
-1
Table 4.3 Crashed Activities
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 971
5. RESULTS
This ongoing project, the work progress
6. CONCLUSION
 Regular monitoring of the work under execution
must be done at least within week in order to take
adequate actions against uncertainty.
 Primary baseline and Gantt chart produced makes
easy to identify critical path and monitoring task
against it progress extremely easy by observing
colors of bars.
 Carrying out review to view deviation in schedule
helped and control against planned agenda is just
piece of cake with this software.
 WBS helped to organize, arrange and knowthework
completion in percentage at everyportions/nodesin
it.
 Augmented scheduling done by effective
relationships between events, project duration of
234 days has been obtained which gives huge carpet
area as compared to 365 days required by
contractor.
 Proper co-ordination and ease of communication of
running of assignment.
 In this project by applying crashingandfasttracking
method duration of selected events is reduced to
reschedule within the baseline.
 Using primavera technique of resource dependency,
compression of various activities is done by
increasing working hours.
 Primavera (P6) proved to be a better tool for
scheduling, monitoringandcontrollingandshowsits
efficiency in providing best results with less effort of
user by preventing enormous volume paperwork.
REFERENCE
1. P Raghunath Reddy, B.Harish Naik “Planning and
Resource Scheduling of Residential (G+7) Project
Using Primavera” Vol. 5, Issue 10,( 2016)
2. Andrew Fernans Tom, Sachin Paul “Project
Monitoring and Control using Primavera” Vol. 2,
Issue 3,( 2013)
3. S M Abdul Mannan Hussain, Madamachi Mani
Chakravarthy, Asra Fatima “Scheduling Of An
Residential Building Using Project Management
Techniques”(2016)
4. Veena H C, Vijay K, Dr. S Rajendra, R Ashok Kumar
“Schedule Control of an Apartment Building using
Primavera Techniques” Vol. 5 Issue 06,(2016)
5. T.Subramani, P.T.Lishitha,M.Kavitha “TimeOverrun
and Cost EffectivenessintheConstructionIndustry”
Vol. 4, Issue 6 (2014)
6. Nisarg M. Mistry, Mayank A. Kanani, Dr. Neeraj D.
Sharma3 “Application Of Primavera Software For
Scheduling Of Row House To Complete Project On
Time”(2015)
Scheduled Duration
For Project
234 Days
Duration
Completed
65 Days
Remaining
Completion
Duration
169 Days
Substructure 100%
Superstructure 22.86%
Project
Accomplished
27.78%
Crashed Period
Value
4 Days
Fast Tracked Value 3 Days
is an
contractor with labors is very important for smooth

More Related Content

What's hot

Primavera P6
Primavera P6Primavera P6
Primavera P6
Piyush Bagade
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
ijtsrd
 
Project Management- introduction
Project Management- introductionProject Management- introduction
Project Management- introduction
Aditi Garg
 
H1303024956
H1303024956H1303024956
H1303024956
IOSR Journals
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
IJSRD
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
krunalchem
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
Suresh G Sankarankutty
 
Primavara
PrimavaraPrimavara
Primavara
danabl
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
IRJET Journal
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
AMIT PAYAL
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
adeel hamid
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET Journal
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and scheduling
Atul Gaur PMP
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
ijtsrd
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 

What's hot (17)

Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Project Management- introduction
Project Management- introductionProject Management- introduction
Project Management- introduction
 
H1303024956
H1303024956H1303024956
H1303024956
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavara
PrimavaraPrimavara
Primavara
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and scheduling
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 

Similar to Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) Villa using Primavera P6

IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
IRJET Journal
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...
IRJET Journal
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET Journal
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
SHAZEBALIKHAN1
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
IRJET Journal
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
KHUSHBU SHAH
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET Journal
 
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
IRJET Journal
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
IRJET Journal
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
POOJA UDAYAN
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
Dr. RICHA SINGHAL
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
ijtsrd
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Efficient Task Management and Scheduling: The Key to Successful Construction ...
Efficient Task Management and Scheduling: The Key to Successful Construction ...Efficient Task Management and Scheduling: The Key to Successful Construction ...
Efficient Task Management and Scheduling: The Key to Successful Construction ...
iFieldsmart Technologies
 
I012335763
I012335763I012335763
I012335763
IOSR Journals
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
IAEME Publication
 

Similar to Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) Villa using Primavera P6 (20)

IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...
 
20320130405009
2032013040500920320130405009
20320130405009
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Efficient Task Management and Scheduling: The Key to Successful Construction ...
Efficient Task Management and Scheduling: The Key to Successful Construction ...Efficient Task Management and Scheduling: The Key to Successful Construction ...
Efficient Task Management and Scheduling: The Key to Successful Construction ...
 
I012335763
I012335763I012335763
I012335763
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
benykoy2024
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
azkamurat
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 

Recently uploaded (20)

01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 

Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) Villa using Primavera P6

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 967 PLANNING, SCHEDULING, RESOURCE ALLOCATING AND TRACKING OF RESIDENTIAL (G+2) VILLA USING PRIMAVERA P6 MOHD ILYAS AHMED1, BRIJBHUSHAN S2, MANEETH P.D3 1M.Tech Student Department of Construction Technology, Visvesvaraya Technological University, PG Studies, Regional Office, Kalaburagi-585105 Karnataka, India 2, 3 Assistant Professor, Department of Construction Technology, Visvesvaraya Technological University, PG Studies, Regional Office,Kalaburagi-585105 Karnataka ,India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Planning, scheduling and required quantity of resources with regular tracking is very important any construction projects to reduce delays of the project. Due to improper scheduling, irregular monitoring and controlling of ongoing activities substantial amount of time andresourcesis wasted with this desired goal is not achieved. In the present work, study is carried out on residential (G+2) villa. This study covers the process of planning, scheduling, tracking and controlling of activities. The software used for this study is primavera p6, this tool is utilized throughout from planning phase to tracking and controlling of a project, it reduced huge amount of paperwork. Only development of schedule doesn’t make a successful project in construction, it further need tobe tracked regularly, for this, baseline have been managed for comparison betweentheplannedprogressandactualprogress by primavera software for proper recognition of problem which cause deviation. Many uncertainties occur in practical work leads to delay. By using software techniques, applying resource dependency, rescheduling of the project by crashing and fast tracking of critical activities overcome the delay duration. Key Words: Planning, Scheduling, Monitoring, Crashing, Fast Tracking. 1. INTRODUCTION In this present scenario, construction is being increased day by day and now it is at higher demand. Constructional companies deals with these many kinds of projects daily. Different worldwide organizations manage the constructions each day and which has turnedintoa most imperative piece of business. In the older days the software were not used in construction projects. No planning or scheduling was done constructional activities as it was directly executed by contractor and planning was done manually Now a days, architectural planning is done with the help of many software but for the execution no proper management was done which leads to the delay for the completion of work. Thus this attempt is made to achievepropermethodoverthe construction activities with the utilization of software. Primavera is an advance computer integrated enterprise project management tool. As we know India is booming in construction industry so we should be familiar with tools like primavera which is highly advance management tool with recorded data base ORACLE this tool is web assessable for modification in an any situation in management activities .this tool work simultaneously for multi project at a time can be monitor and control all the project.so proper management is required with documentation and this can be possible if we know primavera tool completely and properly. 2. OBJECTIVES  To recognize planning procedure utilized in creating planning and scheduling.  Creating work breakdown structure (WBS) in which single large project into small portions/pieces for planning and control purpose.  To find out the stepwise preparation of activities of construction for a residential building.  Scheduling of critical path by keeping duration of activities as constraints.  Allocating required estimated and type of resources to individual activities to perform each events.  To know the significance of providing baseline during tracking of execution of constructional work.  Importance of monitoring on regular basis to progress of villa and distinguish on actual and planned schedule.  Effective rescheduling in plan during negative float to sort within given target.  Overcome the delay in program by analysing compression of critical plan.  Implementation of method and enhancing the schedule by various relationships, duration, man power, calendars for effective management for completion on time.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 968 3. METHODOLOGY 3.1 PLANNING Venture arranging is the capacity in which venture and development administrators and their key staff individuals readies the ground breaking strategy. At that point this all- inclusive strategy is put into time plan by planning responsible which is called extendbooking.Aventuredesign is generally in charge of the achievement or disappointment of a venture. Plan is first step of venture administration reasoning of arranging, sorting out and controlling the execution of the planned setup. It is a most important and challenging activity in management as well as execution of projects. It involves the choice of technology, the definition of effort task, the estimation of required durations andresourcesofindividual activity, and identifies the connections in between different work tasks. A plan is the base for evolving the schedule, development of the constructional plan is an acute task in construction management.Firstlya plannermustkeepa goal which is required to achieve. In this project, primary importance is given to duration of activities, which means duration of all the events in construction are kept as constraints and based on the productivity of resources, the amount of required resources(labor, non-labor) are estimated and assigned to particular activities. 3.2 SCHEDULING It displays the duration and order of various construction activities. Scheduling can be also well-defined as the comprehensive0plot of the project work tasks through0reverence to time. Without schedule it is hard to clarify so system, logic, and manpower requirements means of building a project. The project schedule serves as a primary means of relaying construction plans, The construction schedule also communicates means and methods, as well as planned sequences and timing for a project. itis the lay out of the project activities with a time sequence in which they have to be perform, the start and finish dates are assigned to each activity, relationship with each other of these events are to be provided with logic and common sense with a proper lag of duration if required. Scheduling is completed when all activities in project after providing duration and necessary relation to it. Enteringthe start date of project on data date will automatically provide the all the start and finish date of every activities. 3.3 RESOURCE ALLOCATION Resource allocation is a method use to assign the required resources to the activities. In project management, resource allocation is supply required by those activities while considering both resource availability and project time. Resources include such as man, machinery and material. Before assigning, they have to createdandcategorizedbased on the labor and non-labor, and their units. Amount of resources to be assigned depend on the duration of a particular activity. These sources are calculated by their productivity of it per day. 3.4 TRACKING Supervising the activities of the progress so astoensurethat they are on-schedule and meeting the required goals and objectives . It is nothing but the updating the project as per schedule and recording the progress of individual activities performed based on specified time and resource.Itissecond major stage in project management. Monitoring is like a cautionary mechanism, it is the procedure of collecting, recording and reportthedata regardingprojectperformance that the project manager. Monitoringincludesinspection the advance of in contradiction of time, performanceschedule in addition to resources thru actual effecting of project and it identified the laggingregions whichrequirejudiciousactions besides attention. In the progress of project some activities will complete within provided duration and some delays due to various reasons. Properly monitoring will be helpful in identifying the difference between actual work and original plan. After scheduling it is very vital to monitor the practical operation of work onsite based on the data collected further rescheduling is performed. During theproceedingofproject, monitoring is done by comparing the baseline provided indicated by yellow color, monitoring regularly shows whether the construction is behind or workingasplanned.If the project progress is behind schedule, it shows total floats negative values of delayed number of days.Itshouldbedone on regular within short gap of time in order to implement some methods if any delay took place to make the upcoming schedule parallel with the baseline. 3.5 COMPRESSION When there is a delay during the execution of construction activities, which can occur due to any many uncertainties, delays are the extension of time beyond planned dates of completion. It is the late completion of construction work compared to the contract schedule. This canbereducedonly when the reason for delay is identified.. There are various reasons delay occur due to client, contactor, consultant, designer, materials, equipment’s, labor and weather causes etc. The delay which occurred in critical path of project will have effect on the completion date of project causes to generate slack in minus value, if the delay of such activity occurs which are at the non-critical pathhavingconsiderable total float it will not have effect on the completion of project duration. When there is situation happens that caused the deviation of schedule from its baseline generating undesirable float. To overcome this compressiontechniques can be utilized to reduce the duration of activities and
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 969 overcome the effect of delays. This technique can only be applied to activities that befall on critical path because applying to non-critical will not be advantageous rather it would be disadvantage as goal is not achieved. Compression can be subdivided further into crashing and fast tracking. Crashing is a schedule compressiontechniquein whichextra resources are added to reduce completion time of activity. Initially the critical path should be analyzed and select the desirable event for which crashing should be performed. While using crash procedure it is important to have tab on another path as it has risk that duration of any other path may become critical. Examples for applying crash such as increasing the resources,providingovertimeshifts,inspiring the team by financial/bonus rewards. Fast tracking is also a compression method by using parallel or partially parallel performance of activities can done. This also must be used on critical path by evaluating the schedule, however there is increase on risk as events will be on parallel which were in the sequence when planned in the beginning. It helps in reducing the time to a certain limits it may lead to high risk and undesirable outcome may be resulted. 4. DATA ANALYSIS It is the project based on the G+2 residential building which is being constructed in the kalaburagi city. All the necessary data required have been extracted from the documents provided by client and contractor for the purpose of producing the schedule of activities based on the duration which is involved in construction, providing necessary resources to each one of them. Site is located in a congested area so to practically make the construction is quite tough. This house consists of 8 bed rooms, 3 halls and 6 bathrooms. All the quantities have been taken from the BOQ provided. Duration for each activity is given by contractor based on it scheduling is done. Table 4.1 project details Project name RB villa Type G+2 residential Client Jameel ahmed Contractor Nitin Chauhan Site location Hagarga road, kalaburagi Size of plot 40 x 60 Built up area 4250sqft No of footing Total 18, isolated type Commencement date 25-mar-2017 Finish date 22-dec-2017 Project Duration 234 days Fig 4.1 ground floor plan
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 970 Fig -4.2 first floor plan Fig -4.3 second floor plan Table 4.2: Activities Delayed Details Reasons for above mentioned delay 1. Improper coordination between contractor and labour leads to late start of excavation at original date. 2. There was a conflict as payment was not done caused labours strike and effect schedule. 3. Bricks which were procured was not of desired quality, hence it was returned and exchanged. ID NAME SCHEDULE D DURATION DURATION AFTER CRASHING TOTAL FLOAT ILS1 060 footing shuttering & rebar 5 days 3 days (2-3)= - 1 ILS1 100 plinth beam shuttering & rebar(gf) 6 days 3 days (3-4)= - 1 ILS1 296 brick work above lintel(gf) 5 days 4 days (1-1)=0 Table 4. Fast Tracked Activities ID Name Scheduled start date to finish date Actual start date to finish date Total float ILS1040 footing excavation 27/march/17 to 4/April/17 30/mar/17 to 7/April/17 -3 ILS1110 backfilling 24/April/17 to 27/April/17 28/April/17 to 02/may/17 -4 ILS1290 Brickwork up to lintel (gf) 18/may/17 to 29/may/17 20/may/17 to 30/may/17 -2 Id Name Original Relation with predecessor Changed relationship Total float ILS1070 Footing concrete FS=0 d lag SS=2 d lag FF= 1d lag (1-1)= 0 ILS1140 Column concrete FS=0 d lag FF=0 d lag (1-1)= 0 ILS1142 Lintel concrete FS=0 d lag FF=0 d lag (1-2)= -1 Table 4.3 Crashed Activities
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 971 5. RESULTS This ongoing project, the work progress 6. CONCLUSION  Regular monitoring of the work under execution must be done at least within week in order to take adequate actions against uncertainty.  Primary baseline and Gantt chart produced makes easy to identify critical path and monitoring task against it progress extremely easy by observing colors of bars.  Carrying out review to view deviation in schedule helped and control against planned agenda is just piece of cake with this software.  WBS helped to organize, arrange and knowthework completion in percentage at everyportions/nodesin it.  Augmented scheduling done by effective relationships between events, project duration of 234 days has been obtained which gives huge carpet area as compared to 365 days required by contractor.  Proper co-ordination and ease of communication of running of assignment.  In this project by applying crashingandfasttracking method duration of selected events is reduced to reschedule within the baseline.  Using primavera technique of resource dependency, compression of various activities is done by increasing working hours.  Primavera (P6) proved to be a better tool for scheduling, monitoringandcontrollingandshowsits efficiency in providing best results with less effort of user by preventing enormous volume paperwork. REFERENCE 1. P Raghunath Reddy, B.Harish Naik “Planning and Resource Scheduling of Residential (G+7) Project Using Primavera” Vol. 5, Issue 10,( 2016) 2. Andrew Fernans Tom, Sachin Paul “Project Monitoring and Control using Primavera” Vol. 2, Issue 3,( 2013) 3. S M Abdul Mannan Hussain, Madamachi Mani Chakravarthy, Asra Fatima “Scheduling Of An Residential Building Using Project Management Techniques”(2016) 4. Veena H C, Vijay K, Dr. S Rajendra, R Ashok Kumar “Schedule Control of an Apartment Building using Primavera Techniques” Vol. 5 Issue 06,(2016) 5. T.Subramani, P.T.Lishitha,M.Kavitha “TimeOverrun and Cost EffectivenessintheConstructionIndustry” Vol. 4, Issue 6 (2014) 6. Nisarg M. Mistry, Mayank A. Kanani, Dr. Neeraj D. Sharma3 “Application Of Primavera Software For Scheduling Of Row House To Complete Project On Time”(2015) Scheduled Duration For Project 234 Days Duration Completed 65 Days Remaining Completion Duration 169 Days Substructure 100% Superstructure 22.86% Project Accomplished 27.78% Crashed Period Value 4 Days Fast Tracked Value 3 Days is an contractor with labors is very important for smooth