This document discusses planning, scheduling, and allocating resources for a multi-storey building construction project using Microsoft Project software. It summarizes a study comparing the traditional scheduling approach used in construction with using Microsoft Project. The study found that Microsoft Project is effective for generating Gantt charts and determining minimum construction durations. It also allows for resource scheduling and tracking project costs and budgets. The document provides examples of using Microsoft Project for a hypothetical residential building project, including network diagrams, resource allocation charts, cost overviews, and identifying upcoming tasks and cost overruns. Overall, the study found Microsoft Project can help streamline scheduling, increase efficiency, and reduce construction costs when compared to traditional scheduling methods.
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
Objective: The research aims an empirical study on the application of MSP in every
single aspect of a project from planning and scheduling phase. Irrespective of nature of
work, location or norms in an organization, all the members work on tasks that are varied
and involve people who do not usually work together but for the same objective. Methods:
A project may have a simple goal that may not require many people or a great amount of
capital or it may be complex to a certain extent, calling for various skills and excess of
resources. But, the common line is that every human can manage projects. Due to this, the
purpose of dealing with the project should not be only execution but the effective and
efficient execution of a project is essential which is needed to be emphasized. Construction
companies in India executes the project in a traditional way, this sometimes leads
uneconomical and tedious too. The traditional method is time-consuming and bit confusion
in execution. Findings: This paper will provide how to do planning and scheduling for a
building which is a multi-storied (G+8) with Microsoft Project (MSP) software by
observing the site conditions, labour productivity, and available resources with proper
utilization of time and resources. Application: This approach can be projected to similar
projects of the same size.
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...IJSRD
One of the most challenging jobs that any manager can take on is the management of a large-scale project and it requires numerous activities throughout the project. A Modern project management has developed various techniques based on network techniques in order to plan the projects processes in time, their costs and resources. Critical Path Method (CPM) is one of the best procedures for the planning, scheduling and optimizing the resource usage. CPM scheduling is a basic project control tool hence it is using in the all type of project. Completing a project on time and within the budget is not an easy task. The project scheduling plays an important role in the time and cost aspects of a project. Each project managers have different systems in planning and scheduling, which is usually consists of Gantt chart or Bar chart. The development of Critical Path Method provides a basic and systematic approach to project managers. This results in the use of software’s like Microsoft Project and Primavera.
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
Objective: The research aims an empirical study on the application of MSP in every
single aspect of a project from planning and scheduling phase. Irrespective of nature of
work, location or norms in an organization, all the members work on tasks that are varied
and involve people who do not usually work together but for the same objective. Methods:
A project may have a simple goal that may not require many people or a great amount of
capital or it may be complex to a certain extent, calling for various skills and excess of
resources. But, the common line is that every human can manage projects. Due to this, the
purpose of dealing with the project should not be only execution but the effective and
efficient execution of a project is essential which is needed to be emphasized. Construction
companies in India executes the project in a traditional way, this sometimes leads
uneconomical and tedious too. The traditional method is time-consuming and bit confusion
in execution. Findings: This paper will provide how to do planning and scheduling for a
building which is a multi-storied (G+8) with Microsoft Project (MSP) software by
observing the site conditions, labour productivity, and available resources with proper
utilization of time and resources. Application: This approach can be projected to similar
projects of the same size.
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...IJSRD
One of the most challenging jobs that any manager can take on is the management of a large-scale project and it requires numerous activities throughout the project. A Modern project management has developed various techniques based on network techniques in order to plan the projects processes in time, their costs and resources. Critical Path Method (CPM) is one of the best procedures for the planning, scheduling and optimizing the resource usage. CPM scheduling is a basic project control tool hence it is using in the all type of project. Completing a project on time and within the budget is not an easy task. The project scheduling plays an important role in the time and cost aspects of a project. Each project managers have different systems in planning and scheduling, which is usually consists of Gantt chart or Bar chart. The development of Critical Path Method provides a basic and systematic approach to project managers. This results in the use of software’s like Microsoft Project and Primavera.
Project management tools and techniques- tutorsindia.comTutors India
In this topic, we have discussed the project management tools and techniques. The present article helps the USA, the UK, Europe and the Australian students pursuing their master’s degree to identify the best project management tools and techniques, which are usually considered to be challenging. Tutors India offers UK dissertation in various Domains.
When you Order any reflective report at Tutors India, we promise you the following
Plagiarism free
Always on Time
Outstanding customer support
Written to Standard
Unlimited Revisions support
High-quality Subject Matter Experts.
Contact:
Website: www.tutorsindia.com
Email: info@tutorsindia.com
United Kingdom: +44-1143520021
India: +91-4448137070
Whatsapp Number: +91-8754446690
Reference: http://bit.ly/2v6tBB6
A study of the constraints affecting the proper utilization of computer appli...eSAT Journals
Abstract
Construction is one of the area in which computer application software are highly required to perform different task at various stages of project construction. Computers have been used to enhance the effectiveness of construction management. Efficient utilization of computer application software is a key to enhancing the proper management of construction activities which will contribute to the successful implementation of construction project. Careful selection of computer application software is required by the construction companies for proper management of their resources. The difficulty about computerization especially with regard to the use of computer application software in resource management require the knowledge and expertise of those working in construction companies, and who are directly involved in the management of construction resources. The study was carried out to determine the obstacles confronting the proper utilization of computer application software in resource management. The result of the questionnaire survey used in this research work clearly indicated those constraints, which include, non-understanding about software potentials, lack of qualified personnel to use the software, unaware of most of the resource management software available in the market, communication gap between the vendors and users which contribute to non-understanding of the full scope of the software, greater-know-how required from staff, among numerous others. A total of 22 construction companies were selected for the study. An open ended questionnaire which consist of 22 questions with regard to the constraints affecting the proper utilization of computer application software in resource management was designed, validated, and distributed among Engineers, Project Managers, as well as executives who are directly involved in the activities of the construction site.
Keywords: resource management, application software, construction management
Large Planning is a general term that sets a clear road map that should be followed to reach a destination. The term, therefore, has been used at different levels to mean different things. Planning involves the breakdown of the project into definable, measurable, and identifiable tasks activities, and then establishes the logical interdependences among them. These plans involve four main steps Performing breakdown of work items involved in the project into activities. Identifying the proper sequence by which the activities should be executed. Activities representation. Estimating the resources, time, and cost of individual activities. Planning requires a rigorous effort by the planning team. A planner should know the different categories of work and be familiar with the terminology and knowledge used in general practice. Also, the planning tem should seek the opinion of experts including actual construction experience. This helps produce a realistic plan and avoids problems later on site. P. B. Sudha | Dr. K. Vidhya "Project Planning & Scheduling" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-4 | Issue-5 , August 2020, URL: https://www.ijtsrd.com/papers/ijtsrd31775.pdf Paper Url :https://www.ijtsrd.com/engineering/civil-engineering/31775/project-planning-and-scheduling/p-b-sudha
Planning is a guideline in implementing the project so that development can be
implemented in accordance with the time and cost planned. Control discrepancy
between initial plan and realization that exists in implementation project required a
project management, therefore required optimization analysis of project duration, so
it can be known how long a project is completed and look for the possibility of project
acceleration implementation by Project Evaluation and Review Technique (PERT)
and Critical Path Method (CPM) or critical path method. This research aims to apply
Project Evaluation and Review Technique (PERT) and Critical Project Management
(CPM) methods to find optimize solutions and control the performance of time and
cost in project scheduling. The research method used case study method at hospital
project in Bogor District, Indonesia, by collecting data direct observation and
interview results at contractor. Based on these data, create a schedule by using PERT
and CPM methods, which will be measured performance of time performance and
project cost which is expected to overcome the problem of controlling and completion
of project. The results of this study, using PERT and CPM methods proved to optimize
the project. Based on calculation by PERT method reduce duration of work: 12 days
(13, 18%). Based on calculation by CPM method reduce duration of work: 31 days
(34, 06%) but direct cost increase 112.208,300, - rupiahs (0, 25%).
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
Modern construction system has shown great potential in the field of the conventional construction system. The advantage of using new construction techniques for any type of construction is that the process takes no longer. The modern method of construction is defined as a way of working more effectively to achieve more while using less. The description lends itself heavily to offsite or modular construction techniques the method of prefabricating parts of building offsite before transporting and assembling them at their final location. Unlike traditional methods of construction is defined as a way of working more effectively. Poor construction management will cause the delay. Delay in the contracted project can result in penalties and adversely affect the reputation of the company. It is essential to manage the work within time. If construction time increases, construction cost also increases. It is necessary proper planning and management for construction work. Primavera p6 is a management tool. In this study primavera software help in the planning and scheduling of the project. Primavera gives better quality of project management process and easily understanding results. Shashwat Dubey | Prof. M. C. Paliwal "Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38641.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/38641/review-on-planning-and-scheduling-of-construction-project-by-management-tool-primavera-p6/shashwat-dubey
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
Construction scheduling is a complex and challenging task demanding an in depth
expertise. Consideration of several factors, their influences and likely impact on the
schedule need a thorough understanding. It is mostly experience based knowledge in
the form of heuristics, available with the experienced schedulers. In this connection
this study mainly discusses the factors influencing construction scheduling and
techniques through a comparative study of various international construction
projects. About 40 relevant articles published over the last 25 years have been
reviewed. However, each and every limited formalized knowledge is available in
theoretical form, which is interesting to many researchers for many decades, a
comprehensive research is made and a comparative study on the literatures was
carried out and presented in this paper. The main aim of the paper is to highlight the
major factors which are to be mainly considered for the successful completion of the
project.
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
Project planning is the important task in many areas like construction, resource allocation and many. A sequence of activities has to be performed to complete one task. Each activity has its unique processing time and all together to identify the critical activities which affect the completion of the project. In this paper the probabilistic and deterministic models to determine the project completion time and also the critical activities are considered. A case study on building construction project has been performed to demonstrate the application of the above said models. The two project scheduling namely PERT and CPM are used to determine numerically the different types of floating times of each activity and hence determined the critical path which plays an important role in the project completion time. Also a linear programing model has been developed to reduce the project completion time which optimize the resource allocation. To apply these techniques numerically the primary data from a housing project company in a metropolitan city has been taken, the network diagram of the activities involved in the building construction project has been drawn and the results are tabulated
Project management tools and techniques- tutorsindia.comTutors India
In this topic, we have discussed the project management tools and techniques. The present article helps the USA, the UK, Europe and the Australian students pursuing their master’s degree to identify the best project management tools and techniques, which are usually considered to be challenging. Tutors India offers UK dissertation in various Domains.
When you Order any reflective report at Tutors India, we promise you the following
Plagiarism free
Always on Time
Outstanding customer support
Written to Standard
Unlimited Revisions support
High-quality Subject Matter Experts.
Contact:
Website: www.tutorsindia.com
Email: info@tutorsindia.com
United Kingdom: +44-1143520021
India: +91-4448137070
Whatsapp Number: +91-8754446690
Reference: http://bit.ly/2v6tBB6
A study of the constraints affecting the proper utilization of computer appli...eSAT Journals
Abstract
Construction is one of the area in which computer application software are highly required to perform different task at various stages of project construction. Computers have been used to enhance the effectiveness of construction management. Efficient utilization of computer application software is a key to enhancing the proper management of construction activities which will contribute to the successful implementation of construction project. Careful selection of computer application software is required by the construction companies for proper management of their resources. The difficulty about computerization especially with regard to the use of computer application software in resource management require the knowledge and expertise of those working in construction companies, and who are directly involved in the management of construction resources. The study was carried out to determine the obstacles confronting the proper utilization of computer application software in resource management. The result of the questionnaire survey used in this research work clearly indicated those constraints, which include, non-understanding about software potentials, lack of qualified personnel to use the software, unaware of most of the resource management software available in the market, communication gap between the vendors and users which contribute to non-understanding of the full scope of the software, greater-know-how required from staff, among numerous others. A total of 22 construction companies were selected for the study. An open ended questionnaire which consist of 22 questions with regard to the constraints affecting the proper utilization of computer application software in resource management was designed, validated, and distributed among Engineers, Project Managers, as well as executives who are directly involved in the activities of the construction site.
Keywords: resource management, application software, construction management
Large Planning is a general term that sets a clear road map that should be followed to reach a destination. The term, therefore, has been used at different levels to mean different things. Planning involves the breakdown of the project into definable, measurable, and identifiable tasks activities, and then establishes the logical interdependences among them. These plans involve four main steps Performing breakdown of work items involved in the project into activities. Identifying the proper sequence by which the activities should be executed. Activities representation. Estimating the resources, time, and cost of individual activities. Planning requires a rigorous effort by the planning team. A planner should know the different categories of work and be familiar with the terminology and knowledge used in general practice. Also, the planning tem should seek the opinion of experts including actual construction experience. This helps produce a realistic plan and avoids problems later on site. P. B. Sudha | Dr. K. Vidhya "Project Planning & Scheduling" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-4 | Issue-5 , August 2020, URL: https://www.ijtsrd.com/papers/ijtsrd31775.pdf Paper Url :https://www.ijtsrd.com/engineering/civil-engineering/31775/project-planning-and-scheduling/p-b-sudha
Planning is a guideline in implementing the project so that development can be
implemented in accordance with the time and cost planned. Control discrepancy
between initial plan and realization that exists in implementation project required a
project management, therefore required optimization analysis of project duration, so
it can be known how long a project is completed and look for the possibility of project
acceleration implementation by Project Evaluation and Review Technique (PERT)
and Critical Path Method (CPM) or critical path method. This research aims to apply
Project Evaluation and Review Technique (PERT) and Critical Project Management
(CPM) methods to find optimize solutions and control the performance of time and
cost in project scheduling. The research method used case study method at hospital
project in Bogor District, Indonesia, by collecting data direct observation and
interview results at contractor. Based on these data, create a schedule by using PERT
and CPM methods, which will be measured performance of time performance and
project cost which is expected to overcome the problem of controlling and completion
of project. The results of this study, using PERT and CPM methods proved to optimize
the project. Based on calculation by PERT method reduce duration of work: 12 days
(13, 18%). Based on calculation by CPM method reduce duration of work: 31 days
(34, 06%) but direct cost increase 112.208,300, - rupiahs (0, 25%).
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
Modern construction system has shown great potential in the field of the conventional construction system. The advantage of using new construction techniques for any type of construction is that the process takes no longer. The modern method of construction is defined as a way of working more effectively to achieve more while using less. The description lends itself heavily to offsite or modular construction techniques the method of prefabricating parts of building offsite before transporting and assembling them at their final location. Unlike traditional methods of construction is defined as a way of working more effectively. Poor construction management will cause the delay. Delay in the contracted project can result in penalties and adversely affect the reputation of the company. It is essential to manage the work within time. If construction time increases, construction cost also increases. It is necessary proper planning and management for construction work. Primavera p6 is a management tool. In this study primavera software help in the planning and scheduling of the project. Primavera gives better quality of project management process and easily understanding results. Shashwat Dubey | Prof. M. C. Paliwal "Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38641.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/38641/review-on-planning-and-scheduling-of-construction-project-by-management-tool-primavera-p6/shashwat-dubey
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
Construction scheduling is a complex and challenging task demanding an in depth
expertise. Consideration of several factors, their influences and likely impact on the
schedule need a thorough understanding. It is mostly experience based knowledge in
the form of heuristics, available with the experienced schedulers. In this connection
this study mainly discusses the factors influencing construction scheduling and
techniques through a comparative study of various international construction
projects. About 40 relevant articles published over the last 25 years have been
reviewed. However, each and every limited formalized knowledge is available in
theoretical form, which is interesting to many researchers for many decades, a
comprehensive research is made and a comparative study on the literatures was
carried out and presented in this paper. The main aim of the paper is to highlight the
major factors which are to be mainly considered for the successful completion of the
project.
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
Project planning is the important task in many areas like construction, resource allocation and many. A sequence of activities has to be performed to complete one task. Each activity has its unique processing time and all together to identify the critical activities which affect the completion of the project. In this paper the probabilistic and deterministic models to determine the project completion time and also the critical activities are considered. A case study on building construction project has been performed to demonstrate the application of the above said models. The two project scheduling namely PERT and CPM are used to determine numerically the different types of floating times of each activity and hence determined the critical path which plays an important role in the project completion time. Also a linear programing model has been developed to reduce the project completion time which optimize the resource allocation. To apply these techniques numerically the primary data from a housing project company in a metropolitan city has been taken, the network diagram of the activities involved in the building construction project has been drawn and the results are tabulated
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad