Any development undertaking regardless beginnings with the Layout of the structure or construction followed by Design and Analysis of the construction which is prevailing by cost assessment and making arrangements for the said project. This undertaking includes the format, plan, examination, arranging and cost assessment of a G 4 private structure situated in BicholiMardana, Indore. Primavera P6 has been utilized for arranging the different exercises that encompass the development of a structure. Utilizing primavera we had the option to detail a functioning timetable and furthermore an advancement bar for steady checking of the venture. Utilizing primavera we had the option to allot different assets just as obligations on different individuals identified with the different phases of the venture there by expanding responsibility. The term of the venture utilizing primavera has been determined to be around 374 days which likewise incorporates occasions. The advancement and the connection between different exercises has likewise been appeared as an enlivened Gantt Chart. This graph likewise helps the Project supervisor to disclose to his customers the different perspectives just as progress of the undertaking. The quote for the venture has been determined utilizing Center Line Method in Microsoft Excel. For the Abstract expense CPWD Schedule of rates has been followed and an absolute expense of Rs 5,733,000 has been determined. Nitin Mukesh Bhalla | Mr. Ravindra Raj "Planning, Scheduling and Allocation of Resources for Multi-storeyed Structure using Primevera Software" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-4 , June 2021, URL: https://www.ijtsrd.compapers/ijtsrd42599.pdf Paper URL: https://www.ijtsrd.comengineering/civil-engineering/42599/planning-scheduling-and-allocation-of-resources-for-multistoreyed-structure-using-primevera-software/nitin-mukesh-bhalla
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
This document discusses planning, scheduling, and allocating resources for a multi-storied residential building project using Oracle's Primavera P6 software. It begins with an abstract that outlines the importance of project management tools in the growing construction industry. It then provides background on project management, planning, scheduling, and the benefits of Primavera P6, which include quick scheduling, identifying floats and critical paths, customizable reports, and resource allocation. The document aims to demonstrate the advantages of using Primavera P6 for construction project management.
The document outlines the organization chart and role descriptions for an HRIS project team implementing a new HRIS system, including positions for a project manager, advisory board, procurement manager, user assistance manager, business analyst, platform technology leads, engineers, database administrator, quality assurance leads, and testers. Communication and stakeholder management plans are also discussed.
This document provides a project charter and plan for implementing a new HRIS system with employee self-service modules at GenRays. The project has 4 phases and will be implemented over 12 months. It aims to streamline HR processes, increase efficiencies, and improve employee satisfaction. Key deliverables include requirements documentation, vendor selection, system design and development, user training, and a post-implementation review. The project is funded at $103K and success will be measured by time savings, lower HR costs, and increased employee satisfaction once completed.
Software Project Management: ResearchColab- Budget (Document-12)
Presented in 4th year of Bachelor of Science in Software Engineering (BSSE) course at Institute of Information Technology, University of Dhaka (IIT, DU).
This document discusses project planning and scheduling. It begins by defining project planning as breaking down a project into definable tasks, establishing logical relationships between tasks, and estimating resources, time and costs required. The document then discusses several key aspects of project planning and scheduling including work breakdown structures, network diagrams, critical path analysis and scheduling techniques. It also discusses factors that affect project scheduling such as time, manpower and materials. The document concludes by emphasizing the importance of planning for successfully completing projects on time and within budget while meeting quality requirements.
Resource management involves functions like resource allocation, performance appraisal, and career planning. The presentation discussed a survey of resource management practices, recommendations for improving resource management, and examples from Westfield Insurance and American Greetings. The panel presentations described how those companies assign resources to projects, manage resource availability and workloads, and support career development.
Resource capacity planning guide - best practice, hints, tipsian jones
This document provides guidance on effective resource capacity planning. It defines resource capacity planning as comparing the supply of available resources to the demands placed on those resources. The benefits of proper resource capacity planning include cost savings, improved project throughput and resource morale. The process involves calculating resource supply and demand, identifying variances, and solving issues through actions like hiring or deferring projects. It should be incorporated into regular portfolio management and prioritize allocating resources to higher value work. Spreadsheets are commonly but problematically used for this task.
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
This document discusses planning, scheduling, resource allocation, tracking, and compression techniques for a residential villa project using Primavera P6 software. It begins by introducing the project - a G+2 residential villa. It then outlines the objectives of planning the work breakdown structure, scheduling activities and critical path, allocating resources, tracking progress against the baseline, and addressing delays through rescheduling and compression of critical activities. The methodology section explains the steps of planning, scheduling, resource allocation, tracking, and various techniques for overcoming delays like crashing and fast tracking critical paths. The document emphasizes the importance of proper project management techniques and use of scheduling software like Primavera P6.
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
This document discusses planning, scheduling, and allocating resources for a multi-storied residential building project using Oracle's Primavera P6 software. It begins with an abstract that outlines the importance of project management tools in the growing construction industry. It then provides background on project management, planning, scheduling, and the benefits of Primavera P6, which include quick scheduling, identifying floats and critical paths, customizable reports, and resource allocation. The document aims to demonstrate the advantages of using Primavera P6 for construction project management.
The document outlines the organization chart and role descriptions for an HRIS project team implementing a new HRIS system, including positions for a project manager, advisory board, procurement manager, user assistance manager, business analyst, platform technology leads, engineers, database administrator, quality assurance leads, and testers. Communication and stakeholder management plans are also discussed.
This document provides a project charter and plan for implementing a new HRIS system with employee self-service modules at GenRays. The project has 4 phases and will be implemented over 12 months. It aims to streamline HR processes, increase efficiencies, and improve employee satisfaction. Key deliverables include requirements documentation, vendor selection, system design and development, user training, and a post-implementation review. The project is funded at $103K and success will be measured by time savings, lower HR costs, and increased employee satisfaction once completed.
Software Project Management: ResearchColab- Budget (Document-12)
Presented in 4th year of Bachelor of Science in Software Engineering (BSSE) course at Institute of Information Technology, University of Dhaka (IIT, DU).
This document discusses project planning and scheduling. It begins by defining project planning as breaking down a project into definable tasks, establishing logical relationships between tasks, and estimating resources, time and costs required. The document then discusses several key aspects of project planning and scheduling including work breakdown structures, network diagrams, critical path analysis and scheduling techniques. It also discusses factors that affect project scheduling such as time, manpower and materials. The document concludes by emphasizing the importance of planning for successfully completing projects on time and within budget while meeting quality requirements.
Resource management involves functions like resource allocation, performance appraisal, and career planning. The presentation discussed a survey of resource management practices, recommendations for improving resource management, and examples from Westfield Insurance and American Greetings. The panel presentations described how those companies assign resources to projects, manage resource availability and workloads, and support career development.
Resource capacity planning guide - best practice, hints, tipsian jones
This document provides guidance on effective resource capacity planning. It defines resource capacity planning as comparing the supply of available resources to the demands placed on those resources. The benefits of proper resource capacity planning include cost savings, improved project throughput and resource morale. The process involves calculating resource supply and demand, identifying variances, and solving issues through actions like hiring or deferring projects. It should be incorporated into regular portfolio management and prioritize allocating resources to higher value work. Spreadsheets are commonly but problematically used for this task.
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
This document discusses planning, scheduling, resource allocation, tracking, and compression techniques for a residential villa project using Primavera P6 software. It begins by introducing the project - a G+2 residential villa. It then outlines the objectives of planning the work breakdown structure, scheduling activities and critical path, allocating resources, tracking progress against the baseline, and addressing delays through rescheduling and compression of critical activities. The methodology section explains the steps of planning, scheduling, resource allocation, tracking, and various techniques for overcoming delays like crashing and fast tracking critical paths. The document emphasizes the importance of proper project management techniques and use of scheduling software like Primavera P6.
This project charter outlines GenRays' plan to implement a new HRIS system. The goals are to improve efficiency, reduce costs, and better manage human resources as the company expands. Key deliverables include selecting a vendor, configuring the system, migrating data, training employees, and launching the new HRIS by the end of 2015. The project has a budget of $103,000 and is led by project manager Alan Oviatt. Upon successful completion, the new system is expected to save over $46,000 annually through reduced paperwork and improved access to employee information.
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
This document discusses planning and scheduling a multi-storied building construction project using Microsoft Project software. It begins with an abstract that outlines the objectives of studying scheduling methods for multi-story buildings and applying MS Project software to plan and schedule a hypothetical 7-story residential building. The document then provides background on the benefits of effective project planning and scheduling for reducing construction time and costs. It describes the key aspects and features of MS Project for developing schedules, assigning resources to tasks, tracking progress, managing budgets, and analyzing workloads. The methodology section outlines the steps for using MS Project to plan and schedule the hypothetical building project within time and resource constraints to complete it on schedule.
This presentation discusses managing project resources. It defines resources as sources of supply or support, including human and capital resources. Human resources include project team members and stakeholders. Capital resources are tools and infrastructure used to produce goods and services. The presentation covers estimating and managing resource needs, and techniques for developing project schedules based on resource availability like critical path analysis and schedule compression. The goal is to understand resource types, their importance, and how to apply tools to effectively manage resources and project time.
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
Modern construction system has shown great potential in the field of the conventional construction system. The advantage of using new construction techniques for any type of construction is that the process takes no longer. The modern method of construction is defined as a way of working more effectively to achieve more while using less. The description lends itself heavily to offsite or modular construction techniques the method of prefabricating parts of building offsite before transporting and assembling them at their final location. Unlike traditional methods of construction is defined as a way of working more effectively. Poor construction management will cause the delay. Delay in the contracted project can result in penalties and adversely affect the reputation of the company. It is essential to manage the work within time. If construction time increases, construction cost also increases. It is necessary proper planning and management for construction work. Primavera p6 is a management tool. In this study primavera software help in the planning and scheduling of the project. Primavera gives better quality of project management process and easily understanding results. Shashwat Dubey | Prof. M. C. Paliwal "Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38641.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/38641/review-on-planning-and-scheduling-of-construction-project-by-management-tool-primavera-p6/shashwat-dubey
Construction Project Scheduling of MK Apartment using MS Project 2013IRJET Journal
This document discusses scheduling and resource allocation for the construction of an MK apartment project using Microsoft Project 2013 software. It begins with an abstract that outlines the objectives of using project management tools to improve efficiency in the construction industry by controlling costs, schedules, and resources. It then provides background on project management and scheduling, describing the various steps involved in construction project planning. The document discusses the specific objectives of studying scheduling for the MK apartment construction project using MS Project 2013 to develop an activity schedule, allocate resources, and estimate time and costs. It reviews related literature on other construction project case studies using MS Project and concludes with an introduction to the MK apartment project.
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
This document discusses scheduling and labor management for a residential building project in Mysore, India using Primavera P6 project management software. It describes developing a schedule for construction activities over 4 months, assigning different types of labor to activities, and monitoring and tracking progress against the baseline schedule. The results show Gantt charts displaying the structured work schedule and resource sheet assigning laborers. Tracking compares planned versus actual work, helping control the project to finish on time. In conclusion, Primavera software effectively plans, schedules, and monitors construction projects for optimized labor management and productivity.
IRJET- An Overview on Project ManagementIRJET Journal
This document provides an overview of project management. It discusses the importance of planning, scheduling, and controlling projects. Project planning involves defining objectives, tasks, resource requirements, and cost and duration estimates. Scheduling allocates resources and time to complete activities. Controlling establishes standards, measures performance, and identifies deviations to implement corrective actions. Project management techniques like bar charts, milestone charts, and network diagrams help define work, estimate schedules and costs, and identify potential delays. Proper planning, scheduling, and controlling of projects is necessary for their successful completion.
Project Management Leadership, And Skills : Planning And Control | Assignment...Emre Dirlik
This document discusses planning and control in project management, leadership, and skills. It covers three main parts: network diagrams and critical path analysis, risk analysis and opportunities, and motivation management. In part A, a network diagram of the house renovation project is presented showing the critical path. In part B, risks like cost increases, supply issues, and workforce shortages are analyzed. Risk scores are assigned based on probability and impact. Part C discusses motivation theories as they relate to an unmotivated team member, Kevin, and how removing him from the project could benefit the team and project goals.
The document discusses a framework for assessing and planning complementary soft skills for project teams. It identifies three dimensions to consider: project environment, project type, and project role. Different environmental factors, project types, and roles require different soft skill priorities. The framework provides guidance on determining critical soft skills based on these dimensions. An example case study shows how a project manager used the framework to identify soft skill gaps contributing to project issues. Addressing these gaps through an action plan helped improve team morale and client satisfaction.
This document discusses delay analysis in construction projects. It defines delay as exceeding the planned completion date of a project. Delay can increase costs and negatively impact other tasks. Project management software like Microsoft Project can help track task start and end dates to analyze causes of delay. The document outlines objectives of project management, including completing projects on time and on budget. It also discusses using tools like time sheets for time management and tracking costs. Quality management and risk management are also important aspects of ensuring project success. Overall, the key is properly planning, scheduling, and monitoring tasks to minimize delays.
The document discusses project management at Essar Steel in Hazira, India. It provides background on project management and planning. Essar Steel produces hot briquetted iron, hot rolled coils, and iron plates from raw materials imported via cargo ships. Essar schedules projects through lateral communication between levels, equal task distribution without bias, and a focus on efficiency, relationships, and customer satisfaction following 5S principles. This approach helps Essar achieve success as one of the leading project managers in the steel industry.
The team charter establishes CGR IT Consulting Partners to complete the INFO 461 course project over 5 weeks. Team members are Charles Harrill, Gregory Eskridge, and Ruxandra Zait. Charles will initially lead but leadership will rotate. Strengths include Microsoft Project/Visio skills and academic achievement. Challenges are scheduling face-to-face meetings but they will use online tools. Roles include Charles integrating submissions, Gregory creating Project artifacts and presentations, and Ruxandra creating Visio diagrams and ensuring quality. They will collaborate and adjust roles based on assignment scope.
The document summarizes the roles and responsibilities of various team members in the Project Prosalo. It discusses the role of the Project Controller in developing the project schedule, estimating costs and monitoring progress. Key aspects covered include defining the project lifecycle and milestones, establishing a work breakdown structure, developing a project cost baseline, and employing bottom-up cost estimation. The Project Controller reflects on the importance of using scientific methodology and analytical skills to plan, monitor and control the project budget and schedule.
This presentation covers business English vocabulary related to projects and project management. Visit www.BusinessEnglishPod.com to view the video version of this presentation.
This Project Management Presentation was made for the Ateneo Graduate School of Business (AGSB) Middle Managers Operations Management Class, Semester 1 of 2011.
This document discusses project planning and scheduling for the construction of a residential building. It provides an overview of the project, which involves constructing a G+1 building of approximately 1100 square feet in Shahnoorwadi, India. It describes collecting project data, using the Primavera Project Planner software to develop a network diagram and schedule, and generating reports to analyze the critical path of the project. The objectives are to prepare a CPM chart for the building and gain experience using the Primavera scheduling tool.
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...IRJET Journal
The document discusses scheduling and monitoring of work progress for Reach 2B of the Bangalore Metro Rail Corporation Limited (BMRCL) project from Pier 573 to Pier 735 using Primavera P6 software. It outlines the objectives, literature review, scheduling methodology, and analysis of piling work for some sample piers. The scheduling process in Primavera P6 involves creating activities, assigning durations, updating plans based on progress, and rescheduling delayed activities. The analysis examines activity times for different steps of the piling work and presents data on time taken for individual activities at different project locations.
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
This document discusses planning and scheduling a residential construction project using Microsoft Project. It summarizes the key steps:
1) The activities of constructing two residential blocks were planned and scheduled in MSP, including allocating resources, determining task relationships, and generating a Gantt chart.
2) The total baseline duration of the project was estimated to be 632 days with a total cost of Rs. 154,394,081.
3) Planning and scheduling the project in MSP allowed determining the critical path and monitoring project progress and costs.
Enterprise Project Management using Primavera P6 EPPMIRJET Journal
This document summarizes the use of Primavera P6 Enterprise Project Portfolio Management (EPPM) software for project management. It outlines the key benefits of using Primavera P6, which include reducing errors, optimizing resource allocation, improved visibility, forecasting, tracking, and collaboration capabilities. The document then describes the 20 step process for using Primavera P6, including creating a work breakdown structure, defining activities and durations, assigning relationships between activities, allocating resources, tracking progress, and updating the schedule as needed. The overall purpose is to understand how to plan, schedule and manage projects efficiently using the Primavera P6 project management software.
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
This document discusses planning, scheduling, and optimizing labor resources for the construction of a residential apartment building using Primavera P6 software. It describes how the software was used to plan and schedule each activity through critical path method. To address potential lack of required labor resources, labor resource leveling, smoothing, and overtime working techniques were used to optimize resource allocation. Using these techniques, the total project duration was changed from 935 days to 1011 days with leveling, remained at 935 days with smoothing, and was reduced to 748 days with overtime working, all while maintaining the total labor units and completing the project on schedule.
This project charter outlines GenRays' plan to implement a new HRIS system. The goals are to improve efficiency, reduce costs, and better manage human resources as the company expands. Key deliverables include selecting a vendor, configuring the system, migrating data, training employees, and launching the new HRIS by the end of 2015. The project has a budget of $103,000 and is led by project manager Alan Oviatt. Upon successful completion, the new system is expected to save over $46,000 annually through reduced paperwork and improved access to employee information.
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
This document discusses planning and scheduling a multi-storied building construction project using Microsoft Project software. It begins with an abstract that outlines the objectives of studying scheduling methods for multi-story buildings and applying MS Project software to plan and schedule a hypothetical 7-story residential building. The document then provides background on the benefits of effective project planning and scheduling for reducing construction time and costs. It describes the key aspects and features of MS Project for developing schedules, assigning resources to tasks, tracking progress, managing budgets, and analyzing workloads. The methodology section outlines the steps for using MS Project to plan and schedule the hypothetical building project within time and resource constraints to complete it on schedule.
This presentation discusses managing project resources. It defines resources as sources of supply or support, including human and capital resources. Human resources include project team members and stakeholders. Capital resources are tools and infrastructure used to produce goods and services. The presentation covers estimating and managing resource needs, and techniques for developing project schedules based on resource availability like critical path analysis and schedule compression. The goal is to understand resource types, their importance, and how to apply tools to effectively manage resources and project time.
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
Modern construction system has shown great potential in the field of the conventional construction system. The advantage of using new construction techniques for any type of construction is that the process takes no longer. The modern method of construction is defined as a way of working more effectively to achieve more while using less. The description lends itself heavily to offsite or modular construction techniques the method of prefabricating parts of building offsite before transporting and assembling them at their final location. Unlike traditional methods of construction is defined as a way of working more effectively. Poor construction management will cause the delay. Delay in the contracted project can result in penalties and adversely affect the reputation of the company. It is essential to manage the work within time. If construction time increases, construction cost also increases. It is necessary proper planning and management for construction work. Primavera p6 is a management tool. In this study primavera software help in the planning and scheduling of the project. Primavera gives better quality of project management process and easily understanding results. Shashwat Dubey | Prof. M. C. Paliwal "Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38641.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/38641/review-on-planning-and-scheduling-of-construction-project-by-management-tool-primavera-p6/shashwat-dubey
Construction Project Scheduling of MK Apartment using MS Project 2013IRJET Journal
This document discusses scheduling and resource allocation for the construction of an MK apartment project using Microsoft Project 2013 software. It begins with an abstract that outlines the objectives of using project management tools to improve efficiency in the construction industry by controlling costs, schedules, and resources. It then provides background on project management and scheduling, describing the various steps involved in construction project planning. The document discusses the specific objectives of studying scheduling for the MK apartment construction project using MS Project 2013 to develop an activity schedule, allocate resources, and estimate time and costs. It reviews related literature on other construction project case studies using MS Project and concludes with an introduction to the MK apartment project.
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
This document discusses scheduling and labor management for a residential building project in Mysore, India using Primavera P6 project management software. It describes developing a schedule for construction activities over 4 months, assigning different types of labor to activities, and monitoring and tracking progress against the baseline schedule. The results show Gantt charts displaying the structured work schedule and resource sheet assigning laborers. Tracking compares planned versus actual work, helping control the project to finish on time. In conclusion, Primavera software effectively plans, schedules, and monitors construction projects for optimized labor management and productivity.
IRJET- An Overview on Project ManagementIRJET Journal
This document provides an overview of project management. It discusses the importance of planning, scheduling, and controlling projects. Project planning involves defining objectives, tasks, resource requirements, and cost and duration estimates. Scheduling allocates resources and time to complete activities. Controlling establishes standards, measures performance, and identifies deviations to implement corrective actions. Project management techniques like bar charts, milestone charts, and network diagrams help define work, estimate schedules and costs, and identify potential delays. Proper planning, scheduling, and controlling of projects is necessary for their successful completion.
Project Management Leadership, And Skills : Planning And Control | Assignment...Emre Dirlik
This document discusses planning and control in project management, leadership, and skills. It covers three main parts: network diagrams and critical path analysis, risk analysis and opportunities, and motivation management. In part A, a network diagram of the house renovation project is presented showing the critical path. In part B, risks like cost increases, supply issues, and workforce shortages are analyzed. Risk scores are assigned based on probability and impact. Part C discusses motivation theories as they relate to an unmotivated team member, Kevin, and how removing him from the project could benefit the team and project goals.
The document discusses a framework for assessing and planning complementary soft skills for project teams. It identifies three dimensions to consider: project environment, project type, and project role. Different environmental factors, project types, and roles require different soft skill priorities. The framework provides guidance on determining critical soft skills based on these dimensions. An example case study shows how a project manager used the framework to identify soft skill gaps contributing to project issues. Addressing these gaps through an action plan helped improve team morale and client satisfaction.
This document discusses delay analysis in construction projects. It defines delay as exceeding the planned completion date of a project. Delay can increase costs and negatively impact other tasks. Project management software like Microsoft Project can help track task start and end dates to analyze causes of delay. The document outlines objectives of project management, including completing projects on time and on budget. It also discusses using tools like time sheets for time management and tracking costs. Quality management and risk management are also important aspects of ensuring project success. Overall, the key is properly planning, scheduling, and monitoring tasks to minimize delays.
The document discusses project management at Essar Steel in Hazira, India. It provides background on project management and planning. Essar Steel produces hot briquetted iron, hot rolled coils, and iron plates from raw materials imported via cargo ships. Essar schedules projects through lateral communication between levels, equal task distribution without bias, and a focus on efficiency, relationships, and customer satisfaction following 5S principles. This approach helps Essar achieve success as one of the leading project managers in the steel industry.
The team charter establishes CGR IT Consulting Partners to complete the INFO 461 course project over 5 weeks. Team members are Charles Harrill, Gregory Eskridge, and Ruxandra Zait. Charles will initially lead but leadership will rotate. Strengths include Microsoft Project/Visio skills and academic achievement. Challenges are scheduling face-to-face meetings but they will use online tools. Roles include Charles integrating submissions, Gregory creating Project artifacts and presentations, and Ruxandra creating Visio diagrams and ensuring quality. They will collaborate and adjust roles based on assignment scope.
The document summarizes the roles and responsibilities of various team members in the Project Prosalo. It discusses the role of the Project Controller in developing the project schedule, estimating costs and monitoring progress. Key aspects covered include defining the project lifecycle and milestones, establishing a work breakdown structure, developing a project cost baseline, and employing bottom-up cost estimation. The Project Controller reflects on the importance of using scientific methodology and analytical skills to plan, monitor and control the project budget and schedule.
This presentation covers business English vocabulary related to projects and project management. Visit www.BusinessEnglishPod.com to view the video version of this presentation.
This Project Management Presentation was made for the Ateneo Graduate School of Business (AGSB) Middle Managers Operations Management Class, Semester 1 of 2011.
This document discusses project planning and scheduling for the construction of a residential building. It provides an overview of the project, which involves constructing a G+1 building of approximately 1100 square feet in Shahnoorwadi, India. It describes collecting project data, using the Primavera Project Planner software to develop a network diagram and schedule, and generating reports to analyze the critical path of the project. The objectives are to prepare a CPM chart for the building and gain experience using the Primavera scheduling tool.
Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to ...IRJET Journal
The document discusses scheduling and monitoring of work progress for Reach 2B of the Bangalore Metro Rail Corporation Limited (BMRCL) project from Pier 573 to Pier 735 using Primavera P6 software. It outlines the objectives, literature review, scheduling methodology, and analysis of piling work for some sample piers. The scheduling process in Primavera P6 involves creating activities, assigning durations, updating plans based on progress, and rescheduling delayed activities. The analysis examines activity times for different steps of the piling work and presents data on time taken for individual activities at different project locations.
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
This document discusses planning and scheduling a residential construction project using Microsoft Project. It summarizes the key steps:
1) The activities of constructing two residential blocks were planned and scheduled in MSP, including allocating resources, determining task relationships, and generating a Gantt chart.
2) The total baseline duration of the project was estimated to be 632 days with a total cost of Rs. 154,394,081.
3) Planning and scheduling the project in MSP allowed determining the critical path and monitoring project progress and costs.
Enterprise Project Management using Primavera P6 EPPMIRJET Journal
This document summarizes the use of Primavera P6 Enterprise Project Portfolio Management (EPPM) software for project management. It outlines the key benefits of using Primavera P6, which include reducing errors, optimizing resource allocation, improved visibility, forecasting, tracking, and collaboration capabilities. The document then describes the 20 step process for using Primavera P6, including creating a work breakdown structure, defining activities and durations, assigning relationships between activities, allocating resources, tracking progress, and updating the schedule as needed. The overall purpose is to understand how to plan, schedule and manage projects efficiently using the Primavera P6 project management software.
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
This document discusses planning, scheduling, and optimizing labor resources for the construction of a residential apartment building using Primavera P6 software. It describes how the software was used to plan and schedule each activity through critical path method. To address potential lack of required labor resources, labor resource leveling, smoothing, and overtime working techniques were used to optimize resource allocation. Using these techniques, the total project duration was changed from 935 days to 1011 days with leveling, remained at 935 days with smoothing, and was reduced to 748 days with overtime working, all while maintaining the total labor units and completing the project on schedule.
This document discusses planning and scheduling a residential construction project using Primavera software. The main goals of the project are to study the basics of Primavera, select a residential building plan, estimate quantities, schedule activities, create a work breakdown structure, budget the project, and generate reports. Primavera is a project management tool that uses critical path methodology to calculate activity durations and floats. It has Gantt chart views to display the project schedule. The document defines key terms like project, activity, resource, and time and cost parameters that can be measured using planning software. It also describes the project life cycle and monitoring process to ensure the project stays on schedule and budget.
This document discusses planning and scheduling a residential construction project using Primavera project management software. It begins with an introduction to project management challenges in the construction industry like delays and cost overruns. The methodology section outlines the steps taken: studying the site, creating an actual schedule in Primavera, identifying constraints, reducing constraints, and optimizing labor resources. Two modified schedules are presented that interconnect activities properly and increase resources to reduce the project duration by 5-7 months compared to the actual schedule. The results analyze schedule improvements and reduced costs. It concludes that Primavera helps manage work, reduce risks, and ensure successful project completion on time and within budget.
How To Develop A Project Management PlanOrangescrum
For project managers, a successful outcome is always preceded by a well-prepared project management plan. A lot of effort is put into planning which helps you prepare a better Project Management Plan.
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
This document summarizes a study that planned and scheduled the construction of a multi-story residential building using Microsoft Project software and applied material management techniques. The study categorized building materials using ABC analysis to prioritize those with the greatest cost impact. Scheduling the project in Microsoft Project and analyzing material usage helped optimize costs and duration to increase construction efficiency. Applying material management principles such as inventory control and efficient procurement supported timely material availability and reduced waste.
IRJET- Portfolio Management of Multiple Building Projects using EPPMIRJET Journal
This document discusses portfolio management of multiple building construction projects using Primavera EPPM P6v16.1 software. It analyzes 4 commercial building projects, calculating quantities and scheduling activities. The projects were planned, scheduled and baseline budgets created in Primavera P6. A portfolio of the projects was then prepared to evaluate cash flow, optimize resource use, reduce warehousing and administrative costs. Prior research on using Primavera P6 for project planning, scheduling and monitoring is also reviewed. The objective is to develop the project portfolio and analyze cash flow using the Primavera software.
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
This document summarizes a case study on planning and scheduling two construction blocks of a government housing project in Bhopal, India using Primavera P6 software. The study compares Block A and Block B to identify reasons for delays. Primavera P6 was used to develop schedules, assign resources, and conduct financial risk analysis. Key planning methods discussed include Gantt charts, network scheduling, and work breakdown structures. Scheduling and resource allocation steps are outlined. The case study aims to demonstrate the benefits of using project management software for planning, monitoring, and controlling large infrastructure projects.
This document is a project report for a Gas Inventory Management System created by four students at Jawahar Navodaya Vidyalaya Rajgarh in Madhya Pradesh, India. It includes an introduction to the project, objectives, proposed system description, phases of the system development life cycle used (initiation, concept development, requirements analysis, design, development, integration and testing, implementation, and operations/maintenance). It also includes sections on flowchart, source code, outputs, and hardware/software requirements. The project was created for a Computer Science class and guided by their teacher, Mr. Anil Kant.
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
This document discusses the implementation of the Last Planner System (LPS) in construction projects. It begins with an introduction to lean construction and LPS. The LPS aims to improve project planning and control through short-term planning. It breaks down work into smaller packages and activities and encourages commitment from foremen. The document then discusses the various components of LPS in detail - master planning, phase scheduling, look-ahead planning, weekly work plans, and percentage plan complete. Various tools used for LPS implementation are also explained, including constraints analysis boards, Pareto charts, and commitment monitoring boards. The objective is to study LPS concepts and apply it on a case study to improve labour productivity, minimize time and cost, and achieve reliable workflow.
The document summarizes time and schedule management using Primavera project management software. It discusses how Primavera allows project managers to plan schedules, allocate resources, track progress, and justify project timelines and budgets to management. The document also provides an example of using Primavera to plan and track the schedule for a 140-unit housing project in Libya over 535 days, with progress updates to ensure the project stays on schedule. Primavera is presented as a useful tool for project managers to model schedules, account for risks and uncertainties, and help complete projects on time and on budget.
Resource Optimization in Construction of a Residential Apartment using Primav...IRJET Journal
This document discusses using Primavera P6 software to optimize resource allocation for a residential apartment construction project in India. It begins by explaining the importance of effective resource management for construction projects and challenges related to large-scale projects. The methodology section outlines how the study was conducted in Primavera P6, including collecting project data, assigning resources and durations to activities, identifying overallocated resources, and leveling resources using different optimization probabilities. As a case study, a G+2 residential apartment project is modeled in Primavera P6. Leveling probability 4 is found to best optimize labor resources like masons and mason helpers without extending the project duration. Charts show overallocation before and after leveling
The document discusses various project management methodologies including Waterfall, Agile, Scrum, Kanban, and Critical Path Method (CPM). It provides descriptions of how each methodology works, when it should be used, advantages and disadvantages. The Critical Path Method in particular aims to identify the longest sequence of dependent tasks in a project in order to minimize the overall project duration.
The document discusses various aspects of project planning and management including:
1. The planning process which involves project identification, formulation, and preparation including market analysis, technical factors, and project appraisal.
2. Methods of project budgeting, cost estimation, and risk management.
3. Tools used in project planning such as the work breakdown structure, scheduling, budgeting, and forecasting.
4. The importance of market analysis and demand forecasting in the planning process.
The key steps in the PERT planning process are:
1) Identifying the specific activities and milestones of the project.
2) Determining the proper sequence of activities by constructing a network diagram that shows the interdependencies.
3) Estimating the time required to complete each activity.
4) Identifying the critical path which is the longest sequence of activities that determines the minimum time to complete the project.
Primavera P6.0 is a project management software that provides tools for planning, scheduling, resource allocation, monitoring and controlling projects. Some key features include an Organizational Breakdown Structure (OBS) that represents the project management hierarchy, an Enterprise Project Structure (EPS) to organize projects across an organization, unlimited baselines for comparison, and enhanced calendar capabilities. Primavera P6.0 offers a centralized database for collaborative project planning and increased efficiency of project management.
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
Planning and scheduling have become an essential part of any project for the timely and economical completion of the project. A proper construction schedule can be used for different purposes. By using construction schedule to predict project completion, contractors can adjust crew size, shifts or equipment to speed or slow the progress. All the construction projects will vary from each other in size. All the projects have time constraint. Delay in completion of project will increase the overall cost of the project. Small projects can be managed efficiently manually; whereas large projects are not so large projects can be better handled by the use of computers. Many types of software are available with the help of which project management can be done easily. Large quantities of different kinds of resources are also required for execution and the risk is more in the case of projects. So planning and scheduling of activities for construction of big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis updating of various activities, which is done by using MS Project and MS Excel software, manpower of each activity is determined and allocation is done using the software. Labor requirement for each activity is calculated from standards obtained from site. An updated schedule, which helps to finish the project well in time with optimum resources and update helps in delay analysis, is under the scope of this study.
Similar to Planning, Scheduling and Allocation of Resources for Multi storeyed Structure using Primevera Software (20)
‘Six Sigma Technique’ A Journey Through its Implementationijtsrd
The manufacturing industries all over the world are facing tough challenges for growth, development and sustainability in today’s competitive environment. They have to achieve apex position by adapting with the global competitive environment by delivering goods and services at low cost, prime quality and better price to increase wealth and consumer satisfaction. Cost Management ensures profit, growth and sustainability of the business with implementation of Continuous Improvement Technique like Six Sigma. This leads to optimize Business performance. The method drives for customer satisfaction, low variation, reduction in waste and cycle time resulting into a competitive advantage over other industries which did not implement it. The main objective of this paper ‘Six Sigma Technique A Journey Through Its Implementation’ is to conceptualize the effectiveness of Six Sigma Technique through the journey of its implementation. Aditi Sunilkumar Ghosalkar "‘Six Sigma Technique’: A Journey Through its Implementation" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64546.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64546/‘six-sigma-technique’-a-journey-through-its-implementation/aditi-sunilkumar-ghosalkar
Edge Computing in Space Enhancing Data Processing and Communication for Space...ijtsrd
Edge computing, a paradigm that involves processing data closer to its source, has gained significant attention for its potential to revolutionize data processing and communication in space missions. With the increasing complexity and data volume generated by modern space missions, traditional centralized computing approaches face challenges related to latency, bandwidth, and security. Edge computing in space, involving on board processing and analysis of data, offers promising solutions to these challenges. This paper explores the concept of edge computing in space, its benefits, applications, and future prospects in enhancing space missions. Manish Verma "Edge Computing in Space: Enhancing Data Processing and Communication for Space Missions" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64541.pdf Paper Url: https://www.ijtsrd.com/computer-science/artificial-intelligence/64541/edge-computing-in-space-enhancing-data-processing-and-communication-for-space-missions/manish-verma
Dynamics of Communal Politics in 21st Century India Challenges and Prospectsijtsrd
Communal politics in India has evolved through centuries, weaving a complex tapestry shaped by historical legacies, colonial influences, and contemporary socio political transformations. This research comprehensively examines the dynamics of communal politics in 21st century India, emphasizing its historical roots, socio political dynamics, economic implications, challenges, and prospects for mitigation. The historical perspective unravels the intricate interplay of religious identities and power dynamics from ancient civilizations to the impact of colonial rule, providing insights into the evolution of communalism. The socio political dynamics section delves into the contemporary manifestations, exploring the roles of identity politics, socio economic disparities, and globalization. The economic implications section highlights how communal politics intersects with economic issues, perpetuating disparities and influencing resource allocation. Challenges posed by communal politics are scrutinized, revealing multifaceted issues ranging from social fragmentation to threats against democratic values. The prospects for mitigation present a multifaceted approach, incorporating policy interventions, community engagement, and educational initiatives. The paper conducts a comparative analysis with international examples, identifying common patterns such as identity politics and economic disparities. It also examines unique challenges, emphasizing Indias diverse religious landscape, historical legacy, and secular framework. Lessons for effective strategies are drawn from international experiences, offering insights into inclusive policies, interfaith dialogue, media regulation, and global cooperation. By scrutinizing historical epochs, contemporary dynamics, economic implications, and international comparisons, this research provides a comprehensive understanding of communal politics in India. The proposed strategies for mitigation underscore the importance of a holistic approach to foster social harmony, inclusivity, and democratic values. Rose Hossain "Dynamics of Communal Politics in 21st Century India: Challenges and Prospects" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64528.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/history/64528/dynamics-of-communal-politics-in-21st-century-india-challenges-and-prospects/rose-hossain
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...ijtsrd
Background and Objective Telehealth has become a well known tool for the delivery of health care in Saudi Arabia, and the perspective and knowledge of healthcare providers are influential in the implementation, adoption and advancement of the method. This systematic review was conducted to examine the current literature base regarding telehealth and the related healthcare professional perspective and knowledge in the Kingdom of Saudi Arabia. Materials and Methods This systematic review was conducted by searching 7 databases including, MEDLINE, CINHAL, Web of Science, Scopus, PubMed, PsycINFO, and ProQuest Central. Studies on healthcare practitioners telehealth knowledge and perspectives published in English in Saudi Arabia from 2000 to 2023 were included. Boland directed this comprehensive review. The researchers examined each connected study using the AXIS tool, which evaluates cross sectional systematic reviews. Narrative synthesis was used to summarise and convey the data. Results Out of 1840 search results, 10 studies were included. Positive outlook and limited knowledge among providers were seen across trials. Healthcare professionals like telehealth for its ability to improve quality, access, and delivery, save time and money, and be successful. Age, gender, occupation, and work experience also affect health workers knowledge. In Saudi Arabia, healthcare professionals face inadequate expert assistance, patient privacy, internet connection concerns, lack of training courses, lack of telehealth understanding, and high costs while performing telemedicine. Conclusions Healthcare practitioners telehealth perceptions and knowledge were examined in this systematic study. Its collection of concerned experts different personal attitudes and expertise would help enhance telehealths implementation in Saudi Arabia, develop its healthcare delivery alternative, and eliminate frequent problems. Badriah Mousa I Mulayhi | Dr. Jomin George | Judy Jenkins "Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in Saudi Arabia: A Systematic Review" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64535.pdf Paper Url: https://www.ijtsrd.com/medicine/other/64535/assess-perspective-and-knowledge-of-healthcare-providers-towards-elehealth-in-saudi-arabia-a-systematic-review/badriah-mousa-i-mulayhi
The Impact of Digital Media on the Decentralization of Power and the Erosion ...ijtsrd
The impact of digital media on the distribution of power and the weakening of traditional gatekeepers has gained considerable attention in recent years. The adoption of digital technologies and the internet has resulted in declining influence and power for traditional gatekeepers such as publishing houses and news organizations. Simultaneously, digital media has facilitated the emergence of new voices and players in the media industry. Digital medias impact on power decentralization and gatekeeper erosion is visible in several ways. One significant aspect is the democratization of information, which enables anyone with an internet connection to publish and share content globally, leading to citizen journalism and bypassing traditional gatekeepers. Another aspect is the disruption of conventional media industry business models, as traditional organizations struggle to adjust to the decrease in advertising revenue and the rise of digital platforms. Alternative business models, such as subscription models and crowdfunding, have become more prevalent, leading to the emergence of new players. Overall, the impact of digital media on the distribution of power and the weakening of traditional gatekeepers has brought about significant changes in the media landscape and the way information is shared. Further research is required to fully comprehend the implications of these changes and their impact on society. Dr. Kusum Lata "The Impact of Digital Media on the Decentralization of Power and the Erosion of Traditional Gatekeepers" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64544.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/political-science/64544/the-impact-of-digital-media-on-the-decentralization-of-power-and-the-erosion-of-traditional-gatekeepers/dr-kusum-lata
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...ijtsrd
This research investigates the nexus between online discussions on Dr. B.R. Ambedkars ideals and their impact on social inclusion among college students in Gurugram, Haryana. Surveying 240 students from 12 government colleges, findings indicate that 65 actively engage in online discussions, with 80 demonstrating moderate to high awareness of Ambedkars ideals. Statistically significant correlations reveal that higher online engagement correlates with increased awareness p 0.05 and perceived social inclusion. Variations across colleges and a notable effect of college type on perceived social inclusion highlight the influence of contextual factors. Furthermore, the intersectional analysis underscores nuanced differences based on gender, caste, and socio economic status. Dr. Kusum Lata "Online Voices, Offline Impact: Ambedkar's Ideals and Socio-Political Inclusion - A Study of Gurugram District" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64543.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/political-science/64543/online-voices-offline-impact-ambedkars-ideals-and-sociopolitical-inclusion--a-study-of-gurugram-district/dr-kusum-lata
Problems and Challenges of Agro Entreprenurship A Studyijtsrd
Noting calls for contextualizing Agro entrepreneurs problems and challenges of the agro entrepreneurs and for greater attention to the Role of entrepreneurs in agro entrepreneurship research, we conduct a systematic literature review of extent research in agriculture entrepreneurship to overcome the study objectives of complications of agro entrepreneurs through various factors, Development of agriculture products is a key factor for the overall economic growth of agro entrepreneurs Agro Entrepreneurs produces firsthand large scale employment, utilizes the labor and natural resources, This research outlines the problems of Weather and Soil Erosions, Market price fluctuation, stimulates labor cost problems, reduces concentration of Price volatility, Dependency on Intermediaries, induces Limited Bargaining Power, and Storage and Transportation Costs. This paper mainly devoted to highlight Problems and challenges faced for the sustainable of Agro Entrepreneurs in India. Vinay Prasad B "Problems and Challenges of Agro Entreprenurship - A Study" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64540.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64540/problems-and-challenges-of-agro-entreprenurship--a-study/vinay-prasad-b
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...ijtsrd
Disclosure is a process through which a business enterprise communicates with external parties. A corporate disclosure is communication of financial and non financial information of the activities of a business enterprise to the interested entities. Corporate disclosure is done through publishing annual reports. So corporate disclosure through annual reports plays a vital role in the life of all the companies and provides valuable information to investors. The basic objectives of corporate disclosure is to give a true and fair view of companies to the parties related either directly or indirectly like owner, government, creditors, shareholders etc. in the companies act, provisions have been made about mandatory and voluntary disclosure. The IT sector in India is rapidly growing, the trend to invest in the IT sector is rising and employment opportunities in IT sectors are also increasing. Therefore the IT sector is expected to have fair, full and adequate disclosure of all information. Unfair and incomplete disclosure may adversely affect the entire economy. A research study on disclosure practices of IT companies could play an important role in this regard. Hence, the present research study has been done to study and review comparative analysis of total corporate disclosure of selected IT companies of India and to put forward overall findings and suggestions with a view to increase disclosure score of these companies. The researcher hopes that the present research study will be helpful to all selected Companies for improving level of corporate disclosure through annual reports as well as the government, creditors, investors, all business organizations and upcoming researcher for comparative analyses of level of corporate disclosure with special reference to selected IT companies. Dr. Vaibhavi D. Thaker "Comparative Analysis of Total Corporate Disclosure of Selected IT Companies of India" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64539.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64539/comparative-analysis-of-total-corporate-disclosure-of-selected-it-companies-of-india/dr-vaibhavi-d-thaker
The Impact of Educational Background and Professional Training on Human Right...ijtsrd
This study investigated the impact of educational background and professional training on human rights awareness among secondary school teachers in the Marathwada region of Maharashtra, India. The key findings reveal that higher levels of education, particularly a master’s degree, and fields of study related to education, humanities, or social sciences are associated with greater human rights awareness among teachers. Additionally, both pre service teacher training and in service professional development programs focused on human rights education significantly enhance teacher’s knowledge, skills, and competencies in promoting human rights principles in their classrooms. Baig Ameer Bee Mirza Abdul Aziz | Dr. Syed Azaz Ali Amjad Ali "The Impact of Educational Background and Professional Training on Human Rights Awareness among Secondary School Teachers" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64529.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/64529/the-impact-of-educational-background-and-professional-training-on-human-rights-awareness-among-secondary-school-teachers/baig-ameer-bee-mirza-abdul-aziz
A Study on the Effective Teaching Learning Process in English Curriculum at t...ijtsrd
“One Language sets you in a corridor for life. Two languages open every door along the way” Frank Smith English as a foreign language or as a second language has been ruling in India since the period of Lord Macaulay. But the question is how much we teach or learn English properly in our culture. Is there any scope to use English as a language rather than a subject How much we learn or teach English without any interference of mother language specially in the classroom teaching learning scenario in West Bengal By considering all these issues the researcher has attempted in this article to focus on the effective teaching learning process comparing to other traditional strategies in the field of English curriculum at the secondary level to investigate whether they fulfill the present teaching learning requirements or not by examining the validity of the present curriculum of English. The purpose of this study is to focus on the effectiveness of the systematic, scientific, sequential and logical transaction of the course between the teachers and the learners in the perspective of the 5Es programme that is engage, explore, explain, extend and evaluate. Sanchali Mondal | Santinath Sarkar "A Study on the Effective Teaching Learning Process in English Curriculum at the Secondary Level of West Bengal" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd62412.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/62412/a-study-on-the-effective-teaching-learning-process-in-english-curriculum-at-the-secondary-level-of-west-bengal/sanchali-mondal
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...ijtsrd
This paper reports on a study which was conducted to investigate the role of mentoring and its influence on the effectiveness of the teaching of Physics in secondary schools in the South West Region of Cameroon. The study adopted the convergent parallel mixed methods design, focusing on respondents in secondary schools in the South West Region of Cameroon. Both quantitative and qualitative data were collected, analysed separately, and the results were compared to see if the findings confirm or disconfirm each other. The quantitative analysis found that majority of the respondents 72 of Physics teachers affirmed that they had more experienced colleagues as mentors to help build their confidence, improve their teaching, and help them improve their effectiveness and efficiency in guiding learners’ achievements. Only 28 of the respondents disagreed with these statements. With majority respondents 72 agreeing with the statements, it implies that in most secondary schools, experienced Physics teachers act as mentors to build teachers’ confidence in teaching and improving students’ learning. The interview qualitative data analysis summarized how secondary school Principals use meetings with mentors and mentees to promote mentorship in the school milieu. This has helped strengthen teachers’ classroom practices in secondary schools in the South West Region of Cameroon. With the results confirming each other, the study recommends that mentoring should focus on helping teachers employ social interactions and instructional practices feedback and clarity in teaching that have direct measurable impact on students’ learning achievements. Andrew Ngeim Sumba | Frederick Ebot Ashu | Peter Agborbechem Tambi "The Role of Mentoring and Its Influence on the Effectiveness of the Teaching of Physics in Secondary Schools in the South West Region of Cameroon" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64524.pdf Paper Url: https://www.ijtsrd.com/management/management-development/64524/the-role-of-mentoring-and-its-influence-on-the-effectiveness-of-the-teaching-of-physics-in-secondary-schools-in-the-south-west-region-of-cameroon/andrew-ngeim-sumba
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...ijtsrd
This study primarily focuses on the design of a high side buck converter using an Arduino microcontroller. The converter is specifically intended for use in DC DC applications, particularly in standalone solar PV systems where the PV output voltage exceeds the load or battery voltage. To evaluate the performance of the converter, simulation experiments are conducted using Proteus Software. These simulations provide insights into the input and output voltages, currents, powers, and efficiency under different state of charge SoC conditions of a 12V,70Ah rechargeable lead acid battery. Additionally, the hardware design of the converter is implemented, and practical data is collected through operation, monitoring, and recording. By comparing the simulation results with the practical results, the efficiency and performance of the designed converter are assessed. The findings indicate that while the buck converter is suitable for practical use in standalone PV systems, its efficiency is compromised due to a lower output current. Chan Myae Aung | Dr. Ei Mon "Design Simulation and Hardware Construction of an Arduino-Microcontroller Based DC-DC High-Side Buck Converter for Standalone PV System" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64518.pdf Paper Url: https://www.ijtsrd.com/engineering/mechanical-engineering/64518/design-simulation-and-hardware-construction-of-an-arduinomicrocontroller-based-dcdc-highside-buck-converter-for-standalone-pv-system/chan-myae-aung
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadikuijtsrd
Energy becomes sustainable if it meets the needs of the present without compromising the ability of future generations to meet their own needs. Some of the definitions of sustainable energy include the considerations of environmental aspects such as greenhouse gas emissions, social, and economic aspects such as energy poverty. Generally far more sustainable than fossil fuel are renewable energy sources such as wind, hydroelectric power, solar, and geothermal energy sources. Worthy of note is that some renewable energy projects, like the clearing of forests to produce biofuels, can cause severe environmental damage. The sustainability of nuclear power which is a low carbon source is highly debated because of concerns about radioactive waste, nuclear proliferation, and accidents. The switching from coal to natural gas has environmental benefits, including a lower climate impact, but could lead to delay in switching to more sustainable options. “Carbon capture and storage” can be built into power plants to remove the carbon dioxide CO2 emissions, but this technology is expensive and has rarely been implemented. Leading non renewable energy sources around the world is fossil fuels, coal, petroleum, and natural gas. Nuclear energy is usually considered another non renewable energy source, although nuclear energy itself is a renewable energy source, but the material used in nuclear power plants is not. The paper addresses the issue of sustainable energy, its attendant benefits to the future generation, and humanity in general. Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku "Sustainable Energy" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64534.pdf Paper Url: https://www.ijtsrd.com/engineering/electrical-engineering/64534/sustainable-energy/paul-a-adekunte
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...ijtsrd
This paper aims to outline the executive regulations, survey standards, and specifications required for the implementation of the Sudan Survey Act, and for regulating and organizing all surveying work activities in Sudan. The act has been discussed for more than 5 years. The Land Survey Act was initiated by the Sudan Survey Authority and all official legislations were headed by the Sudan Ministry of Justice till it was issued in 2022. The paper presents conceptual guidelines to be used for the Survey Act implementation and to regulate the survey work practice, standardizing the field surveys, processing, quality control, procedures, and the processes related to survey work carried out by the stakeholders and relevant authorities in Sudan. The conceptual guidelines are meant to improve the quality and harmonization of geospatial data and to aid decision making processes as well as geospatial information systems. The established comprehensive executive regulations will govern and regulate the implementation of the Sudan Survey Geomatics Act in all surveying and mapping practices undertaken by the Sudan Survey Authority SSA and state local survey departments for public or private sector organizations. The targeted standards and specifications include the reference frame, projection, coordinate systems, and the guidelines and specifications that must be followed in the field of survey work, processes, and mapping products. In the last few decades, there has been a growing awareness of the importance of geomatics activities and measurements on the Earths surface in space and time, together with observing and mapping the changes. In such cases, data must be captured promptly, standardized, and obtained with more accuracy and specified in much detail. The paper will also highlight the current situation in Sudan, the degree to which survey standards are used, the problems encountered, and the errors that arise from not using the standards and survey specifications. Kamal A. A. Sami "Concepts for Sudan Survey Act Implementations - Executive Regulations and Standards" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63484.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/63484/concepts-for-sudan-survey-act-implementations--executive-regulations-and-standards/kamal-a-a-sami
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...ijtsrd
The discussions between ellipsoid and geoid have invoked many researchers during the recent decades, especially during the GNSS technology era, which had witnessed a great deal of development but still geoid undulation requires more investigations. To figure out a solution for Sudans local geoid, this research has tried to intake the possibility of determining the geoid model by following two approaches, gravimetric and geometrical geoid model determination, by making use of GNSS leveling benchmarks at Khartoum state. The Benchmarks are well distributed in the study area, in which, the horizontal coordinates and the height above the ellipsoid have been observed by GNSS while orthometric heights were carried out using precise leveling. The Global Geopotential Model GGM represented in EGM2008 has been exploited to figure out the geoid undulation at the benchmarks in the study area. This is followed by a fitting process, that has been done to suit the geoid undulation data which has been computed using GNSS leveling data and geoid undulation inspired by the EGM2008. Two geoid surfaces were created after the fitting process to ensure that they are identical and both of them could be counted for getting the same geoid undulation with an acceptable accuracy. In this respect, statistical operation played an important role in ensuring the consistency and integrity of the model by applying cross validation techniques splitting the data into training and testing datasets for building the geoid model and testing its eligibility. The geometrical solution for geoid undulation computation has been utilized by applying straightforward equations that facilitate the calculation of the geoid undulation directly through applying statistical techniques for the GNSS leveling data of the study area to get the common equation parameters values that could be utilized to calculate geoid undulation of any position in the study area within the claimed accuracy. Both systems were checked and proved eligible to be used within the study area with acceptable accuracy which may contribute to solving the geoid undulation problem in the Khartoum area, and be further generalized to determine the geoid model over the entire country, and this could be considered in the future, for regional and continental geoid model. Ahmed M. A. Mohammed. | Kamal A. A. Sami "Towards the Implementation of the Sudan Interpolated Geoid Model (Khartoum State Case Study)" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63483.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/63483/towards-the-implementation-of-the-sudan-interpolated-geoid-model-khartoum-state-case-study/ahmed-m-a-mohammed
Activating Geospatial Information for Sudans Sustainable Investment Mapijtsrd
Sudan is witnessing an acceleration in the processes of development and transformation in the performance of government institutions to raise the productivity and investment efficiency of the government sector. The development plans and investment opportunities have focused on achieving national goals in various sectors. This paper aims to illuminate the path to the future and provide geospatial data and information to develop the investment climate and environment for all sized businesses, and to bridge the development gap between the Sudan states. The Sudan Survey Authority SSA is the main advisor to the Sudan Government in conducting surveying, mappings, designing, and developing systems related to geospatial data and information. In recent years, SSA made a strategic partnership with the Ministry of Investment to activate Geospatial Information for Sudans Sustainable Investment and in particular, for the preparation and implementation of the Sudan investment map, based on the directives and objectives of the Ministry of Investment MI in Sudan. This paper comes within the framework of activating the efforts of the Ministry of Investment to develop technical investment services by applying techniques adopted by the Ministry and its strategic partners for advancing investment processes in the country. Kamal A. A. Sami "Activating Geospatial Information for Sudan's Sustainable Investment Map" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63482.pdf Paper Url: https://www.ijtsrd.com/engineering/information-technology/63482/activating-geospatial-information-for-sudans-sustainable-investment-map/kamal-a-a-sami
Educational Unity Embracing Diversity for a Stronger Societyijtsrd
In a rapidly changing global landscape, the importance of education as a unifying force cannot be overstated. This paper explores the crucial role of educational unity in fostering a stronger and more inclusive society through the embrace of diversity. By examining the benefits of diverse learning environments, the paper aims to highlight the positive impact on societal strength. The discussion encompasses various dimensions, from curriculum design to classroom dynamics, and emphasizes the need for educational institutions to become catalysts for unity in diversity. It highlights the need for a paradigm shift in educational policies, curricula, and pedagogical approaches to ensure that they are reflective of the diverse fabric of society. This paper also addresses the challenges associated with implementing inclusive educational practices and offers practical strategies for overcoming barriers. It advocates for collaborative efforts between educational institutions, policymakers, and communities to create a supportive ecosystem that promotes diversity and unity. Mr. Amit Adhikari | Madhumita Teli | Gopal Adhikari "Educational Unity: Embracing Diversity for a Stronger Society" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64525.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/64525/educational-unity-embracing-diversity-for-a-stronger-society/mr-amit-adhikari
Integration of Indian Indigenous Knowledge System in Management Prospects and...ijtsrd
The diversity of indigenous knowledge systems in India is vast and can vary significantly between different communities and regions. Preserving and respecting these knowledge systems is crucial for maintaining cultural heritage, promoting sustainable practices, and fostering cross cultural understanding. In this paper, an overview of the prospects and challenges associated with incorporating Indian indigenous knowledge into management is explored. It is found that IIKS helps in management in many areas like sustainable development, tourism, food security, natural resource management, cultural preservation and innovation, etc. However, IIKS integration with management faces some challenges in the form of a lack of documentation, cultural sensitivity, language barriers legal framework, etc. Savita Lathwal "Integration of Indian Indigenous Knowledge System in Management: Prospects and Challenges" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63500.pdf Paper Url: https://www.ijtsrd.com/management/accounting-and-finance/63500/integration-of-indian-indigenous-knowledge-system-in-management-prospects-and-challenges/savita-lathwal
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...ijtsrd
The COVID 19 pandemic has highlighted the crucial need of preventive measures, with widespread use of face masks being a key method for slowing the viruss spread. This research investigates face mask identification using deep learning as a technological solution to be reducing the risk of coronavirus transmission. The proposed method uses state of the art convolutional neural networks CNNs and transfer learning to automatically recognize persons who are not wearing masks in a variety of circumstances. We discuss how this strategy improves public health and safety by providing an efficient manner of enforcing mask wearing standards. The report also discusses the obstacles, ethical concerns, and prospective applications of face mask detection systems in the ongoing fight against the pandemic. Dilip Kumar Sharma | Aaditya Yadav "DeepMask: Transforming Face Mask Identification for Better Pandemic Control in the COVID-19 Era" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64522.pdf Paper Url: https://www.ijtsrd.com/engineering/electronics-and-communication-engineering/64522/deepmask-transforming-face-mask-identification-for-better-pandemic-control-in-the-covid19-era/dilip-kumar-sharma
Streamlining Data Collection eCRF Design and Machine Learningijtsrd
Efficient and accurate data collection is paramount in clinical trials, and the design of Electronic Case Report Forms eCRFs plays a pivotal role in streamlining this process. This paper explores the integration of machine learning techniques in the design and implementation of eCRFs to enhance data collection efficiency. We delve into the synergies between eCRF design principles and machine learning algorithms, aiming to optimize data quality, reduce errors, and expedite the overall data collection process. The application of machine learning in eCRF design brings forth innovative approaches to data validation, anomaly detection, and real time adaptability. This paper discusses the benefits, challenges, and future prospects of leveraging machine learning in eCRF design for streamlined and advanced data collection in clinical trials. Dhanalakshmi D | Vijaya Lakshmi Kannareddy "Streamlining Data Collection: eCRF Design and Machine Learning" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63515.pdf Paper Url: https://www.ijtsrd.com/biological-science/biotechnology/63515/streamlining-data-collection-ecrf-design-and-machine-learning/dhanalakshmi-d
How to Setup Warehouse & Location in Odoo 17 InventoryCeline George
In this slide, we'll explore how to set up warehouses and locations in Odoo 17 Inventory. This will help us manage our stock effectively, track inventory levels, and streamline warehouse operations.
हिंदी वर्णमाला पीपीटी, hindi alphabet PPT presentation, hindi varnamala PPT, Hindi Varnamala pdf, हिंदी स्वर, हिंदी व्यंजन, sikhiye hindi varnmala, dr. mulla adam ali, hindi language and literature, hindi alphabet with drawing, hindi alphabet pdf, hindi varnamala for childrens, hindi language, hindi varnamala practice for kids, https://www.drmullaadamali.com
This presentation was provided by Steph Pollock of The American Psychological Association’s Journals Program, and Damita Snow, of The American Society of Civil Engineers (ASCE), for the initial session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session One: 'Setting Expectations: a DEIA Primer,' was held June 6, 2024.
This presentation includes basic of PCOS their pathology and treatment and also Ayurveda correlation of PCOS and Ayurvedic line of treatment mentioned in classics.
Main Java[All of the Base Concepts}.docxadhitya5119
This is part 1 of my Java Learning Journey. This Contains Custom methods, classes, constructors, packages, multithreading , try- catch block, finally block and more.
How to Build a Module in Odoo 17 Using the Scaffold MethodCeline George
Odoo provides an option for creating a module by using a single line command. By using this command the user can make a whole structure of a module. It is very easy for a beginner to make a module. There is no need to make each file manually. This slide will show how to create a module using the scaffold method.
Executive Directors Chat Leveraging AI for Diversity, Equity, and InclusionTechSoup
Let’s explore the intersection of technology and equity in the final session of our DEI series. Discover how AI tools, like ChatGPT, can be used to support and enhance your nonprofit's DEI initiatives. Participants will gain insights into practical AI applications and get tips for leveraging technology to advance their DEI goals.
How to Make a Field Mandatory in Odoo 17Celine George
In Odoo, making a field required can be done through both Python code and XML views. When you set the required attribute to True in Python code, it makes the field required across all views where it's used. Conversely, when you set the required attribute in XML views, it makes the field required only in the context of that particular view.
Walmart Business+ and Spark Good for Nonprofits.pdfTechSoup
"Learn about all the ways Walmart supports nonprofit organizations.
You will hear from Liz Willett, the Head of Nonprofits, and hear about what Walmart is doing to help nonprofits, including Walmart Business and Spark Good. Walmart Business+ is a new offer for nonprofits that offers discounts and also streamlines nonprofits order and expense tracking, saving time and money.
The webinar may also give some examples on how nonprofits can best leverage Walmart Business+.
The event will cover the following::
Walmart Business + (https://business.walmart.com/plus) is a new shopping experience for nonprofits, schools, and local business customers that connects an exclusive online shopping experience to stores. Benefits include free delivery and shipping, a 'Spend Analytics” feature, special discounts, deals and tax-exempt shopping.
Special TechSoup offer for a free 180 days membership, and up to $150 in discounts on eligible orders.
Spark Good (walmart.com/sparkgood) is a charitable platform that enables nonprofits to receive donations directly from customers and associates.
Answers about how you can do more with Walmart!"
Strategies for Effective Upskilling is a presentation by Chinwendu Peace in a Your Skill Boost Masterclass organisation by the Excellence Foundation for South Sudan on 08th and 09th June 2024 from 1 PM to 3 PM on each day.
2. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1294
1.2. Proper time assessment of each action.
Project organizer should know the commitments of time for
the venture culmination and conveyance.
The exercises, for example, should begin and should
complete ought to be set up all around recessed.
Sorting out of exercises which are pivotal to opportune
finishing of undertaking ought to be perceived and
remembered.
1.3. About Primavera
Prophet's Primavera P6 is the internationally available and
world's quickest, incredible, easy to understand, simple to
utilize hearty and programming application whichisutilized
to oversee ventures, projects and port folios. Focusing on,
Managing, Scheduling, Planningshouldbepossibleforthe all
around the world found activities. It gives single answer for
oversee adjust and update the venture of any scale.Asoflate
there is P6 delivered 8.2 as an overhaul in the last form.
What's more, it is completely electronic arrangement and
there is up degree of taking care of ventures of enormous
scope is been executed to as indicated by the clients'
necessities and P6 discharge 8.2 can be gotten to through
web from anyplace whenever across the globe. In basic
words it is 100% program basedarrangementincludingjobs
explicit usefulness to fulfill every single related individual
with the task, partners' necessities their obligations and the
abilities It is being developed as a work area project
planning framework in the time of 1980 primavera has
unloaded into one of the careful and completely highlighted
venture project portfolio the executives (EPPM)
arrangement by offering elite apparatus for different
undertaking based associations.
1.4. Benefits of Primavera P6
1. It is exceptionally useful in arranging and bookingofthe
undertakings rapidly and advantageously.
2. It perceives the accessible buoys and decide the all
conceivable basic ways by the undertaking.
3. In this product there is office togettheappealingredone
brilliant Gantt graphs, network charts, histograms and
time based rationale outlines.
4. It makes chief program plan by coordinating the
timetables from proprietors, engineers, designers,
organizers and subcontractors.
5. It controls financial plans, gauges even after changes at
completing point to relic effective conveyance of the
task.
6. It empowers spot and moment getting ready for the
impending days, weeks, months, a long time, etc and
exercises.
7. Application of attempts to allot the assets for the
exercises should be possible correctly to frequent how
the work is conveyed.
8. Improves relationship and union by opportune E-
mailing to the concerned whole undertaking.
9. To comprehend the advancement in the changed forms
"guarantee digger" is to be looked.
10. It speeds up the correspondence identified with project
status to the partners, workers for hire, proprietorsand
other task supervisory group individuals by modified
reports of industry guidelines.
11. If makes great co-appointment among the Labors,
Material, Equipment and subcontractors to ensure on-
time and on spending plan completion.It records real
expense, acquired worth, units and arranged worth by
once redoing the monetary year time framewhichhelps
in examination of future and latest things.
12. In this examination between genuine expenses and
work performed can be tweaked to gauge spending
plans by keeping up self-governing renditions of cost
total assessment.
13. It makes boundless number of "consider the possibility
that" situations to decide the choices ways.
14. Any exercises can be squashed to more modest
characterized steps to empower us following the
achievement of the messed up advances survey the
action percent complete.
15. It ascertains hazard and shows hazard openness
esteems and these dangers plausible effects on the
ventures timetable, term and the budgetary expense.
16. It gives project execution these holds and shows notices
of execution on the off chance that it is veered off past
least or passable execution window of adequate.
17. Issues identified with plan of venture which references
consideration or some remedial exercises could be
logged via mailing issues subtleties alongside the
connections of notes, history of related issues
18. To form any sort of new activities bringing down of
formats is the best practice to follow up and it is even
useful for the total venture also
19. By utilizing prior execution of exercises in the task
acquired worth investigation should be possible to see
the future more exact expense for fruition.
2. Literature Review
Deals with squander materials are talked about in the
ensuing headings thoroughly.
Subsequent to going through specific diaries and survey
papers distributed which are identified with this
examination, it is empowered me to investigate a lot of
thoughts and sensible contemplating the point and how to
utilize the Primavera P6 programming in productive
manner. There are numerous such papers and diarieswhich
are distributed on the utilization and practice of primavera
P6 across different businesses however here in this
investigation I have considered a couple of paperswhichare
generally applicable to this examination which are
particularly distributed on the utilization of Primavera in
Construction Projects.
Narlawar et al. (2019), the developmentbusinesswhichgive
huge scope work is the establishment of advancement for
arising nations like India. The efficiency of the development
business relies generally upon asset the board strategies.
Additionally, it is hard to get ready precise and attainable
plans in enormous development projects. As the intricacy of
the task increments and the expense of the undertaking
floods, organizations should successfully deal with their
spending plans and timetables. For development project
observing and control Primavera P6 ends up being a viable
instrument in light of the fact that an opportunity to update
is essentially decreased. This paper intends to give an audit
on utilization of Primavera programming on schedule and
3. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1295
asset the board of development project. The examination
discovers how Primavera P6 programming settles different
intricacies related with arranging, booking, controlling,
checking and following of development projects dependent
on point by point writing study.
K. Suresh Kannan, M. G. Ranjith Kumar (2019) Planning,
booking and controlling are more significantintheventures.
This specialization requires more engaged undertaking
arranging and controlling strategiesthatendup being better
for specific sorts of tasks. Arranging prompts improved
execution as far as cost, timetable and activities, adjusting
the contending needs of an undertaking. Arranging is
accustomed to following of work and costcontrol ofthetask.
This task predominantly accomplishingforprivatestructure
utilizing primavera p6 programming. Thispaperattemptsto
clarify about the two story private structure arranging,
booking utilizing the primavera p6 programming
3. Research Methodology
Working Principle of Primavera P6-8.2
By and large Primavera P6 do deals with the philosophy of dynamic booking. Which to be sure furnishes the Project
Management office with a reasonable course map, which is expected to set up the most ideal advanced arrangement of the
undertaking by utilizing 'consider the possibility that' situations hazard extenuation strategies. Regardless of, the way that it
show the Project Manager's ability to deliver the board changeopportunitiesforthe ProjectManagementgrouptochoosefrom
the when fluctuations by the proposed project Baseline are being taken note. The strategy for dynamic booking outlines the
base or the stages for the undertaking planning which is intended to help the group of Project Management with certain
authority ways of thinking, strategy, rules, wording, formats and techniques which could incorporate the instructing and
preparing device or stage through which a specific timetable of occasions, steps, and the task achievements are refined.
Dynamic planning system depends on the beneath referenced some circuitous exercises which are executed by the different
Project Management group and its partners.
1. Work/Budget Scope – Project Management Team/office
2. Strategic Planning - Project Management Team/office
3. Project Work Breakdown Structure – Scheduler of the venture
4. Focussed of the geological and the actual breakdown of the past finished,
3.1. System to start the Project in Primavera Construction Schedule pertinence in Primavera
Other than the overall destinations of doling out the dates to project exercises, the venture Schedule is expected to meet the
prerequisite of coordinating with assets like work, material and gear concerning the undertaking exercises over the time
interval. A proficient and sound timetable of development evades the bugs' stirred because of blockage ofcreation workswith
correct time obtainment of essential materials and subsequently guarantees the task consummation date as right on time as
could really be expected.
Following is the concise system how in any case a task in Primavera P6 with genuine screen captures.
Fig 1 Entry of all the Activities in Primavera
3.2. The project Work Break-down Structure
The term Work Breakdown Structure is in short normallycalled as WBS. It isan interaction of collection variouscomponentsof
the venture with worried to explicit item and it coordinates or encroaches to characterize the general aim of the task.
4. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1296
Fig 2.Gantt Chart Showing the time scale and relationship between Activities
3.3. Assigning responsibility and measuring project progress
Exercises burn-through time and assets in this way, their appointing and estimation are to be done unequivocally. Allocating
exercises to responsible gatherings is prevailing as it extensively help in breaking the undertaking into controllable pieces,
doling out them to the gatherings that are effective to finish the errand. As well as characterizing the movement plan the
program with huge number of pages with no help to the troughs in getting them.
Fig 3 AssigningResources to the various activities
3.4. Bar Charts
Henry Gantt created bar outlines in 1917, bar graphs shows with regards to when the exercises are planned. Bar outlines are
the most ordinarily utilized visual device in the development business because of their straightforward and visual lucidity.
Organizers with no experience can peruse and set them up consequently it is basic. Notwithstanding, the appearance of basic
way strategy and headway of PCs have revived the significance and reliance on bar diagrams. Utilized less as standard
instrument, the cutting edge bar graphs havea CPMdeterminedtimetableorupdatesupportingthem regardlessofwhetherit's
not appeared on the diagram
5. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1297
3.5. Network Diagram
An organization outline addresses a venture plan exhaustively graphically;itshowsthework rationaleandfundamental action
progression. In wide the organization graph shows the '10,000 foot view' like what next and whattherequestforeventis.This
component makes the organization chart precise, productive and trustworthy audit technique to keep any terrible rationale
from losing all sense of direction in the booking programming device and thusly it is significant that the gatherings included
know to peruse the organization graph and assess them. The priority graphing technique PDM is generally amazing,
mainstream, adaptable and viable programming strategy utilized in the development business.Becauseofthesimplicityofage
and use and furthermore because of its joining of four significant action connections the organization graph is utilized in the
greater part of the planning programming. Tasks are acquainted with network graphs.Theseoutlinesgiveamazing perception
of the situation with position and relationship among various undertaking exercises. These are the fundamental asset of
imparting among organizers and eyewitnesses in the undertaking.
Fig 4.YellowHighlightShowingcompletedactivities
Fig 5 Gantt Chart after updating the progress
6. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1298
4. Results
The quote incorporates the amounts of the different materials that have been utilized and furthermore a theoretical expense
for the development of the structure. The quote has been arrangedutilizingMicrosoft Excel.DevelopmentCostCalculatorExcel
Sheet has been followed for the estimation of the different amounts. The initial segment of the Cost gaugecontainstheamount
overview for different materials and it has been done independently for every one of the 4 stories and furthermore for the
earthwork and the ground floor.
4.1. Use Construction Cost Calculator Excel Sheet
Enter just plot region like length and width in feet
Change Construction cost per sqft rate in a given field.
Check development cost of the structure. There will 67.56 % Material expense, 22.44% Labor cost, and 10 % project
worker benefit. So, the Total Cost of Construction will Rs. 5,733,000 Lakhs
Add your neighborhood rate in the field to get exact outcomes
So, the Total Cost of Construction Material Rs.33.03 Lakhs in previouslyaddingBuildingConstructioncostRs.57.33Lakhs.
Table: 1. Cost Calculator Excel Sheet for construction materials
Table: 2. Cost Calculator Excel Sheet for construction
The amount gauge for concrete and rebar has been taken from the development cost per sqft rate in a given field. The
development cost per sqft of the aggregate sum of substantial takeoffforthesuperstructurealongsidetherebarprerequisiteof
different measurements. The heaviness of rebar was in type of Newton (N) which was changed over to tons or kg. The second
piece of the quote incorporates the Abstract Cost of the structure floor astute. The rates utilized in the theoretical have been
taken from the PWD Schedule of Rates for Indore. Above is the Complete CostEstimate includingtheamountgauge andunique
expense of the proposed G+4 Residential structure in BicholiMardana Indore (M.P.)
7. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD42599 | Volume – 5 | Issue – 4 | May-June 2021 Page 1299
5. Conclusions
Primavera P6 has been utilized for arranging the different
exercises that encompass the development of a structure.
1. Using primavera we had the option to form a
functioning timetable and furthermoreanadvancement
bar for steady checking of the venture.
2. Using primavera we had the option to relegate different
assets just as obligations on different individuals
identified with the different phases of the task there by
expanding responsibility.
3. The length of the task utilizing primavera has been
determined to be around 374 days which additionally
incorporates occasions.
4. The advancement and the connection betweendifferent
exercises has additionally been appeared as a vivified
Gantt Chart.
5. This outline likewise helps the Project supervisor to
disclose to his customers the differentviewpointsjustas
progress of the venture.
6. The quote for the undertaking has been determined
utilizing in Microsoft Excel.
7. For the Abstract expense PWD Schedule of rates has
been followed and an all out cost of one story Rs
5,733,000 has been determined.
The venture offers premium quality 3BHK condos with pre-
appended conveniences. This private municipality is spread
across a gigantic region. Every one of the condos are
deliberately planned and all around ventilated.
BicholiMardana is a standout amongst other local locations
in Indore. Some superb schools, top-class medical clinics,
and enormous shopping centers are situated in nearness to
this area.
References
[1] Narlawar, Suchithra L, Jose Renoldo S (2019), “The
board of Multi Construction Projects utilizing
Primavera", International Journal of Innovative
Research in Science, Engineering and Technology
(IJIRSET), ISSN: 2319-8753, Vol. 6, Issue 7
[2] K. Suresh Kannan,Ashfaq Ahmed (2019),
Acknowledgment on Construction the board of
private condos", IOSR Journal of Mechanical and Civil
Engineering (IOSR-JMCE), e-ISSN:2278-1684,p-ISSN:
2320-334X, Volume 13, Issue 3, PP 49-56
[3] FathimaZerin T, Angela C. Joy, (2018), "EVM Analysis
with Primavera", International Research Journal of
Engineering and Technology (IRJET), e-ISSN: 2395 -
0056, p-ISSN: 2395-0072, Volume: 03, Issue: 06
[4] Vishal Annappa Nimbal1 & Prof.
BalasahebJamadar(2017), "Booking, Monitoring And
Cost Analysis By Earned Value Method Of Phase-2
(Reach-2a From Pier No.443 To Pier No.470) Using
Primavera P6, International Journal of Engineering
DevelopmentandResearch(IJEDR),ISSN:2321-9939,
Volume 5, Issue 3
[5] Shah Harsh,
MamtaRajgor&JayeshkumarPitroda(2017), "Cost
Controlling Using Earned Value Analysis in
Construction Industries",
[6] International Journal of Engineering and Innovative
Technology (IJEIT), ISSN: 2277-3754,Volume1,Issue
4
[7] Chiranjeevi, Narayana G, Rajeeva S J (2017), "An
Exploratory Study on EffectiveTimeManagementofa
Project", International Journal of Current Trends in
Engineering and Research (IJCTER), e-ISSN 2455–
1392, Volume 2, Issue 3, pp. 151 – 157
[8] Belsur, Suchithra S (2016), "Arranging, Scheduling
and Tracking of Residential Building Using Project
Management Software",SSRGInternational Journal of
Civil Engineering-(ICRTCETM) - Special Issue, ISSN :
2348 – 8352
[9] Dhinesh M, Kaleeswaran S, Manikandan Ashok S
(2017), “Planning, Scheduling and Tracking of
Residential Building Using Project Management
Software”, SSRG International Journal of Civil
Engineering- (ICRTCETM) -Special Issue, ISSN : 2348
– 8352
[10] Anne et al. (2017), "Arranging, Scheduling and Time
Management of Six Lanes Road Construction Work at
V.O.C Port Trust utilizing Primavera P6 Software",
International Journal of Science Technology and
Engineering (IJSTE), ISSN (on the web): 2349-784X,
Volume 2, Issue 11
[11] Ranjithkumar et al. (2017), "Undertaking Monitoring
and Control utilizing Primavera", International
Journal of Innovative Research in Science,
Engineering and Technology (IJIRSET), ISSN: 2319-
8753, Vol. 2, Issue 3
[12] Saini et al. (2017), “Project Monitoring and Control
using Primavera”, International Journal of Innovative
Research in Science, Engineering and Technology
(IJIRSET), ISSN: 2319-8753, Vol. 2, Issue 3
[13] Esakki, Madamachi Mani Chakravarthy, Asra Fatima
(2017"Undertaking Monitoring and Control utilizing
Primavera", International Journal of Innovative
Research in Science, Engineering and Technology
(IJIRSET), ISSN: 2319-8753, Vol. 2, Issue 3