SCHEDULING AND MONITORING OF WORK PROGRESS AT REACH 2B
(FROM PIER NO. 573 TO PIER NO. 735) BMRCL USING PRIMAVERA P6
ARINDAM DEBNATH
1
, DR SHREENIVAS REDDY SHAHAPUR2
,MANEETH P.D3
1
M.Tech. Student, Department of Construction Technology, Visvesvaraya Technological University, PG Studies,
Regional Office, Kalaburagi-585105 Karnataka, India.
2
Chairman & Professor, Department of Construction Technology, Visvesvaraya Technological University, PG
Studies, Regional Office, Kalaburagi-585105 Karnataka, India.
3Assistant Professor, Department of Construction Technology, Visvesvaraya Technological University, PG Studies,
Regional Office, Kalaburagi-585105 Karnataka, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
ABSTRACT: A venture is a cooperation to arrange and
accomplish a specific point. Extend includes a few errandsto
be finished from begin to the last point of venture
fulfillment. A timetable of errands is produced in the
arranging stage by the venture arranging and booking
group that obviously expresses thedifferentventurepoints of
reference and exercises in detail from venture begin to
venture wrap up. The nature of the calendar created from
Primavera P6, one of the for the most part utilized
programming for Project arranging, and booking ought to
affirm with industry scales as popular in the western
countries. Absence of the learning of different parts of
timetable advancement regularly brings about a calendar
which is not justifiable by the lion's share of
individuals required in the venture and henceforth not
useable. The obliviousness with respect to scheduler for the
most part results in such kind of timetable which is not
reasonable by other individuals, customerschipping awayat
site. In this way, it is a push to show and ad lib on the
calendar improvement by highlighting different fields that
are frequently overlooked in the advancement of a decent
development plan. Very few complete reviews have been
done on the noteworthiness of Activity ID and Description in
moderate sized venture plans, in India. A step hasbeentaken
to clarify their significance in detail. Booking assumes an
imperative part in enhancing the possibilities of fruitful
usage of metro ventures. The planning is only one of the
apparatuses will be utilized to oversee exercises and
term. Work separate structure will be readied length and
forerunners for every movement will be dealed out.
1. INTRODUCTION
Primavera P6 adaptation has been the least demanding
and most utilized programming today. It helps in breaking
down the everyday work in the development business. As
metro undertakings being a bigger tasks, so the
postponement and dangers required in this activities are
more. Primavera helps in breaking down the venture by
utilizing Critical way technique; it additionally helps in
review the venture in Gantt or Pert arrangement. Extend
directors, Planning specialists ought to have a full top to
bottom learning about this productbeforeuse.P6isbased on
Oracle and Microsoft server connection database for big
business wide venture administration scalability.P6 fits
effortlessly into todays appropriated workplace by keeping
all partners and venture colleagues cutting-edge on venture
fruition. The following element of primavera p6 enables
customers to produce reports and keep up legitimate gauge.
It helps in separating the mind boggling ventures into a
littler achievable, under stable and in a simple way. It
decreases the time and the venture can run easily with
proficient ways.
Presently a day Metro Rail assumes virtual part in India.
As a result of developing movement clog, unprecedented
growth of individual vehicles, to stay away from blockage at
peak hours, efficient of transporting travellers and fuel
utilization. Development industry is a basic segment of a
nation's framework and moderndevelopment.Thisindustry
is the second biggest industry in India still it's development
has been differential the country over. There is a huge
distinction of improvement in the rural and urban ranges.
Here emerges the requirement for compelling task
administration. Numerous issues and issues are being
confronted by the development business, major of them are
cost invades and time overwhelms due to insufficient
venture definition, lack of foresight for implementation and
disgraceful administration amid execution. Numerous
investigators express that normal cost of extend goes up by
30% as of the planned cost because of uncalledforarranging
and booking. Perceptions demonstrate that appropriate
skilful administration is fundamental for a venture to finish
inside time, assessed spending plan and with apportioned
assets. Giving great arranging, legitimate association,
adequate stream of assets to venture can consequently
accomplish the coveted outcome. Primavera Project Planner
is had some expertise in dealing with a wide range of
undertakings, little, medium and extensive; all through the
world.it has adequate capacities to help the client anticipate
the time, assets and cost and then later screen them. It is
utilized handle very vast and complex ventures, particularly
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2128
in the designing and development business. Working
venture in primavera resembles working in gathering of
exercises with a methodical work breakdown structure.
1.1 OBJECTIVES
1) To distinguish whether the customer prerequisites are
met.
2) To guarantee that the top request choices are made in
view of accessible site information and arranging.
3) To show where enhancements should be made.
4) To decrease the length of the venture by applying
appropriate exercises and assets time to time.
5) To examine the venture delay by legitimate followingof
the work on regular schedule
2. LITERATURE REVIEW
1] Veena HC et al (2016): In this paper it has been the
generaltimetable control methods are valuable in
streamlining asset booking and venture length. General
strategies, for example, are slamming procedures,
lessening the action span, expanding the assets, applying
timetable or expanding the working hours of the assets.
2] Umesh Y Polekar et al (2015): In this venture
legitimate arranging is made with booking and what are
the purposes behind the postponement in the venture is
contemplated with appropriate following and refreshing.
What, who and Where the work is done today and how
much the function is finished on regular schedule is
refreshed.
3] T. Siva Nagaraju et al (2016): Proper Planning and
booking is critical in Metro Rail development ventures for
diminishing and controlling deferrals of the venture.
Considerable measure of time, cash, and assets are
squandered every year ina developmentindustry becauseof
inappropriate arranging and booking.
4] Satinder Chopra et al (2014): Deliberate stream of
work is received by utilizing systems called Critical Path
Method (CPM) and Program Evaluation and Review
procedure (PERT). The state for administration of the
venture .and the objective proposed to accomplish extends
arranging is to deliver a period table of work with every
exercise. The fundamental objective expected from the
venture is too finished with legitimate arrangement and
timetable inside the gross spending plan apportioned for
real venture.
3. SCHEDULING
Arranging is the assurance of the planning and gathering of
operations in the undertaking and their get together to give
the general fruition time.
3.1: STEPSINVOLVEDFOR SCHEDULINGINPROGRESS OF
PROJECT BY PRIMAVERA:
Creating a New OBS: In an association where best level
administration people group’s assignment isdepictedunder
their expert experience is keep running into chain of
command level.
Creating a New EPS: The Enterprise Project Structure is
incorporated administration of different undertakingssorts
work in the association, a progressive based structure that
speaks to how activities are composed.
Creating a WBS: The gathering of occasions and
undertakings in a venture isolating or recognizing into little
work bundles depending up their merits is assigned in
project.
Creating calendars: Creating another logbook or Modify to
alter a current one. Choosing the Calendar that we need to
use as a layout for new Projects. Modify the Work Week
include work/non-work days. Check the "Default" Box to
make the default Calendar for every future venture.
Adding Activities: Exercises are the essential work
components of venture and they can additionally separate
into steps. Exercises are the most reduced level of WBS.
Duration: It's the reason for assessing the chose
movement's fulfillment time which decides if the timetable,
asset accessibility or cost is most imperative when
refreshing exercises
Reschedule: Distinguishing the postponed movement
entering the genuine rate of finish set up of virtual rate to
know the effect of deferral to run the real term remains
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2129
ENTIRE PROCESS OF SCHEDULING WITH UPDATE PLAN
BENEFITS OF PRIMAVERA SOFTWARE
i. Primavera P6 Reduces Risk: Precisely when your
timetable has variations from the norm, messes up,
or assault issues, meander costs will make. This
could mean cutting more fundamental parts of the
errand to change for the wealth spending costs.
Utilizing P6 sees and mitigates dangers to navigate
of orchestrating, directing, and completing an
attempt.
ii. Forecasting of each activity in the project: As an
attempt develops, the meander needs additional
assets, activities, and errands which will help in
accomplishing demands. Inside Primavera P6,
meander chiefs may analyze the figures for assets,
works out, and other meander needs.
iii. Tracking Activities: The accompanying segments
of Primavera P6 empower clients to rapidly make
reports, guarantee all expects are done asaskedfor,
and keep up example adherence.
iv. Organization improvement: Since
correspondence is redesigned all through a
meander, it's definitely not hard to perceive how
improved correspondence changes over into
upgraded joint exertion. This is especially basic
when activities cross immense zones. For example,
meanders in the vitality time business endeavors
may require joint exertion between variousvarying
gatherings.
v. Difficult Projects break down: Level of an
endeavor can overwhelm.P6 licensesmeander boss
to break immense attempts into tinier, easy
attempts, errands, activities.
4. METHODOLOGY AND ANALYSIS:
I filled in as understudy in BMRCL ltd. as per the VTU
embraced syllabus in third semester. It was an amazing
opportunity to working improvement industry people. The
worked almost and took after the improvement of Metro
works at Bangalore. The season of my impermanent
employment was 4 months. I closely watched all the work
which was been going out there and the contribution with
the all-inclusive community working there give me a
compact idea in regards to wearing down my M.Tech
expand. The data which I assembled in the midst of my
transitory occupation period help metro do the wander.
Extend title is "arranging of metro wander of association
application using” prophet primavera P6.
4.1 WORK DETAILS
Improvement OF above ground level structure of 4.869
km(APROX) from Pattanagere to Challegata for Bangalore
Metro Phase2 extend which incorporates 2 station lastly
ends at the mouth of the new challegatta terminal.
1) MAILASANDARA STATION (135M)
2) KENGERI STATION (135M)
3) DEPOT STATION (135M)
4.2 EXCLUSIVE STATIONS-:
A) Start of Contract to Mailasandra Station
PIER 573-PIER 629 (EXCLUSIVE STATION)
B) Mailasandra Station to Kengeri Station
PIER 630-PIER 686 (EXCLUSIVE STATION)
C) Kengeri Station to Start of depot turnout
PIER 687-PIER 735 (EXCLUSIVE STATION)
4.3 CONSTRUCTION METHODOLOGY:
For the entire Reach 2B Extension line pile
foundation has been selected. At Stationsmaximumpilesare
end bearing piles, there are two different sizes of pile used
(1) 1.2m Diameter Pile (2) 0.6m Diameter Pile.
End Bearing Piles: These piles are taken till hard rock
strata, and most of the carrying capacity is derived from the
base of the pile on to the hard rock strata.
Surveying: First step for piling is surveying, to locate the
pile. The survey activity at the beginning shall be carried
out with a total station of 1” accuracy and from the
transverse the stationed engineeratthesiteshall takepoints
shown in the approved drawings the levels at each location.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2130
Fabrication of reinforcement cage: Reinforcement cage is
fabricated at the casting yard and transported to site using a
trailer.
Boring: After the pile point is located, boring is started
with a hydraulic rig using a Auger. This initial boring is
done till a depth of 4m.
Socketing: After a hard rock stratum has been reached,
Tripod is erected and Connected with a winch to carry out
Chiseling and bailing in the bore.
Lowering Reinforcement Cage: The reinforcement cage is
Cut as per the depth of the pile. The cage is lifted with the
Help of type mounted crane of 15Ton capacity and lowered
in to the pile.
Concreting: The temporary casing is lifted from the ground
level and covered on the sides with the help of bags of sand.
Before concreting starts tremie pipes are to be fitted and
lowered
RELATIONSHIPS:
For piling:
Augerboring→chiseling→cage
lowering→flushing→concreting
For pile cap including backfilling:
Pile excavation→chipping of pile→levelling with PCC
bed→reinforcement ring for pile
cap→shuttering→concreting
For pier:
Pier starter→reinforcement
tieing→shuttering→concreting→curing
Table No.1 Showing the Activity Summary Of Piling For
Pier No. 585
ACTIVITY TIME(HOURS)
Auger boring 6.3
Core cutting 0.5
Chiseling 12
Bailing 6.1
Cage lowering 3
Winch erection 2
Tremie pipe lowering 1.8
Flushing 2
Concreting 4
Au
ge
r
bo
rin
g
Co
re
ba
rre
l
Ch
isc
llin
g
Ba
ilin
g
Ca
ge
lo
we
rin
g
Wi
nc
h
er
ec
tio
n
Tr
e
mi
e
pi
pe
lo
w…
Flu
shi
ng
co
nc
ret
in
g
TIME(HOUR
S)
6 1 12 6 3 2 2 2 4
0
2
4
6
8
10
12
14
time
ACTIVITY TIME(HOURS)
Graph No 1. Activity Time Cycle For Piling
Comment: hence here we observe thatthelongest time
is consumed during the process of chiselling
Table No 2. Showing Summery Of Activity for Piling
Of Pier 626
ACTIVITY TIME(HOURS)
Survey 1.00
Auger boring 5.42
Casing 1.00
Core cutting 1.00
Chiseling 11.16
Bailing 6.00
Cage lowering 1.75
Winch erection 2.00
Tremie pipe lowering 1.08
Flushing 1.33
Concreting 4.50
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2131
Sur
vey
Au
ger
bor
ing
Cas
ing
Cor
e
cull
tin
g
Chi
scll
ing
Bai
ling
Ca
ge
low
eri
ng
Wi
nc
h
ere
cti
on
Tre
mi
e
pip
e
low
eri
ng
Flu
shi
ng
co
ncr
eti
ng
TIME(HOURS) 1 5.42 1 1 11.2 6 1.75 2 1.081.33 4.5
0
2
4
6
8
10
12
TIME
ACTIVITY TIME(HOURS)
Graph No.2 Time Cycle Activity for Piling of Pier 626
Comments: hence from both the time cycle to observe that
the maximum time is consumed during the process of
chisclling.
Table No.3: Showing Activity Time Cycle Of Pier
Segment on Pier Segment Mould
SL
NO.
ACTIVITY TIME(HOURS)
1 Clean the bed 0.5
2 Fix the external
formwork(outer
shutter) including
cleaning and oiling
done parallel activity
1.5
3 Fix end bulk heads
from one side
1.0
4 Lower the rebar cage
and place it over
casting bed using 20T
gantry
1.0
5 Fix the anchorages 2.0
6 Attach the sheathing
pipe to the trumpet
1.0
7 Inspection by client 1.0
8 Provide inserts, holes
etc. for temporary
lifting and pre
stressing
1.0
9 Fix bulk heads of span
side
1.0
10 Inspection and 1.0
approval from client
for concreting
11 Concreting of the
segment
3.0
12 Setting time for
concrete and waiting
period for attaining
M25 so that the shutter
can be removed
30.0
13 Lifting of segment 1
Total 45 hours
Typical cycle time=1.5 days
Above cycle time can easily produce 15/16 segments per
mould per month
Requirement of production for erecting 18 spans per
month=18x2=36 segments
No. of moulds requires=36/16=2 moulds
As far as possible the pier segment shall be cast during day
time for proper supervision and monitoring purpose.
Table No. 4: Showing Activity Time Cycle Of Normal
Segment on Long Line Bed
SL NO. ACTIVITY TIME(HOURS)
1 Clean the bed 1.0
2 Fix the external
formwork(outer shutter)
including cleaning and oiling
done parallel activity
2.0
3 Lower the rebar cage and place
it over casting bed using 20t
gantry
1.O
4 Inspection by client 1.0
5 Attach the sheathing pipe to the
match casting segment
1.0
6 Fix end bulk heads from the
other side
1.0
7 Provide inserts, holes etc. For
lifting &temporary pre
stressing
1.0
8 Inspection and approval from
client for concreting
1.0
9 Concreting of the segment 4.0
10 Setting time for concrete and
waiting period for attaining
M25 so that shutter can be
removed
24
TOTAL 36 HRS
Typical cycle time=2days
Above cycle time can easily produce 10 segments per 7 days
which means at least 4 spans per month.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2132
Requirement of production for erecting 18 spans per
month=18/4=4.5 longline.
5. RESULTS AND DISCUSSION:
1) As the project is ongoing so it is on the progress
stage and is going as per the schedule.
2) In stretch 1 from Start of contract to Mailasandra
station i.e. from pier 573 to pier 629 all the pier
works are completed only the launching of span is
not started and the work is going as per schedule.
3) In stretch 2 from Mailasandra to Kengeri station
that is from pier 630 to pier 686 only 13 piers have
been completed, 9 are ongoing and the rest are not
started yet.
4) In stretch 3 from Kengeri station to Start of Depot
turnout i.e., from pier 687 to pier735 all the piers,
portal piers are completed only the launching work
is left
Finally the project compares all the schedule
techniques and let us knows theactual performance
of the project, so as to take quick decision by the
planning engineer/project manager in case of
schedule parameters
CONCLUSION
1] The outcome is inferred that the Activity ID and
Activity Description both the most unused part can
enormously upgrade the nature of the timetable if
utilized legitimately.
2] It is the obligation of the arranging group to
precisely choose the Activity ID structure ahead of
time in this way, that timetable planning streams
easily with no contentions.
3] Thus all the necessary factors with respect to risk
management in metro rail projects has been
formulated and questionnaire has been designed
and the questionnaire will be distributed to the
corresponding persons who are working in metro
rail projects and by making use of software the
response collected from the distributed
questionnaire will be analyzed and appropriate
suggestion and recommendations are made.
4] Studying activities of the project has been done by
using primavera which describe easily each of
activity of the project.
5] Analyzing the input data of the project and
reporting the output data by which the ability for
comparison between the original planoftheproject
and the required date of the project can be
performed.
ACKNOWLEDGEMENT
I wish to express my sincere thanks & gratitudetothank
my parents, teachers & all people who have helped me
directly or indirectly for the completion of this project
work. I hereby acknowledge with deep sense of
gratitude the valuable guidance, encouragement and
suggestions given by my M.Tech project guide Dr.
Shreenivas Reddy Shahpur & Prof. Maneeth P.D
REFERENCES
1) Veena Hc (2016)‘Schedule control of an
apartment building using primavera technique’
2) Umesh Y Polekar (2015)‘Planning, scheduling and
tracking of a residential project’
3) T. Siva Nagaraju (2016) “Schedule and resources
optimization using primavera in metro rail project”
4) Satinder Chopra (2014) “Planning scheduling,
tracking and application administration using
primavera web logic p6”
5) N. Banuchandar (2014) “Development of
management model for the underground corridor
construction for metro rail risk” Volume: 1 Issue: 2
08-Mar-2014,ISSN_NO: 2320-723X
6) R.K. Pandey(2013)‘Timeandschedulemanagement
by using primavera’

More Related Content

What's hot

IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner SystemIRJET Journal
 
Genrays Project Charter
Genrays Project CharterGenrays Project Charter
Genrays Project CharterApril Drake
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPMI_IREP_TP
 
Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!sanjeeev bahadur, m.tech,mba
 
Resume - Arvind Jha
Resume  -  Arvind JhaResume  -  Arvind Jha
Resume - Arvind JhaArvind Jha
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple ProjectsIRJET Journal
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
A project report on Six sigma for filmmaking process
A project report on Six sigma for filmmaking processA project report on Six sigma for filmmaking process
A project report on Six sigma for filmmaking processSachin Pandit
 
GenRays Project Scope Document
GenRays Project Scope DocumentGenRays Project Scope Document
GenRays Project Scope DocumentApril Drake
 
Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Yordan Dimitrov
 
Project management
Project managementProject management
Project managementArup Ray
 
Project initiation document
Project initiation documentProject initiation document
Project initiation documentLenka Tomsova
 
GenRays Communications Management
GenRays Communications ManagementGenRays Communications Management
GenRays Communications ManagementApril Drake
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET Journal
 
Powerpoint created for Holland Management Consultant
Powerpoint created for Holland Management ConsultantPowerpoint created for Holland Management Consultant
Powerpoint created for Holland Management ConsultantBarbara Smith
 
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdf
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdfTRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdf
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdfThanh Vân Trịnh
 

What's hot (20)

IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
Genrays Project Charter
Genrays Project CharterGenrays Project Charter
Genrays Project Charter
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar Mudiakal
 
Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!
 
Yogesh Sharma
Yogesh SharmaYogesh Sharma
Yogesh Sharma
 
Resume - Arvind Jha
Resume  -  Arvind JhaResume  -  Arvind Jha
Resume - Arvind Jha
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
Choudhary Divyang Resume
Choudhary Divyang ResumeChoudhary Divyang Resume
Choudhary Divyang Resume
 
project updated 1
project updated 1project updated 1
project updated 1
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
A project report on Six sigma for filmmaking process
A project report on Six sigma for filmmaking processA project report on Six sigma for filmmaking process
A project report on Six sigma for filmmaking process
 
GenRays Project Scope Document
GenRays Project Scope DocumentGenRays Project Scope Document
GenRays Project Scope Document
 
Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)Project Management Report for Blue Bag Films (University Assignment)
Project Management Report for Blue Bag Films (University Assignment)
 
Project management
Project managementProject management
Project management
 
Project initiation document
Project initiation documentProject initiation document
Project initiation document
 
GenRays Communications Management
GenRays Communications ManagementGenRays Communications Management
GenRays Communications Management
 
Ce seminar
Ce seminarCe seminar
Ce seminar
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Powerpoint created for Holland Management Consultant
Powerpoint created for Holland Management ConsultantPowerpoint created for Holland Management Consultant
Powerpoint created for Holland Management Consultant
 
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdf
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdfTRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdf
TRINH_THANHVAN_PERFORMANCE_EVALUATION_PROJECT.pdf
 

Similar to Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to Pier No. 735) BMRCL using Primavera P6

Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...ijtsrd
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
 
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET Journal
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET Journal
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction ManagementIRJET Journal
 
IRJET- Portfolio Management of Multiple Building Projects using EPPM
IRJET- 	  Portfolio Management of Multiple Building Projects using EPPMIRJET- 	  Portfolio Management of Multiple Building Projects using EPPM
IRJET- Portfolio Management of Multiple Building Projects using EPPMIRJET Journal
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 

Similar to Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to Pier No. 735) BMRCL using Primavera P6 (20)

Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- An Overview on Project Management
IRJET- An Overview on Project ManagementIRJET- An Overview on Project Management
IRJET- An Overview on Project Management
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
 
IRJET- Portfolio Management of Multiple Building Projects using EPPM
IRJET- 	  Portfolio Management of Multiple Building Projects using EPPMIRJET- 	  Portfolio Management of Multiple Building Projects using EPPM
IRJET- Portfolio Management of Multiple Building Projects using EPPM
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Scheduling and Monitoring of Work Progress at Reach 2B (From Pier No. 573 to Pier No. 735) BMRCL using Primavera P6

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2127 SCHEDULING AND MONITORING OF WORK PROGRESS AT REACH 2B (FROM PIER NO. 573 TO PIER NO. 735) BMRCL USING PRIMAVERA P6 ARINDAM DEBNATH 1 , DR SHREENIVAS REDDY SHAHAPUR2 ,MANEETH P.D3 1 M.Tech. Student, Department of Construction Technology, Visvesvaraya Technological University, PG Studies, Regional Office, Kalaburagi-585105 Karnataka, India. 2 Chairman & Professor, Department of Construction Technology, Visvesvaraya Technological University, PG Studies, Regional Office, Kalaburagi-585105 Karnataka, India. 3Assistant Professor, Department of Construction Technology, Visvesvaraya Technological University, PG Studies, Regional Office, Kalaburagi-585105 Karnataka, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- ABSTRACT: A venture is a cooperation to arrange and accomplish a specific point. Extend includes a few errandsto be finished from begin to the last point of venture fulfillment. A timetable of errands is produced in the arranging stage by the venture arranging and booking group that obviously expresses thedifferentventurepoints of reference and exercises in detail from venture begin to venture wrap up. The nature of the calendar created from Primavera P6, one of the for the most part utilized programming for Project arranging, and booking ought to affirm with industry scales as popular in the western countries. Absence of the learning of different parts of timetable advancement regularly brings about a calendar which is not justifiable by the lion's share of individuals required in the venture and henceforth not useable. The obliviousness with respect to scheduler for the most part results in such kind of timetable which is not reasonable by other individuals, customerschipping awayat site. In this way, it is a push to show and ad lib on the calendar improvement by highlighting different fields that are frequently overlooked in the advancement of a decent development plan. Very few complete reviews have been done on the noteworthiness of Activity ID and Description in moderate sized venture plans, in India. A step hasbeentaken to clarify their significance in detail. Booking assumes an imperative part in enhancing the possibilities of fruitful usage of metro ventures. The planning is only one of the apparatuses will be utilized to oversee exercises and term. Work separate structure will be readied length and forerunners for every movement will be dealed out. 1. INTRODUCTION Primavera P6 adaptation has been the least demanding and most utilized programming today. It helps in breaking down the everyday work in the development business. As metro undertakings being a bigger tasks, so the postponement and dangers required in this activities are more. Primavera helps in breaking down the venture by utilizing Critical way technique; it additionally helps in review the venture in Gantt or Pert arrangement. Extend directors, Planning specialists ought to have a full top to bottom learning about this productbeforeuse.P6isbased on Oracle and Microsoft server connection database for big business wide venture administration scalability.P6 fits effortlessly into todays appropriated workplace by keeping all partners and venture colleagues cutting-edge on venture fruition. The following element of primavera p6 enables customers to produce reports and keep up legitimate gauge. It helps in separating the mind boggling ventures into a littler achievable, under stable and in a simple way. It decreases the time and the venture can run easily with proficient ways. Presently a day Metro Rail assumes virtual part in India. As a result of developing movement clog, unprecedented growth of individual vehicles, to stay away from blockage at peak hours, efficient of transporting travellers and fuel utilization. Development industry is a basic segment of a nation's framework and moderndevelopment.Thisindustry is the second biggest industry in India still it's development has been differential the country over. There is a huge distinction of improvement in the rural and urban ranges. Here emerges the requirement for compelling task administration. Numerous issues and issues are being confronted by the development business, major of them are cost invades and time overwhelms due to insufficient venture definition, lack of foresight for implementation and disgraceful administration amid execution. Numerous investigators express that normal cost of extend goes up by 30% as of the planned cost because of uncalledforarranging and booking. Perceptions demonstrate that appropriate skilful administration is fundamental for a venture to finish inside time, assessed spending plan and with apportioned assets. Giving great arranging, legitimate association, adequate stream of assets to venture can consequently accomplish the coveted outcome. Primavera Project Planner is had some expertise in dealing with a wide range of undertakings, little, medium and extensive; all through the world.it has adequate capacities to help the client anticipate the time, assets and cost and then later screen them. It is utilized handle very vast and complex ventures, particularly
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2128 in the designing and development business. Working venture in primavera resembles working in gathering of exercises with a methodical work breakdown structure. 1.1 OBJECTIVES 1) To distinguish whether the customer prerequisites are met. 2) To guarantee that the top request choices are made in view of accessible site information and arranging. 3) To show where enhancements should be made. 4) To decrease the length of the venture by applying appropriate exercises and assets time to time. 5) To examine the venture delay by legitimate followingof the work on regular schedule 2. LITERATURE REVIEW 1] Veena HC et al (2016): In this paper it has been the generaltimetable control methods are valuable in streamlining asset booking and venture length. General strategies, for example, are slamming procedures, lessening the action span, expanding the assets, applying timetable or expanding the working hours of the assets. 2] Umesh Y Polekar et al (2015): In this venture legitimate arranging is made with booking and what are the purposes behind the postponement in the venture is contemplated with appropriate following and refreshing. What, who and Where the work is done today and how much the function is finished on regular schedule is refreshed. 3] T. Siva Nagaraju et al (2016): Proper Planning and booking is critical in Metro Rail development ventures for diminishing and controlling deferrals of the venture. Considerable measure of time, cash, and assets are squandered every year ina developmentindustry becauseof inappropriate arranging and booking. 4] Satinder Chopra et al (2014): Deliberate stream of work is received by utilizing systems called Critical Path Method (CPM) and Program Evaluation and Review procedure (PERT). The state for administration of the venture .and the objective proposed to accomplish extends arranging is to deliver a period table of work with every exercise. The fundamental objective expected from the venture is too finished with legitimate arrangement and timetable inside the gross spending plan apportioned for real venture. 3. SCHEDULING Arranging is the assurance of the planning and gathering of operations in the undertaking and their get together to give the general fruition time. 3.1: STEPSINVOLVEDFOR SCHEDULINGINPROGRESS OF PROJECT BY PRIMAVERA: Creating a New OBS: In an association where best level administration people group’s assignment isdepictedunder their expert experience is keep running into chain of command level. Creating a New EPS: The Enterprise Project Structure is incorporated administration of different undertakingssorts work in the association, a progressive based structure that speaks to how activities are composed. Creating a WBS: The gathering of occasions and undertakings in a venture isolating or recognizing into little work bundles depending up their merits is assigned in project. Creating calendars: Creating another logbook or Modify to alter a current one. Choosing the Calendar that we need to use as a layout for new Projects. Modify the Work Week include work/non-work days. Check the "Default" Box to make the default Calendar for every future venture. Adding Activities: Exercises are the essential work components of venture and they can additionally separate into steps. Exercises are the most reduced level of WBS. Duration: It's the reason for assessing the chose movement's fulfillment time which decides if the timetable, asset accessibility or cost is most imperative when refreshing exercises Reschedule: Distinguishing the postponed movement entering the genuine rate of finish set up of virtual rate to know the effect of deferral to run the real term remains
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2129 ENTIRE PROCESS OF SCHEDULING WITH UPDATE PLAN BENEFITS OF PRIMAVERA SOFTWARE i. Primavera P6 Reduces Risk: Precisely when your timetable has variations from the norm, messes up, or assault issues, meander costs will make. This could mean cutting more fundamental parts of the errand to change for the wealth spending costs. Utilizing P6 sees and mitigates dangers to navigate of orchestrating, directing, and completing an attempt. ii. Forecasting of each activity in the project: As an attempt develops, the meander needs additional assets, activities, and errands which will help in accomplishing demands. Inside Primavera P6, meander chiefs may analyze the figures for assets, works out, and other meander needs. iii. Tracking Activities: The accompanying segments of Primavera P6 empower clients to rapidly make reports, guarantee all expects are done asaskedfor, and keep up example adherence. iv. Organization improvement: Since correspondence is redesigned all through a meander, it's definitely not hard to perceive how improved correspondence changes over into upgraded joint exertion. This is especially basic when activities cross immense zones. For example, meanders in the vitality time business endeavors may require joint exertion between variousvarying gatherings. v. Difficult Projects break down: Level of an endeavor can overwhelm.P6 licensesmeander boss to break immense attempts into tinier, easy attempts, errands, activities. 4. METHODOLOGY AND ANALYSIS: I filled in as understudy in BMRCL ltd. as per the VTU embraced syllabus in third semester. It was an amazing opportunity to working improvement industry people. The worked almost and took after the improvement of Metro works at Bangalore. The season of my impermanent employment was 4 months. I closely watched all the work which was been going out there and the contribution with the all-inclusive community working there give me a compact idea in regards to wearing down my M.Tech expand. The data which I assembled in the midst of my transitory occupation period help metro do the wander. Extend title is "arranging of metro wander of association application using” prophet primavera P6. 4.1 WORK DETAILS Improvement OF above ground level structure of 4.869 km(APROX) from Pattanagere to Challegata for Bangalore Metro Phase2 extend which incorporates 2 station lastly ends at the mouth of the new challegatta terminal. 1) MAILASANDARA STATION (135M) 2) KENGERI STATION (135M) 3) DEPOT STATION (135M) 4.2 EXCLUSIVE STATIONS-: A) Start of Contract to Mailasandra Station PIER 573-PIER 629 (EXCLUSIVE STATION) B) Mailasandra Station to Kengeri Station PIER 630-PIER 686 (EXCLUSIVE STATION) C) Kengeri Station to Start of depot turnout PIER 687-PIER 735 (EXCLUSIVE STATION) 4.3 CONSTRUCTION METHODOLOGY: For the entire Reach 2B Extension line pile foundation has been selected. At Stationsmaximumpilesare end bearing piles, there are two different sizes of pile used (1) 1.2m Diameter Pile (2) 0.6m Diameter Pile. End Bearing Piles: These piles are taken till hard rock strata, and most of the carrying capacity is derived from the base of the pile on to the hard rock strata. Surveying: First step for piling is surveying, to locate the pile. The survey activity at the beginning shall be carried out with a total station of 1” accuracy and from the transverse the stationed engineeratthesiteshall takepoints shown in the approved drawings the levels at each location.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2130 Fabrication of reinforcement cage: Reinforcement cage is fabricated at the casting yard and transported to site using a trailer. Boring: After the pile point is located, boring is started with a hydraulic rig using a Auger. This initial boring is done till a depth of 4m. Socketing: After a hard rock stratum has been reached, Tripod is erected and Connected with a winch to carry out Chiseling and bailing in the bore. Lowering Reinforcement Cage: The reinforcement cage is Cut as per the depth of the pile. The cage is lifted with the Help of type mounted crane of 15Ton capacity and lowered in to the pile. Concreting: The temporary casing is lifted from the ground level and covered on the sides with the help of bags of sand. Before concreting starts tremie pipes are to be fitted and lowered RELATIONSHIPS: For piling: Augerboring→chiseling→cage lowering→flushing→concreting For pile cap including backfilling: Pile excavation→chipping of pile→levelling with PCC bed→reinforcement ring for pile cap→shuttering→concreting For pier: Pier starter→reinforcement tieing→shuttering→concreting→curing Table No.1 Showing the Activity Summary Of Piling For Pier No. 585 ACTIVITY TIME(HOURS) Auger boring 6.3 Core cutting 0.5 Chiseling 12 Bailing 6.1 Cage lowering 3 Winch erection 2 Tremie pipe lowering 1.8 Flushing 2 Concreting 4 Au ge r bo rin g Co re ba rre l Ch isc llin g Ba ilin g Ca ge lo we rin g Wi nc h er ec tio n Tr e mi e pi pe lo w… Flu shi ng co nc ret in g TIME(HOUR S) 6 1 12 6 3 2 2 2 4 0 2 4 6 8 10 12 14 time ACTIVITY TIME(HOURS) Graph No 1. Activity Time Cycle For Piling Comment: hence here we observe thatthelongest time is consumed during the process of chiselling Table No 2. Showing Summery Of Activity for Piling Of Pier 626 ACTIVITY TIME(HOURS) Survey 1.00 Auger boring 5.42 Casing 1.00 Core cutting 1.00 Chiseling 11.16 Bailing 6.00 Cage lowering 1.75 Winch erection 2.00 Tremie pipe lowering 1.08 Flushing 1.33 Concreting 4.50
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2131 Sur vey Au ger bor ing Cas ing Cor e cull tin g Chi scll ing Bai ling Ca ge low eri ng Wi nc h ere cti on Tre mi e pip e low eri ng Flu shi ng co ncr eti ng TIME(HOURS) 1 5.42 1 1 11.2 6 1.75 2 1.081.33 4.5 0 2 4 6 8 10 12 TIME ACTIVITY TIME(HOURS) Graph No.2 Time Cycle Activity for Piling of Pier 626 Comments: hence from both the time cycle to observe that the maximum time is consumed during the process of chisclling. Table No.3: Showing Activity Time Cycle Of Pier Segment on Pier Segment Mould SL NO. ACTIVITY TIME(HOURS) 1 Clean the bed 0.5 2 Fix the external formwork(outer shutter) including cleaning and oiling done parallel activity 1.5 3 Fix end bulk heads from one side 1.0 4 Lower the rebar cage and place it over casting bed using 20T gantry 1.0 5 Fix the anchorages 2.0 6 Attach the sheathing pipe to the trumpet 1.0 7 Inspection by client 1.0 8 Provide inserts, holes etc. for temporary lifting and pre stressing 1.0 9 Fix bulk heads of span side 1.0 10 Inspection and 1.0 approval from client for concreting 11 Concreting of the segment 3.0 12 Setting time for concrete and waiting period for attaining M25 so that the shutter can be removed 30.0 13 Lifting of segment 1 Total 45 hours Typical cycle time=1.5 days Above cycle time can easily produce 15/16 segments per mould per month Requirement of production for erecting 18 spans per month=18x2=36 segments No. of moulds requires=36/16=2 moulds As far as possible the pier segment shall be cast during day time for proper supervision and monitoring purpose. Table No. 4: Showing Activity Time Cycle Of Normal Segment on Long Line Bed SL NO. ACTIVITY TIME(HOURS) 1 Clean the bed 1.0 2 Fix the external formwork(outer shutter) including cleaning and oiling done parallel activity 2.0 3 Lower the rebar cage and place it over casting bed using 20t gantry 1.O 4 Inspection by client 1.0 5 Attach the sheathing pipe to the match casting segment 1.0 6 Fix end bulk heads from the other side 1.0 7 Provide inserts, holes etc. For lifting &temporary pre stressing 1.0 8 Inspection and approval from client for concreting 1.0 9 Concreting of the segment 4.0 10 Setting time for concrete and waiting period for attaining M25 so that shutter can be removed 24 TOTAL 36 HRS Typical cycle time=2days Above cycle time can easily produce 10 segments per 7 days which means at least 4 spans per month.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2132 Requirement of production for erecting 18 spans per month=18/4=4.5 longline. 5. RESULTS AND DISCUSSION: 1) As the project is ongoing so it is on the progress stage and is going as per the schedule. 2) In stretch 1 from Start of contract to Mailasandra station i.e. from pier 573 to pier 629 all the pier works are completed only the launching of span is not started and the work is going as per schedule. 3) In stretch 2 from Mailasandra to Kengeri station that is from pier 630 to pier 686 only 13 piers have been completed, 9 are ongoing and the rest are not started yet. 4) In stretch 3 from Kengeri station to Start of Depot turnout i.e., from pier 687 to pier735 all the piers, portal piers are completed only the launching work is left Finally the project compares all the schedule techniques and let us knows theactual performance of the project, so as to take quick decision by the planning engineer/project manager in case of schedule parameters CONCLUSION 1] The outcome is inferred that the Activity ID and Activity Description both the most unused part can enormously upgrade the nature of the timetable if utilized legitimately. 2] It is the obligation of the arranging group to precisely choose the Activity ID structure ahead of time in this way, that timetable planning streams easily with no contentions. 3] Thus all the necessary factors with respect to risk management in metro rail projects has been formulated and questionnaire has been designed and the questionnaire will be distributed to the corresponding persons who are working in metro rail projects and by making use of software the response collected from the distributed questionnaire will be analyzed and appropriate suggestion and recommendations are made. 4] Studying activities of the project has been done by using primavera which describe easily each of activity of the project. 5] Analyzing the input data of the project and reporting the output data by which the ability for comparison between the original planoftheproject and the required date of the project can be performed. ACKNOWLEDGEMENT I wish to express my sincere thanks & gratitudetothank my parents, teachers & all people who have helped me directly or indirectly for the completion of this project work. I hereby acknowledge with deep sense of gratitude the valuable guidance, encouragement and suggestions given by my M.Tech project guide Dr. Shreenivas Reddy Shahpur & Prof. Maneeth P.D REFERENCES 1) Veena Hc (2016)‘Schedule control of an apartment building using primavera technique’ 2) Umesh Y Polekar (2015)‘Planning, scheduling and tracking of a residential project’ 3) T. Siva Nagaraju (2016) “Schedule and resources optimization using primavera in metro rail project” 4) Satinder Chopra (2014) “Planning scheduling, tracking and application administration using primavera web logic p6” 5) N. Banuchandar (2014) “Development of management model for the underground corridor construction for metro rail risk” Volume: 1 Issue: 2 08-Mar-2014,ISSN_NO: 2320-723X 6) R.K. Pandey(2013)‘Timeandschedulemanagement by using primavera’