Review on Planning and Scheduling of Construction
Project by Management Tool Primavera P6
Shashwat Dubey1, Prof. M. C. Paliwal2
1PG Student, 2Associate Professor,
1,2Department of Civil & Environmental Engineering, NITTTR, Bhopal, Madhya Pradesh, India
ABSTRACT
Modern construction system has shown great potential in the field of the
conventional construction system. The advantage of using new construction
techniques for any type of construction isthattheprocess takesnolonger.The
modern method of construction is defined as a way of working more
effectively to achieve more while using less. The description lends itself
heavily to offsite or modular construction techniques the method of
prefabricating parts of building offsite before transporting and assembling
them at their final location. Unlike traditional methods of construction is
defined as a way of working more effectively. Poor construction management
will cause the delay. Delay in the contracted project can resultinpenaltiesand
adversely affect the reputation of the company. It is essential to manage the
work within time. If construction time increases, construction cost also
increases. It is necessary proper planning and management for construction
work. Primavera p6 is a management tool. In this study primavera software
help in the planning and scheduling of the project. Primavera gives better
quality of project management process and easily understanding results.
KEYWORDS: Scheduling, Planning, Primavera P6, Delay
How to cite this paper: Shashwat Dubey|
Prof. M. C. Paliwal "Review on Planning
and Scheduling of ConstructionProject by
Management Tool Primavera P6"
Published in
International Journal
of Trend in Scientific
Research and
Development(ijtsrd),
ISSN: 2456-6470,
Volume-5 | Issue-2,
February 2021,
pp.1052-1054, URL:
www.ijtsrd.com/papers/ijtsrd38641.pdf
Copyright © 2021 by author(s) and
International Journal ofTrendinScientific
Research and Development Journal. This
is an Open Access article distributed
under the terms of
the Creative
Commons Attribution
License (CC BY 4.0)
(http://creativecommons.org/licenses/by/4.0)
I. INTRODUCTION
Planning and scheduling are a part of modern construction
techniques. They are an important role play in civil project
management. Planning and scheduling are terms in a
construction project which refers to attain the expected
goals. Project scheduling is a technique to meet up the
sequence of activities and the type of resources that will be
assigned to complete those activities in the planned frame.
The organization has schedules and available resources. It
needs to be documented to plan those activities. Project
scheduling is performed in four steps. First, define the tasks
of the project. A project is a collection of activities and
events, each activity has a start date andfinishdate.The next
step is to define activities complete estimates of time and
efforts. In this step calculation of duration concerning
resources. The third step is a define activities order and the
last step is assigning resources Planning and scheduling are
necessary for a project to perform in a standard way and
complete in planned time. Cause of planning and scheduling
results we know about activities, their sequence, amount of
resources before performing the task. For planning and
scheduling many software available Primavera, MSP
software, etc. This software helps to control andmonitorthe
project.
II. LITERATURE REVIEW
In thischapter, literature reviewhasbeenpresentedbygoing
through various articles and websites. Information about
heart diagnosing and its details are also available on some
websites; these are also referredtoandlistedinthereference
section. Various related literature proceedings of various
national and international conferences were reviewed.
[1] R. KALAVIVANNA (2020)has studied the planning and
scheduling of G +3residential building construction by using
primavera software. Theobjectiveoftheresearchpaperwork
is to schedule the residential building construction using
primavera p6 and optimize the resources utilized in the
project. The contract period of the project is 11 months.
Construction start date 30 December 2019. In this paper, the
result was observed that after planning and scheduling the
time duration of the building completion was reduced by
nearly 1 month.
[2]S. KUMAR M, MANISANKARS (2020) have studieddelay
analysis of highway construction by using primavera
software. The project location is Thanjavur. The duration of
the project was 24 months. Construction of the project was
started on 06/09/2018. It isobserved conclusionofresearch
work is a delay of the construction project was easily
analyzed by primavera software. The status of each activity
was easily seen with help of Primavera software.
[3]PRANAV TAWALE, ANKIT MISHRA, KARAN JADHAV,
SWAPNLI ONKAR (2020)have studied construction
planning of high-rise building by using primavera software.
The high-rise building is located at Waliv, Vasai in
Maharashtra. Proper planning is a very important part of a
IJTSRD38641
International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD38641 | Volume – 5 | Issue – 2 | January-February 2021 Page 1053
construction project to reduce delays of the projects. The
waring mechanism must be present, which can alert the
project owner of possible completionthroughouttheproject.
The advantage of planning and controlling the project are
Fewer construction times.
Estimated approx. costs and overruns.
Keep a track of the project.
[4] ANKIT GUPTA, DR. SANJAY TIWARI (2020)have
studied leveling resources for construction project G + 3
hospital by various software-based leveling tools. The
objective of this paper was tocalculate an optimum schedule
for construction project resources. The studied work
represents a comparison of resource leveling by levelingtool
of primavera and MS project. In this paper, the author
appliesa different type of leveling tool to examine the best
leveling tool. Leveling tool available in both software.
Activities can split to be leveled in MS-project unlike in
Primavera.
[5] SUVARNA, YATEEN LOKESH, DR. S. P. MAHENDRA
(2018)have studied planning, scheduling, and tracking of
bridge construction by using primavera software &the EVM
technique. The location of the project is Sangapura.
Construction started in January 2016. The duration of the
project as per the baseline schedule is 867 days. Conclusion
of literature provedtohelpmeasureconstraintsperformance
of a project in EVM and enable the analysis oftheefficiencyof
various parameters related to the progress of the report.
Following steps of the methodology followed by authors:
Implementation of primavera p6 on a project.
Calculation of critical path of the planned schedule.
Calculation of earn value management.
[6]ANURAG MAHURE, AMIT KUMAR RANIT (2018)have
studied projectmanagementof200traineehostelbuildingby
using primavera software. The project is located at the
campus of Dr. Panjabrao, Deshmukh prabodhini Amravati.
The contract period of project construction was 24 months.
Conclusion of work observes an implementation of planning
and scheduling by using primavera software the time
duration was reduced by nearly 3 months.
[7] MOHAMMAD AFZAL S. SIDDIQUI, ABHIJIT N. BHIRUD
(2018)have studied, project management in Pune metro
Maharashtra. The author tried to demonstrate the planning
for a stretch of 10 K. M. of the metro bridge from Pimpri
Chinch wad to Range hills. The conclusion of this paperwork
was the estimation in a period of the Pune metro project by
using primavera software. The estimated duration of the
Pune metro duration by the author was not considering a
major cause of delay. The future scope of studies is updating
and monitoring the schedule work.
[8] Vishal AnnappaNimbal,PROF.BALASAHEBJAMADAR
(2017)have studied planning, scheduling & allocation of
resource of a multi-storied building by using primavera
software. The location of the project is Pune Maharashtra.
Literature explained the importance of oracle software
primavera in the construction field and applies it to the
management of a multi-story structure. He finds out the
estimated finishing period for the project and plans it along
with resource allocation and helps us to understand the
concept of primavera in a precise manner giving an example
of works done in Primavera P6. He concludes that the main
objective of his study was to know the role of planning and
management of the project within the duration
accomplishment of any construction project. His project was
fulfilled with the help of literature references and unique
methodologies in control and monitoring using project
management application.
[9]BHAJANTHRITHIRUMALESHA,BASAVARAJ(2017)have
studied resource optimization in the construction of
residential apartments using primavera p6. The residential
apartment building with two blocks located at Navalgunda,
Karnataka. The name of the site is the Karnataka police
quarters building. The objective of the authors was how to
find the over-allocated resources and how to balance them.
This studied conclude the following result:
Over allocated resources are eliminated from the
activities.
Optimization of resources can be done withoutchanging
the project duration.
[10]PUNEET SINGH (2016) has done a comparative
analysis of construction techniques onto different projects
by using primavera software P6. A questionnaire was
formulated and personal interviews were conducted with
the senior engineers and managers of both the projects by
the author. The survey was conducted through direct
interactions to get realistic and explained responses. The
responses were recorded and analyzed statistically and the
following major problems were identified that were
responsible for the late completion of the project. Name of
projects given below
National bank, New Delhi
Project B C/o Punjab C/oShaheedSukhdevCollege,New
Delhi
[11]P. ESAKI THAANA (2016) hasusedprimaverasoftware
for planning of road construction.Timesupervisionsystemis
focused to complete a key role in a construction company,
which is accountable to finish the project in budget value
within a certain duration. Poor task management and fund
performance are major problems faced by construction
organizations. The objective of this research istopreparethe
planning and managementforroadworkconstructionatVOC
PORT TRUST, Tuticorin. Primavera P6 software helped for
monitoring and controlling the road project work.
[12] T. SHIVA NAGARAJU (2016)has studied the schedule
and resource optimization of Kochi metro station using
primavera software. Theobjectiveoftheresearchpaperwork
is to schedule the project and proper allocation of resources
for construction. The average cost of the projects goes up by
30 percent of the estimated cost due to lack of planning and
scheduling. Observations show that skillful management is
the key for a project to complete within an allotted time
frame in an estimated budget and with the allocated
resources. Providinggoodplanning,properorganization,and
a sufficient flow of resources to projects can automatically
achieve the desired result. The result of the study shows the
drawback of the actual project management system.
[13]B.S.KREDDY(2015)saysthatresourceplaysimportant
role in any construction project. The performance of any
construction project directly depends upon resource
management. For resource optimization and leveling author
choose primavera p6 software in an ongoing construction
project in Dubai in UAE. The main objective of this paperisto
minimize under allocation of resources. After using
primavera software author concluded that there is a 5. 65%
resource reduction.
International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD38641 | Volume – 5 | Issue – 2 | January-February 2021 Page 1054
[14] T. SUBRAMANI A. SARKUNAM, Jayalakshmi
(2014)have studied comparison in time performing of the
conventional method of construction for residential and
industrial building system method by total construction
duration. Schedule work was developed using oracle
software primavera. The positive change includes creating a
healthy working environment among thoseinvolveddirectly
in the construction industry. The major players in the
engineer’s town planners, contractor and supplier or
manufacture have to play their duty in enhancing their
working system, management, and administration to enable
the modernization in the company.
[15] ANDREW FERNANS TOM, SACHIN PAUL (2013) have
work explained project planning and controlling is the
process of collecting information concerning project
performance. The study deals with the monitoringprocessof
a four-storeyed (G+3) factory building in Cochin Kerala. A
comparison between the planned progress of construction
work and actual progress is performed in this study using
primavera software.
The methodology followed by the authors are
Earn value supervision
Cost performance supervision
Work performance supervision
III. CONCLUSION
From the various studies, we can conclude planning and
controlling is essential for every construction project for
better performance.Projectmanagementhelpsinforecasting
the project. Primavera software is a planning tool to help
manage project activity and know about the status of a
project. The main aim of project planning is to overcome the
delay of the project. In the conventional method, project
organizations don’t know the best path for project
completion. The study of the literature review proves
application of the primavera tool is best over the
conventional method of construction. It was found that most
of the authors have used primavera software in the planning
of high-rise buildings,roadconstruction,bridgeconstruction,
metro construction, hospital building, hostel building, etc.
IV. REFERENCES
[1] S. Rajlumar, P. RamPramoth, J. Sankaranarayanan, R.
Kalaivannam (2020) “planningandSchedulingofG+3
building construction using primavera p6” IRJET |
Volume 7 | Issue: 07 | Aug. 2020, P – ISSN: 2395 –
0072.
[2] Ankit Gupta, Dr. Sanjay Tiwari (2020) “Levelling
resources of a construction project by various
software-basedleveling tool” IJRASET | Volume 8 |
Issue: 09 | Sept. 2020| ISSN: 2321-9653.
[3] Anurag Mahure, Amit Kumar Ranit (2018) “Project
management using primavera P6” IJSTE -
International Journal of Science Technology &
Engineering | Volume 7 | Issue 04 | April 2018, ISSN:
2278-181.
[4] Mohamad Afzal S. Siddiqui, Abhijit N. Bhirud (2018)
“EPS, OBS, PROJECT ACTIVITIES FOR PUNE METRO
PHASE 1 IN PRIMAVERA P6” International Journal of
Science Technology & Engineering|Volume15|Issue
2 | April 2018 ISSN: 2230-7540.
[5] Akshay R. Kohil (2017), “Enterprise project
management using primavera P6” IJSTE -
International Journal of Science Technology &
Engineering | Volume 4 | Issue 12 | December 2017,p
– ISSN: 2395 -0072.
[6] Vishal AnnappaNimbal, Prof. Balasaheb Jamadar
(2017) “Planning, Scheduling and Allocation of
Resources for multi-storied Structure using Oracle’s
Primavera p6 software”, International Research
Journal of Engineering and Technology (IRJET)e-
Volume: 04 Issue:07| July 2017 ISSN:2395-0056.
[7] P. EsakkiThangam, R. M. Benila, (2016) “Planning,
Scheduling and Time Management of Six Lanes Road
Construction Work at V. O. C Port Trust using
Primavera P6 Software” IJSTE - International Journal
of Science Technology & Engineering | Volume 2 |
Issue 11 | May 2016.
[8] T. Subramani, A. Sarkunam, J. Jayalakshmi (2014)
“Planning and Scheduling of Highrise Building Using
Primavera” Journal of Engineering Research and
Applications www.ijera.com ISSN: 2248-9622, Vol. 4,
Issue6 (Version 5), June 2014, pp. 134-144.
[9] Andrew fernans tom, Sachin paul (2013) “Project
monitoring and control using Primavera” IJSTE -
International Journal of Science Technology &
Engineering | Volume 2 | Issue 3 | March 2013 ISSN:
2385 -8753

More Related Content

What's hot

Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
Susitra Anandan
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
maria_singh
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
Aishwarya Phalke
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
Toyin Osunlaja
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
Sagar Kaptan
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
Ahmed El-Askalany, CSTE, CSQA, PMP, CQIA, ITIL
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
IAEME Publication
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Ahmed Fouad, MCIArb, PMP, SP, RMP
 
Project Planning
Project PlanningProject Planning
Project Planning
Srinivasan Rengasamy
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
monishkumark
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
Rubnawaz Bhatti
 

What's hot (19)

Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 

Similar to Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6

Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
IRJET Journal
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET Journal
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...
IRJET Journal
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
Piyush Bagade
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
IJERA Editor
 
I012335763
I012335763I012335763
I012335763
IOSR Journals
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
ijtsrd
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
IRJET Journal
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
IRJET Journal
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
IJERA Editor
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET Journal
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
IJAEMSJORNAL
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
ijtsrd
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
AI Publications
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
ijtsrd
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.com
Tutors India
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
IJSRD
 

Similar to Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6 (20)

Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
 
I012335763
I012335763I012335763
I012335763
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
 
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
Planning, Scheduling and Allocation of Resources for Multi storeyed Structure...
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.com
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 

More from ijtsrd

‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation
ijtsrd
 
Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...
ijtsrd
 
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and ProspectsDynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
ijtsrd
 
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
ijtsrd
 
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
ijtsrd
 
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
ijtsrd
 
Problems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A StudyProblems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A Study
ijtsrd
 
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
ijtsrd
 
The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...
ijtsrd
 
A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...
ijtsrd
 
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
ijtsrd
 
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
ijtsrd
 
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. SadikuSustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
ijtsrd
 
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
ijtsrd
 
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
ijtsrd
 
Activating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment MapActivating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment Map
ijtsrd
 
Educational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger SocietyEducational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger Society
ijtsrd
 
Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...
ijtsrd
 
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
ijtsrd
 
Streamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine LearningStreamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine Learning
ijtsrd
 

More from ijtsrd (20)

‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation
 
Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...
 
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and ProspectsDynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
 
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
 
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
 
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
 
Problems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A StudyProblems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A Study
 
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
 
The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...
 
A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...
 
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
 
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
 
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. SadikuSustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
 
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
 
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
 
Activating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment MapActivating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment Map
 
Educational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger SocietyEducational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger Society
 
Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...
 
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
 
Streamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine LearningStreamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine Learning
 

Recently uploaded

বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
paigestewart1632
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5
sayalidalavi006
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 

Recently uploaded (20)

বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5Community pharmacy- Social and preventive pharmacy UNIT 5
Community pharmacy- Social and preventive pharmacy UNIT 5
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 

Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6

  • 1. International Journal of Trend in Scientific Research and Development (IJTSRD) Volume 5 Issue 2, January-February 2021 Available Online: www.ijtsrd.com e-ISSN: 2456 – 6470 @ IJTSRD | Unique Paper ID – IJTSRD38641 | Volume – 5 | Issue – 2 | January-February 2021 Page 1052 Review on Planning and Scheduling of Construction Project by Management Tool Primavera P6 Shashwat Dubey1, Prof. M. C. Paliwal2 1PG Student, 2Associate Professor, 1,2Department of Civil & Environmental Engineering, NITTTR, Bhopal, Madhya Pradesh, India ABSTRACT Modern construction system has shown great potential in the field of the conventional construction system. The advantage of using new construction techniques for any type of construction isthattheprocess takesnolonger.The modern method of construction is defined as a way of working more effectively to achieve more while using less. The description lends itself heavily to offsite or modular construction techniques the method of prefabricating parts of building offsite before transporting and assembling them at their final location. Unlike traditional methods of construction is defined as a way of working more effectively. Poor construction management will cause the delay. Delay in the contracted project can resultinpenaltiesand adversely affect the reputation of the company. It is essential to manage the work within time. If construction time increases, construction cost also increases. It is necessary proper planning and management for construction work. Primavera p6 is a management tool. In this study primavera software help in the planning and scheduling of the project. Primavera gives better quality of project management process and easily understanding results. KEYWORDS: Scheduling, Planning, Primavera P6, Delay How to cite this paper: Shashwat Dubey| Prof. M. C. Paliwal "Review on Planning and Scheduling of ConstructionProject by Management Tool Primavera P6" Published in International Journal of Trend in Scientific Research and Development(ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2, February 2021, pp.1052-1054, URL: www.ijtsrd.com/papers/ijtsrd38641.pdf Copyright © 2021 by author(s) and International Journal ofTrendinScientific Research and Development Journal. This is an Open Access article distributed under the terms of the Creative Commons Attribution License (CC BY 4.0) (http://creativecommons.org/licenses/by/4.0) I. INTRODUCTION Planning and scheduling are a part of modern construction techniques. They are an important role play in civil project management. Planning and scheduling are terms in a construction project which refers to attain the expected goals. Project scheduling is a technique to meet up the sequence of activities and the type of resources that will be assigned to complete those activities in the planned frame. The organization has schedules and available resources. It needs to be documented to plan those activities. Project scheduling is performed in four steps. First, define the tasks of the project. A project is a collection of activities and events, each activity has a start date andfinishdate.The next step is to define activities complete estimates of time and efforts. In this step calculation of duration concerning resources. The third step is a define activities order and the last step is assigning resources Planning and scheduling are necessary for a project to perform in a standard way and complete in planned time. Cause of planning and scheduling results we know about activities, their sequence, amount of resources before performing the task. For planning and scheduling many software available Primavera, MSP software, etc. This software helps to control andmonitorthe project. II. LITERATURE REVIEW In thischapter, literature reviewhasbeenpresentedbygoing through various articles and websites. Information about heart diagnosing and its details are also available on some websites; these are also referredtoandlistedinthereference section. Various related literature proceedings of various national and international conferences were reviewed. [1] R. KALAVIVANNA (2020)has studied the planning and scheduling of G +3residential building construction by using primavera software. Theobjectiveoftheresearchpaperwork is to schedule the residential building construction using primavera p6 and optimize the resources utilized in the project. The contract period of the project is 11 months. Construction start date 30 December 2019. In this paper, the result was observed that after planning and scheduling the time duration of the building completion was reduced by nearly 1 month. [2]S. KUMAR M, MANISANKARS (2020) have studieddelay analysis of highway construction by using primavera software. The project location is Thanjavur. The duration of the project was 24 months. Construction of the project was started on 06/09/2018. It isobserved conclusionofresearch work is a delay of the construction project was easily analyzed by primavera software. The status of each activity was easily seen with help of Primavera software. [3]PRANAV TAWALE, ANKIT MISHRA, KARAN JADHAV, SWAPNLI ONKAR (2020)have studied construction planning of high-rise building by using primavera software. The high-rise building is located at Waliv, Vasai in Maharashtra. Proper planning is a very important part of a IJTSRD38641
  • 2. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD38641 | Volume – 5 | Issue – 2 | January-February 2021 Page 1053 construction project to reduce delays of the projects. The waring mechanism must be present, which can alert the project owner of possible completionthroughouttheproject. The advantage of planning and controlling the project are Fewer construction times. Estimated approx. costs and overruns. Keep a track of the project. [4] ANKIT GUPTA, DR. SANJAY TIWARI (2020)have studied leveling resources for construction project G + 3 hospital by various software-based leveling tools. The objective of this paper was tocalculate an optimum schedule for construction project resources. The studied work represents a comparison of resource leveling by levelingtool of primavera and MS project. In this paper, the author appliesa different type of leveling tool to examine the best leveling tool. Leveling tool available in both software. Activities can split to be leveled in MS-project unlike in Primavera. [5] SUVARNA, YATEEN LOKESH, DR. S. P. MAHENDRA (2018)have studied planning, scheduling, and tracking of bridge construction by using primavera software &the EVM technique. The location of the project is Sangapura. Construction started in January 2016. The duration of the project as per the baseline schedule is 867 days. Conclusion of literature provedtohelpmeasureconstraintsperformance of a project in EVM and enable the analysis oftheefficiencyof various parameters related to the progress of the report. Following steps of the methodology followed by authors: Implementation of primavera p6 on a project. Calculation of critical path of the planned schedule. Calculation of earn value management. [6]ANURAG MAHURE, AMIT KUMAR RANIT (2018)have studied projectmanagementof200traineehostelbuildingby using primavera software. The project is located at the campus of Dr. Panjabrao, Deshmukh prabodhini Amravati. The contract period of project construction was 24 months. Conclusion of work observes an implementation of planning and scheduling by using primavera software the time duration was reduced by nearly 3 months. [7] MOHAMMAD AFZAL S. SIDDIQUI, ABHIJIT N. BHIRUD (2018)have studied, project management in Pune metro Maharashtra. The author tried to demonstrate the planning for a stretch of 10 K. M. of the metro bridge from Pimpri Chinch wad to Range hills. The conclusion of this paperwork was the estimation in a period of the Pune metro project by using primavera software. The estimated duration of the Pune metro duration by the author was not considering a major cause of delay. The future scope of studies is updating and monitoring the schedule work. [8] Vishal AnnappaNimbal,PROF.BALASAHEBJAMADAR (2017)have studied planning, scheduling & allocation of resource of a multi-storied building by using primavera software. The location of the project is Pune Maharashtra. Literature explained the importance of oracle software primavera in the construction field and applies it to the management of a multi-story structure. He finds out the estimated finishing period for the project and plans it along with resource allocation and helps us to understand the concept of primavera in a precise manner giving an example of works done in Primavera P6. He concludes that the main objective of his study was to know the role of planning and management of the project within the duration accomplishment of any construction project. His project was fulfilled with the help of literature references and unique methodologies in control and monitoring using project management application. [9]BHAJANTHRITHIRUMALESHA,BASAVARAJ(2017)have studied resource optimization in the construction of residential apartments using primavera p6. The residential apartment building with two blocks located at Navalgunda, Karnataka. The name of the site is the Karnataka police quarters building. The objective of the authors was how to find the over-allocated resources and how to balance them. This studied conclude the following result: Over allocated resources are eliminated from the activities. Optimization of resources can be done withoutchanging the project duration. [10]PUNEET SINGH (2016) has done a comparative analysis of construction techniques onto different projects by using primavera software P6. A questionnaire was formulated and personal interviews were conducted with the senior engineers and managers of both the projects by the author. The survey was conducted through direct interactions to get realistic and explained responses. The responses were recorded and analyzed statistically and the following major problems were identified that were responsible for the late completion of the project. Name of projects given below National bank, New Delhi Project B C/o Punjab C/oShaheedSukhdevCollege,New Delhi [11]P. ESAKI THAANA (2016) hasusedprimaverasoftware for planning of road construction.Timesupervisionsystemis focused to complete a key role in a construction company, which is accountable to finish the project in budget value within a certain duration. Poor task management and fund performance are major problems faced by construction organizations. The objective of this research istopreparethe planning and managementforroadworkconstructionatVOC PORT TRUST, Tuticorin. Primavera P6 software helped for monitoring and controlling the road project work. [12] T. SHIVA NAGARAJU (2016)has studied the schedule and resource optimization of Kochi metro station using primavera software. Theobjectiveoftheresearchpaperwork is to schedule the project and proper allocation of resources for construction. The average cost of the projects goes up by 30 percent of the estimated cost due to lack of planning and scheduling. Observations show that skillful management is the key for a project to complete within an allotted time frame in an estimated budget and with the allocated resources. Providinggoodplanning,properorganization,and a sufficient flow of resources to projects can automatically achieve the desired result. The result of the study shows the drawback of the actual project management system. [13]B.S.KREDDY(2015)saysthatresourceplaysimportant role in any construction project. The performance of any construction project directly depends upon resource management. For resource optimization and leveling author choose primavera p6 software in an ongoing construction project in Dubai in UAE. The main objective of this paperisto minimize under allocation of resources. After using primavera software author concluded that there is a 5. 65% resource reduction.
  • 3. International Journal of Trend in Scientific Research and Development (IJTSRD) @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD38641 | Volume – 5 | Issue – 2 | January-February 2021 Page 1054 [14] T. SUBRAMANI A. SARKUNAM, Jayalakshmi (2014)have studied comparison in time performing of the conventional method of construction for residential and industrial building system method by total construction duration. Schedule work was developed using oracle software primavera. The positive change includes creating a healthy working environment among thoseinvolveddirectly in the construction industry. The major players in the engineer’s town planners, contractor and supplier or manufacture have to play their duty in enhancing their working system, management, and administration to enable the modernization in the company. [15] ANDREW FERNANS TOM, SACHIN PAUL (2013) have work explained project planning and controlling is the process of collecting information concerning project performance. The study deals with the monitoringprocessof a four-storeyed (G+3) factory building in Cochin Kerala. A comparison between the planned progress of construction work and actual progress is performed in this study using primavera software. The methodology followed by the authors are Earn value supervision Cost performance supervision Work performance supervision III. CONCLUSION From the various studies, we can conclude planning and controlling is essential for every construction project for better performance.Projectmanagementhelpsinforecasting the project. Primavera software is a planning tool to help manage project activity and know about the status of a project. The main aim of project planning is to overcome the delay of the project. In the conventional method, project organizations don’t know the best path for project completion. The study of the literature review proves application of the primavera tool is best over the conventional method of construction. It was found that most of the authors have used primavera software in the planning of high-rise buildings,roadconstruction,bridgeconstruction, metro construction, hospital building, hostel building, etc. IV. REFERENCES [1] S. Rajlumar, P. RamPramoth, J. Sankaranarayanan, R. Kalaivannam (2020) “planningandSchedulingofG+3 building construction using primavera p6” IRJET | Volume 7 | Issue: 07 | Aug. 2020, P – ISSN: 2395 – 0072. [2] Ankit Gupta, Dr. Sanjay Tiwari (2020) “Levelling resources of a construction project by various software-basedleveling tool” IJRASET | Volume 8 | Issue: 09 | Sept. 2020| ISSN: 2321-9653. [3] Anurag Mahure, Amit Kumar Ranit (2018) “Project management using primavera P6” IJSTE - International Journal of Science Technology & Engineering | Volume 7 | Issue 04 | April 2018, ISSN: 2278-181. [4] Mohamad Afzal S. Siddiqui, Abhijit N. Bhirud (2018) “EPS, OBS, PROJECT ACTIVITIES FOR PUNE METRO PHASE 1 IN PRIMAVERA P6” International Journal of Science Technology & Engineering|Volume15|Issue 2 | April 2018 ISSN: 2230-7540. [5] Akshay R. Kohil (2017), “Enterprise project management using primavera P6” IJSTE - International Journal of Science Technology & Engineering | Volume 4 | Issue 12 | December 2017,p – ISSN: 2395 -0072. [6] Vishal AnnappaNimbal, Prof. Balasaheb Jamadar (2017) “Planning, Scheduling and Allocation of Resources for multi-storied Structure using Oracle’s Primavera p6 software”, International Research Journal of Engineering and Technology (IRJET)e- Volume: 04 Issue:07| July 2017 ISSN:2395-0056. [7] P. EsakkiThangam, R. M. Benila, (2016) “Planning, Scheduling and Time Management of Six Lanes Road Construction Work at V. O. C Port Trust using Primavera P6 Software” IJSTE - International Journal of Science Technology & Engineering | Volume 2 | Issue 11 | May 2016. [8] T. Subramani, A. Sarkunam, J. Jayalakshmi (2014) “Planning and Scheduling of Highrise Building Using Primavera” Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue6 (Version 5), June 2014, pp. 134-144. [9] Andrew fernans tom, Sachin paul (2013) “Project monitoring and control using Primavera” IJSTE - International Journal of Science Technology & Engineering | Volume 2 | Issue 3 | March 2013 ISSN: 2385 -8753