SlideShare a Scribd company logo
Ashish Kumar Ganguli
Date: 21.01.2017
PERCETANGE IMPEDENCE OF TRANSFORMER
&
IT'S IMPORATANCE IN POWER SYSTEM STUDIES.
---------------------------------------------------------------------------------------------------------
BY :
ASHISH KUMAR GANGULI
Bachelor of Engineering - Electrical
MOBILE : 0091-9109782929
EMAIL : ashish_ganguli06@yahoo.co.in
---------------------------------------------------------------------------------------------------------
Ashish Kumar Ganguli
Date: 21.01.2017
DEFINITAION:
Percentage impedance of a transformer is the percentage of rated voltage applied at one
side (primary winding) to circulate rated current on transformer keeping its other side
(secondary winding) under short circuit conditions. It is marked on transformer
nameplate.
EXPLANATION:
If we apply rated voltage at primary winding of a transformer keeping its secondary
winding short circuited, then amount of current at both windings will be extremely
high as compared to the rated current. This current is called short circuit current and its
magnitude is very high due to zero impedance offered by the load (secondary winding
is short circuited).
Consider,
V : Rated Primary Voltage of Transformer
Z% : Percentage Impedance of Transformer
Irated : Rated Primary Current of Transformer
Zactual : Actual Impedance of Transformer (referred to primary winding)
Based on above explanation, we are applying a percentage (Z %) of rated primary
voltage. Therefore applied voltage is equal to V x Z% / 100. This voltage drives rated
current in transformer winding.
By Ohms Law:
Voltage = Current x Actual Impedance
V x Z% /100 = Irated x Zactual
Z% = Irated Zactual x 100 / V
Now, if we reduce the applied voltage on the
transformer primary i.e. we apply percentage of
rated voltage in transformer primary, current on
both windings will also reduce. At a particular
percentage of rated voltage, rated current will flow
on transformer windings. This percentage of rated
voltage at one side of transformer which circulates
rated current on transformer windings keeping its
other side winding short circuited, is called
percentage impedance of transformer.
Ashish Kumar Ganguli
Date: 21.01.2017
ROLE OF Z% IN SHORT CIRCUIT CALCULATION
Percentage impedance of transformer plays extremely vital role is network calculation
i.e. short circuit calculation and voltage drop calculation.
We can find the short circuit contribution of a transformer as per below explanation:
As considered above, secondary winding of transformer is short circuited.
Now,
If Voltage (V Z% /100) is applied on Transformer Primary, Rated Current (Irated) flows.
If Voltage (V) is applied on Transformer Primary, Current (Irated x 100 / Z%) will flow.
Therefore, when we apply rated voltage at primary winding of a transformer whose
secondary winding is short circuited, short circuit current (Irated x 100 / Z%) will flow on
transformer windings. Value of Z% is same for both windings as it is percentage of
rated voltage. However value of Irated will be different for primary and secondary
winding. Accordingly value of short circuit current will also be different for primary
and secondary windings.
Short Circuit Current (Isc) = Irated x 100 / Z%
If percentage impedance of a transformer is less, its short circuit current will be more
which will produce more stress in insulation. This is a negative factor. On the other
hand, if percentage impedance of a transformer is less, voltage drop on transformer
winding will be less which will facilitate better voltage regulation. This is a positive
factor. Therefore, percentage impedance of transformer has to be precisely selected to
maintain a proper balance between fault level and voltage regulation.
PERMITTED TOLERANCE IN Z%
Percentage impedance of transformer is specified at the time of ordering. But it must
be noted that IEC 76 permits +/- 10% tolerance in percentage impedance at
manufacturer's end. Therefore, if we order a transformer with 8% percentage
impedance, its actual percentage impedance after manufacturing may be any value
between 7.2% (-10% of 8) to 8.8% (+10% of 8), unless it is specifically agreed with
manufacturer at the time of ordering. Tolerance in percentage impedance must be
considered for power system calculations and accordingly system fault level & voltage
regulation must be finalized.
Ashish Kumar Ganguli
Date: 21.01.2017
ROLE OF Z% IN PARALLEL OPERATION OF TRANSFORMERS
If the ratios of kVA rating to percent impedance of two transformers operating in
parallel are equal, they will share equal load. However if ratio is different, they will
share unequal load. This may result in overloading of one transformer.
In order to analyses this criterion; let us consider two transformers operating in parallel
as shown in below diagram.
I1 : Load current from transformer 1
I2 : Load current from transformer 2
IL : Total load current (IL = I1 + I2)
Z1 : Actual impedance of transformer 1
Z2 : Actual impedance of transformer 2
Z1% : Percentage Impedance of transformer 2
Z2% : Percentage Impedance of transformer 2
kVA1 : kVA rating of transformer 1
kVA2 : kVA rating of transformer 2
kVAL : Total load kVA
Ashish Kumar Ganguli
Date: 21.01.2017
We know that
V x Z% / 100 = Irated Zactual
Therefore,
Z1 = (V x Z%1)/ (100 x I1)
Z2 = (V x Z%2)/ (100 x I2)
If we substitute value of actual impedance (Z1 & Z2) as per above equation, we get
If we multiply both sides with kV, we get
If ratio kVA1 / Z1% and kVA2 / Z2% are equal, then kVA1 and kVA2 will be same. That
means, both transformers will share equal load i.e. 50% of total load. This factor must
be analyzed before paralleling two transformers to avoid unequal load sharing and
overloading of one transformer.

More Related Content

What's hot

Transformer Failures and Case Studies
Transformer Failures and Case StudiesTransformer Failures and Case Studies
Transformer Failures and Case Studies
ProSIM R & D Pvt. Ltd.
 
Classification of unified power quality compensators
Classification of unified power quality compensatorsClassification of unified power quality compensators
Classification of unified power quality compensators
DuvvuruSravya
 
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
Rohit vijay
 
Transformer
TransformerTransformer
Transformer
Sandeep Kumar
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
Roberto Costa
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
Rakesh Joshi
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc system
Aazim Rasool
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
Power System Operation
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
Aman Ansari
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
Ameen San
 
Power system transients (IV-EEE)
Power system transients (IV-EEE)Power system transients (IV-EEE)
Power system transients (IV-EEE)
betasam
 
Motor & generator protection example settings
Motor & generator protection example settingsMotor & generator protection example settings
Motor & generator protection example settings
H. Kheir
 
Firing angle control
Firing angle controlFiring angle control
Firing angle control
jawaharramaya
 
FREQUENCY STABILITY
FREQUENCY STABILITYFREQUENCY STABILITY
FREQUENCY STABILITY
Power System Operation
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
vikasgupta1965
 
Transient overvoltages and currents: ferroresonance effects
Transient overvoltages and currents: ferroresonance effectsTransient overvoltages and currents: ferroresonance effects
Transient overvoltages and currents: ferroresonance effects
Bruno De Wachter
 
AC AC converters
AC AC convertersAC AC converters
AC AC converters
Firas Obeidat
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
Prashant Kumar
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
Himmelstern
 
Function relay types
Function relay typesFunction relay types
Function relay types
jawaharramaya
 

What's hot (20)

Transformer Failures and Case Studies
Transformer Failures and Case StudiesTransformer Failures and Case Studies
Transformer Failures and Case Studies
 
Classification of unified power quality compensators
Classification of unified power quality compensatorsClassification of unified power quality compensators
Classification of unified power quality compensators
 
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
 
Transformer
TransformerTransformer
Transformer
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc system
 
Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
 
Power system transients (IV-EEE)
Power system transients (IV-EEE)Power system transients (IV-EEE)
Power system transients (IV-EEE)
 
Motor & generator protection example settings
Motor & generator protection example settingsMotor & generator protection example settings
Motor & generator protection example settings
 
Firing angle control
Firing angle controlFiring angle control
Firing angle control
 
FREQUENCY STABILITY
FREQUENCY STABILITYFREQUENCY STABILITY
FREQUENCY STABILITY
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transient overvoltages and currents: ferroresonance effects
Transient overvoltages and currents: ferroresonance effectsTransient overvoltages and currents: ferroresonance effects
Transient overvoltages and currents: ferroresonance effects
 
AC AC converters
AC AC convertersAC AC converters
AC AC converters
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
 
Function relay types
Function relay typesFunction relay types
Function relay types
 

Viewers also liked

Types of transformer
Types of transformerTypes of transformer
Types of transformer
Raafat Ismael
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
gourav1245
 
Power transformer
Power transformerPower transformer
Power transformer
Asif Ahmed Khan
 
Power transformer
Power transformerPower transformer
Power transformer
ZunAib Ali
 
Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
Dheeraj Upadhyay
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
ajayknows
 

Viewers also liked (6)

Types of transformer
Types of transformerTypes of transformer
Types of transformer
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
 
Power transformer
Power transformerPower transformer
Power transformer
 
Power transformer
Power transformerPower transformer
Power transformer
 
Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )Power Transformer ( Summer Training presentation BHEL )
Power Transformer ( Summer Training presentation BHEL )
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 

Similar to Percentage Impedance of Transformer

Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Power System Operation
 
Ms3621652169
Ms3621652169Ms3621652169
Ms3621652169
IJERA Editor
 
C0212014018
C0212014018C0212014018
C0212014018
theijes
 
New zv zcs full bridge dc-dc converter with fuzzy & pi control
New zv zcs full bridge dc-dc converter with fuzzy & pi controlNew zv zcs full bridge dc-dc converter with fuzzy & pi control
New zv zcs full bridge dc-dc converter with fuzzy & pi control
IAEME Publication
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdf
ShanmukhSaiR
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharing
Vivek Arun
 
Voltage Regulators IC
Voltage Regulators ICVoltage Regulators IC
Voltage Regulators IC
Dr.Raja R
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
Muthar Hussain
 
8925273.ppt
8925273.ppt8925273.ppt
Performance Evaluation of Synchronous Generator under Sudden Loss of Excitation
Performance Evaluation of Synchronous Generator under Sudden Loss of ExcitationPerformance Evaluation of Synchronous Generator under Sudden Loss of Excitation
Performance Evaluation of Synchronous Generator under Sudden Loss of Excitation
paperpublications3
 
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
IRJET Journal
 
P.u systems.pptx
P.u systems.pptxP.u systems.pptx
P.u systems.pptx
GireeshkumarD
 
Sizing generators-for-leading-power-factor white-paper-24_feb14
Sizing generators-for-leading-power-factor white-paper-24_feb14Sizing generators-for-leading-power-factor white-paper-24_feb14
Sizing generators-for-leading-power-factor white-paper-24_feb14
Insanul Aziz
 
ALL DAY EFFICIENCY
ALL DAY EFFICIENCYALL DAY EFFICIENCY
ALL DAY EFFICIENCY
Maria Romina Angustia
 
Swing equation
Swing equationSwing equation
Swing equation
Darshil Shah
 
Comulatively Compounded DC Generator
Comulatively Compounded DC GeneratorComulatively Compounded DC Generator
Comulatively Compounded DC Generator
Asim Raza
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - II
karthi1017
 
Earth Faults and Reverse Power in Transmission Lines
Earth Faults and Reverse Power in Transmission LinesEarth Faults and Reverse Power in Transmission Lines
Earth Faults and Reverse Power in Transmission Lines
ToshaliMohapatra
 
On line nonlinearity compensation technique for pwm inverter drives
On   line nonlinearity compensation technique for pwm inverter drivesOn   line nonlinearity compensation technique for pwm inverter drives
On line nonlinearity compensation technique for pwm inverter drives
IAEME Publication
 

Similar to Percentage Impedance of Transformer (20)

Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
 
Ms3621652169
Ms3621652169Ms3621652169
Ms3621652169
 
C0212014018
C0212014018C0212014018
C0212014018
 
New zv zcs full bridge dc-dc converter with fuzzy & pi control
New zv zcs full bridge dc-dc converter with fuzzy & pi controlNew zv zcs full bridge dc-dc converter with fuzzy & pi control
New zv zcs full bridge dc-dc converter with fuzzy & pi control
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdf
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharing
 
Voltage Regulators IC
Voltage Regulators ICVoltage Regulators IC
Voltage Regulators IC
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
8925273.ppt
8925273.ppt8925273.ppt
8925273.ppt
 
Performance Evaluation of Synchronous Generator under Sudden Loss of Excitation
Performance Evaluation of Synchronous Generator under Sudden Loss of ExcitationPerformance Evaluation of Synchronous Generator under Sudden Loss of Excitation
Performance Evaluation of Synchronous Generator under Sudden Loss of Excitation
 
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
IRJET- Series and Shunt Compensation in UPFC using Cascaded Multilevel Invert...
 
P.u systems.pptx
P.u systems.pptxP.u systems.pptx
P.u systems.pptx
 
Sizing generators-for-leading-power-factor white-paper-24_feb14
Sizing generators-for-leading-power-factor white-paper-24_feb14Sizing generators-for-leading-power-factor white-paper-24_feb14
Sizing generators-for-leading-power-factor white-paper-24_feb14
 
ALL DAY EFFICIENCY
ALL DAY EFFICIENCYALL DAY EFFICIENCY
ALL DAY EFFICIENCY
 
Swing equation
Swing equationSwing equation
Swing equation
 
Comulatively Compounded DC Generator
Comulatively Compounded DC GeneratorComulatively Compounded DC Generator
Comulatively Compounded DC Generator
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - II
 
Earth Faults and Reverse Power in Transmission Lines
Earth Faults and Reverse Power in Transmission LinesEarth Faults and Reverse Power in Transmission Lines
Earth Faults and Reverse Power in Transmission Lines
 
On line nonlinearity compensation technique for pwm inverter drives
On   line nonlinearity compensation technique for pwm inverter drivesOn   line nonlinearity compensation technique for pwm inverter drives
On line nonlinearity compensation technique for pwm inverter drives
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 

Percentage Impedance of Transformer

  • 1. Ashish Kumar Ganguli Date: 21.01.2017 PERCETANGE IMPEDENCE OF TRANSFORMER & IT'S IMPORATANCE IN POWER SYSTEM STUDIES. --------------------------------------------------------------------------------------------------------- BY : ASHISH KUMAR GANGULI Bachelor of Engineering - Electrical MOBILE : 0091-9109782929 EMAIL : ashish_ganguli06@yahoo.co.in ---------------------------------------------------------------------------------------------------------
  • 2. Ashish Kumar Ganguli Date: 21.01.2017 DEFINITAION: Percentage impedance of a transformer is the percentage of rated voltage applied at one side (primary winding) to circulate rated current on transformer keeping its other side (secondary winding) under short circuit conditions. It is marked on transformer nameplate. EXPLANATION: If we apply rated voltage at primary winding of a transformer keeping its secondary winding short circuited, then amount of current at both windings will be extremely high as compared to the rated current. This current is called short circuit current and its magnitude is very high due to zero impedance offered by the load (secondary winding is short circuited). Consider, V : Rated Primary Voltage of Transformer Z% : Percentage Impedance of Transformer Irated : Rated Primary Current of Transformer Zactual : Actual Impedance of Transformer (referred to primary winding) Based on above explanation, we are applying a percentage (Z %) of rated primary voltage. Therefore applied voltage is equal to V x Z% / 100. This voltage drives rated current in transformer winding. By Ohms Law: Voltage = Current x Actual Impedance V x Z% /100 = Irated x Zactual Z% = Irated Zactual x 100 / V Now, if we reduce the applied voltage on the transformer primary i.e. we apply percentage of rated voltage in transformer primary, current on both windings will also reduce. At a particular percentage of rated voltage, rated current will flow on transformer windings. This percentage of rated voltage at one side of transformer which circulates rated current on transformer windings keeping its other side winding short circuited, is called percentage impedance of transformer.
  • 3. Ashish Kumar Ganguli Date: 21.01.2017 ROLE OF Z% IN SHORT CIRCUIT CALCULATION Percentage impedance of transformer plays extremely vital role is network calculation i.e. short circuit calculation and voltage drop calculation. We can find the short circuit contribution of a transformer as per below explanation: As considered above, secondary winding of transformer is short circuited. Now, If Voltage (V Z% /100) is applied on Transformer Primary, Rated Current (Irated) flows. If Voltage (V) is applied on Transformer Primary, Current (Irated x 100 / Z%) will flow. Therefore, when we apply rated voltage at primary winding of a transformer whose secondary winding is short circuited, short circuit current (Irated x 100 / Z%) will flow on transformer windings. Value of Z% is same for both windings as it is percentage of rated voltage. However value of Irated will be different for primary and secondary winding. Accordingly value of short circuit current will also be different for primary and secondary windings. Short Circuit Current (Isc) = Irated x 100 / Z% If percentage impedance of a transformer is less, its short circuit current will be more which will produce more stress in insulation. This is a negative factor. On the other hand, if percentage impedance of a transformer is less, voltage drop on transformer winding will be less which will facilitate better voltage regulation. This is a positive factor. Therefore, percentage impedance of transformer has to be precisely selected to maintain a proper balance between fault level and voltage regulation. PERMITTED TOLERANCE IN Z% Percentage impedance of transformer is specified at the time of ordering. But it must be noted that IEC 76 permits +/- 10% tolerance in percentage impedance at manufacturer's end. Therefore, if we order a transformer with 8% percentage impedance, its actual percentage impedance after manufacturing may be any value between 7.2% (-10% of 8) to 8.8% (+10% of 8), unless it is specifically agreed with manufacturer at the time of ordering. Tolerance in percentage impedance must be considered for power system calculations and accordingly system fault level & voltage regulation must be finalized.
  • 4. Ashish Kumar Ganguli Date: 21.01.2017 ROLE OF Z% IN PARALLEL OPERATION OF TRANSFORMERS If the ratios of kVA rating to percent impedance of two transformers operating in parallel are equal, they will share equal load. However if ratio is different, they will share unequal load. This may result in overloading of one transformer. In order to analyses this criterion; let us consider two transformers operating in parallel as shown in below diagram. I1 : Load current from transformer 1 I2 : Load current from transformer 2 IL : Total load current (IL = I1 + I2) Z1 : Actual impedance of transformer 1 Z2 : Actual impedance of transformer 2 Z1% : Percentage Impedance of transformer 2 Z2% : Percentage Impedance of transformer 2 kVA1 : kVA rating of transformer 1 kVA2 : kVA rating of transformer 2 kVAL : Total load kVA
  • 5. Ashish Kumar Ganguli Date: 21.01.2017 We know that V x Z% / 100 = Irated Zactual Therefore, Z1 = (V x Z%1)/ (100 x I1) Z2 = (V x Z%2)/ (100 x I2) If we substitute value of actual impedance (Z1 & Z2) as per above equation, we get If we multiply both sides with kV, we get If ratio kVA1 / Z1% and kVA2 / Z2% are equal, then kVA1 and kVA2 will be same. That means, both transformers will share equal load i.e. 50% of total load. This factor must be analyzed before paralleling two transformers to avoid unequal load sharing and overloading of one transformer.