SlideShare a Scribd company logo
Testing
of
Transformer
K.N.Srinivasan
Traceabllity
Accuracy
Precision
Probability
Std. deviation
Standards
Accreditation
Insulation tests
Short ckt test
Power rating
Other tests
Overview
A MODERN TRANSFORMER IS A
COMPLEX ELECTROMAGNETIC
APPARATUS
TRANSFORMERS SERVE FOR
TRANSMISSION AND DISTRIBUTION
OF ELECTRICAL ENERGY
TRANSFORMERS (DISTRIBUTION)
ARE THE LAST MAJOR LINK
BETWEEN UTILITY & CONSUMER
Introduction
TRANSFORMERS ARE STATIC
ALTERNATING CURRENT MACHINES
PRINCIPLE IS BASED ON MUTUAL
INDUCTION BETWEEN WINDINGS
THROUGH A COMMON CORE
OIL-IMMERSED AND DRY TYPES
POWER AND DISTRIBUTION TYPES
SPECIAL TYPES
Transformer on load
ϕ
V1
I0
E2
I1I’2
I2
E = - 4.44 φmf N
 Measurement of winding resistance
 Measurement of voltage ratio
 Polarity test
 Measurement of no-load loss & no-load current
 Measurement of load-loss & short-circuit impedance
 Measurement of insulation resistance
 Dielectric tests
Routine tests
 Measurement of winding resistance
 Measurement of voltage ratio
 Polarity test
 Measurement of no-load loss & no-load current
 Measurement of load-loss & short-circuit impedance
 Measurement of insulation resistance
 Dielectric tests
 Temperature-rise test
Type tests
 Dielectric test
 Short-circuit test
 Measurement of zero-sequence
impedance of three phase transformers
 Measurement of acoustic noise level
 Measurement of harmonics of the no-load
current
 Measurement of power taken by the fans
& oil pumps
Special tests
 Dielectric test
 Short-circuit test
 Measurement of zero-sequence
impedance of three phase transformers
 Measurement of acoustic noise level
 Measurement of harmonics of the no-load
current
 Measurement of power taken by the fans
& oil pumps
Special tests
• Separate source voltage withstand test
• Induced over voltage withstand test
• Impulse voltage withstand test
Dielectric test
Terminals of windings under test connected to HV terminal of the
source . All other windings, core, frame and tank are earthed.
Duration of test is 60 secs.
Highest system voltage(kV) Power frequency voltage(kV)
1.1 3
3.6 10
7.2 20
12 28
24 50
36 70
52 95
72.5 140
Separate source voltage withstand test
 This test is useful in determining
layer insulation and inter turn
insulation of windings.
 HV is kept open & twice the rated
voltage at twice the rated frequency
is applied to the LV for a duration of
60 secs.
Induced over voltage withstand test
Testing facilities
• Impulse generator
• Discharge circuit
• Recording system
• Voltage divider for measurement
Standard Impulse wave
Impulse withstand test
Wave shape
 Standard wave shape of impulse voltage is
1.2/50µsec.
 t1 is the rise time = 1.2µsecs.
 t2 is the tail time = 50 µ secs.
 Tolerance on t1 is ±30% & ±20% on t2.
Impulse generator
 Impulse wave is generated by discharge of
capacitors charged in parallel into a wave shaping
circuit.
Connection
Fig.7.3.1.Connection diagram
lmpulse Application : (Negative Polarity).
Oscillograms : 7.3.1 Reduced full wave 100 kV (Peak)
7.3.2. 100% full wave 170 kV (Peak)
7.3.3 Reduced Chopped wave 103 kV (Peak)
7.3.4. 100% chopped wave 170 kV (Peak)
7.3.5. 100% chopped wave 170 kV (Peak)
7.3.6. 100% full wave 170 kV (Peak)
7.2.7. 100% full wave 170 kV (Peak)
Oscilograms
Oscilograms contd.
Oscilograms contd.
Fig 7.3.3 Connection diagram
Generator capacitance 0.0625 uF
Series resistance 160 ohms
Tail resistance 1040 ohms
Voltage divider 1200 pF in parallel with 100 ohms
Impulse applications : (Negative Polarity)
Oscillogram No. 7.3.15. Reduced full wave 43 kV (Peak)
7.3.16. 100% full wave - 75 kV (Peak)
7.3.17. 100% full wave 75 kV (peak)
Comparison of oscillograms 15 & 16 indicates that the second voltage wave
oscillogram has collapsed and the corresponding point of the neutral current
there are high frequency oscillations. This indicates an arc over across major
portion of the transformer winding as a result of failure of the transformer
insulation.
Oscillograms 7.3.15 to 7.3.17
 MINOR INSULATION -conductor turns,
layers
●
enamel, paper
●
oil ducts, paper cylinders
 MAJOR INSULATION- winding, core
●
press board cylinders, oil ducts
BUSHINGS - porcelain , condenser
Power & distribution transformers must be constructed to
withstand mechanical stresses caused by external faults.
These stresses are produced due to electromagnetic forces
as a result of very high current in the windings during
short-circuits.
Short-circuit test
 Prior to the short-circuit, transformer
is subjected to routine tests.
Asymmetrical current
 The peak current that transformer is
required to withstand = Isc(peak)=K Isc
Dynamic ability to withstand short-circuit
Value of K :
x/r 1 1.5 2 3 4 5 6 8 10 >14
K 1.51 1.64 1.76 1.95 2.09 2.19 2.27 2.38 2.46 2.55
Short-circuit may be
a) Preset or
b) Post set
Duration of each test
being 0.5 sec. ( > 5 MVA 0.25 sec)
For 1φ Transformers
No. of tests = Three
one test with tap at highest voltage ratio, one test in principal taping &
one test in
lowest voltage ratio
Short-circuit testing procedure
3φ Transformers
 No. of tests = Nine
 Three tests with tap at highest voltage ratio, three
tests in principal taping & three tests in lowest voltage
ratio
Tolerances on
 Asymmetrical current = ±5 %
 Symmetrical current = ±10 %
 Test duration = ±10 %
Oscillogram of dynamic short-circuit test on
3Phase 11/0.433kV 500kVA Distribution
transformer
 All the routine tests shall be repeated
 Dielectric test shall be at 75%
 Transformer shall be untanked
 Reactance measured after s.c. test shall not
differ by more than 2% for circular coils & 7.5%
for non-circular coils.
Analysis of the results
SC Test contd.
This is to ascertain that transformer & its cooling arrangements
are effectively designed so that temp. rise of winding & cooling
medium does not exceed the permissible limits.
Temp. rise limits for Dry type transformers
Class of insulation Temp. rise °C
A 50
E 65
B 70
F 90
H 115
C 140
Temperature rise test
Temp. rise limits for oil immersed transformers
Part Temp. rise °C
External cooling medium
Air Water
Winding 55 60
(temp.rise by resistance method)
Top oil 50 55
(temp.rise by thermometer method)
a) Direct loading
b) Back-to-Back method
c) Short-circuit method
Loading methods
Duration of test
Top oil temperature-rise does not vary more than
10
C/hour during 4 consecutive hourly readings
Partial Discharge Tests
100pC
500pC
Sound pressure level 20 log10 d/0.00002 dB
d Newton per square meter
Noise Level
meter
Highest voltage
for equipment
Um
kV
(r.m.s. value)
Rated short duration
power frequency
withstand voltage
kV
(r.m.s. value)
Rated
lightning impulse
withstand voltage
kV
(peak value)
3.6 10 20
40
7.2 20 40
60
12 28 60
75
95
17.5 38 75
95
24 50 95
125
145
36 70 145
170
52 95 250
72.5 140 325
123 (185)
230
450
550
145 (185)
230
275
(450)
550
650
170 (230)
275
325
(550)
650
750
245 (275)
(325)
360
395
460
(650)
(750)
850
950
1050
Highest
voltage for
equipment
Um
kV
(r.m.s. value)
Standard switching impulse
withstand voltage
--------------------------------------
-------------------
Longitudinal Phase-to-earth
Phase-to-phase
Insulation
(ratio to the
(note 1)
phase-to-earth
kV kV
peak value)
(peak value) (peak value)
Standard
lightning impulse
withstand voltage
kV
(peak value)
300 750 750 1,50 850
950
750 850 1,50 950
1050
362 850 850 1,50 950
1050
850 950 1,50 1050
1175
420 850 850 1,60 1050
1175
950 950 1,50 1175
1300
950 1050 1,50 1300
1425
525 950 950 1,70 1175
1300
950 1050 1,60 1300
1425
950 1175 1,50 1425
1550
765 1175 1300 1,70 1675
1800
1175 1425 1,70 1800
1950
1175 1550 1,60 1950
2100

More Related Content

What's hot

Transformer
TransformerTransformer
Transformer
Sandeep Kumar
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
Rakesh Joshi
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
Geetesh Verma
 
Design of transformer
Design of transformerDesign of transformer
Design of transformer
Subrata Dey
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
D Målîk
 
Full transformer
Full transformerFull transformer
Full transformer
Prateek Anandpara
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
Kabilesh K
 
Instrument Transformer Presentation
Instrument Transformer PresentationInstrument Transformer Presentation
Instrument Transformer Presentation
Rishi Raj
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
siddharam kantoli
 
Unit I design of electrical machines
Unit I   design of electrical machinesUnit I   design of electrical machines
Unit I design of electrical machines
nganesh90
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
pandiyarajanc
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
Sumeet Ratnawat
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
PremanandDesai
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
Preet_patel
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
Roberto Costa
 
Three phase transformer ( vector groups)
Three phase  transformer ( vector groups)Three phase  transformer ( vector groups)
Three phase transformer ( vector groups)
Dr.Raja Masood Larik
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
SARAVANAN A
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 

What's hot (20)

Transformer
TransformerTransformer
Transformer
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Design of transformer
Design of transformerDesign of transformer
Design of transformer
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
Full transformer
Full transformerFull transformer
Full transformer
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Instrument Transformer Presentation
Instrument Transformer PresentationInstrument Transformer Presentation
Instrument Transformer Presentation
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Unit I design of electrical machines
Unit I   design of electrical machinesUnit I   design of electrical machines
Unit I design of electrical machines
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Three phase transformer ( vector groups)
Three phase  transformer ( vector groups)Three phase  transformer ( vector groups)
Three phase transformer ( vector groups)
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 

Viewers also liked

EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4
ruhiyah
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
Pooja Dubey
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
MILAN MANAVAR
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6
ruhiyah
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)
ruhiyah
 
Lecture 8 bjt_1
Lecture 8 bjt_1Lecture 8 bjt_1
Lecture 8 bjt_1
Napex Terra
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORS
AJAL A J
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)firozamin
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behin
Behin anben
 

Viewers also liked (9)

EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)
 
Lecture 8 bjt_1
Lecture 8 bjt_1Lecture 8 bjt_1
Lecture 8 bjt_1
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORS
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behin
 

Similar to Testing of transformer

Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromerpretty gurna
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
hiiarindam
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
NguyenXuanTung12
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
Muthar Hussain
 
Differential protection
Differential protectionDifferential protection
Differential protection
Rishi Tandon
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
vikas kumar
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
Thorne & Derrick International
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Asha Anu Kurian
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
ChristinaBoyd12
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
santubanga333
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
ssuser1f60f6
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
Satish Pydimarla
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
Leonardo ENERGY
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformer
kennypowerhv
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
Muthar Hussain
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Insulation co cordination design
Insulation co cordination designInsulation co cordination design
Insulation co cordination design
Naresh Surisetti
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
MANOJ KUMAR MAHARANA
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
Abdul Rahman Ibrahim
 

Similar to Testing of transformer (20)

Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromer
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
Differential protection
Differential protectionDifferential protection
Differential protection
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformer
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
Testing
TestingTesting
Testing
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Insulation co cordination design
Insulation co cordination designInsulation co cordination design
Insulation co cordination design
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
 

Recently uploaded

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 

Recently uploaded (20)

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 

Testing of transformer

  • 3. Insulation tests Short ckt test Power rating Other tests
  • 4. Overview A MODERN TRANSFORMER IS A COMPLEX ELECTROMAGNETIC APPARATUS TRANSFORMERS SERVE FOR TRANSMISSION AND DISTRIBUTION OF ELECTRICAL ENERGY TRANSFORMERS (DISTRIBUTION) ARE THE LAST MAJOR LINK BETWEEN UTILITY & CONSUMER
  • 5. Introduction TRANSFORMERS ARE STATIC ALTERNATING CURRENT MACHINES PRINCIPLE IS BASED ON MUTUAL INDUCTION BETWEEN WINDINGS THROUGH A COMMON CORE OIL-IMMERSED AND DRY TYPES POWER AND DISTRIBUTION TYPES SPECIAL TYPES
  • 7.  Measurement of winding resistance  Measurement of voltage ratio  Polarity test  Measurement of no-load loss & no-load current  Measurement of load-loss & short-circuit impedance  Measurement of insulation resistance  Dielectric tests Routine tests
  • 8.  Measurement of winding resistance  Measurement of voltage ratio  Polarity test  Measurement of no-load loss & no-load current  Measurement of load-loss & short-circuit impedance  Measurement of insulation resistance  Dielectric tests  Temperature-rise test Type tests
  • 9.  Dielectric test  Short-circuit test  Measurement of zero-sequence impedance of three phase transformers  Measurement of acoustic noise level  Measurement of harmonics of the no-load current  Measurement of power taken by the fans & oil pumps Special tests
  • 10.  Dielectric test  Short-circuit test  Measurement of zero-sequence impedance of three phase transformers  Measurement of acoustic noise level  Measurement of harmonics of the no-load current  Measurement of power taken by the fans & oil pumps Special tests
  • 11. • Separate source voltage withstand test • Induced over voltage withstand test • Impulse voltage withstand test Dielectric test
  • 12. Terminals of windings under test connected to HV terminal of the source . All other windings, core, frame and tank are earthed. Duration of test is 60 secs. Highest system voltage(kV) Power frequency voltage(kV) 1.1 3 3.6 10 7.2 20 12 28 24 50 36 70 52 95 72.5 140 Separate source voltage withstand test
  • 13.  This test is useful in determining layer insulation and inter turn insulation of windings.  HV is kept open & twice the rated voltage at twice the rated frequency is applied to the LV for a duration of 60 secs. Induced over voltage withstand test
  • 14. Testing facilities • Impulse generator • Discharge circuit • Recording system • Voltage divider for measurement Standard Impulse wave Impulse withstand test
  • 15. Wave shape  Standard wave shape of impulse voltage is 1.2/50µsec.  t1 is the rise time = 1.2µsecs.  t2 is the tail time = 50 µ secs.  Tolerance on t1 is ±30% & ±20% on t2. Impulse generator  Impulse wave is generated by discharge of capacitors charged in parallel into a wave shaping circuit.
  • 16. Connection Fig.7.3.1.Connection diagram lmpulse Application : (Negative Polarity). Oscillograms : 7.3.1 Reduced full wave 100 kV (Peak) 7.3.2. 100% full wave 170 kV (Peak) 7.3.3 Reduced Chopped wave 103 kV (Peak) 7.3.4. 100% chopped wave 170 kV (Peak) 7.3.5. 100% chopped wave 170 kV (Peak) 7.3.6. 100% full wave 170 kV (Peak) 7.2.7. 100% full wave 170 kV (Peak)
  • 19. Oscilograms contd. Fig 7.3.3 Connection diagram Generator capacitance 0.0625 uF Series resistance 160 ohms Tail resistance 1040 ohms Voltage divider 1200 pF in parallel with 100 ohms Impulse applications : (Negative Polarity) Oscillogram No. 7.3.15. Reduced full wave 43 kV (Peak) 7.3.16. 100% full wave - 75 kV (Peak) 7.3.17. 100% full wave 75 kV (peak) Comparison of oscillograms 15 & 16 indicates that the second voltage wave oscillogram has collapsed and the corresponding point of the neutral current there are high frequency oscillations. This indicates an arc over across major portion of the transformer winding as a result of failure of the transformer insulation.
  • 21.  MINOR INSULATION -conductor turns, layers ● enamel, paper ● oil ducts, paper cylinders  MAJOR INSULATION- winding, core ● press board cylinders, oil ducts BUSHINGS - porcelain , condenser
  • 22. Power & distribution transformers must be constructed to withstand mechanical stresses caused by external faults. These stresses are produced due to electromagnetic forces as a result of very high current in the windings during short-circuits. Short-circuit test
  • 23.  Prior to the short-circuit, transformer is subjected to routine tests. Asymmetrical current  The peak current that transformer is required to withstand = Isc(peak)=K Isc Dynamic ability to withstand short-circuit Value of K : x/r 1 1.5 2 3 4 5 6 8 10 >14 K 1.51 1.64 1.76 1.95 2.09 2.19 2.27 2.38 2.46 2.55
  • 24. Short-circuit may be a) Preset or b) Post set Duration of each test being 0.5 sec. ( > 5 MVA 0.25 sec) For 1φ Transformers No. of tests = Three one test with tap at highest voltage ratio, one test in principal taping & one test in lowest voltage ratio Short-circuit testing procedure
  • 25. 3φ Transformers  No. of tests = Nine  Three tests with tap at highest voltage ratio, three tests in principal taping & three tests in lowest voltage ratio Tolerances on  Asymmetrical current = ±5 %  Symmetrical current = ±10 %  Test duration = ±10 %
  • 26. Oscillogram of dynamic short-circuit test on 3Phase 11/0.433kV 500kVA Distribution transformer
  • 27.  All the routine tests shall be repeated  Dielectric test shall be at 75%  Transformer shall be untanked  Reactance measured after s.c. test shall not differ by more than 2% for circular coils & 7.5% for non-circular coils. Analysis of the results SC Test contd.
  • 28. This is to ascertain that transformer & its cooling arrangements are effectively designed so that temp. rise of winding & cooling medium does not exceed the permissible limits. Temp. rise limits for Dry type transformers Class of insulation Temp. rise °C A 50 E 65 B 70 F 90 H 115 C 140 Temperature rise test
  • 29. Temp. rise limits for oil immersed transformers Part Temp. rise °C External cooling medium Air Water Winding 55 60 (temp.rise by resistance method) Top oil 50 55 (temp.rise by thermometer method)
  • 30. a) Direct loading b) Back-to-Back method c) Short-circuit method Loading methods Duration of test Top oil temperature-rise does not vary more than 10 C/hour during 4 consecutive hourly readings
  • 32. Sound pressure level 20 log10 d/0.00002 dB d Newton per square meter Noise Level
  • 33.
  • 34.
  • 35. meter
  • 36. Highest voltage for equipment Um kV (r.m.s. value) Rated short duration power frequency withstand voltage kV (r.m.s. value) Rated lightning impulse withstand voltage kV (peak value) 3.6 10 20 40 7.2 20 40 60 12 28 60 75 95 17.5 38 75 95 24 50 95 125 145 36 70 145 170 52 95 250 72.5 140 325 123 (185) 230 450 550 145 (185) 230 275 (450) 550 650 170 (230) 275 325 (550) 650 750 245 (275) (325) 360 395 460 (650) (750) 850 950 1050
  • 37. Highest voltage for equipment Um kV (r.m.s. value) Standard switching impulse withstand voltage -------------------------------------- ------------------- Longitudinal Phase-to-earth Phase-to-phase Insulation (ratio to the (note 1) phase-to-earth kV kV peak value) (peak value) (peak value) Standard lightning impulse withstand voltage kV (peak value) 300 750 750 1,50 850 950 750 850 1,50 950 1050 362 850 850 1,50 950 1050 850 950 1,50 1050 1175 420 850 850 1,60 1050 1175 950 950 1,50 1175 1300 950 1050 1,50 1300 1425 525 950 950 1,70 1175 1300 950 1050 1,60 1300 1425 950 1175 1,50 1425 1550 765 1175 1300 1,70 1675 1800 1175 1425 1,70 1800 1950 1175 1550 1,60 1950 2100