SlideShare a Scribd company logo
1 of 19
PERT
(Project or Program Evaluation
and Review Techniques)
PROJECT EVALUATION REVIEW TECHNIQUE
In the critical path method, the time estimates are assumed to be
known with certainty. In certain projects like research and
development, new product introductions, it is difficult to estimate
the time of various activities.
Hence PERT is used in such projects with a probabilistic method using three
time estimates for an activity, rather than a single estimate, as shown in Figure
Optimistic time tO:
It is the shortest time taken to complete the
activity. It means that if everything goes well
then there is more chance of completing the
activity within this time.
Most likely time tm:
It is the normal time taken to complete an activity,
if the activity were frequently repeated under the
same conditions.
Pessimistic time tp:
It is the longest time that an activity would take to
complete. It is the worst time estimate that an
activity would take if unexpected problems are
faced.
Taking all these time estimates into consideration, the expected
time of an activity is arrived at.
The average or mean (ta) value
of the activity duration is
given by,
The variance of the activity
time is calculated using the
formula,
The probability of completing the
project within the scheduled time
(Ts) or contracted time may be
obtained by using the standard
normal deviate where Te is the
expected time of project
completion.
Probability for Project Duration
Probability of completing the
project within the scheduled time is,
An R & D project has a list of tasks to be performed whose time
estimates are given in the Table 8.11, as follows.
Example Problem of PERT
a. Draw the project network.
b. Find the critical path.
c. Find the probability that the project is completed in 19 days. If the
probability is less than 20%, find the probability of completing it in 24 days.
Time expected for each activity is
calculated using the formula (5):
Similarly, the expected time is
calculated for all the activities.
The variance of activity time is
calculated using the formula (6).
Similarly, variances of all the
activities are calculated.
calculate the time earliest (TE) and time Latest (TL) for all the activities.
A) Construct a network diagram:
From the network diagram Figure 8.24, the critical path is identified
as 1-4, 4-6, 6-7, with a project duration of 22 days.
C) The probability of completing the project within 19 days
is given by, P (Z< Z0)
To find Z0 ,
we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099)
= 0.5 – 0.4099
= 0.0901
= 9.01%
Thus, the probability of completing the R & D project in 19 days is 9.01%.
Since the probability of completing the project in 19
days is less than 20% As in question, we find the
probability of completing it in 24 days.
COST ANALYSIS
The two important components of any activity are the cost and time. Cost is
directly proportional to time and vice versa.
For example, in constructing a shopping complex, the expected time of completion
can be calculated using the time estimates of various activities. But if the
construction has to be finished earlier, it requires additional cost to complete the
project. We need to arrive at a time/cost trade-off between total cost of project and
total time required to complete it.
Normal time:
Normal time is the time required to complete
the activity at normal conditions and cost.
Crash time:
Crash time is the shortest possible activity
time; crashing more than the normal time
will increase the direct cost.
Cost Slope
Cost slope is the increase in cost per unit of
time saved by crashing. A linear cost curve
is shown in Figure 8.27.
An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is possible
to complete the activity in 2 days with an additional cost of Rs. 700.00, what is the
incremental cost of the activity?
Example
Incremental Cost or Cost Slope
It means, if one day is reduced we have to spend Rs. 100/- extra per day.
Project Crashing
Procedure for crashing
Step1: Draw the network diagram and mark the Normal time and Crash time.
Step2: Calculate TE and TL for all the activities.
Step3: Find the critical path and other paths.
Step 4: Find the slope for all activities and rank them in ascending order.
Step 5: Establish a tabular column with required field.
Step 6: Select the lowest ranked activity; check whether it is a critical activity. If
so,crash the activity, else go to the next highest ranked activity.
Note: The critical path must remain critical while crashing.
Step 7: Calculate the total cost of project for each crashing
Step 8: Repeat Step 6 until all the activities in the critical path are fully
crashed.
Example
The following Table 8.13 gives the activities of a construction project and other
data.
If the indirect cost is Rs. 20 per day, crash the activities to find the
minimum duration of the project and the project cost associated.
From the data provided in the table, draw the network diagram (Figure 8.28)
and find the critical path.
Solution
From the diagram, we observe
that the critical path is 1-2-5 with
project duration of 14 days
The cost slope for all activities and their rank is calculated as shown in Table 8.14
The available paths of the network are listed down in Table 8.15
indicating the sequence of crashing (see Figure 8.29).
The sequence of crashing and
the total cost involved is given
in Table 8.16 Initial direct cost
= sum of all normal costs given
= Rs. 490.00
It is not possible to crash more than 10 days, as all the activities in
the critical path are fully crashed. Hence the minimum project
duration is 10 days with the total cost of Rs. 970.00.
Activity
Crashed
Project
Duration
Critical Path Direct Cost in (Rs.) Indirect
Cost in (Rs.)
Total
Cost in
(Rs.)
- 14 1-2-5 490 14 x 20 =
280
770
1 – 2(2)
2 – 5(2)
2 – 4(1)
3 – 4(2)
10 1 – 2 – 5
1 – 3 – 4 – 5
1 – 2 – 4 – 5
490 + (2 x 15) + (2 x
100) + (1 x 10) + (2 x
20) = 770
10 x 20 =
200
970
Assignment
a. Draw the project network diagram.
b. Calculate the length and variance of the critical path.
c. What is the probability that the jobs on the critical path can be
completed in 41 days?
THANK YOU

More Related Content

What's hot

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
Β 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
Β 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
Β 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4Sammer Qader
Β 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
Β 
Pert Analysis
Pert AnalysisPert Analysis
Pert AnalysisKaizer Dave
Β 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
Β 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
Β 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
Β 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
Β 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
Β 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPMMunaf Dayee
Β 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.Muhammad Safeer Aabbasi
Β 

What's hot (20)

Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Β 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Β 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Β 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Β 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
Β 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
Β 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4
Β 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Β 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Β 
Project cost management
Project cost managementProject cost management
Project cost management
Β 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
Β 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Β 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
Β 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Β 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
Β 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
Β 
Pert cpm
Pert cpmPert cpm
Pert cpm
Β 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
Β 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
Β 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Β 

Viewers also liked

Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpmJulius Cuaresma
Β 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
Β 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
Β 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
Β 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project ManagementJ. Scott Christianson
Β 
Critical path analysis for pmp exam
Critical path analysis for pmp examCritical path analysis for pmp exam
Critical path analysis for pmp examManish Purwar
Β 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path PptJeff Hilton
Β 
Critical path method
Critical path methodCritical path method
Critical path methodHarshit Jhawar
Β 
Net Work Planning (nwp)
Net Work Planning (nwp)Net Work Planning (nwp)
Net Work Planning (nwp)Nurul Angreliany
Β 
Monte Carlo Statistical Methods
Monte Carlo Statistical MethodsMonte Carlo Statistical Methods
Monte Carlo Statistical MethodsChristian Robert
Β 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management FundamentalAndy Pham, PMP
Β 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyekD Istigfarin
Β 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & SkillsPMC Mentor
Β 
PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areassandeep sonkusale
Β 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
Β 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_newshengvn
Β 

Viewers also liked (20)

Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
Β 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
Β 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Β 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
Β 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
Β 
Critical path analysis for pmp exam
Critical path analysis for pmp examCritical path analysis for pmp exam
Critical path analysis for pmp exam
Β 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Β 
Critical path method
Critical path methodCritical path method
Critical path method
Β 
CTU Transcript
CTU TranscriptCTU Transcript
CTU Transcript
Β 
Network planning 1
Network planning 1Network planning 1
Network planning 1
Β 
Net Work Planning (nwp)
Net Work Planning (nwp)Net Work Planning (nwp)
Net Work Planning (nwp)
Β 
Monte Carlo Statistical Methods
Monte Carlo Statistical MethodsMonte Carlo Statistical Methods
Monte Carlo Statistical Methods
Β 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management Fundamental
Β 
Executing
ExecutingExecuting
Executing
Β 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyek
Β 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
Β 
PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areas
Β 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
Β 
Flash Memory
Flash MemoryFlash Memory
Flash Memory
Β 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_new
Β 

Similar to Per tand project crashing

4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
Β 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptxBetshaTizazu2
Β 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
Β 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpmIrtizaMalik
Β 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
Β 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
Β 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
Β 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
Β 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Sonali Srivastava
Β 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertDagnaygebawGoshme
Β 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
Β 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLSiddanna Balapgol
Β 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1M.D.Giri Reddy
Β 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pertSheetu Goel
Β 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARMitesh Kumar
Β 

Similar to Per tand project crashing (20)

4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
Β 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
Β 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Β 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
Β 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
Β 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
Β 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
Β 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
Β 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
Β 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
Β 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
Β 
Ovi project
Ovi  projectOvi  project
Ovi project
Β 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
Β 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
Β 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
Β 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Β 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1
Β 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Β 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
Β 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
Β 

More from Harinadh Karimikonda

Ppt on key growth drivers of indian medical education for fdi
Ppt on key growth drivers of indian medical education for fdiPpt on key growth drivers of indian medical education for fdi
Ppt on key growth drivers of indian medical education for fdiHarinadh Karimikonda
Β 
Types and sources of financing for start up businesses
Types and sources of financing for start up businessesTypes and sources of financing for start up businesses
Types and sources of financing for start up businessesHarinadh Karimikonda
Β 
Project plan or business plan.
Project plan or business plan.Project plan or business plan.
Project plan or business plan.Harinadh Karimikonda
Β 
Market structures and price determination
Market structures and price determinationMarket structures and price determination
Market structures and price determinationHarinadh Karimikonda
Β 
Round 4 chiefs of company for MBA Quiz
Round   4 chiefs of company for MBA QuizRound   4 chiefs of company for MBA Quiz
Round 4 chiefs of company for MBA QuizHarinadh Karimikonda
Β 
Round 2 products for MBA Quiz
Round   2 products for MBA QuizRound   2 products for MBA Quiz
Round 2 products for MBA QuizHarinadh Karimikonda
Β 
Round 5 company origin for MBA Quiz
Round   5 company origin for MBA QuizRound   5 company origin for MBA Quiz
Round 5 company origin for MBA QuizHarinadh Karimikonda
Β 
Cost Analysis : Definition of Cost, Types of Cost and Cost-output Relationship
Cost Analysis : Definition of Cost, Types of Cost and Cost-output RelationshipCost Analysis : Definition of Cost, Types of Cost and Cost-output Relationship
Cost Analysis : Definition of Cost, Types of Cost and Cost-output RelationshipHarinadh Karimikonda
Β 
Class 3 isocosts & isoquants
Class 3 isocosts & isoquantsClass 3 isocosts & isoquants
Class 3 isocosts & isoquantsHarinadh Karimikonda
Β 
Class 1 definition and importance of production function2
Class 1 definition and importance of production function2Class 1 definition and importance of production function2
Class 1 definition and importance of production function2Harinadh Karimikonda
Β 

More from Harinadh Karimikonda (20)

Ppt on key growth drivers of indian medical education for fdi
Ppt on key growth drivers of indian medical education for fdiPpt on key growth drivers of indian medical education for fdi
Ppt on key growth drivers of indian medical education for fdi
Β 
Types and sources of financing for start up businesses
Types and sources of financing for start up businessesTypes and sources of financing for start up businesses
Types and sources of financing for start up businesses
Β 
Project plan or business plan.
Project plan or business plan.Project plan or business plan.
Project plan or business plan.
Β 
Project management
Project managementProject management
Project management
Β 
Project life cycle
Project life cycleProject life cycle
Project life cycle
Β 
New Product Development
New Product DevelopmentNew Product Development
New Product Development
Β 
Process development
Process developmentProcess development
Process development
Β 
Feasibilitty study
Feasibilitty studyFeasibilitty study
Feasibilitty study
Β 
Round 3 chiefs of company
Round   3 chiefs of companyRound   3 chiefs of company
Round 3 chiefs of company
Β 
Market structures and price determination
Market structures and price determinationMarket structures and price determination
Market structures and price determination
Β 
Class 8 bep analysis
Class 8 bep analysisClass 8 bep analysis
Class 8 bep analysis
Β 
Class 2 economies of scale2
Class 2 economies of scale2Class 2 economies of scale2
Class 2 economies of scale2
Β 
Round 4 chiefs of company for MBA Quiz
Round   4 chiefs of company for MBA QuizRound   4 chiefs of company for MBA Quiz
Round 4 chiefs of company for MBA Quiz
Β 
Round 2 products for MBA Quiz
Round   2 products for MBA QuizRound   2 products for MBA Quiz
Round 2 products for MBA Quiz
Β 
Round 1 logos for MBA Quiz
Round   1  logos for MBA QuizRound   1  logos for MBA Quiz
Round 1 logos for MBA Quiz
Β 
Round 5 company origin for MBA Quiz
Round   5 company origin for MBA QuizRound   5 company origin for MBA Quiz
Round 5 company origin for MBA Quiz
Β 
Cost Analysis : Definition of Cost, Types of Cost and Cost-output Relationship
Cost Analysis : Definition of Cost, Types of Cost and Cost-output RelationshipCost Analysis : Definition of Cost, Types of Cost and Cost-output Relationship
Cost Analysis : Definition of Cost, Types of Cost and Cost-output Relationship
Β 
Class 3 isocosts & isoquants
Class 3 isocosts & isoquantsClass 3 isocosts & isoquants
Class 3 isocosts & isoquants
Β 
Class 3 economies of scale
Class 3 economies of scaleClass 3 economies of scale
Class 3 economies of scale
Β 
Class 1 definition and importance of production function2
Class 1 definition and importance of production function2Class 1 definition and importance of production function2
Class 1 definition and importance of production function2
Β 

Recently uploaded

Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
Β 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
Β 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
Β 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
Β 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetEnjoy Anytime
Β 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
Β 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
Β 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
Β 
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
Β 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
Β 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
Β 
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | DelhiFULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhisoniya singh
Β 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Hyundai Motor Group
Β 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
Β 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
Β 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
Β 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
Β 

Recently uploaded (20)

Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
Β 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Β 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
Β 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
Β 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
Β 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
Β 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Β 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
Β 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
Β 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Β 
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 βœ“Call Girls In Kalyan ( Mumbai ) secure service
Β 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Β 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
Β 
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | DelhiFULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY πŸ” 8264348440 πŸ” Call Girls in Diplomatic Enclave | Delhi
Β 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
Β 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2
Β 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
Β 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Β 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Β 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
Β 

Per tand project crashing

  • 1. PERT (Project or Program Evaluation and Review Techniques)
  • 2. PROJECT EVALUATION REVIEW TECHNIQUE In the critical path method, the time estimates are assumed to be known with certainty. In certain projects like research and development, new product introductions, it is difficult to estimate the time of various activities. Hence PERT is used in such projects with a probabilistic method using three time estimates for an activity, rather than a single estimate, as shown in Figure Optimistic time tO: It is the shortest time taken to complete the activity. It means that if everything goes well then there is more chance of completing the activity within this time. Most likely time tm: It is the normal time taken to complete an activity, if the activity were frequently repeated under the same conditions. Pessimistic time tp: It is the longest time that an activity would take to complete. It is the worst time estimate that an activity would take if unexpected problems are faced.
  • 3. Taking all these time estimates into consideration, the expected time of an activity is arrived at. The average or mean (ta) value of the activity duration is given by, The variance of the activity time is calculated using the formula, The probability of completing the project within the scheduled time (Ts) or contracted time may be obtained by using the standard normal deviate where Te is the expected time of project completion. Probability for Project Duration Probability of completing the project within the scheduled time is,
  • 4. An R & D project has a list of tasks to be performed whose time estimates are given in the Table 8.11, as follows. Example Problem of PERT a. Draw the project network. b. Find the critical path. c. Find the probability that the project is completed in 19 days. If the probability is less than 20%, find the probability of completing it in 24 days.
  • 5. Time expected for each activity is calculated using the formula (5): Similarly, the expected time is calculated for all the activities. The variance of activity time is calculated using the formula (6). Similarly, variances of all the activities are calculated.
  • 6. calculate the time earliest (TE) and time Latest (TL) for all the activities. A) Construct a network diagram: From the network diagram Figure 8.24, the critical path is identified as 1-4, 4-6, 6-7, with a project duration of 22 days.
  • 7. C) The probability of completing the project within 19 days is given by, P (Z< Z0) To find Z0 , we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099) = 0.5 – 0.4099 = 0.0901 = 9.01% Thus, the probability of completing the R & D project in 19 days is 9.01%.
  • 8. Since the probability of completing the project in 19 days is less than 20% As in question, we find the probability of completing it in 24 days.
  • 9. COST ANALYSIS The two important components of any activity are the cost and time. Cost is directly proportional to time and vice versa. For example, in constructing a shopping complex, the expected time of completion can be calculated using the time estimates of various activities. But if the construction has to be finished earlier, it requires additional cost to complete the project. We need to arrive at a time/cost trade-off between total cost of project and total time required to complete it. Normal time: Normal time is the time required to complete the activity at normal conditions and cost. Crash time: Crash time is the shortest possible activity time; crashing more than the normal time will increase the direct cost. Cost Slope Cost slope is the increase in cost per unit of time saved by crashing. A linear cost curve is shown in Figure 8.27.
  • 10. An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is possible to complete the activity in 2 days with an additional cost of Rs. 700.00, what is the incremental cost of the activity? Example Incremental Cost or Cost Slope It means, if one day is reduced we have to spend Rs. 100/- extra per day. Project Crashing Procedure for crashing Step1: Draw the network diagram and mark the Normal time and Crash time. Step2: Calculate TE and TL for all the activities. Step3: Find the critical path and other paths. Step 4: Find the slope for all activities and rank them in ascending order.
  • 11. Step 5: Establish a tabular column with required field. Step 6: Select the lowest ranked activity; check whether it is a critical activity. If so,crash the activity, else go to the next highest ranked activity. Note: The critical path must remain critical while crashing. Step 7: Calculate the total cost of project for each crashing Step 8: Repeat Step 6 until all the activities in the critical path are fully crashed. Example The following Table 8.13 gives the activities of a construction project and other data. If the indirect cost is Rs. 20 per day, crash the activities to find the minimum duration of the project and the project cost associated.
  • 12. From the data provided in the table, draw the network diagram (Figure 8.28) and find the critical path. Solution From the diagram, we observe that the critical path is 1-2-5 with project duration of 14 days The cost slope for all activities and their rank is calculated as shown in Table 8.14
  • 13. The available paths of the network are listed down in Table 8.15 indicating the sequence of crashing (see Figure 8.29). The sequence of crashing and the total cost involved is given in Table 8.16 Initial direct cost = sum of all normal costs given = Rs. 490.00
  • 14. It is not possible to crash more than 10 days, as all the activities in the critical path are fully crashed. Hence the minimum project duration is 10 days with the total cost of Rs. 970.00. Activity Crashed Project Duration Critical Path Direct Cost in (Rs.) Indirect Cost in (Rs.) Total Cost in (Rs.) - 14 1-2-5 490 14 x 20 = 280 770 1 – 2(2) 2 – 5(2) 2 – 4(1) 3 – 4(2) 10 1 – 2 – 5 1 – 3 – 4 – 5 1 – 2 – 4 – 5 490 + (2 x 15) + (2 x 100) + (1 x 10) + (2 x 20) = 770 10 x 20 = 200 970
  • 16.
  • 17.
  • 18. a. Draw the project network diagram. b. Calculate the length and variance of the critical path. c. What is the probability that the jobs on the critical path can be completed in 41 days?