SlideShare a Scribd company logo
By
NIKHIL KUMAR
11026A0130
 “An agreement enforceable by law is a
Contract.”
 “Every promise and every set of
promises, forming the consideration for
each other , is an Agreement.”
 “The agreement must create legal
obligations between the parties is an
Enforceable.”
 Contract: It is an undertaking by a firm or
a person to do any work under certain
terms and conditions.
 Contractor: A person or a firm who
undertakes any type of contract.
 Arranging Contractor: Contract for a
work is arranged by inviting sealed
tenders, by issuing tender notices.
 Site investigations should have revealed
ground conditions.
 Decisions will have been taken on the way
design is to be carried out.
 A Planning Supervisor will have been
appointed.
 Decisions will have been taken on the
breakdown of construction into different
contract packages to suit capabilities of
potential tenders for civil works, plant
suppliers, etc.
 Environmental studies will have been
undertaken and requirements assessed.
 Initial project programmes will have
been produced to indicate
the sequences of construction.
 Financial planning will have been
completed to ensure funds will
be available.
 Approvals
 Price Given in Advance Contracts
(Priced-based Contracts)
 Cost Reimbursement Contracts
(Cost-based Contracts)
 01) Lump sum contract
 02) Lump sum and schedule contract
 03) Schedule contracts or Item Rate
contract
 04) Labour contract
 05) Target contract
 06) Materials supply contract
 07) Piece-Work agreement
 08) Cost Reimbursement Contracts
 a) Cost plus fixed fee contract
 b) Cost plus percentage contract
 c) Cost plus fluctuating fee contract
 d) Percentage rate contract
 Sometimes called Drawings and
Specifications Contract.
 The contractor agrees to perform a
stipulated job of work in exchange for a
fixed sum of money.
 To complete it in all respects within a
specified time for a fixed amount.
 Payment may be staged at intervals of
time on the completion of milestones.
 Deposit of 10%security money is taken by
the department.
 The contractor is responsible for
preparing his B.O.Q. (Bill of Quantities ).
 On completion of the work no detailed
measurements of different items of work
is required.
 Lower financial risk to Employer.
 Higher financial risk to Contractor.
 The final price is known, by the owner,
before the work commences.
 The contractor has more incentive to
reduce his cost to increase the profit.
 The contractor hopes to complete the
job as quickly as possible, to minimize
overhead, to maximize profit and to
move to the next Job.
 When level of risks is low and
quantifiable, and
 When the client does not wish to be
involved in the management of his
project.
 That can be accurately and completely
described at the time of bidding such as
residential and building construction.
 When limited variation is needed.
 Changes in drawings and specifications
can be very expensive and source of
trouble. In other words the contract has
very limited flexibility for design changes.
 The contractor carries much of the risks.
The tendered price may include high risk
contingency.
 Competent contractors may decide not
to bid to avoid a high-risk lump sum
contract.
 In this type of contract, the schedule of
rates is also provided in the contract
agreement.
 Measurement of extra items only shall
have to be taken. The original work is
however be checked and compared.
 The contract however includes a fixed
sum within a fixed time along with the
detailed specifications and conditions,
and the scheduled rates.
 The contractor undertakes the execution
or construction of a work on the item
rate basis only.
 The payment to the contractor is made
by detailed measurement of different
items of works actually done by the
contractor.
 The amount ,the contractor receives
depends on the number of items of work
done.
 The contract agreement includes
quantities, rates and amounts of various
items of work.
 It also includes the 10% security money,
penalties, etc.
 Item rate contract may also be a
percentage above or below the printed
schedule of rates of the department.
 Used for repair and maintenance works
or under conditions of urgency.
 Estimated quantities are surveyed by
Architect/Engineer.
 Contractors enter unit prices against the
estimated quantities of work.
 Useful on projects where the nature of
the work is well defined, but the
quantities of work cannot be accurately
determined in advance of construction.
Suitable for highways, dams, airports…
 It is also called as UNIT PRICE CONTRACT
 Fair basis for competition.
 In comparing with lump-sum contract,
A) Changes in contract documents can
be made easily by the owner.
B) Lower risk for contractor.
 The exact final price of the project is not
known to the owner until the completion
of the project.
 All materials for the construction are
arranged and supplied at the site of
work by the department or owner.
 The labour contractor engages the
labour and gets the work done
according to specifications.
 The contract is on item rate basis for
labour portion only.
 The contractor is paid for the quantities
of work done on measurement of the
different items of work at the stipulated
rate as in agreement.
 Contractor uses his own tools for working.
 Plants and machineries are arranged by
the department or owner.
 This system of contract is not generally
adopted in government works but
preferable for private sectors.
 In this form of contract, the contractors
have to offer their rates for supply of the
required quantity of materials , inclusive
of all local taxes, carriage and delivery
charges of materials to the specified site
within the time fixed in the tender.
 In this system, contractor is given certain
percentage over the actual cost of the
construction as his profit.
 Contractor arranges materials and
labour at his cost and keeps proper
account.
 He is paid by the department by a profit
of say 10% as his profit as agreed upon
beforehand.
 Construction can start before design is
completed.
 If the contractor is efficient in the
utilization of resources then the cost to
the client should represent a fair price for
the work undertaken.
• The project total cost is completely
unknown before the project start.
 Owner must exercise tight cost control,
which may be difficult and/or costly.
 Minimum efficiency maximizes the profit.
 COST PLUS FIXED FEE CONTRACT : In this
type of contract, the contractor is paid
by the owner an agreed lump-sum
amount over and above the actual cost
of work.
 COST PLUS FLUCTUATING FEE CONTRACT:
In this type of contract, the contractor is
paid by the owner the actual cost of
construction plus an amount of fee
inversely variable according to the
increase or decrease of the estimated
cost agreed first by both the parties.
 The appropriateness for providing an
adequate incentive for efficient
performance by the contractor
 The ability to introduce changes
 The allocation of risks
 The start and completion date of the
project
 Title page – Name of work, contract
bond
number, etc.
 Index page --Content of the agreement
with page references.
 Tender notice--
Giving brief description of work, etc.
Usually 2% of the estimated cost is
deposited along with tender.
 Tender form–
Contractor’s rates and time of
completion, penalty clause, etc.
 Bill of quantities–
Giving quantities and rates of each
item of work and the total cost of the
whole work.
 Schedule of issue of materials–
Giving list of materials to be issued to
the contractor with rates and place of
issue.
 General specifications—
Specifying the class and type of
works .
 Detailed specifications–
Each item of work and of each
material to be used in the work.
 Drawings—
Complete set of drawings like plans,
elevations, etc. and site plan, of fully
dimensioned.
1) Rates inclusive of materials, labour,etc.
2) Amount of security money
3) Time for completion of work
4) Progress to be maintained
5) Penalty for bad work
6) Mode of payment
7) Extension of time limit for delay
8) Termination of contract
9) Compensation to labour, minimum wages,
etc.
civil engineering-Contracts
civil engineering-Contracts

More Related Content

What's hot

Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGTejaswiniNarayane
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement designRohit Ranjan
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 

What's hot (20)

Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 

Viewers also liked

Types of contract
Types of contractTypes of contract
Types of contractSweetp999
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksDr K M SONI
 
Introduction to Contract Law
Introduction to Contract LawIntroduction to Contract Law
Introduction to Contract Lawtheacademist
 
Contracts PowerPoint Presentation
Contracts PowerPoint PresentationContracts PowerPoint Presentation
Contracts PowerPoint Presentationmbachnak
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil constructiondiasawada12345
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 

Viewers also liked (20)

Types of contract
Types of contractTypes of contract
Types of contract
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Types of conract
Types of conractTypes of conract
Types of conract
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
 
Tender
TenderTender
Tender
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Introduction to Contract Law
Introduction to Contract LawIntroduction to Contract Law
Introduction to Contract Law
 
Contracts PowerPoint Presentation
Contracts PowerPoint PresentationContracts PowerPoint Presentation
Contracts PowerPoint Presentation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Study notes contract law
Study notes   contract lawStudy notes   contract law
Study notes contract law
 
Contract ppt
Contract pptContract ppt
Contract ppt
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Contract law
Contract lawContract law
Contract law
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
 
Tender processing
Tender processingTender processing
Tender processing
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 

Similar to civil engineering-Contracts

contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.pptmayuray
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxsulevrunda
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contractsMohammedAlfayad2
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costingCollen Mahambo
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
types of contracts
 types of contracts types of contracts
types of contractsKEVINMISTRY8
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their typesTouqeer1
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdfThanoonQasem
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptxVasuV18
 

Similar to civil engineering-Contracts (20)

contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
types of contracts
 types of contracts types of contracts
types of contracts
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
3 Type of contracts.pdf
3 Type of contracts.pdf3 Type of contracts.pdf
3 Type of contracts.pdf
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 

Recently uploaded

ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptxfaamieahmd
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdfKamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...Amil baba
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdfKamal Acharya
 

Recently uploaded (20)

ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 

civil engineering-Contracts

  • 2.  “An agreement enforceable by law is a Contract.”  “Every promise and every set of promises, forming the consideration for each other , is an Agreement.”  “The agreement must create legal obligations between the parties is an Enforceable.”
  • 3.  Contract: It is an undertaking by a firm or a person to do any work under certain terms and conditions.  Contractor: A person or a firm who undertakes any type of contract.  Arranging Contractor: Contract for a work is arranged by inviting sealed tenders, by issuing tender notices.
  • 4.  Site investigations should have revealed ground conditions.  Decisions will have been taken on the way design is to be carried out.  A Planning Supervisor will have been appointed.  Decisions will have been taken on the breakdown of construction into different contract packages to suit capabilities of potential tenders for civil works, plant suppliers, etc.
  • 5.  Environmental studies will have been undertaken and requirements assessed.  Initial project programmes will have been produced to indicate the sequences of construction.  Financial planning will have been completed to ensure funds will be available.  Approvals
  • 6.  Price Given in Advance Contracts (Priced-based Contracts)  Cost Reimbursement Contracts (Cost-based Contracts)
  • 7.  01) Lump sum contract  02) Lump sum and schedule contract  03) Schedule contracts or Item Rate contract  04) Labour contract  05) Target contract  06) Materials supply contract
  • 8.  07) Piece-Work agreement  08) Cost Reimbursement Contracts  a) Cost plus fixed fee contract  b) Cost plus percentage contract  c) Cost plus fluctuating fee contract  d) Percentage rate contract
  • 9.  Sometimes called Drawings and Specifications Contract.  The contractor agrees to perform a stipulated job of work in exchange for a fixed sum of money.  To complete it in all respects within a specified time for a fixed amount.
  • 10.  Payment may be staged at intervals of time on the completion of milestones.  Deposit of 10%security money is taken by the department.  The contractor is responsible for preparing his B.O.Q. (Bill of Quantities ).  On completion of the work no detailed measurements of different items of work is required.  Lower financial risk to Employer.  Higher financial risk to Contractor.
  • 11.  The final price is known, by the owner, before the work commences.  The contractor has more incentive to reduce his cost to increase the profit.  The contractor hopes to complete the job as quickly as possible, to minimize overhead, to maximize profit and to move to the next Job.
  • 12.  When level of risks is low and quantifiable, and  When the client does not wish to be involved in the management of his project.  That can be accurately and completely described at the time of bidding such as residential and building construction.  When limited variation is needed.
  • 13.  Changes in drawings and specifications can be very expensive and source of trouble. In other words the contract has very limited flexibility for design changes.  The contractor carries much of the risks. The tendered price may include high risk contingency.  Competent contractors may decide not to bid to avoid a high-risk lump sum contract.
  • 14.  In this type of contract, the schedule of rates is also provided in the contract agreement.  Measurement of extra items only shall have to be taken. The original work is however be checked and compared.  The contract however includes a fixed sum within a fixed time along with the detailed specifications and conditions, and the scheduled rates.
  • 15.  The contractor undertakes the execution or construction of a work on the item rate basis only.  The payment to the contractor is made by detailed measurement of different items of works actually done by the contractor.  The amount ,the contractor receives depends on the number of items of work done.
  • 16.  The contract agreement includes quantities, rates and amounts of various items of work.  It also includes the 10% security money, penalties, etc.  Item rate contract may also be a percentage above or below the printed schedule of rates of the department.  Used for repair and maintenance works or under conditions of urgency.
  • 17.  Estimated quantities are surveyed by Architect/Engineer.  Contractors enter unit prices against the estimated quantities of work.  Useful on projects where the nature of the work is well defined, but the quantities of work cannot be accurately determined in advance of construction. Suitable for highways, dams, airports…  It is also called as UNIT PRICE CONTRACT
  • 18.  Fair basis for competition.  In comparing with lump-sum contract, A) Changes in contract documents can be made easily by the owner. B) Lower risk for contractor.  The exact final price of the project is not known to the owner until the completion of the project.
  • 19.  All materials for the construction are arranged and supplied at the site of work by the department or owner.  The labour contractor engages the labour and gets the work done according to specifications.  The contract is on item rate basis for labour portion only.
  • 20.  The contractor is paid for the quantities of work done on measurement of the different items of work at the stipulated rate as in agreement.  Contractor uses his own tools for working.  Plants and machineries are arranged by the department or owner.  This system of contract is not generally adopted in government works but preferable for private sectors.
  • 21.  In this form of contract, the contractors have to offer their rates for supply of the required quantity of materials , inclusive of all local taxes, carriage and delivery charges of materials to the specified site within the time fixed in the tender.
  • 22.  In this system, contractor is given certain percentage over the actual cost of the construction as his profit.  Contractor arranges materials and labour at his cost and keeps proper account.  He is paid by the department by a profit of say 10% as his profit as agreed upon beforehand.
  • 23.  Construction can start before design is completed.  If the contractor is efficient in the utilization of resources then the cost to the client should represent a fair price for the work undertaken.
  • 24. • The project total cost is completely unknown before the project start.  Owner must exercise tight cost control, which may be difficult and/or costly.  Minimum efficiency maximizes the profit.
  • 25.  COST PLUS FIXED FEE CONTRACT : In this type of contract, the contractor is paid by the owner an agreed lump-sum amount over and above the actual cost of work.  COST PLUS FLUCTUATING FEE CONTRACT: In this type of contract, the contractor is paid by the owner the actual cost of construction plus an amount of fee inversely variable according to the increase or decrease of the estimated cost agreed first by both the parties.
  • 26.  The appropriateness for providing an adequate incentive for efficient performance by the contractor  The ability to introduce changes  The allocation of risks  The start and completion date of the project
  • 27.  Title page – Name of work, contract bond number, etc.  Index page --Content of the agreement with page references.  Tender notice-- Giving brief description of work, etc. Usually 2% of the estimated cost is deposited along with tender.
  • 28.  Tender form– Contractor’s rates and time of completion, penalty clause, etc.  Bill of quantities– Giving quantities and rates of each item of work and the total cost of the whole work.  Schedule of issue of materials– Giving list of materials to be issued to the contractor with rates and place of issue.
  • 29.  General specifications— Specifying the class and type of works .  Detailed specifications– Each item of work and of each material to be used in the work.  Drawings— Complete set of drawings like plans, elevations, etc. and site plan, of fully dimensioned.
  • 30. 1) Rates inclusive of materials, labour,etc. 2) Amount of security money 3) Time for completion of work 4) Progress to be maintained 5) Penalty for bad work 6) Mode of payment 7) Extension of time limit for delay 8) Termination of contract 9) Compensation to labour, minimum wages, etc.

Editor's Notes

  1. INDIAN CONTRACT ACT CAME INTO FORCE ON 1ST Sept,1872.