SlideShare a Scribd company logo
Project
Management
Agero, Venessa
Chua, Francisco
Erispe, Angelique
Lao, Inna
Santiago, Chiara 1
Chapter Outline
12.1 Introduction of Project Management
12.2 PERT/CPM
12.3 PERT/Cost
12.4 Project Crashing
12.5 Other Topics in Project Management
2
Things to remember
● The first step in planning and scheduling a project is
to develop the work breakdown structure.
● An activity is a job or task that is a part of a project.
● The beginning or end of an activity is called an
event.
● For more information, please check:
http://www.projectinsight.net/project-management-basics/basic-project-
management-phases
● http://www.prenhall.com/divisions/bp/app/russellcd/PROTECT/CHAPT
ERS/CHAP17/HEAD05.HTM
3
Quantitative analysis techniques
● The program evaluation
and review technique.
● PERT is probabilistic
● Developed by the Special
Projects Office of the U.S
Navy in 1958
● Used to plan and control
the Polaris missile
program.
● The critical path method.
● CPM is deterministic.
● Developed by J. E Kelly of
Remington Rand and M.R,
Walker of du Pont in 1957.
● Used to assist in the
building and maintenance
of chemical plants at du
Pont.
PERT CPM
4
Six steps of PERT/CPM
1. Define the project and all of its significant activities or tasks.
2. Develop the relationships among the activities. Decide which activities
must precede
others.
3. Draw the network connecting all of the activities.
4. Assign time and/or cost estimates to each activity.
5. Compute the longest time path through the network; this is called the
critical path.
6. Use the network to help plan, schedule, monitor, and control the project.
5
General Foundry Example
● General Foundry, Inc. has long been trying to avoid the
expense of installing air pollution control equipment.
● The local environmental protection group has recently given the
foundry 16 weeks to install a complex air filter system on its
main smokestack.
● General Foundry was warned that it will be forced to close
unless the device is installed in the allotted period.
● They want to make sure that installation of the filtering system
progresses smoothly and on time.
6
Drawing the PERT/CPM Network
● Activity-on-node (AON) where the nodes represent activities.
● Activity-on-arc (AOA) where the arcs are used to represent the
activities.
● The AON approach is easier and more commonly found in
software packages.
● One node represents the start of the project, one node for the
end of the project, and nodes for each of the activities.
● The arcs are used to show the predecessors for each activity.
7
Network of General Foundry
8
Activity Times
Times Estimates in PERT are:
Optimistic Time (a)=time activity will take if everything
goes as well as possible, small percentage happening
Pessimistic Time (b)=time activity will take assuming
unfavorable conditions, small percentage happening
Most likely Time (m)=most realistic time estimate to
complete activity
9
Activity Times
Beta Probability Distribution with Three Time Estimates
10
Activity Times Formulas
Expected Activity Time:
Dispersion/Variance of Activity Completion
Time:
11
Activity Times
Time Estimates (weeks) for General Fondry
12
How to Find the Critical Path
We accept the expected completion time for each task as the actual
time for now. The total of 25 weeks in Table 12.2 does not take into
account the obvious fact that some of the tasks could be taking place
at the same time. To find out how long the project will take we perform
the critical path analysis for the network.
The Critical Path is the longest path through the
network.
13
How to Find the Critical Path
General Fondry’s Network with Expected Activity Times
14
To find the critical path, we need to determine the following:
1. Earliest start time (ES): earliest time an activity can
begin
2. Earliest finish time (EF): the earliest time an activity can
end
3. Latest start time (LS): latest time an activity can begin
4. Latest finish time (LF): latest time an activity can begin
How to Find the Critical Path
15
In the nodes, the activity time and early and late
start finish times are represented like below:
How to Find the Critical Path
16
Earliest finish time = Earliest start time + Expected
activity TIme
EF = ES + t
Earliest start time = Largest of the earliest finish
times of immediate predecessors
ES= Largest EF of immediate predecessors
Computation of Earliest Times
17
At the start of the project, we set the time to
zero, so ES=0 for both A and B.
How to Find the Critical Path
18
General Fondry’s Earliest Start (ES) and Earliest Finish
(EF) Times
How to Find the Critical Path
19
Finding the Critical Path
Latest start time = Latest finish time - Activity
time (LS = LF - t)
Latest finish time = Smallest of latest start
times for following activities.
LF = Smallest LS of following activities.
Slack = LS - ES, or Slack = LF - EF
20
General Foundry’s Critical Path
TABLE 12.3
General Foundry’s
Schedule and Slack
Times
FIGURE 12.5
General Foundry’s
Latest Start (LS)
and Latest Finish
(LF) Times
21
General Foundry’s Critical Path
● From Table 12.3 we see activities A, C, E, G, and H have no slack
time.
● These are called critical activities and they are said to be on the critical
path.
● The total project completion time is 15 weeks.
● Industrial managers call this a boundary timetable.
22
Probability of Project Completion
● The critical path analysis helped us determine that the foundry’s
expected project completion time is 15 weeks.
● If the project is not complete in 16, the foundry will have to close.
● PERT uses the variance of critical path activities to help determine the
variance of the overall project.
23
(cont.)
*Project variance = ∑ variances of activities on the critical path
24
Results
Project standard deviation
= σT = √Project Variance
= √3.11 = 1.76 weeks
25
Probability of Project Completion
26
The probability that the project
can be completed in 16 weeks is
.716
Results
● The project’s expected completion date is 15
weeks.
● There is a 71.6% chance that the equipment will
be in place within the 16-week deadline.
● Five activities (A, C, E, G, H) are on the critical
path.
● Three activities (B, D, F) are not critical but have
some slack time built in.
27
Using Excel QM in the
General Foundry Example
28
Excel QM Initialization
Screen for General
Foundry Example
with Three Time
Estimates
Using Excel QM in the
General Foundry Example
29
Excel QM Input
Screen and Solution
for General Foundry
Example with Three
Time Estimates
Project Crashing
● Projects have deadlines that are impossible to meet
through normal procedures.
● Through exceptional methods, it’s possible to finish
the project in less time than normally required at a
greater cost.
● Reducing a project’s completion time is called
crashing.
30
Project Crashing
Crashing a project start with using the normal
time to create the critical path. The normal cost is
the cost for completing the activity using normal
procedures. If the project will not meet the required
deadline, extraordinary measures must be taken.
The crash time is the shortest possible activity
time and will require additional resources. The crash
cost is the price of completing the activity in the
earlier-than- normal time.
31
Four Steps to Project Crashing
1. Find the normal critical path and identify the critical
activities.
2. Get the crash cost per time period for all activities in
the network with this formula:
Crash cost/Time period = Crash cost - Normal
cost
Normal time - Crash time
32
Four Steps to Project Crashing
33
3. Select smallest crash cost per week on the critical
path and crash this to the maximum extent possible
or to the point at which your desired deadline has
been reached.
4. Check to be sure that the critical path you were
crashing is still critical. If it is still the longest path
through the network, return to step 3. If not, find the
new critical path and return to step 2.
General Foundry
Instead of 16 weeks, General Foundry has been given 14
weeks to install the new equipment. The critical path is 15
weeks. What options does the firm have?
The normal crash times and costs are shown in table 12.9. Crash costs
are assumed to be linear and Figure 12.11 shows the crash cost for activity
B.
Crashing activities B and A will shorten the completion time
to 14 but it creates a second critical path. Any further
crashing must be done to both critical paths.
34
General Foundry
Normal and Crash Data for General Foundry, Inc.
Table 12.9
Time (Weeks) Cost ($)
Activity Normal Crash Normal Crash Crash Cost per
Week ($)
Critical Path
A 2 1 22000 23000 1000 Yes
B 3 1 30000 34000 2000 No
C 2 1 26000 27000 1000 Yes
D 4 3 48000 49000 1000 No
E 4 2 56000 58000 1000 Yes
F 3 2 30000 30500 500 No
G 5 2 80000 86000 2000 Yes
H 2 1 16000 19000 3000 Yes
35
General Foundry
Crash and Normal Times and Costs for Activity B
Figure 12.11
36
Project Crashing with Linear
Programming
•Another approach to finding the best project crashing
schedule.
•The data needed are derived from the normal and
crash data for General Foundry and the project network
with activity times.
37
Project Crashing with Linear
Programming
General Foundry’s Network With Activity Times
Figure 12.12
38
Project Crashing with Linear
Programming
Objective function:
Minimize crash cost = 1,000YA+ 2,000YB+ 1,000YC+ 1,000YD+ 1,000YE+ 500YF+ 2,000YG+
3,000YH
Subject to these constraints:
YA≤1 YG≤3
YB≤2 YH≤1
YC≤1 Xfinish≤ 12
YD≤1 Xfinish≥ XH
YE≤2
YF≤1
39
Project Crashing with Linear
Programming
where,
XA= EF for activity A
XB= EF for activity B
XC= EF for activity C
XD= EF for activity D
XE= EF for activity E
XF= EF for activity F
XG= EF for activity G
XH= EF for activity H
Xstart= start time for project (usually 0)
Xfinish= earliest finish time for the project
40
Project Crashing with Linear
Programming
Constraints describing the network have the form:
EF time≥ EF time for predecessor + Activity time
EF≥ EFpredecessor+ (t–Y), or
X≥ Xpredecessor+ (t–Y)
For activity A,XA≥ Xstart+ (2 –YA) or XA–Xstart+ YA≥ 2
For activity B,XB≥ Xstart+ (3 –YB) or XB–Xstart+ YB≥ 3
For activity C,XC≥ XA+ (2 –YC) or XC–XA+ YC≥ 2
For activity D,XD≥ XB+ (4 –YD) or XD–XB+ YD≥ 4
For activity E,XE≥ XC+ (4 –YE) or XE–XC+ YE≥ 4
For activity F,XF≥ XC+ (3 –YF) or XF–XC+ YF≥ 3
For activity G,XG≥ XD+ (5 –YG) or XG–XD+ YG≥ 5
For activity G,XG≥ XE+ (5 –YG) or XG–XE+ YG≥ 5
For activity H,XH≥ XF+ (2 –YH) or XH–XF+ YH≥ 2
For activity H,XH≥ XG+ (2 –YH) or XH–XG+ YH≥ 2
41
Solution to Crashing Problem Using
Solver in Excel
Program 12.2 42
Other Topics in Project Management
Subprojects Milestones Resources Leveling Software
•Extremely large
projects
•Creation of several
small sub-activities
which is subproject
of the original
•Major events in a
project
•Gantt and PERT
charts to show
importance of
reaching these
events
•Adjusting at the
start of the event
•Even distribution
of resources
•Creates PERT and
Gantt charts
•Budget schedules,
adjust future start
times, and level
resource utilization
43
1. The earliest start time for an activity is equal to 3. If activity A is not on the critical path, then the
a. the largest EF of the immediate predecessors. slack for A will equal
b. the smallest EF of the immediate predecessors. a. LF - EF.
c. the largest ES of the immediate predecessors. b. EF - ES.
d. the smallest ES of the immediate predecessors c. 0
2. The standard deviation for the PERT project is d. all of the above
approximately 4. The critical
path is the
a. the square root of the sum of the variances along thea.shortest path in a network.
critical path. b. longest
path in a network.
b. the sum of the critical path activity standard deviations. c. path with the smallest variance.
c. the square root of the sum of the variances of the project d. path with the largest variance.
activities. e. none of
the above.
d. all of the above. 5. PERT stands for
______________.
e. none of the above. 6. Project crashing can be
performed using a _____________.
Sample Exercises
44
1. A
2. A
3. A
4. B
5. Program Evaluation and Review Techniques
6. Linear Programming model
Answers to sample exercises
45
1. Sid Davidson is the personnel director of Babson and Willcount, a
company that specializes in consulting and research. One of the
training programs that Sid is considering for the middle-level managers
of Babson and Willcount is leadership training. Sid has listed a number
of activities that must be completed before a training program of this
nature could be conducted. The activities and immediate predecessors
appear in the following table.
Develop a network for this problem
Sample Problem
46
Answers to sample problem
47
http://www.projectinsight.net/project-management-basics/basic-project-
management-phases
https://www.youtube.com/watch?v=BjOLdukjAck
http://www.prenhall.com/divisions/bp/app/russellcd/PROTECT/CHAPTERS/
CHAP17/HEAD05.HTM
http://www.prenhall.com/divisions/bp/app/russellcd/PROTECT/CHAPTERS/
CHAP17/HEAD05.HTM
References
48

More Related Content

What's hot

Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
Internal Controls at Construction Site
Internal Controls at Construction SiteInternal Controls at Construction Site
Internal Controls at Construction Site
sandesh mundra
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
Suresh G Sankarankutty
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
HafixFarhan
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
Pragnendra Rahevar
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)
Jags Jagdish
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt
benito procia
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
Lori Krein Studios
 
EDUC 224 RA 6713 Draft.pptx
EDUC 224 RA 6713 Draft.pptxEDUC 224 RA 6713 Draft.pptx
EDUC 224 RA 6713 Draft.pptx
AaronBenedictChi1
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
DavidMcLachlan1
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
ssuserb4074f
 
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Juan Paolo Somorostro - Aranas, MPA, BSOSM
 
Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management
A Makwana
 
Managing project teams.
Managing project teams. Managing project teams.
Managing project teams.
Juliana A. Kplorfia, PMP
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
The 7 principles of Engineering Economy
The 7 principles of Engineering EconomyThe 7 principles of Engineering Economy
The 7 principles of Engineering Economy
M. Zahaib Mudabber Khan
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
Saqib Raza
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009Nderitu Muriithi
 

What's hot (20)

Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Internal Controls at Construction Site
Internal Controls at Construction SiteInternal Controls at Construction Site
Internal Controls at Construction Site
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt326918375-Barangay-Development-Planning.ppt
326918375-Barangay-Development-Planning.ppt
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
EDUC 224 RA 6713 Draft.pptx
EDUC 224 RA 6713 Draft.pptxEDUC 224 RA 6713 Draft.pptx
EDUC 224 RA 6713 Draft.pptx
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management
 
Managing project teams.
Managing project teams. Managing project teams.
Managing project teams.
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
The 7 principles of Engineering Economy
The 7 principles of Engineering EconomyThe 7 principles of Engineering Economy
The 7 principles of Engineering Economy
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009
 

Similar to Project management

Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
Chandra Shekar Immani
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
Akihisa Akimoto
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
IOSR Journals
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
Drprem Jerusha
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Sheetu Goel
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
DrAsifMohammad
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
DejeneDay
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
ahsanrabbani
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
AhmadAbdullah626071
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
PHOEBEANNEARTECHE1
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)

Similar to Project management (20)

Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 

Project management

  • 1. Project Management Agero, Venessa Chua, Francisco Erispe, Angelique Lao, Inna Santiago, Chiara 1
  • 2. Chapter Outline 12.1 Introduction of Project Management 12.2 PERT/CPM 12.3 PERT/Cost 12.4 Project Crashing 12.5 Other Topics in Project Management 2
  • 3. Things to remember ● The first step in planning and scheduling a project is to develop the work breakdown structure. ● An activity is a job or task that is a part of a project. ● The beginning or end of an activity is called an event. ● For more information, please check: http://www.projectinsight.net/project-management-basics/basic-project- management-phases ● http://www.prenhall.com/divisions/bp/app/russellcd/PROTECT/CHAPT ERS/CHAP17/HEAD05.HTM 3
  • 4. Quantitative analysis techniques ● The program evaluation and review technique. ● PERT is probabilistic ● Developed by the Special Projects Office of the U.S Navy in 1958 ● Used to plan and control the Polaris missile program. ● The critical path method. ● CPM is deterministic. ● Developed by J. E Kelly of Remington Rand and M.R, Walker of du Pont in 1957. ● Used to assist in the building and maintenance of chemical plants at du Pont. PERT CPM 4
  • 5. Six steps of PERT/CPM 1. Define the project and all of its significant activities or tasks. 2. Develop the relationships among the activities. Decide which activities must precede others. 3. Draw the network connecting all of the activities. 4. Assign time and/or cost estimates to each activity. 5. Compute the longest time path through the network; this is called the critical path. 6. Use the network to help plan, schedule, monitor, and control the project. 5
  • 6. General Foundry Example ● General Foundry, Inc. has long been trying to avoid the expense of installing air pollution control equipment. ● The local environmental protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. ● General Foundry was warned that it will be forced to close unless the device is installed in the allotted period. ● They want to make sure that installation of the filtering system progresses smoothly and on time. 6
  • 7. Drawing the PERT/CPM Network ● Activity-on-node (AON) where the nodes represent activities. ● Activity-on-arc (AOA) where the arcs are used to represent the activities. ● The AON approach is easier and more commonly found in software packages. ● One node represents the start of the project, one node for the end of the project, and nodes for each of the activities. ● The arcs are used to show the predecessors for each activity. 7
  • 8. Network of General Foundry 8
  • 9. Activity Times Times Estimates in PERT are: Optimistic Time (a)=time activity will take if everything goes as well as possible, small percentage happening Pessimistic Time (b)=time activity will take assuming unfavorable conditions, small percentage happening Most likely Time (m)=most realistic time estimate to complete activity 9
  • 10. Activity Times Beta Probability Distribution with Three Time Estimates 10
  • 11. Activity Times Formulas Expected Activity Time: Dispersion/Variance of Activity Completion Time: 11
  • 12. Activity Times Time Estimates (weeks) for General Fondry 12
  • 13. How to Find the Critical Path We accept the expected completion time for each task as the actual time for now. The total of 25 weeks in Table 12.2 does not take into account the obvious fact that some of the tasks could be taking place at the same time. To find out how long the project will take we perform the critical path analysis for the network. The Critical Path is the longest path through the network. 13
  • 14. How to Find the Critical Path General Fondry’s Network with Expected Activity Times 14
  • 15. To find the critical path, we need to determine the following: 1. Earliest start time (ES): earliest time an activity can begin 2. Earliest finish time (EF): the earliest time an activity can end 3. Latest start time (LS): latest time an activity can begin 4. Latest finish time (LF): latest time an activity can begin How to Find the Critical Path 15
  • 16. In the nodes, the activity time and early and late start finish times are represented like below: How to Find the Critical Path 16
  • 17. Earliest finish time = Earliest start time + Expected activity TIme EF = ES + t Earliest start time = Largest of the earliest finish times of immediate predecessors ES= Largest EF of immediate predecessors Computation of Earliest Times 17
  • 18. At the start of the project, we set the time to zero, so ES=0 for both A and B. How to Find the Critical Path 18
  • 19. General Fondry’s Earliest Start (ES) and Earliest Finish (EF) Times How to Find the Critical Path 19
  • 20. Finding the Critical Path Latest start time = Latest finish time - Activity time (LS = LF - t) Latest finish time = Smallest of latest start times for following activities. LF = Smallest LS of following activities. Slack = LS - ES, or Slack = LF - EF 20
  • 21. General Foundry’s Critical Path TABLE 12.3 General Foundry’s Schedule and Slack Times FIGURE 12.5 General Foundry’s Latest Start (LS) and Latest Finish (LF) Times 21
  • 22. General Foundry’s Critical Path ● From Table 12.3 we see activities A, C, E, G, and H have no slack time. ● These are called critical activities and they are said to be on the critical path. ● The total project completion time is 15 weeks. ● Industrial managers call this a boundary timetable. 22
  • 23. Probability of Project Completion ● The critical path analysis helped us determine that the foundry’s expected project completion time is 15 weeks. ● If the project is not complete in 16, the foundry will have to close. ● PERT uses the variance of critical path activities to help determine the variance of the overall project. 23
  • 24. (cont.) *Project variance = ∑ variances of activities on the critical path 24
  • 25. Results Project standard deviation = σT = √Project Variance = √3.11 = 1.76 weeks 25
  • 26. Probability of Project Completion 26 The probability that the project can be completed in 16 weeks is .716
  • 27. Results ● The project’s expected completion date is 15 weeks. ● There is a 71.6% chance that the equipment will be in place within the 16-week deadline. ● Five activities (A, C, E, G, H) are on the critical path. ● Three activities (B, D, F) are not critical but have some slack time built in. 27
  • 28. Using Excel QM in the General Foundry Example 28 Excel QM Initialization Screen for General Foundry Example with Three Time Estimates
  • 29. Using Excel QM in the General Foundry Example 29 Excel QM Input Screen and Solution for General Foundry Example with Three Time Estimates
  • 30. Project Crashing ● Projects have deadlines that are impossible to meet through normal procedures. ● Through exceptional methods, it’s possible to finish the project in less time than normally required at a greater cost. ● Reducing a project’s completion time is called crashing. 30
  • 31. Project Crashing Crashing a project start with using the normal time to create the critical path. The normal cost is the cost for completing the activity using normal procedures. If the project will not meet the required deadline, extraordinary measures must be taken. The crash time is the shortest possible activity time and will require additional resources. The crash cost is the price of completing the activity in the earlier-than- normal time. 31
  • 32. Four Steps to Project Crashing 1. Find the normal critical path and identify the critical activities. 2. Get the crash cost per time period for all activities in the network with this formula: Crash cost/Time period = Crash cost - Normal cost Normal time - Crash time 32
  • 33. Four Steps to Project Crashing 33 3. Select smallest crash cost per week on the critical path and crash this to the maximum extent possible or to the point at which your desired deadline has been reached. 4. Check to be sure that the critical path you were crashing is still critical. If it is still the longest path through the network, return to step 3. If not, find the new critical path and return to step 2.
  • 34. General Foundry Instead of 16 weeks, General Foundry has been given 14 weeks to install the new equipment. The critical path is 15 weeks. What options does the firm have? The normal crash times and costs are shown in table 12.9. Crash costs are assumed to be linear and Figure 12.11 shows the crash cost for activity B. Crashing activities B and A will shorten the completion time to 14 but it creates a second critical path. Any further crashing must be done to both critical paths. 34
  • 35. General Foundry Normal and Crash Data for General Foundry, Inc. Table 12.9 Time (Weeks) Cost ($) Activity Normal Crash Normal Crash Crash Cost per Week ($) Critical Path A 2 1 22000 23000 1000 Yes B 3 1 30000 34000 2000 No C 2 1 26000 27000 1000 Yes D 4 3 48000 49000 1000 No E 4 2 56000 58000 1000 Yes F 3 2 30000 30500 500 No G 5 2 80000 86000 2000 Yes H 2 1 16000 19000 3000 Yes 35
  • 36. General Foundry Crash and Normal Times and Costs for Activity B Figure 12.11 36
  • 37. Project Crashing with Linear Programming •Another approach to finding the best project crashing schedule. •The data needed are derived from the normal and crash data for General Foundry and the project network with activity times. 37
  • 38. Project Crashing with Linear Programming General Foundry’s Network With Activity Times Figure 12.12 38
  • 39. Project Crashing with Linear Programming Objective function: Minimize crash cost = 1,000YA+ 2,000YB+ 1,000YC+ 1,000YD+ 1,000YE+ 500YF+ 2,000YG+ 3,000YH Subject to these constraints: YA≤1 YG≤3 YB≤2 YH≤1 YC≤1 Xfinish≤ 12 YD≤1 Xfinish≥ XH YE≤2 YF≤1 39
  • 40. Project Crashing with Linear Programming where, XA= EF for activity A XB= EF for activity B XC= EF for activity C XD= EF for activity D XE= EF for activity E XF= EF for activity F XG= EF for activity G XH= EF for activity H Xstart= start time for project (usually 0) Xfinish= earliest finish time for the project 40
  • 41. Project Crashing with Linear Programming Constraints describing the network have the form: EF time≥ EF time for predecessor + Activity time EF≥ EFpredecessor+ (t–Y), or X≥ Xpredecessor+ (t–Y) For activity A,XA≥ Xstart+ (2 –YA) or XA–Xstart+ YA≥ 2 For activity B,XB≥ Xstart+ (3 –YB) or XB–Xstart+ YB≥ 3 For activity C,XC≥ XA+ (2 –YC) or XC–XA+ YC≥ 2 For activity D,XD≥ XB+ (4 –YD) or XD–XB+ YD≥ 4 For activity E,XE≥ XC+ (4 –YE) or XE–XC+ YE≥ 4 For activity F,XF≥ XC+ (3 –YF) or XF–XC+ YF≥ 3 For activity G,XG≥ XD+ (5 –YG) or XG–XD+ YG≥ 5 For activity G,XG≥ XE+ (5 –YG) or XG–XE+ YG≥ 5 For activity H,XH≥ XF+ (2 –YH) or XH–XF+ YH≥ 2 For activity H,XH≥ XG+ (2 –YH) or XH–XG+ YH≥ 2 41
  • 42. Solution to Crashing Problem Using Solver in Excel Program 12.2 42
  • 43. Other Topics in Project Management Subprojects Milestones Resources Leveling Software •Extremely large projects •Creation of several small sub-activities which is subproject of the original •Major events in a project •Gantt and PERT charts to show importance of reaching these events •Adjusting at the start of the event •Even distribution of resources •Creates PERT and Gantt charts •Budget schedules, adjust future start times, and level resource utilization 43
  • 44. 1. The earliest start time for an activity is equal to 3. If activity A is not on the critical path, then the a. the largest EF of the immediate predecessors. slack for A will equal b. the smallest EF of the immediate predecessors. a. LF - EF. c. the largest ES of the immediate predecessors. b. EF - ES. d. the smallest ES of the immediate predecessors c. 0 2. The standard deviation for the PERT project is d. all of the above approximately 4. The critical path is the a. the square root of the sum of the variances along thea.shortest path in a network. critical path. b. longest path in a network. b. the sum of the critical path activity standard deviations. c. path with the smallest variance. c. the square root of the sum of the variances of the project d. path with the largest variance. activities. e. none of the above. d. all of the above. 5. PERT stands for ______________. e. none of the above. 6. Project crashing can be performed using a _____________. Sample Exercises 44
  • 45. 1. A 2. A 3. A 4. B 5. Program Evaluation and Review Techniques 6. Linear Programming model Answers to sample exercises 45
  • 46. 1. Sid Davidson is the personnel director of Babson and Willcount, a company that specializes in consulting and research. One of the training programs that Sid is considering for the middle-level managers of Babson and Willcount is leadership training. Sid has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities and immediate predecessors appear in the following table. Develop a network for this problem Sample Problem 46
  • 47. Answers to sample problem 47