Project Management – Spring 2024
Dr. Ibrahim Nabil Eldesouky
Faculty of Engineering
German International University (GIU)
Topics
1. Project Management basic concepts
2. Define the Project scope and priorities.
3. Estimate the project time and cost.
4. Develop project schedule.
5. Risk Management.
6. Schedule resources.
7. Project team management.
8. Progress and performance evaluation.
9. Project closing
17 March 2024 Dr. Ibrahim Eldesouky 2
Lecture 6 - The Project Time and Cost
17 March 2024 Dr. Ibrahim Eldesouky 3
Learning Outcomes
• Calculating the probability that a project will be completed within a
certain time.
• Reducing the project time (crashing).
• Cost evaluation and forecasting.
17 March 2024 Dr. Ibrahim Eldesouky 4
Probabilistic Time Estimates
• Optimistic time (a)
• Time required under optimal conditions
• Pessimistic time (b)
• Time required under worst conditions
• Most likely time (m)
• Most probable length of time that will be required
17 March 2024 Dr. Ibrahim Eldesouky 5
CPM with Probabilistic Time Estimates
Step 1: Identify activities.
Step 2: Sequence activities and construct network.
Step 3: Determine the three time estimates for
each activity.
a = optimistic time
m = most likely time
b = pessimistic time
Step 4: Calculate the Expected Time (ET) for each activity.
6
b
4m
a
ET
+
+
=
The calculation is a weighted average of the three-time estimates, a, m, and b
using weights of 1‐4‐1, respectively.
17 March 2024 Dr. Ibrahim Eldesouky 6
CPM with Probabilistic Time Estimates
Step 5: Calculate the variance (σ2) for each activity.
In this case, the “6” is an assumption that the range of the distribution covers six
standard deviations (6σ) so that 99.7 percent of all cases were greater than a and
less than b; 2
2
6





 

a
b

17 March 2024 Dr. Ibrahim Eldesouky 7
Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
Estimating the Probability of Completion Dates
Step 7: Determine the probability of completing the project
by a certain date.
p
p
ET
D
Z



D = Desired completion date for the project
ETp = Expected completion time for the path
σp = Standard deviation for the path
17 March 2024 Dr. Ibrahim Eldesouky 8
Project Activity Expected Time
17 March 2024 Dr. Ibrahim Eldesouky 9
Activity
Optimistic
time
Most likely
time
Pessimistic
time
Expected
time
A 2 4 6 4
B 3 7 10 6.83
C 2 3 5 3.17
D 4 7 9 6.83
E 12 16 20 16
F 2 5 8 5
G 2 2 2 2
H 2 3 4 3
I 2 3 5 3.17
J 2 4 6 4
K 2 2 2 2
Project Activity Variance
Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
17 March 2024 Dr. Ibrahim Eldesouky 10
Build AOA Network & Identify Paths
17 March 2024 Dr. Ibrahim Eldesouky 11
Variances of Each Path through the Network
Path
Number
Activities on
Path
Path Time
(Weeks)
Path Variance
(weeks)
1 A,B,D,E,G,H,J,k 44.66 4.82
2 A,B,D,E,G,I,J,K 44.83 4.96
3 A,C,F,G,H,J,K 23.17 2.24
4 A,C,F,G,I,J,K 23.34 2.38
17 March 2024 Dr. Ibrahim Eldesouky 12
ABDEGIJK is the expected critical path & the project has an expected duration
of 44.83 weeks
Example: Calculating the probability of finishing the project
in 48 weeks
• Use the z values in Appendix B to determine probabilities
• e.g. probability for path 1 is
Path
Number
Activities on Path Path Variance
(weeks)
z-value Probability of
Completion
1 A,B,D,E,G,H,J,k 4.82 1.52 0.93
2 A,B,D,E,G,I,J,K 4.96 1.42 0.92
3 A,C,F,G,H,J,K 2.24 16.59 1.00
4 A,C,F,G,I,J,K 2.38 15.98 1.00
17 March 2024 Dr. Ibrahim Eldesouky 13
17 March 2024 Dr. Ibrahim Eldesouky 14
17 March 2024 Dr. Ibrahim Eldesouky 15
Reducing Project Completion Time
• Project completion times may need to be shortened because:
• Penalty.
• Need to put resources on a new project.
• Promised completion dates.
• Reduced project completion time is “crashing”
17 March 2024 Dr. Ibrahim Eldesouky 16
Reducing Project Completion Time – con’t
• Crashing a project needs to balance
• Shorten a project duration
• Cost to shorten the project duration
• Crashing a project requires you to know
• Crash time of each activity
• Crash cost of each activity
Crash cost/duration = (crash cost-normal cost)/(normal time – crash time)
17 March 2024 Dr. Ibrahim Eldesouky 17
Reducing the Time of a Project (crashing)
Activity Normal
Time (wk)
Normal
Cost ($)
Crash
Time
(wk)
Crash
Cost ($)
Max. weeks
of reduction
Reduce cost
per week
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1 5,000
C 3 6,000 3 6,000 0 0
D 6 24,000 4 28,000 2 2,000
E 14 60,000 12 72,000 2 6,000
F 5 5,000 4 6,500 1 1500
G 2 6,000 2 6,000 0 0
H 2 4,000 2 4,000 0 0
I 3 4,000 2 5,000 1 1,000
J 4 4,000 2 6,400 2 1,200
K 2 5,000 2 5,000 0 0
17 March 2024 Dr. Ibrahim Eldesouky 18
Crashing Example: Suppose the Cables By Us project manager
wants to reduce the new product project from 41 to 36 weeks.
• Crashing Costs are considered to be linear
• Look to crash activities on the critical path
• Crash the least expensive activities on the critical path first
(based on cost per week)
• Crash activity I from 3 weeks to 2 weeks $1000
• Crash activity J from 4 weeks to 2 weeks $2400
• Crash activity D from 6 weeks to 4 weeks $4000
• Recommend Crash Cost $7400
17 March 2024 Dr. Ibrahim Eldesouky 19
Crashed Network A-O-N Diagram
17 March 2024 Dr. Ibrahim Eldesouky 20
Crashed Network A-O-N Diagram
17 March 2024 Dr. Ibrahim Eldesouky 21
Estimate Activity Costs
Elements
• Labor
• Materials
• Equipment
• Facilities
• Subcontractors and consultants
• Travel
• Reserve
Good Practices
• Have the person responsible
estimate costs.
• Use historical data to inform the
current project manager.
• Be reasonable and realistic.
• Estimate near-term activities more
accurately.
• Elaborate on other costs as
additional information is known.
17 March 2024 Dr. Ibrahim Eldesouky 22
Consumer Market Study Project
Estimated Costs
17 March 2024 Dr. Ibrahim Eldesouky 23
Total Budgeted Cost
• Establish a Total Budgeted
Cost TBC for each work
package
• Determine the process
• Top-down
• Bottom-up
• If sum of initial estimates
exceeds sponsor budget,
then reduce costs and
recalculate
17 March 2024 Dr. Ibrahim Eldesouky 24
Packaging Machine Project
Aggregate Total Budgeted Cost
17 March 2024 Dr. Ibrahim Eldesouky 25
Packaging Machine Project
Develop Cumulative Budgeted Cost
• Determine budgeted cost by period
• Graph the cumulative budgeted cost
curve
17 March 2024 Dr. Ibrahim Eldesouky 26
Determine Actual Cost
• Actual Cost
• Collect data regularly for funds actually spent
• Charge to work package numbers
• Compare Actual Cost To Budgeted Cost
• Calculate cumulative actual cost
• Compare to cumulative budgeted cost
17 March 2024 Dr. Ibrahim Eldesouky 27
Packaging Machine Project
Determine Actual Cost
• End of Week 8
• Planned cost = $64,000
• Actual cost = $68,000
• Compare Cumulative Actual
Cost CAC with Cumulative
Budgeted Cost CBC
17 March 2024 Dr. Ibrahim Eldesouky 28
Determine the Earned Value of Work Performed
Example Project
• Paint 10 similar rooms
• Total budgeted cost of $2,000
• Budget is $200 per room
At Day 5
• $1,000 has been spent
• 3 rooms have been painted
• Earned value =
0.30 X $2,000 = $600
• Have spent $400 more than the
Earned Value
17 March 2024 Dr. Ibrahim Eldesouky 29
Packaging Machine Project
Determine the Earned Value of Work Performed
17 March 2024 Dr. Ibrahim Eldesouky 30
EV = % of work completed x TBC
Analyze Cost Performance
• Four cost-related measures
• TBC – Total Budgeted Cost
• CBC – Cumulative Budgeted Cost
• CAC – Cumulative Actual Cost
• CEV – Cumulative Earned Value
• To analyze project cost performance
• Plot CBC, CAC, and CEV curves on the same graph
• Reveal any trends toward improving or deteriorating cost performance
17 March 2024 Dr. Ibrahim Eldesouky 31
Packaging Machine Project
Analyze Cost Performance
17 March 2024 Dr. Ibrahim Eldesouky 32
CBC CAC CEV
Cost Performance Index
• Measure of the cost efficiency with which the project is being
performed
• Cost performance index =
Cumulative earned value/Cumulative actual cost
CPI = CEV/CAC
17 March 2024 Dr. Ibrahim Eldesouky 33
Packaging Machine Project
Cost Performance Index
End of Week 8
• $64,000 was budgeted
• $68,000 was actually expended
• $54,000 was the earned value of
work actually performed
• CEV = $54,000
• CAC = $68,000
Determine CPI
• CPI = CEV/CAC
= $54,000/$68,000
= 0.79
For every $1.00 actually
expended, only $0.79 of earned
value was received.
17 March 2024 Dr. Ibrahim Eldesouky 34
Cost Variance
• Indicator of cost performance
• Difference between the cumulative earned value of the work
performed and the cumulative actual cost
• Cost variance =
Cumulative earned value – Cumulative actual cost
CV = CEV – CAC
17 March 2024 Dr. Ibrahim Eldesouky 35
Packaging Machine Project
Cost Variance
End of Week 8
• $64,000 was budgeted
• $68,000 was actually expended
• $54,000 was the earned value of
work actually performed
• CEV = $54,000
• CAC = $68,000
Determine CV
• CV = CEV – CAC
= $54,000 – $68,000
= –$14,000
The value of the work
performed through week 8 is
$14,000 less than the amount
actually expended.
17 March 2024 Dr. Ibrahim Eldesouky 36
Estimate Cost at Completion
• Forecast what the total costs will be at the completion of the project
or work package
• 3 different methods
• FCAC = TBC / CPI
• FCAC = CAC + (TBC – CEV)
• FCAC = CAC + Re-estimate of remaining work
• Another method
• To Complete performance index
• TCPI = (TBC – CEV)/(TBC – CAC)
17 March 2024 Dr. Ibrahim Eldesouky 37
To complete performance index
• TCPI indicates the target cost performance index (CPI) that is needed
to complete the project at the target budget.
• To-complete-performance index is the result of dividing the
remaining budget according to the plan by the actually available
budget.
• TCPI = 1: the project can continue with the current budget
consumption rate
• TCPI < 1: based on the current cost variance, the project will be
completed at total cost lower than the budget.
• TCPI > 1: if the project continues working with the present cost
variance, it will complete at a budget overrun.
17 March 2024 Dr. Ibrahim Eldesouky 38
Packaging Machine Project
Estimate Cost at Completion
End of Week 8
• $64,000 was budgeted
• $68,000 was actually expended
• $54,000 was the earned value of
work actually performed
• CEV = $54,000
• CAC = $68,000
• CPI = 0.79
• TBC = $100,000
Determine FCAC
• FCAC = TBC / CPI
= $100,000/0.79 = $126,582
• FCAC = CAC + (TBC – CEV)
= $68,000 + ($100,000 – $54,000)
= $68,000 + $46,000
= $114,000
• TCPI = (TBC – CEV)/(TBC – CAC)
= ($100,000 − $54,000)/($100,000 − $68,000)
= $46,000/$32,000
= 1.44
17 March 2024 Dr. Ibrahim Eldesouky 39
Manage Cash Flow
• Ensure that cash comes in faster than it goes out
• Negotiate payment terms
• Provide a down payment
• Make equal monthly payments
• Provide frequent payments
• Avoid only one payment at end of project
• Control outflow of cash
17 March 2024 Dr. Ibrahim Eldesouky 40
Any questions?
17 March 2024 Dr. Ibrahim Eldesouky 41

GIU_2743_62_16479_2024-03-17T11_45_07.pdf

  • 1.
    Project Management –Spring 2024 Dr. Ibrahim Nabil Eldesouky Faculty of Engineering German International University (GIU)
  • 2.
    Topics 1. Project Managementbasic concepts 2. Define the Project scope and priorities. 3. Estimate the project time and cost. 4. Develop project schedule. 5. Risk Management. 6. Schedule resources. 7. Project team management. 8. Progress and performance evaluation. 9. Project closing 17 March 2024 Dr. Ibrahim Eldesouky 2
  • 3.
    Lecture 6 -The Project Time and Cost 17 March 2024 Dr. Ibrahim Eldesouky 3
  • 4.
    Learning Outcomes • Calculatingthe probability that a project will be completed within a certain time. • Reducing the project time (crashing). • Cost evaluation and forecasting. 17 March 2024 Dr. Ibrahim Eldesouky 4
  • 5.
    Probabilistic Time Estimates •Optimistic time (a) • Time required under optimal conditions • Pessimistic time (b) • Time required under worst conditions • Most likely time (m) • Most probable length of time that will be required 17 March 2024 Dr. Ibrahim Eldesouky 5
  • 6.
    CPM with ProbabilisticTime Estimates Step 1: Identify activities. Step 2: Sequence activities and construct network. Step 3: Determine the three time estimates for each activity. a = optimistic time m = most likely time b = pessimistic time Step 4: Calculate the Expected Time (ET) for each activity. 6 b 4m a ET + + = The calculation is a weighted average of the three-time estimates, a, m, and b using weights of 1‐4‐1, respectively. 17 March 2024 Dr. Ibrahim Eldesouky 6
  • 7.
    CPM with ProbabilisticTime Estimates Step 5: Calculate the variance (σ2) for each activity. In this case, the “6” is an assumption that the range of the distribution covers six standard deviations (6σ) so that 99.7 percent of all cases were greater than a and less than b; 2 2 6         a b  17 March 2024 Dr. Ibrahim Eldesouky 7 Activity Optimistic Most Likely Pessimistic Variance A 2 4 6 0.44 B 3 7 10 1.36 C 2 3 5 0.25 D 4 7 9 0.69 E 12 16 20 1.78 F 2 5 8 1.00 G 2 2 2 0.00 H 2 3 4 0.11 I 2 3 5 0.25 J 2 4 6 0.44 K 2 2 2 0.00
  • 8.
    Estimating the Probabilityof Completion Dates Step 7: Determine the probability of completing the project by a certain date. p p ET D Z    D = Desired completion date for the project ETp = Expected completion time for the path σp = Standard deviation for the path 17 March 2024 Dr. Ibrahim Eldesouky 8
  • 9.
    Project Activity ExpectedTime 17 March 2024 Dr. Ibrahim Eldesouky 9 Activity Optimistic time Most likely time Pessimistic time Expected time A 2 4 6 4 B 3 7 10 6.83 C 2 3 5 3.17 D 4 7 9 6.83 E 12 16 20 16 F 2 5 8 5 G 2 2 2 2 H 2 3 4 3 I 2 3 5 3.17 J 2 4 6 4 K 2 2 2 2
  • 10.
    Project Activity Variance ActivityOptimistic Most Likely Pessimistic Variance A 2 4 6 0.44 B 3 7 10 1.36 C 2 3 5 0.25 D 4 7 9 0.69 E 12 16 20 1.78 F 2 5 8 1.00 G 2 2 2 0.00 H 2 3 4 0.11 I 2 3 5 0.25 J 2 4 6 0.44 K 2 2 2 0.00 17 March 2024 Dr. Ibrahim Eldesouky 10
  • 11.
    Build AOA Network& Identify Paths 17 March 2024 Dr. Ibrahim Eldesouky 11
  • 12.
    Variances of EachPath through the Network Path Number Activities on Path Path Time (Weeks) Path Variance (weeks) 1 A,B,D,E,G,H,J,k 44.66 4.82 2 A,B,D,E,G,I,J,K 44.83 4.96 3 A,C,F,G,H,J,K 23.17 2.24 4 A,C,F,G,I,J,K 23.34 2.38 17 March 2024 Dr. Ibrahim Eldesouky 12 ABDEGIJK is the expected critical path & the project has an expected duration of 44.83 weeks
  • 13.
    Example: Calculating theprobability of finishing the project in 48 weeks • Use the z values in Appendix B to determine probabilities • e.g. probability for path 1 is Path Number Activities on Path Path Variance (weeks) z-value Probability of Completion 1 A,B,D,E,G,H,J,k 4.82 1.52 0.93 2 A,B,D,E,G,I,J,K 4.96 1.42 0.92 3 A,C,F,G,H,J,K 2.24 16.59 1.00 4 A,C,F,G,I,J,K 2.38 15.98 1.00 17 March 2024 Dr. Ibrahim Eldesouky 13
  • 14.
    17 March 2024Dr. Ibrahim Eldesouky 14
  • 15.
    17 March 2024Dr. Ibrahim Eldesouky 15
  • 16.
    Reducing Project CompletionTime • Project completion times may need to be shortened because: • Penalty. • Need to put resources on a new project. • Promised completion dates. • Reduced project completion time is “crashing” 17 March 2024 Dr. Ibrahim Eldesouky 16
  • 17.
    Reducing Project CompletionTime – con’t • Crashing a project needs to balance • Shorten a project duration • Cost to shorten the project duration • Crashing a project requires you to know • Crash time of each activity • Crash cost of each activity Crash cost/duration = (crash cost-normal cost)/(normal time – crash time) 17 March 2024 Dr. Ibrahim Eldesouky 17
  • 18.
    Reducing the Timeof a Project (crashing) Activity Normal Time (wk) Normal Cost ($) Crash Time (wk) Crash Cost ($) Max. weeks of reduction Reduce cost per week A 4 8,000 3 11,000 1 3,000 B 6 30,000 5 35,000 1 5,000 C 3 6,000 3 6,000 0 0 D 6 24,000 4 28,000 2 2,000 E 14 60,000 12 72,000 2 6,000 F 5 5,000 4 6,500 1 1500 G 2 6,000 2 6,000 0 0 H 2 4,000 2 4,000 0 0 I 3 4,000 2 5,000 1 1,000 J 4 4,000 2 6,400 2 1,200 K 2 5,000 2 5,000 0 0 17 March 2024 Dr. Ibrahim Eldesouky 18
  • 19.
    Crashing Example: Supposethe Cables By Us project manager wants to reduce the new product project from 41 to 36 weeks. • Crashing Costs are considered to be linear • Look to crash activities on the critical path • Crash the least expensive activities on the critical path first (based on cost per week) • Crash activity I from 3 weeks to 2 weeks $1000 • Crash activity J from 4 weeks to 2 weeks $2400 • Crash activity D from 6 weeks to 4 weeks $4000 • Recommend Crash Cost $7400 17 March 2024 Dr. Ibrahim Eldesouky 19
  • 20.
    Crashed Network A-O-NDiagram 17 March 2024 Dr. Ibrahim Eldesouky 20
  • 21.
    Crashed Network A-O-NDiagram 17 March 2024 Dr. Ibrahim Eldesouky 21
  • 22.
    Estimate Activity Costs Elements •Labor • Materials • Equipment • Facilities • Subcontractors and consultants • Travel • Reserve Good Practices • Have the person responsible estimate costs. • Use historical data to inform the current project manager. • Be reasonable and realistic. • Estimate near-term activities more accurately. • Elaborate on other costs as additional information is known. 17 March 2024 Dr. Ibrahim Eldesouky 22
  • 23.
    Consumer Market StudyProject Estimated Costs 17 March 2024 Dr. Ibrahim Eldesouky 23
  • 24.
    Total Budgeted Cost •Establish a Total Budgeted Cost TBC for each work package • Determine the process • Top-down • Bottom-up • If sum of initial estimates exceeds sponsor budget, then reduce costs and recalculate 17 March 2024 Dr. Ibrahim Eldesouky 24
  • 25.
    Packaging Machine Project AggregateTotal Budgeted Cost 17 March 2024 Dr. Ibrahim Eldesouky 25
  • 26.
    Packaging Machine Project DevelopCumulative Budgeted Cost • Determine budgeted cost by period • Graph the cumulative budgeted cost curve 17 March 2024 Dr. Ibrahim Eldesouky 26
  • 27.
    Determine Actual Cost •Actual Cost • Collect data regularly for funds actually spent • Charge to work package numbers • Compare Actual Cost To Budgeted Cost • Calculate cumulative actual cost • Compare to cumulative budgeted cost 17 March 2024 Dr. Ibrahim Eldesouky 27
  • 28.
    Packaging Machine Project DetermineActual Cost • End of Week 8 • Planned cost = $64,000 • Actual cost = $68,000 • Compare Cumulative Actual Cost CAC with Cumulative Budgeted Cost CBC 17 March 2024 Dr. Ibrahim Eldesouky 28
  • 29.
    Determine the EarnedValue of Work Performed Example Project • Paint 10 similar rooms • Total budgeted cost of $2,000 • Budget is $200 per room At Day 5 • $1,000 has been spent • 3 rooms have been painted • Earned value = 0.30 X $2,000 = $600 • Have spent $400 more than the Earned Value 17 March 2024 Dr. Ibrahim Eldesouky 29
  • 30.
    Packaging Machine Project Determinethe Earned Value of Work Performed 17 March 2024 Dr. Ibrahim Eldesouky 30 EV = % of work completed x TBC
  • 31.
    Analyze Cost Performance •Four cost-related measures • TBC – Total Budgeted Cost • CBC – Cumulative Budgeted Cost • CAC – Cumulative Actual Cost • CEV – Cumulative Earned Value • To analyze project cost performance • Plot CBC, CAC, and CEV curves on the same graph • Reveal any trends toward improving or deteriorating cost performance 17 March 2024 Dr. Ibrahim Eldesouky 31
  • 32.
    Packaging Machine Project AnalyzeCost Performance 17 March 2024 Dr. Ibrahim Eldesouky 32 CBC CAC CEV
  • 33.
    Cost Performance Index •Measure of the cost efficiency with which the project is being performed • Cost performance index = Cumulative earned value/Cumulative actual cost CPI = CEV/CAC 17 March 2024 Dr. Ibrahim Eldesouky 33
  • 34.
    Packaging Machine Project CostPerformance Index End of Week 8 • $64,000 was budgeted • $68,000 was actually expended • $54,000 was the earned value of work actually performed • CEV = $54,000 • CAC = $68,000 Determine CPI • CPI = CEV/CAC = $54,000/$68,000 = 0.79 For every $1.00 actually expended, only $0.79 of earned value was received. 17 March 2024 Dr. Ibrahim Eldesouky 34
  • 35.
    Cost Variance • Indicatorof cost performance • Difference between the cumulative earned value of the work performed and the cumulative actual cost • Cost variance = Cumulative earned value – Cumulative actual cost CV = CEV – CAC 17 March 2024 Dr. Ibrahim Eldesouky 35
  • 36.
    Packaging Machine Project CostVariance End of Week 8 • $64,000 was budgeted • $68,000 was actually expended • $54,000 was the earned value of work actually performed • CEV = $54,000 • CAC = $68,000 Determine CV • CV = CEV – CAC = $54,000 – $68,000 = –$14,000 The value of the work performed through week 8 is $14,000 less than the amount actually expended. 17 March 2024 Dr. Ibrahim Eldesouky 36
  • 37.
    Estimate Cost atCompletion • Forecast what the total costs will be at the completion of the project or work package • 3 different methods • FCAC = TBC / CPI • FCAC = CAC + (TBC – CEV) • FCAC = CAC + Re-estimate of remaining work • Another method • To Complete performance index • TCPI = (TBC – CEV)/(TBC – CAC) 17 March 2024 Dr. Ibrahim Eldesouky 37
  • 38.
    To complete performanceindex • TCPI indicates the target cost performance index (CPI) that is needed to complete the project at the target budget. • To-complete-performance index is the result of dividing the remaining budget according to the plan by the actually available budget. • TCPI = 1: the project can continue with the current budget consumption rate • TCPI < 1: based on the current cost variance, the project will be completed at total cost lower than the budget. • TCPI > 1: if the project continues working with the present cost variance, it will complete at a budget overrun. 17 March 2024 Dr. Ibrahim Eldesouky 38
  • 39.
    Packaging Machine Project EstimateCost at Completion End of Week 8 • $64,000 was budgeted • $68,000 was actually expended • $54,000 was the earned value of work actually performed • CEV = $54,000 • CAC = $68,000 • CPI = 0.79 • TBC = $100,000 Determine FCAC • FCAC = TBC / CPI = $100,000/0.79 = $126,582 • FCAC = CAC + (TBC – CEV) = $68,000 + ($100,000 – $54,000) = $68,000 + $46,000 = $114,000 • TCPI = (TBC – CEV)/(TBC – CAC) = ($100,000 − $54,000)/($100,000 − $68,000) = $46,000/$32,000 = 1.44 17 March 2024 Dr. Ibrahim Eldesouky 39
  • 40.
    Manage Cash Flow •Ensure that cash comes in faster than it goes out • Negotiate payment terms • Provide a down payment • Make equal monthly payments • Provide frequent payments • Avoid only one payment at end of project • Control outflow of cash 17 March 2024 Dr. Ibrahim Eldesouky 40
  • 41.
    Any questions? 17 March2024 Dr. Ibrahim Eldesouky 41