 TENDERING
Ar Jit Kumar Gupta
Chandigarh
 Tender- an offer in writing made by one party- contractor
 - to another- owner to
 -- supply
 - construct
 --remove/ repair
 - provide a service
 --in construction/ execution of a building
 - within a stipulated time
 - under conditions specified in the tender
 -- Tender must be in writing
 - must be in a proper form
 -- signed by persons duly authorized
 -state has liberty to invite tenders from one class of
contractors to exclusion of others
 Objectives--Give wide publicity
 Obtain competitive bidding
 Get quality work at competitive rates
 Provide equal opportunity to large number of contractors
 Have wider choice for owner
 Obtaining value for money by owner
 Essentials of Tender Notice– NIT--must contain:
 --Brief description of work
 --Estimated cost, EMD- Earnest money deposit;
 --Cost of Tender,
 Time of completion, eligibility of contractor;
 -- Last date of obtaining tender
 -- Place and period of issue of tender
 -- date , time and place of tender
 -Date, time and place of opening tenders
 -Supply of materials by tenderer
 - Cancellation of tender/contract in case of non-commencement of
work in time
 --Availability of clear site
 --Availability of adequate funds
 -Material procurement
 - Finalized and working drawings
 --list of pre-qualified contractors
 - Statutory clearances from competent authorities
 --basic infrastructure at site
 -- access to site during inspection
 -- special bye-laws to be followed , if any at site
 i. Notice inviting tender in detail
 ii. General conditions of contract-
 - security deposit;
 --Bonus/ fine clauses
 - stages of payment
 -- final bill
 -- completion certificate
 -- material supply- owner/contractor
 -- advances
 - escalation, variations
 -- defective work
 - defect liability period
 -- arbitration
 - other conditions
 - EMD
 -Specific conditions in specialized work
 Iii. Schedule of Quantities
 Iv. Tender Drawings
 V. Specifications in detail
 Vi Form of Agreement
 Vii Formats and statements- safety code; labour
regulations; bank guarantee etc
 Ix Detailed architectural, structural and service
drawings
 X Network Chart
 Two Cover Bidding system– done post qualification-
Technical bid/ price or financial bid
 Pre- bid conference– for specialized works- to explain
details to perspective bidders – before the date
specified for bidding- become part of contract
 Receipt and opening of tender;
 - at a specified place and time- as notified in tender
 --Committee constituted to check all details including-
 --Number of tenderers.
 -- EMD;
 -Bank Guarantee;
 --signatures
 --documents etc
 -- recording them in a register
 - signed by all bidders/representatives and members of
the committee
 Evaluation of tender;
 Checking discrepancies between /in rates and
quantities
 -- arithmetic calculations
 - figures in words and numbers
 -- market value analysis
 -- overhead amounts
 - justified amount of each bidder
 -
 Issues during bidding process;
 - Lack of essential documents
 --late receipt of tender
 --bidder signatures
 --discrepancies in rates/amount
 -Non- submission of EMD
 --Withdrawal of bid before opening
 -- Withdrawal of bid before validity period
 -- depositing security amount
 --signing formal agreement
 -- No relaxation of eligibility criteria
 --no change in scope of work after receipts of bids
 --formation of cartel
 --poor response necessitating re-tendering
 --Contract awarded ;
 -lowest financial bidder
 -can be rejected if
 --rates appear to be high
 -if based on false information
 -- change in scope of work
 -cartel formation
 -- In private sector- negotiation is possible to further
rationalise the rates
 Work order given to-
 -Given to selected contractor/bidder
 -within validity period
 -before issue- clear site
 -- statutory approvals in place
 --funds available
 --work order issued in writing and contains;
 --tendered amount
 --all relevant correspondence
 - negotiation details if any
 - letter with particular conditions defined in tender
document
 Commencement of Work –
 --handing over of site to contractor
 - making available mobilisation advance-- in large
projects
 - materials issued- if specified in the contract
 --resource mobilisation
 --bank guarantee
 -- drawings
 -
 -
 - Releasing clear site
 --Timely release of funds
 -making available drawings
 -Non-interference
 --providing licenses where required
 -- making available materials
 --settle about escalations
 --taking over of site after completion
 -- settlement of final bill
 --release of security deposit
 --timely payment to contractor—payment of final bill
as per contract conditions
 --
 -
 - after receiving work order
 -- take possession of the site
 --setting up a site office
 -- mobilise money and machinery and labour
 -- Engage quality and experienced labour
 -- site management
 -- providing quality work
 -- avoid all wastage
 -- follow specification provided
 - completion of project within the given time schedule
 - follow the drawings issued by the architect
 --de-mobilitsaion of work after completion
 --handing over the project to owner
 --rectification of defects with liability period
 -- identification of sub-contractors and vendors
 --no misuse/abuse of site during progress of work
 -- Maintaining all site records
 -- Take all safety measures
 --
 --
 -

More Related Content

What's hot

Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
gandrajuadityavarmagav
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
vvsasane
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract management
VISHAKA BOTHRA
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
arpantripathi2
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
Prateek Kashyap
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
Rajat Nainwal
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
Ritesh Kumar Baranwal
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Tender
TenderTender
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
JIT KUMAR GUPTA
 
Construction practices
Construction practicesConstruction practices
Construction practices
Arun Kurali
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
Aditya Sanyal
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
politeknik malaysia
 

What's hot (20)

Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract management
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Tender
TenderTender
Tender
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 

Similar to Tendering presenation

Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 
contract and arbitration.pdf
contract and arbitration.pdfcontract and arbitration.pdf
contract and arbitration.pdf
GUDAGUDA
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
tendering
 tendering tendering
tendering
KEVINMISTRY8
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
neharajpl
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
Swamy Vanapalli
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
Aditya Sanyal
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 
Notes unit 2A.ppt
Notes unit 2A.pptNotes unit 2A.ppt
Notes unit 2A.ppt
piyushbhandari36
 
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
LuminaJulie1
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
ArchDuty
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
Venkata Bhaskar Damera
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
Mohib Ullah
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
Padmasinh Patil
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
Akash Bharti
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
ssuser4ae21a
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
TanmayBhatt22
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
mekuannintdemeke
 
TENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.pptTENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.ppt
2ke21cv405
 
TENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.pptTENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.ppt
2ke21cv405
 

Similar to Tendering presenation (20)

Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
contract and arbitration.pdf
contract and arbitration.pdfcontract and arbitration.pdf
contract and arbitration.pdf
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
tendering
 tendering tendering
tendering
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Notes unit 2A.ppt
Notes unit 2A.pptNotes unit 2A.ppt
Notes unit 2A.ppt
 
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
1449739458979-TENDERSANDCONTRACTS -FINAL.ppt
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
TENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.pptTENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.ppt
 
TENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.pptTENDERS AND TENDER DOCUMENTS.ppt
TENDERS AND TENDER DOCUMENTS.ppt
 

More from JIT KUMAR GUPTA

Role and Relevance of Architects and architecture in Sustainability
Role and Relevance of Architects and architecture in SustainabilityRole and Relevance of Architects and architecture in Sustainability
Role and Relevance of Architects and architecture in Sustainability
JIT KUMAR GUPTA
 
Bridging gap between resources and responsibilities at Local level.
Bridging gap between resources and responsibilities at Local level.Bridging gap between resources and responsibilities at Local level.
Bridging gap between resources and responsibilities at Local level.
JIT KUMAR GUPTA
 
Construction Industry Through Artificial Intelligence -.docx
Construction Industry Through Artificial Intelligence -.docxConstruction Industry Through Artificial Intelligence -.docx
Construction Industry Through Artificial Intelligence -.docx
JIT KUMAR GUPTA
 
Making Urban India a Role Model of Planned Urban Growth a.docx
Making Urban India a Role Model of Planned Urban Growth a.docxMaking Urban India a Role Model of Planned Urban Growth a.docx
Making Urban India a Role Model of Planned Urban Growth a.docx
JIT KUMAR GUPTA
 
Redefining Globalization, urbanisation and Localisation
Redefining Globalization, urbanisation and LocalisationRedefining Globalization, urbanisation and Localisation
Redefining Globalization, urbanisation and Localisation
JIT KUMAR GUPTA
 
Knowing, Understanding and Planning Cities- Role and Relevance Physical Plan...
Knowing, Understanding and Planning Cities- Role and Relevance  Physical Plan...Knowing, Understanding and Planning Cities- Role and Relevance  Physical Plan...
Knowing, Understanding and Planning Cities- Role and Relevance Physical Plan...
JIT KUMAR GUPTA
 
Land as a Resource for urban finanace- 24-1-23.ppt
Land as a Resource  for urban finanace- 24-1-23.pptLand as a Resource  for urban finanace- 24-1-23.ppt
Land as a Resource for urban finanace- 24-1-23.ppt
JIT KUMAR GUPTA
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
JIT KUMAR GUPTA
 
Making Buildings cost-effective , Energy Efficient ptx
Making Buildings cost-effective , Energy Efficient  ptxMaking Buildings cost-effective , Energy Efficient  ptx
Making Buildings cost-effective , Energy Efficient ptx
JIT KUMAR GUPTA
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
JIT KUMAR GUPTA
 
Factors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docxFactors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docx
JIT KUMAR GUPTA
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
JIT KUMAR GUPTA
 
Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategies
JIT KUMAR GUPTA
 
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy..._Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
JIT KUMAR GUPTA
 
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
JIT KUMAR GUPTA
 
Rationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docxRationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docx
JIT KUMAR GUPTA
 
Suggestion and Options for integrating villages. within the framework of the...
Suggestion and Options for  integrating villages. within the framework of the...Suggestion and Options for  integrating villages. within the framework of the...
Suggestion and Options for integrating villages. within the framework of the...
JIT KUMAR GUPTA
 
Making cities Climate Responsive and Sustainable
Making cities Climate Responsive and SustainableMaking cities Climate Responsive and Sustainable
Making cities Climate Responsive and Sustainable
JIT KUMAR GUPTA
 
Managing Planning and Development of Citie- 26-2-24.docx
Managing Planning and  Development of  Citie-  26-2-24.docxManaging Planning and  Development of  Citie-  26-2-24.docx
Managing Planning and Development of Citie- 26-2-24.docx
JIT KUMAR GUPTA
 
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
JIT KUMAR GUPTA
 

More from JIT KUMAR GUPTA (20)

Role and Relevance of Architects and architecture in Sustainability
Role and Relevance of Architects and architecture in SustainabilityRole and Relevance of Architects and architecture in Sustainability
Role and Relevance of Architects and architecture in Sustainability
 
Bridging gap between resources and responsibilities at Local level.
Bridging gap between resources and responsibilities at Local level.Bridging gap between resources and responsibilities at Local level.
Bridging gap between resources and responsibilities at Local level.
 
Construction Industry Through Artificial Intelligence -.docx
Construction Industry Through Artificial Intelligence -.docxConstruction Industry Through Artificial Intelligence -.docx
Construction Industry Through Artificial Intelligence -.docx
 
Making Urban India a Role Model of Planned Urban Growth a.docx
Making Urban India a Role Model of Planned Urban Growth a.docxMaking Urban India a Role Model of Planned Urban Growth a.docx
Making Urban India a Role Model of Planned Urban Growth a.docx
 
Redefining Globalization, urbanisation and Localisation
Redefining Globalization, urbanisation and LocalisationRedefining Globalization, urbanisation and Localisation
Redefining Globalization, urbanisation and Localisation
 
Knowing, Understanding and Planning Cities- Role and Relevance Physical Plan...
Knowing, Understanding and Planning Cities- Role and Relevance  Physical Plan...Knowing, Understanding and Planning Cities- Role and Relevance  Physical Plan...
Knowing, Understanding and Planning Cities- Role and Relevance Physical Plan...
 
Land as a Resource for urban finanace- 24-1-23.ppt
Land as a Resource  for urban finanace- 24-1-23.pptLand as a Resource  for urban finanace- 24-1-23.ppt
Land as a Resource for urban finanace- 24-1-23.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Making Buildings cost-effective , Energy Efficient ptx
Making Buildings cost-effective , Energy Efficient  ptxMaking Buildings cost-effective , Energy Efficient  ptx
Making Buildings cost-effective , Energy Efficient ptx
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
 
Factors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docxFactors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docx
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
 
Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategies
 
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy..._Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
 
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
 
Rationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docxRationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docx
 
Suggestion and Options for integrating villages. within the framework of the...
Suggestion and Options for  integrating villages. within the framework of the...Suggestion and Options for  integrating villages. within the framework of the...
Suggestion and Options for integrating villages. within the framework of the...
 
Making cities Climate Responsive and Sustainable
Making cities Climate Responsive and SustainableMaking cities Climate Responsive and Sustainable
Making cities Climate Responsive and Sustainable
 
Managing Planning and Development of Citie- 26-2-24.docx
Managing Planning and  Development of  Citie-  26-2-24.docxManaging Planning and  Development of  Citie-  26-2-24.docx
Managing Planning and Development of Citie- 26-2-24.docx
 
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
 

Recently uploaded

Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
gb193092
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
deeptiverma2406
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 

Recently uploaded (20)

Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 

Tendering presenation

  • 1.  TENDERING Ar Jit Kumar Gupta Chandigarh
  • 2.  Tender- an offer in writing made by one party- contractor  - to another- owner to  -- supply  - construct  --remove/ repair  - provide a service  --in construction/ execution of a building  - within a stipulated time  - under conditions specified in the tender  -- Tender must be in writing  - must be in a proper form  -- signed by persons duly authorized  -state has liberty to invite tenders from one class of contractors to exclusion of others
  • 3.  Objectives--Give wide publicity  Obtain competitive bidding  Get quality work at competitive rates  Provide equal opportunity to large number of contractors  Have wider choice for owner  Obtaining value for money by owner  Essentials of Tender Notice– NIT--must contain:  --Brief description of work  --Estimated cost, EMD- Earnest money deposit;  --Cost of Tender,  Time of completion, eligibility of contractor;  -- Last date of obtaining tender  -- Place and period of issue of tender  -- date , time and place of tender  -Date, time and place of opening tenders  -Supply of materials by tenderer  - Cancellation of tender/contract in case of non-commencement of work in time
  • 4.  --Availability of clear site  --Availability of adequate funds  -Material procurement  - Finalized and working drawings  --list of pre-qualified contractors  - Statutory clearances from competent authorities  --basic infrastructure at site  -- access to site during inspection  -- special bye-laws to be followed , if any at site
  • 5.  i. Notice inviting tender in detail  ii. General conditions of contract-  - security deposit;  --Bonus/ fine clauses  - stages of payment  -- final bill  -- completion certificate  -- material supply- owner/contractor  -- advances  - escalation, variations  -- defective work  - defect liability period  -- arbitration  - other conditions  - EMD  -Specific conditions in specialized work
  • 6.  Iii. Schedule of Quantities  Iv. Tender Drawings  V. Specifications in detail  Vi Form of Agreement  Vii Formats and statements- safety code; labour regulations; bank guarantee etc  Ix Detailed architectural, structural and service drawings  X Network Chart  Two Cover Bidding system– done post qualification- Technical bid/ price or financial bid  Pre- bid conference– for specialized works- to explain details to perspective bidders – before the date specified for bidding- become part of contract
  • 7.  Receipt and opening of tender;  - at a specified place and time- as notified in tender  --Committee constituted to check all details including-  --Number of tenderers.  -- EMD;  -Bank Guarantee;  --signatures  --documents etc  -- recording them in a register  - signed by all bidders/representatives and members of the committee
  • 8.  Evaluation of tender;  Checking discrepancies between /in rates and quantities  -- arithmetic calculations  - figures in words and numbers  -- market value analysis  -- overhead amounts  - justified amount of each bidder  -
  • 9.  Issues during bidding process;  - Lack of essential documents  --late receipt of tender  --bidder signatures  --discrepancies in rates/amount  -Non- submission of EMD  --Withdrawal of bid before opening  -- Withdrawal of bid before validity period  -- depositing security amount  --signing formal agreement  -- No relaxation of eligibility criteria  --no change in scope of work after receipts of bids  --formation of cartel  --poor response necessitating re-tendering
  • 10.  --Contract awarded ;  -lowest financial bidder  -can be rejected if  --rates appear to be high  -if based on false information  -- change in scope of work  -cartel formation  -- In private sector- negotiation is possible to further rationalise the rates
  • 11.  Work order given to-  -Given to selected contractor/bidder  -within validity period  -before issue- clear site  -- statutory approvals in place  --funds available  --work order issued in writing and contains;  --tendered amount  --all relevant correspondence  - negotiation details if any  - letter with particular conditions defined in tender document
  • 12.  Commencement of Work –  --handing over of site to contractor  - making available mobilisation advance-- in large projects  - materials issued- if specified in the contract  --resource mobilisation  --bank guarantee  -- drawings  -  -
  • 13.  - Releasing clear site  --Timely release of funds  -making available drawings  -Non-interference  --providing licenses where required  -- making available materials  --settle about escalations  --taking over of site after completion  -- settlement of final bill  --release of security deposit  --timely payment to contractor—payment of final bill as per contract conditions  --  -
  • 14.  - after receiving work order  -- take possession of the site  --setting up a site office  -- mobilise money and machinery and labour  -- Engage quality and experienced labour  -- site management  -- providing quality work  -- avoid all wastage  -- follow specification provided  - completion of project within the given time schedule  - follow the drawings issued by the architect  --de-mobilitsaion of work after completion  --handing over the project to owner  --rectification of defects with liability period  -- identification of sub-contractors and vendors  --no misuse/abuse of site during progress of work  -- Maintaining all site records  -- Take all safety measures  --  --  -