SlideShare a Scribd company logo
USE OF NEW MATERIALS AND
TECHNOLOGIES BY CPWD AT MUMBAI
DR K M SONI
CHIEF ENGINEER, CPWD, MUMBAI
Post Tensioned Slabs
• POST TENSIONED SLABS
– CBI OFFICE BUILDING
– NISM BUILDINGS (PARTLY)
– INCOME TAX BUILDING UNDER CONSTRUCTION
– IDBI BUILDING UNDER CONSTRUCTION
Advantages of PT Slab
• Material Savings
• Reduction in concrete is due to thinner
concrete members.
• Reduction in rebar in floor elements.
• Reduction in dead load resulting into saving in
concrete and reinforcement of structural
members including foundation.
• Saving in building cladding, vertical
mechanical/service elements, rebar and
concrete in shear walls and other materials
due to lesser sizes.
Steps in construction
• Design
– The existing design has been based on Presscrete Post-Tensioning System (PPS). Concrete in
one member panel shall be placed in one operation continuously without interruption.
• Concreting
– Care is taken that the pre-stressing tendons do not get displaced or damaged prior to casting
and during casting. It is ensured that discharge of concrete is not directed onto the pre-
stressing tendons. Vibrating is avoided from coming into contact with the pre-stressing
tendons whenever possible. Proper compaction of the concrete in anchorage areas is ensured
due to high local stresses in these areas and care taken that all the grout hoses remain
exposed and protruding from the concrete surface.
• Stressing
– After concreting, the carpenter removes the vertical sides end form work. All the stressing
recesses are cleared and pre-stressing barrels and wedges fixed to all pre-stressing castings.
When concrete has reached the transfer strength as per the shop drawings (from the results
of cube tests), stressing of cables is carried out. All cables are tensioned to the required
jacking force and monitored through the pressure gauges.
• Grouting
– Excess cable length is cut after the stressing. All pre-stressing tendons are ensured to be
flushed with clean water. Grout is mixed according to the design mix for at least two minutes
until a colloidal consistency is produced. The water is put into the container first and the
cement is then slowly added. When the cement and water are thoroughly mixed, the non-
shrink additive added to the mix. The grout then is injected into the pre-stressing tendons.
Grouting is carried out by injection at one end of the duct until clear grout flows out from the
other end. The grout hose at the both end is then sealed. Grouting works commence when all
scaffolds at a particular storey where grouting works are to be carried out, are removed.
Limitations
• Since the cables or tendons in the slab have
been stretched to high tensile strengths, it is
extremely important that the slab is not
drilled, cut, chiselled or disturb in a way so as
to expose the tendons
AAC BLOCKS
• LOW DENSITY
• GREEN MATERIAL
Service trenches
• Not a very new concept
• Being adopted in NISM
GFRC PANELS IN FACADE
• Can be manufactured in many shapes
• Can be painted
STAMPED FINISH CONCRETE
• Can be achieved in desired colours
• The process includes
– preparation of sub-grade,
– placing of forms,
– providing reinforcement for stability,
– placing the concrete,
– screeding and finishing the concrete,
– applying colour and
– stamping the concrete using desired moulds.
Stamped finish concrete
Innovative Floorings
• Wood plastic composite flooring,
• Maple hardwood sports flooring for special
applications,
• Geofoam block flooring
• Crazy patterned flooring of leather finish,
flamed and polished granite
• Italian marble flooring
GEOFOAMFLOORING IN STEPS
Seating arrangement of class rooms
Innovative False Ceiling
• Acoustic false ceiling
• Cloud acoustic false ceiling
ACCOUSTIC FALSE CEILING
• Anutone False ceiling
Double Stack Car Parking
Glass
• Structural Glazing
• Partitions
• Fire resistant Lobbies
• Doors
• Murals
• Solar PV Panels
Dry Stone Cladding
STP
SOLAR ROOF TOP PANELS
AHU ON TOILET SLAB
SYNTHETIC GRASS
FOLDABLE PARTITION
LOUVERS
Energy efficiency
• In new buildings only LED fitting or energy
efficient T5 fittings are provided.
• Energy efficient Chillers are provided
• Solar roof top PV Panels
• Recycling waste water
• Rain water harvesting
Pumping system
• CPWD has adopted hydro-pneumatic
pumping system for water supply in most of
large projects.
Green buildings
• CPWD is constructing all green buildings and
getting them rated in Mumbai
• CBI – 4 star GRIHA
• IDBI Belapur – 3 star GRIHA
• NISM – 4 star GRIHA
• NTH – 3 star GRIHA
• Income Tax Building – 4 star GRIHA
CBI OFFICE
BUILDING
NATIONAL INSTITUTE OF SECURITIES MARKETS
Student and MDP Hostel blocks
Residential Block
NISM: Images
Orientation Block
Academic Block Amphitheater
Hostel & MDP Block
Landscape development
Orientation Block
New Building Materials
New Building Materials

More Related Content

What's hot

Low cost building materials and construction techniques
Low cost building materials and construction techniquesLow cost building materials and construction techniques
Low cost building materials and construction techniques
Yash Kotgirwar
 
BUILDING MATERIALS AS A PLASTIC
BUILDING MATERIALS AS A PLASTICBUILDING MATERIALS AS A PLASTIC
BUILDING MATERIALS AS A PLASTIC
Abhishek Mewada
 
13 construction material from the future
13 construction material from the future13 construction material from the future
13 construction material from the future
Masoud Fayeq
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
JenilPatel22
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
Ar Jitendra
 
Industrial building
Industrial buildingIndustrial building
Industrial building
tausif_k
 
Introduction of Concrete
Introduction of ConcreteIntroduction of Concrete
Introduction of Concrete
Naveen Kumar
 
Sustainable building materials
Sustainable building materialsSustainable building materials
Sustainable building materials
TEJAL PATEL
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
Madan Mohan Jana
 
Alternative for wall construction
Alternative for wall   constructionAlternative for wall   construction
Alternative for wall construction
Basirat Amir
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ravi Savani
 
Transparent Wood
Transparent WoodTransparent Wood
Transparent Wood
Shinjini Bhattacharjee
 
Timber- Building material
Timber- Building materialTimber- Building material
Timber- Building material
Grace Henry
 
Green concrete
Green concreteGreen concrete
Green concrete
ghildiyal8811
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
SAI KIRAN
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
Divya Vishnoi
 
Ferrocement ppt
Ferrocement pptFerrocement ppt
Ferrocement ppt
jvaghani
 
BAMBOO AS A BUILDING MATERIAL
BAMBOO AS A BUILDING MATERIALBAMBOO AS A BUILDING MATERIAL
BAMBOO AS A BUILDING MATERIAL
seminarppts
 
Plastics as a building material
Plastics as a building materialPlastics as a building material
Plastics as a building material
anjali s
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
Shailja km
 

What's hot (20)

Low cost building materials and construction techniques
Low cost building materials and construction techniquesLow cost building materials and construction techniques
Low cost building materials and construction techniques
 
BUILDING MATERIALS AS A PLASTIC
BUILDING MATERIALS AS A PLASTICBUILDING MATERIALS AS A PLASTIC
BUILDING MATERIALS AS A PLASTIC
 
13 construction material from the future
13 construction material from the future13 construction material from the future
13 construction material from the future
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
Industrial building
Industrial buildingIndustrial building
Industrial building
 
Introduction of Concrete
Introduction of ConcreteIntroduction of Concrete
Introduction of Concrete
 
Sustainable building materials
Sustainable building materialsSustainable building materials
Sustainable building materials
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Alternative for wall construction
Alternative for wall   constructionAlternative for wall   construction
Alternative for wall construction
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Transparent Wood
Transparent WoodTransparent Wood
Transparent Wood
 
Timber- Building material
Timber- Building materialTimber- Building material
Timber- Building material
 
Green concrete
Green concreteGreen concrete
Green concrete
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Ferrocement ppt
Ferrocement pptFerrocement ppt
Ferrocement ppt
 
BAMBOO AS A BUILDING MATERIAL
BAMBOO AS A BUILDING MATERIALBAMBOO AS A BUILDING MATERIAL
BAMBOO AS A BUILDING MATERIAL
 
Plastics as a building material
Plastics as a building materialPlastics as a building material
Plastics as a building material
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 

Viewers also liked

High Tech Building Materials: ETFE
High Tech Building Materials: ETFEHigh Tech Building Materials: ETFE
High Tech Building Materials: ETFE
Sneha Nagarajan
 
Advanced material of construction..ppt24545452
Advanced material of construction..ppt24545452Advanced material of construction..ppt24545452
Advanced material of construction..ppt24545452
SHUBHAM DABHADE
 
2014 Smart Structures/NDE
2014 Smart Structures/NDE2014 Smart Structures/NDE
2014 Smart Structures/NDEEngku Fahmi
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
Dr K M SONI
 
SMART STRUCTURES
SMART STRUCTURESSMART STRUCTURES
SMART STRUCTURES
Selva Prakash
 
Fear
FearFear
Issue for thesis
Issue for thesisIssue for thesis
Issue for thesis
Tanzil Faraz
 
Use of Glass
Use of GlassUse of Glass
Use of Glass
Dr K M SONI
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
Avinash Kumar Gupta
 
Waste to Resource
Waste to ResourceWaste to Resource
Waste to Resource
Dr K M SONI
 
Soil investigation – some views
Soil investigation – some viewsSoil investigation – some views
Soil investigation – some views
Dr K M SONI
 
Construction safety ii
Construction safety iiConstruction safety ii
Construction safety ii
Avinash Kumar Gupta
 
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...Development of-new-control-techniques-for-vibration-isolation-of-structures-u...
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...Cemal Ardil
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
Avinash Kumar Gupta
 
Integrity pact
Integrity pactIntegrity pact
Integrity pact
Avinash Kumar Gupta
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
Avinash Kumar Gupta
 
Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste
Dr K M SONI
 
Safety management in construction
Safety management in construction   Safety management in construction
Safety management in construction
Dr K M SONI
 
Robotics in construction
Robotics in constructionRobotics in construction
Robotics in construction
Saul Lustgarten
 
Handbook of repair
Handbook of repairHandbook of repair
Handbook of repair
chanduforever
 

Viewers also liked (20)

High Tech Building Materials: ETFE
High Tech Building Materials: ETFEHigh Tech Building Materials: ETFE
High Tech Building Materials: ETFE
 
Advanced material of construction..ppt24545452
Advanced material of construction..ppt24545452Advanced material of construction..ppt24545452
Advanced material of construction..ppt24545452
 
2014 Smart Structures/NDE
2014 Smart Structures/NDE2014 Smart Structures/NDE
2014 Smart Structures/NDE
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
 
SMART STRUCTURES
SMART STRUCTURESSMART STRUCTURES
SMART STRUCTURES
 
Fear
FearFear
Fear
 
Issue for thesis
Issue for thesisIssue for thesis
Issue for thesis
 
Use of Glass
Use of GlassUse of Glass
Use of Glass
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
 
Waste to Resource
Waste to ResourceWaste to Resource
Waste to Resource
 
Soil investigation – some views
Soil investigation – some viewsSoil investigation – some views
Soil investigation – some views
 
Construction safety ii
Construction safety iiConstruction safety ii
Construction safety ii
 
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...Development of-new-control-techniques-for-vibration-isolation-of-structures-u...
Development of-new-control-techniques-for-vibration-isolation-of-structures-u...
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Integrity pact
Integrity pactIntegrity pact
Integrity pact
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste Avoidance of waste and recycling of construction and demolition waste
Avoidance of waste and recycling of construction and demolition waste
 
Safety management in construction
Safety management in construction   Safety management in construction
Safety management in construction
 
Robotics in construction
Robotics in constructionRobotics in construction
Robotics in construction
 
Handbook of repair
Handbook of repairHandbook of repair
Handbook of repair
 

Similar to New Building Materials

training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ErLavKushPrasad
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
Dr K M SONI
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
AnchitSharma17
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
Aglaia Connect
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Md Raijul Islam
 
national building code
national building codenational building code
national building code
Ruhiya Garg
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SakshiMahadik3
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
Deepak Pradhan
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
Nithyashree594058
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
NisshantSinghSaud
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
Rajesh Kolli
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
SayedaAmrin
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
Shubham Pradhan
 
Precast post tensioned tank brochure
Precast post tensioned tank brochurePrecast post tensioned tank brochure
Precast post tensioned tank brochure
Adrian Frantescu
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
AshrafulHaqueTushar1
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
Ravi Shankar
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
Sreekutty S
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
ANURAG KASHYAP
 

Similar to New Building Materials (20)

training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
national building code
national building codenational building code
national building code
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
 
Precast post tensioned tank brochure
Precast post tensioned tank brochurePrecast post tensioned tank brochure
Precast post tensioned tank brochure
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
 

More from Dr K M SONI

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
Dr K M SONI
 
Project Management
Project ManagementProject Management
Project Management
Dr K M SONI
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
Dr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management
Dr K M SONI
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
Dr K M SONI
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
Dr K M SONI
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
Dr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
Dr K M SONI
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
Dr K M SONI
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
Dr K M SONI
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
Dr K M SONI
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
Dr K M SONI
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
Dr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management
Dr K M SONI
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
Dr K M SONI
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
Dr K M SONI
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
Dr K M SONI
 

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

New Building Materials

  • 1. USE OF NEW MATERIALS AND TECHNOLOGIES BY CPWD AT MUMBAI DR K M SONI CHIEF ENGINEER, CPWD, MUMBAI
  • 2. Post Tensioned Slabs • POST TENSIONED SLABS – CBI OFFICE BUILDING – NISM BUILDINGS (PARTLY) – INCOME TAX BUILDING UNDER CONSTRUCTION – IDBI BUILDING UNDER CONSTRUCTION
  • 3.
  • 4.
  • 5.
  • 6. Advantages of PT Slab • Material Savings • Reduction in concrete is due to thinner concrete members. • Reduction in rebar in floor elements. • Reduction in dead load resulting into saving in concrete and reinforcement of structural members including foundation. • Saving in building cladding, vertical mechanical/service elements, rebar and concrete in shear walls and other materials due to lesser sizes.
  • 7. Steps in construction • Design – The existing design has been based on Presscrete Post-Tensioning System (PPS). Concrete in one member panel shall be placed in one operation continuously without interruption. • Concreting – Care is taken that the pre-stressing tendons do not get displaced or damaged prior to casting and during casting. It is ensured that discharge of concrete is not directed onto the pre- stressing tendons. Vibrating is avoided from coming into contact with the pre-stressing tendons whenever possible. Proper compaction of the concrete in anchorage areas is ensured due to high local stresses in these areas and care taken that all the grout hoses remain exposed and protruding from the concrete surface. • Stressing – After concreting, the carpenter removes the vertical sides end form work. All the stressing recesses are cleared and pre-stressing barrels and wedges fixed to all pre-stressing castings. When concrete has reached the transfer strength as per the shop drawings (from the results of cube tests), stressing of cables is carried out. All cables are tensioned to the required jacking force and monitored through the pressure gauges. • Grouting – Excess cable length is cut after the stressing. All pre-stressing tendons are ensured to be flushed with clean water. Grout is mixed according to the design mix for at least two minutes until a colloidal consistency is produced. The water is put into the container first and the cement is then slowly added. When the cement and water are thoroughly mixed, the non- shrink additive added to the mix. The grout then is injected into the pre-stressing tendons. Grouting is carried out by injection at one end of the duct until clear grout flows out from the other end. The grout hose at the both end is then sealed. Grouting works commence when all scaffolds at a particular storey where grouting works are to be carried out, are removed.
  • 8. Limitations • Since the cables or tendons in the slab have been stretched to high tensile strengths, it is extremely important that the slab is not drilled, cut, chiselled or disturb in a way so as to expose the tendons
  • 9.
  • 10.
  • 11.
  • 12.
  • 13. AAC BLOCKS • LOW DENSITY • GREEN MATERIAL
  • 14. Service trenches • Not a very new concept • Being adopted in NISM
  • 15. GFRC PANELS IN FACADE • Can be manufactured in many shapes • Can be painted
  • 16.
  • 17. STAMPED FINISH CONCRETE • Can be achieved in desired colours • The process includes – preparation of sub-grade, – placing of forms, – providing reinforcement for stability, – placing the concrete, – screeding and finishing the concrete, – applying colour and – stamping the concrete using desired moulds.
  • 19.
  • 20. Innovative Floorings • Wood plastic composite flooring, • Maple hardwood sports flooring for special applications, • Geofoam block flooring • Crazy patterned flooring of leather finish, flamed and polished granite • Italian marble flooring
  • 22.
  • 23. Seating arrangement of class rooms
  • 24.
  • 25.
  • 26. Innovative False Ceiling • Acoustic false ceiling • Cloud acoustic false ceiling
  • 27. ACCOUSTIC FALSE CEILING • Anutone False ceiling
  • 28.
  • 29.
  • 30.
  • 31. Double Stack Car Parking
  • 32. Glass • Structural Glazing • Partitions • Fire resistant Lobbies • Doors • Murals • Solar PV Panels
  • 33.
  • 34.
  • 35.
  • 36.
  • 38. STP
  • 39. SOLAR ROOF TOP PANELS
  • 44. Energy efficiency • In new buildings only LED fitting or energy efficient T5 fittings are provided. • Energy efficient Chillers are provided • Solar roof top PV Panels • Recycling waste water • Rain water harvesting
  • 45. Pumping system • CPWD has adopted hydro-pneumatic pumping system for water supply in most of large projects.
  • 46. Green buildings • CPWD is constructing all green buildings and getting them rated in Mumbai • CBI – 4 star GRIHA • IDBI Belapur – 3 star GRIHA • NISM – 4 star GRIHA • NTH – 3 star GRIHA • Income Tax Building – 4 star GRIHA
  • 48. NATIONAL INSTITUTE OF SECURITIES MARKETS
  • 49. Student and MDP Hostel blocks Residential Block NISM: Images Orientation Block Academic Block Amphitheater Hostel & MDP Block Landscape development Orientation Block