MODERN CONSTRUCTION
TECHNOLOGIES IN ENGINEERING
PERSPECTIVE
Dr K M Soni
ADG(TD), CPWD, N. Delhi
Advantages of Modern Technologies
• Faster Construction
• Quality
• Non availability of Economic Conventional
Technologies and Workers
• Non availability of Skilled Workers or highly
costly workers
• Environmental consideration
• Use of Waste Materials
• Aesthetic considerations and Innovation
Applications of Modern Technologies
• Buildings
• Roads and Highways
• Tunnelling
• Retaining Walls
• Irrigation Structures
• Nuclear Installations
• Development Works and Services
Buildings
• Conventional Buildings
• Pre-fab / Pre cast Buildings
• Pre-engineered Buildings
Conventional Buildings
• Load bearing structures,
• RCC framed structures,
• Steel structures and
• Temporary/semi permanent structures
Load Bearing Structures
Brick/stone masonry structures
• Modern materials and technologies may include;
• CC blocks – Solid/hollow
– With blocks made of stone dust
– With C & D waste recycled concrete blocks, AAC Blocks or
fly ash bricks
• Cavity walls
• Mortar/Adhesives
• Robotic Laying of block/brickwork, Plaster and
Painting
RCC Framed Structures
• Formwork
• Slab/beams/Columns
• Plaster
• Flooring
• Ceiling
• Painting
• Services
Components
• Floorings
• Roofing
• Cladding
• Panelings
• Casting of concrete
• PT Slabs
• Confined Masonry Construction
Services
• Anchoring
• Trenchless Technologies
• Recycling Asphalt
• Reinforced Soil
• Robotics
• 3 D Printing
• Energy Efficient Technologies
• Tree Plantation
Formwork
• Conventional shuttering
Jump formwork,
aluminium formwork,
aluminium-plastic composite formwork,
Tunnel formwork,
Plastic formwork or of similar other materials
For Monolithic construction
Monolithic Construction
• Monolithic construction means in situ casting
of slab, beams and columns / walls
simultaneously.
• Such construction is carried out by
specialized shuttering/formwork normally for
RCC walls.
• Therefore, new technology is in the use of
shuttering only and other construction may
be conventional.
Advantages
• As the construction is with RCC walls, wall
thickness is less than masonry members or
columns having advantage of higher carpet area.
• Also, it has few construction joints and even
may not require cement plaster on the walls and
• Provide better seismic resistance than
conventional RCC construction.
• Construction is faster, and
• Highly suitable for repetitive multi-storeyed
construction particularly in housing.
Limitations
• Limited modular sizes in some cases,
• High cost in case of non-repetitive units,
• Changes not feasible after casting or during life
time of the building,
• Feasibility of limited architectural features,
• Less energy efficient due to façade having low
insulation characteristics, and
• Difficulty and higher cost in repair and
rehabilitation of services and structure during its
life time.
Formwork
• Jump formwork
• Aluminium formwork,
• Tunnel formwork
Jump Shuttering
• Central core (Generally core housing lifts, staircase etc) is
constructed first using a climbing or jump formwork system
• A frame is constructed over the central core and steel formwork
hung from it. Once the climbing formwork is in position, the
formwork panels are closed and concrete wall is casted. After the
walls are casted, the formwork is released.
• Jacks then lift the whole frame up to next level. All the formwork
panels are then attached to the frame and the process continued.
The formwork get supported on the concrete casted earlier and
thus does not rely on supports or access from other parts of the
building or permanent works.
• Suitable for multi-storeyed vertical concrete such as shear walls,
core walls, lift shafts and stair shafts in buildings thus advantage
in high rise construction as central core can be effectively used for
other activities.
Aluminium Formwork
• Allows casting of a floor in single operation.
• Advantage of such formwork is that architectural
features like projections, cornices, planters, curved
beams etc can also be casted in one operation though
it cannot be combined with other formwork materials
such as plywood and steel.
• The formwork is largely hand held and does not need
the services of a crane for movement either vertically
or horizontally.
• These can be effectively used for repetitive works like
multi-storeyed construction or row houses
Aluminium Formwork
Tunnel Formwork
• It comes in half units in the form of an
inverted “L”. When two halves are bolted
together at the top, they form the tunnel
(Fig. 3) hence the name.
Tunnel Formwork
• The inbuilt wheels and the jacks help the formwork move
in and out of the position and adjusted to the final height
to cast walls and slabs in one operation in a daily cycle.
• In casting process, prefabricated wall reinforcement is
placed by crane along the entire wing prior to casting the
kickers used to position wall formwork then two and a
half tunnel placed in position by crane, bolted together
and ties added.
• The formwork system provides for a pour to be wrapped
in tarpaulins and for the use of butane heaters to maintain
a sufficiently high temperature for the concrete to reach
its desired strength overnight for removal of formwork
next day.
• The process is repeated for the next two bays.
Tunnel Formwork
• Apart from limitations described earlier, in
tunnel formwork, walls are to be planned in
same alignment of the formwork, external
projections avoided and shaft openings to be
provided from inside.
Tunnel Formwork
Prefab/Pre-cast Buildings
• Pre-cast concrete buildings, or steel buildings.
• Precast concrete buildings use precast RCC structural members
such as beams, slabs, columns, walls, staircases, footings etc.
• Normally such members are fabricated at the casting yard or in
the factory with in-situ jointing and foundation casting.
• Structurally, connectivity of the members is to be ensured and
designed suiting to loading requirements including seismic and
lateral loads, if any.
• Advantage of such construction is pollution and dust control,
quality assurance of precast products, faster construction and less
storage space required at the site.
• Limitations are of module sizes, limited architectural features,
constraints of service lines and assurance of connectivity
particularly during lateral loads.
CPWD Constructed Building at
Hyderabad
• Costly compared to conventional
• Better quality
• Uniform sizes
• Faster
• Limited storage space required at site
Pre-Cast Construction
It uses standard steel sections and is widely adopted in
crowded areas having space constraints and noise
pollution restrictions particularly for industrial set ups,
large span structures, and even high rise construction of
any type of usage where RCC members requires large
sections though welding may be required at site in many
cases.
In such construction any module size is feasible but special
precautions are to be taken for fire safety and as such fire
retardant coatings/paints are to be applied on structural
members or to be made composite. False ceiling may be
required due to aesthetic considerations. After 9/11
incidence in US, impact due to collision of air strike has
also become of concern.
Pre Engineered Buildings
• They are custom designed having varied sections
as per the loading requirements, fabricated in
factory, without welding (only bolting).
• Saves rection time, erection cost, and
maintenance cost.
• In case column of free structures like exhibition
halls, large convention centres, auditoriums etc,
PEBs have the advantage over other type of
conventional buildings.
Confined Masonry Construction
• Concept of confined masonry construction is similar
to Assam walling or ekra walling construction used
long time back in semi permanent buildings in north
eastern India, difference being that in place of
wooden vertical posts and horizontal members in
ekra walling construction, members in confined
masonry construction are casted in reinforced
concrete while infill walls are replaced with masonry
work in place of bamboo mat. Like ekra walling
construction was having higher seismic resistance,
confined construction also exhibits similar properties.
Stamped Finish Concrete Flooring
Technology
Modern floorings, i.e. stamped or textured or
imprint concrete, a decorative finish in desired
colours and surface resembling to bricks, stones,
tiles or even wood.
The process includes preparation of sub-grade,
placing of forms, providing reinforcement for
stability, placing the concrete, screeding and
finishing the concrete, applying colour and in
the last stamping the concrete using desired
moulds.
Stamped Finish Concrete
Post Tensioned Slab Technology
• PT construction technology has advantage of
elimination or reduction in sizes of beams
hence has the advantage of larger headroom
or more floors in same height hence highly
suitable for high rise and air-conditioned
buildings. The tendons are pre-stressed
hence immediately tested for maximum
loading conditions and leads to material
saving, fast construction and increased
performance.
PT Slabs
HPC Technology
• HPC is a high strength concrete made by
lowering the water-cement (w/c) ratio than
0.35, utilizing fine pozzolanic materials. Low w/c
ratio and the use of silica fume make concrete
mixes significantly less workable. To compensate
the reduced workability, super plasticizers are
commonly added to high-strength mixtures.
• High strength concrete like self compaction
concrete is normally used in post tensioned
construction, and even in monolithic
construction.
Cool Roof Technology
• Cool roof is the one that reflects the sun’s heat
back into the atmosphere. The roof thus,
becomes cooler.
• Such roofs offer advantages of reducing heat-
gain, and improving energy efficiency of
buildings, improving thermal comfort in
buildings or reducing air conditioning load.
Though there is a criticism that cool roofs
enhance outside air
temperature or reflect heat
on some other surface.
GFRC Technology
• Architectural features are essential components of any
building. Some of the constructions like monolithic have
no or limited architectural features. Such features can be
added in the buildings by applying GFRC construction
technology being very light in weight, weather and
corrosion resistant and crack resistant.
• GFRC is also used in various other applications like water
storage tanks, septic tanks, domes for the buildings,
roofing sheets, door frames and shutters, canopies,
chimneys, pipes, gratings, column claddings, cooling
towers, sculptures and statues, dustbins, furniture,
external claddings and for rehabilitation and retrofitting of
structures.
Reinforced Soil Technology
• Reinforced soil concept is applied by
providing reinforcement in frictional soils as
the principle is based on friction between soil
and the reinforcement.
• Reinforcement is generally in the form of
metallic strips or sheet generally of
geostextiles or geogrids.
Anchoring technology
• Mechanical Anchoring
• Chemical Anchoring
Robotics
• Robots can be used in buildings to roads,
railways to underground structures, nuclear
structures to disaster rescue operations,
demolition of structures to inspections of
deep sewer lines.
• Maintenance of roads, railway tracks and
electric power lines.
3D Printing Technology
• It refers to various techniques that use 3D
printing as a core method to fabricate buildings or
the components though at present in nascent stage.
• Such technology is going to be integration of
owner’s design acceptability, architect’s vision, on
site but mainly off site fabrication, robotics and use
of IT.
Trenchless Technology
• Trenchless technology largely avoids cutting of
roads and paths to pass through utility services
in soils. Such technology avoids disruption of
traffic and also helps in pollution control. The
technology includes “no dig” methods like micro
tunnelling, horizontal directional drilling, pipe
ramming, auger boring, moling etc.
Energy Efficient Technologies
• Building materials produced from such technologies include
PPC, flyash based bricks, blocks and concrete, light weight
and waste containing products, wood substitutes, C&D
waste products, low VOC paints, and low water consuming
faucets.
• Similarly in E&M services, LED technology, solar power
generation, regenerative lifts, IBMS, occupancy and other
sensors, smart equipment and gadgets, energy efficient
chillers and geo thermal heat exchange system for air-
conditioning.
Re-plantation Technologies
• The tree transplanter works on hydraulically
operated spades. Conical shaped blades penetrate
into the soil. Once all the blades penetrate inside
soil, then the earth ball is lifted above ground level,
and a pit is dug lifting the tree along with roots and
soil. Trees of even one meter basal girth can be re-
transplanted.
Conclusions
• New Technologies will continue to come due to
innovations.
• Due to ICT, new and modern technologies will
be less dependent on workforce .
• “Smart” concept will be part of new
technologies.
• Though little costlier, new technologies will
have to qualify for quality, better finish, green
concept, aesthetics, less maintenance and faster
construction.
• Each technology has some limitations and as
such should be chosen as per the requirements.
Acknowledgements
• Photographs have been taken from internet
sources and mostly not taken by the author.
The original sources are gratefully
acknowledged.
Thank you

More Related Content

What's hot

Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
Divya Vishnoi
 
Waste material concrete ppt
Waste material  concrete pptWaste material  concrete ppt
Waste material concrete ppt
Uday Kakde
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT
Nischay N Gowda
 
Ferrocement ppt
Ferrocement pptFerrocement ppt
Ferrocement ppt
jvaghani
 
074 Modern Methods of Construction
074 Modern Methods of Construction074 Modern Methods of Construction
074 Modern Methods of Construction
Dr Fereidoun Dejahang
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Green building rating system
Green building rating systemGreen building rating system
Green building rating system
Hajrah Nanda Putri
 
Embodied Energy In Building Construction
Embodied Energy In Building ConstructionEmbodied Energy In Building Construction
Embodied Energy In Building Construction
Sandeep Jaiswal
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
Sofia Rajesh
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Udisha15
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materialsAkash Patel
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
Abdul Rahman
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
GAURAV. H .TANDON
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
Prince Srinivas
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
selva ganesh
 
Building Components
Building ComponentsBuilding Components
Building Components
GAURAV. H .TANDON
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
Suman Nandi
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
IEI GSC
 
Low Cost Housing Concept
Low Cost Housing ConceptLow Cost Housing Concept
Low Cost Housing Concept
Dr K M SONI
 

What's hot (20)

Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Waste material concrete ppt
Waste material  concrete pptWaste material  concrete ppt
Waste material concrete ppt
 
Cost effective construction tech PPT
Cost effective construction tech PPT Cost effective construction tech PPT
Cost effective construction tech PPT
 
Ferrocement ppt
Ferrocement pptFerrocement ppt
Ferrocement ppt
 
074 Modern Methods of Construction
074 Modern Methods of Construction074 Modern Methods of Construction
074 Modern Methods of Construction
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Green building rating system
Green building rating systemGreen building rating system
Green building rating system
 
Embodied Energy In Building Construction
Embodied Energy In Building ConstructionEmbodied Energy In Building Construction
Embodied Energy In Building Construction
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 
Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
 
Building Components
Building ComponentsBuilding Components
Building Components
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Low Cost Housing Concept
Low Cost Housing ConceptLow Cost Housing Concept
Low Cost Housing Concept
 

Similar to MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE

Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Precast Construction
Precast ConstructionPrecast Construction
Precast Construction
mukul srivastava
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SakshiMahadik3
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
NisshantSinghSaud
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
national building code
national building codenational building code
national building code
Ruhiya Garg
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
Yee Len Wan
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
SOUMYA KHANDELWAL
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
AnchitSharma17
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
Prashant Borge
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
SayedaAmrin
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
chirag aggarwal
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
Deepak Pradhan
 
BSS552 LECT 2.pptx
BSS552 LECT 2.pptxBSS552 LECT 2.pptx
BSS552 LECT 2.pptx
TheyCallMeSNQA
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
Shubham Pradhan
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
Bhishma Bhatti
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Rajesh Kolli
 
prestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptxprestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptx
PRASANNABHAVANGR1
 

Similar to MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE (20)

Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Precast Construction
Precast ConstructionPrecast Construction
Precast Construction
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
national building code
national building codenational building code
national building code
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
BSS552 LECT 2.pptx
BSS552 LECT 2.pptxBSS552 LECT 2.pptx
BSS552 LECT 2.pptx
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
 
prestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptxprestressed concrete and precast concrete technology.pptx
prestressed concrete and precast concrete technology.pptx
 

More from Dr K M SONI

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
Dr K M SONI
 
Project Management
Project ManagementProject Management
Project Management
Dr K M SONI
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
Dr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management
Dr K M SONI
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
Dr K M SONI
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
Dr K M SONI
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
Dr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
Dr K M SONI
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
Dr K M SONI
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
Dr K M SONI
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
Dr K M SONI
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
Dr K M SONI
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
Dr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management
Dr K M SONI
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
Dr K M SONI
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
Dr K M SONI
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
Dr K M SONI
 

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 

Recently uploaded

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE

  • 1. MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE Dr K M Soni ADG(TD), CPWD, N. Delhi
  • 2. Advantages of Modern Technologies • Faster Construction • Quality • Non availability of Economic Conventional Technologies and Workers • Non availability of Skilled Workers or highly costly workers • Environmental consideration • Use of Waste Materials • Aesthetic considerations and Innovation
  • 3. Applications of Modern Technologies • Buildings • Roads and Highways • Tunnelling • Retaining Walls • Irrigation Structures • Nuclear Installations • Development Works and Services
  • 4. Buildings • Conventional Buildings • Pre-fab / Pre cast Buildings • Pre-engineered Buildings
  • 5. Conventional Buildings • Load bearing structures, • RCC framed structures, • Steel structures and • Temporary/semi permanent structures
  • 6. Load Bearing Structures Brick/stone masonry structures • Modern materials and technologies may include; • CC blocks – Solid/hollow – With blocks made of stone dust – With C & D waste recycled concrete blocks, AAC Blocks or fly ash bricks • Cavity walls • Mortar/Adhesives • Robotic Laying of block/brickwork, Plaster and Painting
  • 7. RCC Framed Structures • Formwork • Slab/beams/Columns • Plaster • Flooring • Ceiling • Painting • Services
  • 8. Components • Floorings • Roofing • Cladding • Panelings • Casting of concrete • PT Slabs • Confined Masonry Construction
  • 9. Services • Anchoring • Trenchless Technologies • Recycling Asphalt • Reinforced Soil • Robotics • 3 D Printing • Energy Efficient Technologies • Tree Plantation
  • 10. Formwork • Conventional shuttering Jump formwork, aluminium formwork, aluminium-plastic composite formwork, Tunnel formwork, Plastic formwork or of similar other materials For Monolithic construction
  • 11. Monolithic Construction • Monolithic construction means in situ casting of slab, beams and columns / walls simultaneously. • Such construction is carried out by specialized shuttering/formwork normally for RCC walls. • Therefore, new technology is in the use of shuttering only and other construction may be conventional.
  • 12. Advantages • As the construction is with RCC walls, wall thickness is less than masonry members or columns having advantage of higher carpet area. • Also, it has few construction joints and even may not require cement plaster on the walls and • Provide better seismic resistance than conventional RCC construction. • Construction is faster, and • Highly suitable for repetitive multi-storeyed construction particularly in housing.
  • 13. Limitations • Limited modular sizes in some cases, • High cost in case of non-repetitive units, • Changes not feasible after casting or during life time of the building, • Feasibility of limited architectural features, • Less energy efficient due to façade having low insulation characteristics, and • Difficulty and higher cost in repair and rehabilitation of services and structure during its life time.
  • 14. Formwork • Jump formwork • Aluminium formwork, • Tunnel formwork
  • 15. Jump Shuttering • Central core (Generally core housing lifts, staircase etc) is constructed first using a climbing or jump formwork system • A frame is constructed over the central core and steel formwork hung from it. Once the climbing formwork is in position, the formwork panels are closed and concrete wall is casted. After the walls are casted, the formwork is released. • Jacks then lift the whole frame up to next level. All the formwork panels are then attached to the frame and the process continued. The formwork get supported on the concrete casted earlier and thus does not rely on supports or access from other parts of the building or permanent works. • Suitable for multi-storeyed vertical concrete such as shear walls, core walls, lift shafts and stair shafts in buildings thus advantage in high rise construction as central core can be effectively used for other activities.
  • 16.
  • 17. Aluminium Formwork • Allows casting of a floor in single operation. • Advantage of such formwork is that architectural features like projections, cornices, planters, curved beams etc can also be casted in one operation though it cannot be combined with other formwork materials such as plywood and steel. • The formwork is largely hand held and does not need the services of a crane for movement either vertically or horizontally. • These can be effectively used for repetitive works like multi-storeyed construction or row houses
  • 19.
  • 20. Tunnel Formwork • It comes in half units in the form of an inverted “L”. When two halves are bolted together at the top, they form the tunnel (Fig. 3) hence the name.
  • 21. Tunnel Formwork • The inbuilt wheels and the jacks help the formwork move in and out of the position and adjusted to the final height to cast walls and slabs in one operation in a daily cycle. • In casting process, prefabricated wall reinforcement is placed by crane along the entire wing prior to casting the kickers used to position wall formwork then two and a half tunnel placed in position by crane, bolted together and ties added. • The formwork system provides for a pour to be wrapped in tarpaulins and for the use of butane heaters to maintain a sufficiently high temperature for the concrete to reach its desired strength overnight for removal of formwork next day. • The process is repeated for the next two bays.
  • 22. Tunnel Formwork • Apart from limitations described earlier, in tunnel formwork, walls are to be planned in same alignment of the formwork, external projections avoided and shaft openings to be provided from inside.
  • 24.
  • 25.
  • 26. Prefab/Pre-cast Buildings • Pre-cast concrete buildings, or steel buildings. • Precast concrete buildings use precast RCC structural members such as beams, slabs, columns, walls, staircases, footings etc. • Normally such members are fabricated at the casting yard or in the factory with in-situ jointing and foundation casting. • Structurally, connectivity of the members is to be ensured and designed suiting to loading requirements including seismic and lateral loads, if any. • Advantage of such construction is pollution and dust control, quality assurance of precast products, faster construction and less storage space required at the site. • Limitations are of module sizes, limited architectural features, constraints of service lines and assurance of connectivity particularly during lateral loads.
  • 27.
  • 28. CPWD Constructed Building at Hyderabad • Costly compared to conventional • Better quality • Uniform sizes • Faster • Limited storage space required at site
  • 29. Pre-Cast Construction It uses standard steel sections and is widely adopted in crowded areas having space constraints and noise pollution restrictions particularly for industrial set ups, large span structures, and even high rise construction of any type of usage where RCC members requires large sections though welding may be required at site in many cases. In such construction any module size is feasible but special precautions are to be taken for fire safety and as such fire retardant coatings/paints are to be applied on structural members or to be made composite. False ceiling may be required due to aesthetic considerations. After 9/11 incidence in US, impact due to collision of air strike has also become of concern.
  • 30.
  • 31. Pre Engineered Buildings • They are custom designed having varied sections as per the loading requirements, fabricated in factory, without welding (only bolting). • Saves rection time, erection cost, and maintenance cost. • In case column of free structures like exhibition halls, large convention centres, auditoriums etc, PEBs have the advantage over other type of conventional buildings.
  • 32.
  • 33. Confined Masonry Construction • Concept of confined masonry construction is similar to Assam walling or ekra walling construction used long time back in semi permanent buildings in north eastern India, difference being that in place of wooden vertical posts and horizontal members in ekra walling construction, members in confined masonry construction are casted in reinforced concrete while infill walls are replaced with masonry work in place of bamboo mat. Like ekra walling construction was having higher seismic resistance, confined construction also exhibits similar properties.
  • 34. Stamped Finish Concrete Flooring Technology Modern floorings, i.e. stamped or textured or imprint concrete, a decorative finish in desired colours and surface resembling to bricks, stones, tiles or even wood. The process includes preparation of sub-grade, placing of forms, providing reinforcement for stability, placing the concrete, screeding and finishing the concrete, applying colour and in the last stamping the concrete using desired moulds.
  • 36. Post Tensioned Slab Technology • PT construction technology has advantage of elimination or reduction in sizes of beams hence has the advantage of larger headroom or more floors in same height hence highly suitable for high rise and air-conditioned buildings. The tendons are pre-stressed hence immediately tested for maximum loading conditions and leads to material saving, fast construction and increased performance.
  • 38. HPC Technology • HPC is a high strength concrete made by lowering the water-cement (w/c) ratio than 0.35, utilizing fine pozzolanic materials. Low w/c ratio and the use of silica fume make concrete mixes significantly less workable. To compensate the reduced workability, super plasticizers are commonly added to high-strength mixtures. • High strength concrete like self compaction concrete is normally used in post tensioned construction, and even in monolithic construction.
  • 39. Cool Roof Technology • Cool roof is the one that reflects the sun’s heat back into the atmosphere. The roof thus, becomes cooler. • Such roofs offer advantages of reducing heat- gain, and improving energy efficiency of buildings, improving thermal comfort in buildings or reducing air conditioning load. Though there is a criticism that cool roofs enhance outside air temperature or reflect heat on some other surface.
  • 40. GFRC Technology • Architectural features are essential components of any building. Some of the constructions like monolithic have no or limited architectural features. Such features can be added in the buildings by applying GFRC construction technology being very light in weight, weather and corrosion resistant and crack resistant. • GFRC is also used in various other applications like water storage tanks, septic tanks, domes for the buildings, roofing sheets, door frames and shutters, canopies, chimneys, pipes, gratings, column claddings, cooling towers, sculptures and statues, dustbins, furniture, external claddings and for rehabilitation and retrofitting of structures.
  • 41. Reinforced Soil Technology • Reinforced soil concept is applied by providing reinforcement in frictional soils as the principle is based on friction between soil and the reinforcement. • Reinforcement is generally in the form of metallic strips or sheet generally of geostextiles or geogrids.
  • 42. Anchoring technology • Mechanical Anchoring • Chemical Anchoring
  • 43. Robotics • Robots can be used in buildings to roads, railways to underground structures, nuclear structures to disaster rescue operations, demolition of structures to inspections of deep sewer lines. • Maintenance of roads, railway tracks and electric power lines.
  • 44. 3D Printing Technology • It refers to various techniques that use 3D printing as a core method to fabricate buildings or the components though at present in nascent stage. • Such technology is going to be integration of owner’s design acceptability, architect’s vision, on site but mainly off site fabrication, robotics and use of IT.
  • 45. Trenchless Technology • Trenchless technology largely avoids cutting of roads and paths to pass through utility services in soils. Such technology avoids disruption of traffic and also helps in pollution control. The technology includes “no dig” methods like micro tunnelling, horizontal directional drilling, pipe ramming, auger boring, moling etc.
  • 46. Energy Efficient Technologies • Building materials produced from such technologies include PPC, flyash based bricks, blocks and concrete, light weight and waste containing products, wood substitutes, C&D waste products, low VOC paints, and low water consuming faucets. • Similarly in E&M services, LED technology, solar power generation, regenerative lifts, IBMS, occupancy and other sensors, smart equipment and gadgets, energy efficient chillers and geo thermal heat exchange system for air- conditioning.
  • 47. Re-plantation Technologies • The tree transplanter works on hydraulically operated spades. Conical shaped blades penetrate into the soil. Once all the blades penetrate inside soil, then the earth ball is lifted above ground level, and a pit is dug lifting the tree along with roots and soil. Trees of even one meter basal girth can be re- transplanted.
  • 48. Conclusions • New Technologies will continue to come due to innovations. • Due to ICT, new and modern technologies will be less dependent on workforce . • “Smart” concept will be part of new technologies. • Though little costlier, new technologies will have to qualify for quality, better finish, green concept, aesthetics, less maintenance and faster construction. • Each technology has some limitations and as such should be chosen as per the requirements.
  • 49. Acknowledgements • Photographs have been taken from internet sources and mostly not taken by the author. The original sources are gratefully acknowledged. Thank you