SlideShare a Scribd company logo
1 of 4
Download to read offline
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1751
A Review on Earned Value Management and Earned Schedule Method
for Construction Project
Mr. Girish Ambadas Gaddam1, Prof. A. B. Landage2
1Mr. Girish A Gaddam (M. Tech – Construction Management), Civil Engineering Department, Government College
of Engineering Karad, Maharashtra, India
2Prof. A. B. Landage Assistant Professor, Civil Engineering Department, Government College of Engineering Karad,
Maharashtra, India
---------------------------------------------------------------------***-------------------------------------------------------------------
Abstract - The most essential governing factors in project
success are project cost and time. Private and public
construction projects have a long history of cost and
schedule overruns. Earned value management (EVM) and
Earned Schedule (ES) are project management
methodologies for monitoring project performance that
have been adopted. The methodologies assist in the
comparison of budgeted and actual work costs, as well as
scheduling delays.
EV (Earned Value Management) is an effective methodology
for project evaluation and controlling. By implementing this
methodology on a project executive, project managers, and
other stakeholders will be able to visualize project status
throughout the project's lifecycle, allowing them to better
manage the project.
Earned Schedule (ES) is a concept and practice that builds
on Earned Value Management. It is new extend to EVM
methodology. To improve the evaluation of the project
schedule performance and predict the duration needed to
complete the project, the earned schedule allows earned
value management outcomes to be converted to time or
duration metrics. The earned schedule improves the project
manager's comprehension of project schedule forecasts and
helps him make better scheduling decisions. The purpose of
the study is to apply EVM and ESM to a real-time
infrastructure flyover construction project in Rajkot
Gujarat, to analyse schedule delay and cost overrun, using
above mythologies and then compare the results of two
deterministic predicting techniques, EVM and ESM, using MS
Software (MSP).
Key Words: Earned Value Management (EVM), Project
Management, Earned Schedule (ESM)etc.
1 INTRODUCTION
Projects are an unavoidable aspect of any organization's
strategy and operational goals nowadays. As a result,
businesses follow the project management principles and
criteria outlined in PMBOK by the Project Management
Institute (PMI). An organization can exert proper
management and control over projects by using these
project management methodologies and principles. Earned
Value Analysis is a useful tool for tracking and controlling
the project' cost constraints. The three limitations,
according to PMI, are scope, schedule, and budget. As a
project manager, you must deal with these critical obstacles
and effectively manage them. As a result, it is critical for
them to keep a watchful watch on the status of the projects
in accordance to these constraints in real time. EVM was
used to measure project performance and predict project
costs at completion. EVM data were rarely utilized to
estimate the time it would take to finish an activity, work
package, or project, or to predict when they would be
completed. Insufficient data poses a risk to the project
manager's ability to make right decisions. The Earned
Schedule (ES) concept allows EVM indicators to be
transferred into time or duration metrics to improve
project schedule evaluation and forecasting. As a result, the
Project Manager can use the EVM& ESM Concept to predict
schedule and budget problems early in the project and
address them.
2 LITERATURE REVIEW
Sagar K. Bhosekar, Gayatri Vyas (2012) “Cost Controlling
Using Earned Value Analysis in Construction Industries”,
author focuses on earned value management in the real
estate construction industry in this article. The importance
of the EVM tool was studied, and the basic formula of the
EVM was discussed with performance indicators, and a case
study for a residential building with a floor area of 120 sq.m
was used to compute EVM analysis with time and cost
tracking for the given case study. For comparison of EVM
analysis with MSP, P6, and SQL created software, the author
uses a variety of project management tools. & finally, a
comparison of EVM Analysis different management tools.
Virle, Rajesh, Mhaske, Sumedh, (2013) “Application of
Earned Value and Earned Schedule to Construction Project”,
In this paper author identified application of EVM in
construction projects & discus elements of EVM and defined
various factors & importance of EVM & ES Concept. Author
at the end calculated EVM factors & with the help of EVM
factors, ES Factors calculated for sky walk project. & finally
based on the results conclusion drawn.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1752
Rajesh Ganpat, Virle and Sumedh Mhanske(2013),
“Monitoring of Construction Projects Using EVM And ESM
Tools” The EVA project may be confidently dissected, and
the actions taken will have a considerably higher
possibility of success, according to this article. EVM is
sophisticated, yet it is built on a simple base, as previously
indicated. It aids in the tracking of project performance
through simple arithmetical calculations & conclude
comparison between EVM & ESM tools.
Shaik Mohammad Masood, Dayanand, Harsha H.N (2014),
“An Analysis on Resource Planning, Cost Estimation and
Tracking of Project by Earned Value Management” In this
research focused on understanding the impact of EVM in
monitoring and controlling construction project progress
and timely completion. The main message was that Earned
Value Analysis allows you to recognize possible problems
early in the project and take action to fix them. A case
study of a "Windmills of Your Mind" Duplex Apartment in
Whitefield, Bangalore was taken. For project planning and
EVM calculations, Primavera P6 software was used.
'Earned Value Management is a remarkable way of project
management since it incorporates cost, schedule, and
scope and can be used to estimate future performance and
project completion dates,' the article stated. It enables
projects to be managed more efficiently and on time.
S Suresh and Ganapathy N (2015),"Analysis of Project
Performance Using Earned Value Analysis," Volume: 04
Issue: 04 | April-2015 | International Research Journal of
Engineering and Technology (IRJET). This article
addresses Earned Value Analysis as a tool for analysing
project performance. EVM enables a better understanding
of costs as well as other aspects such as scope, risks, and
performance. It drives the management team to pay very
close attention to cost, time, and progress, allowing the
project to run more smoothly.
P. A. Chavan & P. S. Bhamre (2015), “Efficient Planning
Scheduling and Delay Analysis of Residential Project” In
this project research focused on construction project
planning, scheduling, and delay analysis, with information
on introduction to planning, steps in project planning,
introduction to scheduling, Project Scheduling Steps,
Manpower Management, and manpower planning. In
addition, a case study of a residential unit project was
presented utilizing MS Project and MS Excel software. At
the conclusion of the paper, there was a discussion about
the Master Schedule, Activities, and other topics. Unskilled
labor, labor shortages, and labor shortages. the delay is
caused by a lack of materials, poor management, poor
planning, and weather issues. Recommendations were also
made in order to reduce the time spent waiting.
H. Tserng, Wen Lin, Chien Li, Kai-Wei Weng, and Denise C.
Loisel,(2015)“Research on The Earned Value Management
System Applied in Consultancy Project Performance”,
Journal of marine science & technology Volume 23, Issue-1,
Article-4- 2015 The main focus of this research work is on
the development of project classification factor assessment
indicators and a web-based information system. It is
investigated which classification elements and performance
evaluation indicators are suitable to consulting businesses
utilising various instances. The future project tendency is
governed by eight performance control values. This article
concluded that EVM is appropriate for project management
monitoring in engineering consulting businesses. This
article investigates the use of EVM in consulting projects.
The discriminant analysis method is used to generate real-
time project cost and schedule performance monitoring
with predictive capabilities. For a construction project, we
conducted a case study and verification.
Amruta B. Vyas, (2016) “Tracking of Construction Projects
by Earned Value Management” In this paper researcher
focused on the earned value management in the
construction industry. How Earned value management is
better option over the traditional methods. Weaknesses of
traditional methods over EVM methods are discussed.
Researcher also takes helps of other literature for analysis
of EVM. Benefits of Project management are also studied in
this paper. Importance of EVM in construction Projects also
illustrated. Basic elements of EVM is given with
performance indicator is explained with the example &
conclude about how project delays and cost are risk factor
for decision making.
Shyama Sasikumar, (2016) “Application of Earned Value
Analysis in Analyzing Project Performance” In this paper
author researched on application of EVM for construction
project & also define various factors for project planning
and rate analysis preparation for resource calculation.
Researcher also finds various EVM factors & indicators for
case study by using EVM techniques. Based on results final
conclusion about project calculated.
Lavanya S, G Narayana (2019), “Cost Analysis of
Construction Building by Earned Value Method using MS
Project Software”, This article defined cost orientated
parameters from EV analysis was done as before already
done but only focused on cost factor using MSP Software for
residential building. Based on calculation defined project
status as on status date for better controlling and
monitoring work in cost point of view.
Tejas A. Topkar (2020) “Study of Management of Earned
Value by Advance Software” The mainly author focused on
advance software with EVM analysis for residential
buildings only. In this author was defined advantages &
disadvantages of EVM analysis and only review part with
EV calculation done using Prima Vera P6 Software for
advance point of view.
Vaibhava, Prakash, Dheeraj and Chandra(2020),
“Application of earned value method and earned schedule
method for a residential apartment” In this paper author
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1753
defined various factors EVM & ES Concept and by using
EVM & ES tool he calculated schedule variance, cost
variance & various factors for residential apartment case
study using primavera p6 software and finally using both
methods compared results & conclusion drawn.
Sachin Nalawade, Omkar Ghode, Piyush Vaidya(May-
2021)“Earn value analysis of construction project using
primavera p6” In this paper author told, what is earn value
management and defined all the parameter use in EVM and
define benefits and also stated about primavera p6
software how to create activity, how it links, how to define
calendar, how allocate resources, and how to track it to
find the performance of the project finally. Conclusion
predicted the complication time & Cost of the project with
EVM technique.
Pavan Kumar (2021), “A Review on Earned Value
Management Analysis in Construction Industry” In this
paper author define various terminologies regarding time
cost optimization techniques & EVM Concept. Also figure
out how EV analysis is going to use for better optimization
for resources using MS Software for residential
project(apartment).
3 CALCULATION PARAMETERS
3.1 EVM PARAMETER (Anbari, F. T. (2012)
Budget at Completion (BAC)
Planned Value (PV) (BCWS)
Earned value (EV)(BCWP)
Actual cost (ACWP)
o CV = EV − AC
o SV = EV − PV
o CPI = EV ÷ AC
o SPI = EV ÷ PV
o EAC = BAC ÷ CPI
o VAC = BAC – EA
3.2 ES PARAMETERS (Anbari, F. T. (2012)
Schedule at Completion (SAC)
Actual Time (AT)
Earned Schedule (ES)
Planned Accomplishment Rate (PAR)
o PAR = BAC ÷ SAC
o TV = SV ÷ PAR
o ES = EV ÷ PAR
o TPI = ES ÷ AT
o TEAC = SAC + TV
o TVAC=SAC-TEAC
4 CONCLUSION
The above literature suggests that Earned Value Analysis
and Earned Schedule Method have a lot of potential in the
construction industry. Just the following literature
implement the use of EVM and ESM as project monitoring &
controlling tools for residential projects. As a result, it has
been demonstrated that it may also be used to control and
monitor the cost and schedule for infrastructure
construction projects. We could predict an early warning of
variance in project duration and cost by employing EVM
and ESM parameters using different project management
software’s.
5 REFERENCESSS
1. Sagar K. Bhosekar, Gayatri Vyas “Cost Controlling
Using Earned Value Analysis in Construction
Industries”, International Research Journal of
Engineering and Technology (IRJET) Volume 1,
Issue 4, April 2012.
2. Virle, Rajesh, Mhaske, Sumedh, “Application of
Earned Value and Earned Schedule to Construction
Project”, International Journal of Scientific
Engineering and Research (IJSER) ISSN (Online):
2347-3878 Volume 1 Issue 1, September 2013
3. Rajesh ganpat virle and sumedh
Mhanske,“Monitoring of Construction Projects
Using EVM And ESM Tools” International journal of
structural and civil engineering research, Volume:
02 Issue: 04 | Nov-2013.
4. Shaik Mohammad Masood, Dayanand, Harsha H.N,
“An Analysis on Resource Planning, Cost Estimation
and Tracking of Project by Earned Value
Management” International Research Journal of
Engineering and Innovative Technology (IRJET)
Volume: 04 Issue: 04 |october-2014.
5. Sandhya Suresh, Ganapathy Ramasamy N, “Analysis
of Project Performance Using Earned Value
Analysis” International Research Journal of
Engineering and Technology (IRJET) Volume: 04
Issue: 04 | April-2015.
6. P. A. Chavan & P. S. Bhamre, “Efficient Planning
Scheduling and Delay Analysis of Residential
Project” Journals of Mechanical & Civil Engineering
(ISOR-JMCE) Volume: 12 Issue: 03 |Jun-2015
PP126-133.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1754
7. H. Ping Tserng, Wen-Shyong Lin, Chien-Chung Li,
Kai-Wei Weng, and Denise C. Loisel. “Research on
The Earned Value Management System Applied in
Consultancy Project Performance”, Journal of
marine science & technology Volume 23, Issue-1,
Article-4- 2015.
8. Amruta B. Vyas, “Tracking of Construction Projects
by Earned Value Management” International
Research Journal of Engineering and Technology
(IRJET) Volume: 05 Issue: 03 |March-2016.
9. Shyama Sasikumar, “Application of Earned Value
Analysis in Analyzing Project Performance”
International Research Journal of Engineering and
Technology (IRJET) Volume: 05 Issue: 09 | Sep-
2016.
10. Lavanya S, G Narayana (2019), “Cost Analysis of
Construction Building by Earned Value Method
using MS Project Software”, International Journal
of Recent Technology and Engineering (IJRTE)
ISSN: 2277-3878, Volume-8, Issue-1C, May 2019.
11. Tejas A. Topkar (2020) “Study of Management of
Earned Value by Advance Software” International
Research Journal of Modernization in Engineering
Technology and Science
Volume:02/Issue:10/October -2020.
12. Vaibhava, Prakash, Dheeraj and Chandra,
“Application of earned value method and earned
schedule method for a residential apartment”
International Conference on Advances in Physical
Sciences and Materials Journal of Physics:
Conference Series 17060-12117 (Year-2020).
13. Sachin Nalawade, Omkar Ghode, Piyush Vaidya
“Earn value analysis of construction project using
primavera p6”, Cikitusi Journal for
Multidisciplinary Research ISSN NO: 0975-6876
2021.
14. Pavan Kumar (2021), “A Review on Earned Value
Management Analysis in Construction Industry”
International Research Journal of Engineering and
Technology (IRJET) e-ISSN: 2395-0056 Volume:
08 Issue: 08 | Aug 2021.
15. https://www.pmi.org
16. https://onlinecourses.nptel.ac.in
6 BIOGRAPHIES
Mr. Girish Ambadas Gaddam
PG Scholar (M. Tech – Construction
Management), Civil Engineering
Department, Government College
of Engineering Karad,
Maharashtra, India.
Prof. A. B. Landage,
Assistant Professor, Civil
Engineering Department,
Government College of
Engineering Karad, Maharashtra,
India. Ph.D. (Pursuing), M. Tech,
B.E., Diploma.

More Related Content

Similar to A Review on Earned Value Management and Earned Schedule Method for Construction Project

Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.IRJET Journal
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheoryIRJET Journal
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...IRJET Journal
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)IAESIJEECS
 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)IAESIJEECS
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET Journal
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
A Systematic Review On Software Cost Estimation In Agile Software Development
A Systematic Review On Software Cost Estimation In Agile Software DevelopmentA Systematic Review On Software Cost Estimation In Agile Software Development
A Systematic Review On Software Cost Estimation In Agile Software DevelopmentBrooke Heidt
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...IJMIT JOURNAL
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 

Similar to A Review on Earned Value Management and Earned Schedule Method for Construction Project (20)

Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)
 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
A Systematic Review On Software Cost Estimation In Agile Software Development
A Systematic Review On Software Cost Estimation In Agile Software DevelopmentA Systematic Review On Software Cost Estimation In Agile Software Development
A Systematic Review On Software Cost Estimation In Agile Software Development
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

A Review on Earned Value Management and Earned Schedule Method for Construction Project

  • 1. © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1751 A Review on Earned Value Management and Earned Schedule Method for Construction Project Mr. Girish Ambadas Gaddam1, Prof. A. B. Landage2 1Mr. Girish A Gaddam (M. Tech – Construction Management), Civil Engineering Department, Government College of Engineering Karad, Maharashtra, India 2Prof. A. B. Landage Assistant Professor, Civil Engineering Department, Government College of Engineering Karad, Maharashtra, India ---------------------------------------------------------------------***------------------------------------------------------------------- Abstract - The most essential governing factors in project success are project cost and time. Private and public construction projects have a long history of cost and schedule overruns. Earned value management (EVM) and Earned Schedule (ES) are project management methodologies for monitoring project performance that have been adopted. The methodologies assist in the comparison of budgeted and actual work costs, as well as scheduling delays. EV (Earned Value Management) is an effective methodology for project evaluation and controlling. By implementing this methodology on a project executive, project managers, and other stakeholders will be able to visualize project status throughout the project's lifecycle, allowing them to better manage the project. Earned Schedule (ES) is a concept and practice that builds on Earned Value Management. It is new extend to EVM methodology. To improve the evaluation of the project schedule performance and predict the duration needed to complete the project, the earned schedule allows earned value management outcomes to be converted to time or duration metrics. The earned schedule improves the project manager's comprehension of project schedule forecasts and helps him make better scheduling decisions. The purpose of the study is to apply EVM and ESM to a real-time infrastructure flyover construction project in Rajkot Gujarat, to analyse schedule delay and cost overrun, using above mythologies and then compare the results of two deterministic predicting techniques, EVM and ESM, using MS Software (MSP). Key Words: Earned Value Management (EVM), Project Management, Earned Schedule (ESM)etc. 1 INTRODUCTION Projects are an unavoidable aspect of any organization's strategy and operational goals nowadays. As a result, businesses follow the project management principles and criteria outlined in PMBOK by the Project Management Institute (PMI). An organization can exert proper management and control over projects by using these project management methodologies and principles. Earned Value Analysis is a useful tool for tracking and controlling the project' cost constraints. The three limitations, according to PMI, are scope, schedule, and budget. As a project manager, you must deal with these critical obstacles and effectively manage them. As a result, it is critical for them to keep a watchful watch on the status of the projects in accordance to these constraints in real time. EVM was used to measure project performance and predict project costs at completion. EVM data were rarely utilized to estimate the time it would take to finish an activity, work package, or project, or to predict when they would be completed. Insufficient data poses a risk to the project manager's ability to make right decisions. The Earned Schedule (ES) concept allows EVM indicators to be transferred into time or duration metrics to improve project schedule evaluation and forecasting. As a result, the Project Manager can use the EVM& ESM Concept to predict schedule and budget problems early in the project and address them. 2 LITERATURE REVIEW Sagar K. Bhosekar, Gayatri Vyas (2012) “Cost Controlling Using Earned Value Analysis in Construction Industries”, author focuses on earned value management in the real estate construction industry in this article. The importance of the EVM tool was studied, and the basic formula of the EVM was discussed with performance indicators, and a case study for a residential building with a floor area of 120 sq.m was used to compute EVM analysis with time and cost tracking for the given case study. For comparison of EVM analysis with MSP, P6, and SQL created software, the author uses a variety of project management tools. & finally, a comparison of EVM Analysis different management tools. Virle, Rajesh, Mhaske, Sumedh, (2013) “Application of Earned Value and Earned Schedule to Construction Project”, In this paper author identified application of EVM in construction projects & discus elements of EVM and defined various factors & importance of EVM & ES Concept. Author at the end calculated EVM factors & with the help of EVM factors, ES Factors calculated for sky walk project. & finally based on the results conclusion drawn. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1752 Rajesh Ganpat, Virle and Sumedh Mhanske(2013), “Monitoring of Construction Projects Using EVM And ESM Tools” The EVA project may be confidently dissected, and the actions taken will have a considerably higher possibility of success, according to this article. EVM is sophisticated, yet it is built on a simple base, as previously indicated. It aids in the tracking of project performance through simple arithmetical calculations & conclude comparison between EVM & ESM tools. Shaik Mohammad Masood, Dayanand, Harsha H.N (2014), “An Analysis on Resource Planning, Cost Estimation and Tracking of Project by Earned Value Management” In this research focused on understanding the impact of EVM in monitoring and controlling construction project progress and timely completion. The main message was that Earned Value Analysis allows you to recognize possible problems early in the project and take action to fix them. A case study of a "Windmills of Your Mind" Duplex Apartment in Whitefield, Bangalore was taken. For project planning and EVM calculations, Primavera P6 software was used. 'Earned Value Management is a remarkable way of project management since it incorporates cost, schedule, and scope and can be used to estimate future performance and project completion dates,' the article stated. It enables projects to be managed more efficiently and on time. S Suresh and Ganapathy N (2015),"Analysis of Project Performance Using Earned Value Analysis," Volume: 04 Issue: 04 | April-2015 | International Research Journal of Engineering and Technology (IRJET). This article addresses Earned Value Analysis as a tool for analysing project performance. EVM enables a better understanding of costs as well as other aspects such as scope, risks, and performance. It drives the management team to pay very close attention to cost, time, and progress, allowing the project to run more smoothly. P. A. Chavan & P. S. Bhamre (2015), “Efficient Planning Scheduling and Delay Analysis of Residential Project” In this project research focused on construction project planning, scheduling, and delay analysis, with information on introduction to planning, steps in project planning, introduction to scheduling, Project Scheduling Steps, Manpower Management, and manpower planning. In addition, a case study of a residential unit project was presented utilizing MS Project and MS Excel software. At the conclusion of the paper, there was a discussion about the Master Schedule, Activities, and other topics. Unskilled labor, labor shortages, and labor shortages. the delay is caused by a lack of materials, poor management, poor planning, and weather issues. Recommendations were also made in order to reduce the time spent waiting. H. Tserng, Wen Lin, Chien Li, Kai-Wei Weng, and Denise C. Loisel,(2015)“Research on The Earned Value Management System Applied in Consultancy Project Performance”, Journal of marine science & technology Volume 23, Issue-1, Article-4- 2015 The main focus of this research work is on the development of project classification factor assessment indicators and a web-based information system. It is investigated which classification elements and performance evaluation indicators are suitable to consulting businesses utilising various instances. The future project tendency is governed by eight performance control values. This article concluded that EVM is appropriate for project management monitoring in engineering consulting businesses. This article investigates the use of EVM in consulting projects. The discriminant analysis method is used to generate real- time project cost and schedule performance monitoring with predictive capabilities. For a construction project, we conducted a case study and verification. Amruta B. Vyas, (2016) “Tracking of Construction Projects by Earned Value Management” In this paper researcher focused on the earned value management in the construction industry. How Earned value management is better option over the traditional methods. Weaknesses of traditional methods over EVM methods are discussed. Researcher also takes helps of other literature for analysis of EVM. Benefits of Project management are also studied in this paper. Importance of EVM in construction Projects also illustrated. Basic elements of EVM is given with performance indicator is explained with the example & conclude about how project delays and cost are risk factor for decision making. Shyama Sasikumar, (2016) “Application of Earned Value Analysis in Analyzing Project Performance” In this paper author researched on application of EVM for construction project & also define various factors for project planning and rate analysis preparation for resource calculation. Researcher also finds various EVM factors & indicators for case study by using EVM techniques. Based on results final conclusion about project calculated. Lavanya S, G Narayana (2019), “Cost Analysis of Construction Building by Earned Value Method using MS Project Software”, This article defined cost orientated parameters from EV analysis was done as before already done but only focused on cost factor using MSP Software for residential building. Based on calculation defined project status as on status date for better controlling and monitoring work in cost point of view. Tejas A. Topkar (2020) “Study of Management of Earned Value by Advance Software” The mainly author focused on advance software with EVM analysis for residential buildings only. In this author was defined advantages & disadvantages of EVM analysis and only review part with EV calculation done using Prima Vera P6 Software for advance point of view. Vaibhava, Prakash, Dheeraj and Chandra(2020), “Application of earned value method and earned schedule method for a residential apartment” In this paper author
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1753 defined various factors EVM & ES Concept and by using EVM & ES tool he calculated schedule variance, cost variance & various factors for residential apartment case study using primavera p6 software and finally using both methods compared results & conclusion drawn. Sachin Nalawade, Omkar Ghode, Piyush Vaidya(May- 2021)“Earn value analysis of construction project using primavera p6” In this paper author told, what is earn value management and defined all the parameter use in EVM and define benefits and also stated about primavera p6 software how to create activity, how it links, how to define calendar, how allocate resources, and how to track it to find the performance of the project finally. Conclusion predicted the complication time & Cost of the project with EVM technique. Pavan Kumar (2021), “A Review on Earned Value Management Analysis in Construction Industry” In this paper author define various terminologies regarding time cost optimization techniques & EVM Concept. Also figure out how EV analysis is going to use for better optimization for resources using MS Software for residential project(apartment). 3 CALCULATION PARAMETERS 3.1 EVM PARAMETER (Anbari, F. T. (2012) Budget at Completion (BAC) Planned Value (PV) (BCWS) Earned value (EV)(BCWP) Actual cost (ACWP) o CV = EV − AC o SV = EV − PV o CPI = EV ÷ AC o SPI = EV ÷ PV o EAC = BAC ÷ CPI o VAC = BAC – EA 3.2 ES PARAMETERS (Anbari, F. T. (2012) Schedule at Completion (SAC) Actual Time (AT) Earned Schedule (ES) Planned Accomplishment Rate (PAR) o PAR = BAC ÷ SAC o TV = SV ÷ PAR o ES = EV ÷ PAR o TPI = ES ÷ AT o TEAC = SAC + TV o TVAC=SAC-TEAC 4 CONCLUSION The above literature suggests that Earned Value Analysis and Earned Schedule Method have a lot of potential in the construction industry. Just the following literature implement the use of EVM and ESM as project monitoring & controlling tools for residential projects. As a result, it has been demonstrated that it may also be used to control and monitor the cost and schedule for infrastructure construction projects. We could predict an early warning of variance in project duration and cost by employing EVM and ESM parameters using different project management software’s. 5 REFERENCESSS 1. Sagar K. Bhosekar, Gayatri Vyas “Cost Controlling Using Earned Value Analysis in Construction Industries”, International Research Journal of Engineering and Technology (IRJET) Volume 1, Issue 4, April 2012. 2. Virle, Rajesh, Mhaske, Sumedh, “Application of Earned Value and Earned Schedule to Construction Project”, International Journal of Scientific Engineering and Research (IJSER) ISSN (Online): 2347-3878 Volume 1 Issue 1, September 2013 3. Rajesh ganpat virle and sumedh Mhanske,“Monitoring of Construction Projects Using EVM And ESM Tools” International journal of structural and civil engineering research, Volume: 02 Issue: 04 | Nov-2013. 4. Shaik Mohammad Masood, Dayanand, Harsha H.N, “An Analysis on Resource Planning, Cost Estimation and Tracking of Project by Earned Value Management” International Research Journal of Engineering and Innovative Technology (IRJET) Volume: 04 Issue: 04 |october-2014. 5. Sandhya Suresh, Ganapathy Ramasamy N, “Analysis of Project Performance Using Earned Value Analysis” International Research Journal of Engineering and Technology (IRJET) Volume: 04 Issue: 04 | April-2015. 6. P. A. Chavan & P. S. Bhamre, “Efficient Planning Scheduling and Delay Analysis of Residential Project” Journals of Mechanical & Civil Engineering (ISOR-JMCE) Volume: 12 Issue: 03 |Jun-2015 PP126-133.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1754 7. H. Ping Tserng, Wen-Shyong Lin, Chien-Chung Li, Kai-Wei Weng, and Denise C. Loisel. “Research on The Earned Value Management System Applied in Consultancy Project Performance”, Journal of marine science & technology Volume 23, Issue-1, Article-4- 2015. 8. Amruta B. Vyas, “Tracking of Construction Projects by Earned Value Management” International Research Journal of Engineering and Technology (IRJET) Volume: 05 Issue: 03 |March-2016. 9. Shyama Sasikumar, “Application of Earned Value Analysis in Analyzing Project Performance” International Research Journal of Engineering and Technology (IRJET) Volume: 05 Issue: 09 | Sep- 2016. 10. Lavanya S, G Narayana (2019), “Cost Analysis of Construction Building by Earned Value Method using MS Project Software”, International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-8, Issue-1C, May 2019. 11. Tejas A. Topkar (2020) “Study of Management of Earned Value by Advance Software” International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:10/October -2020. 12. Vaibhava, Prakash, Dheeraj and Chandra, “Application of earned value method and earned schedule method for a residential apartment” International Conference on Advances in Physical Sciences and Materials Journal of Physics: Conference Series 17060-12117 (Year-2020). 13. Sachin Nalawade, Omkar Ghode, Piyush Vaidya “Earn value analysis of construction project using primavera p6”, Cikitusi Journal for Multidisciplinary Research ISSN NO: 0975-6876 2021. 14. Pavan Kumar (2021), “A Review on Earned Value Management Analysis in Construction Industry” International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 08 Issue: 08 | Aug 2021. 15. https://www.pmi.org 16. https://onlinecourses.nptel.ac.in 6 BIOGRAPHIES Mr. Girish Ambadas Gaddam PG Scholar (M. Tech – Construction Management), Civil Engineering Department, Government College of Engineering Karad, Maharashtra, India. Prof. A. B. Landage, Assistant Professor, Civil Engineering Department, Government College of Engineering Karad, Maharashtra, India. Ph.D. (Pursuing), M. Tech, B.E., Diploma.