SlideShare a Scribd company logo
Prepared by
Prof. Ashish Makwana
Civil Engineering Dept. - MEFGI
Prof. Ashish Makwana 1
PRESENTATION
OUTLINE…
1. Construction Project
2. Phases of a Construction Project
3. Importance of Construction and Construction
Industry
4. Indian Construction Industry
5. Construction Management
6. Importance of Planning, Scheduling and Controlling
Projects
Prof. Ashish Makwana 2
CONSTRUCTION PROJECT
Project
A Project is defined as a temporary
endeavour undertaken to create a unique
product/service/results.
Product
The product in case of a construction
project is the constructed facility such as a
building, a bridge, a highway, a dam, a
canal, a factory etc.
Prof. Ashish Makwana 3
Construction projects
Construction projects involve varying
manpower and their duration can range
from a few weeks to more than five years.
Each construction project is ‘unique’
and ‘temporary’ in nature and so is the
management involved.
Prof. Ashish Makwana 4
Construction projects
Unique Features of a Construction Project
One time activity
A start and finish
Complexity
Involvement of several people on an adhoc
basis
Limited set of resources
High cost
A time frame for completion
Prof. Ashish Makwana 5
High risk of failure
Difficulty in defining quality standards
Sequencing of activities and phases
No practice/rehearsals
Uniqueness of people relationship
Lack of experience of client/owner
Feedback mechanism
High level of subcontracting
Uncertainty exists
Prof. Ashish Makwana 6
PHASES OF
A CONSTRUCTION PROJECT
Briefing stage
Designing stage
Tendering stage
Construction stage
Commissioning stage
Prof. Ashish Makwana 7
1. Briefing stage
• This stage is also called the ‘Report
stage’.
• It is the stage where ideas originated by
individuals are studied with regard to cost
and benefits so as to establish the
economic viability/social utility of a project.
Purpose
• The purpose of the briefing stage is to
enable the client to specify project
functions and permissible costs.
Prof. Ashish Makwana 8
Activities (Briefing stage)
• To appoint a project committee, if
necessary.
• To appoint a project manager who will have
a continuing responsibility to the client
through out the construction project.
• To carry out technical and non-technical
investigation so that alternative proposals
may be given due consideration.
• To study the various alternatives and
identify the most feasible one.
• To prepare the project report which is the
outcome of the first stage.
Prof. Ashish Makwana 9
Feasibility report
• Technical analysis
• Economic analysis
• Financial analysis
• Ecological analysis
Prof. Ashish Makwana 10
2. Designing stage
• It is a very important stage in the field of
construction because any modification of the
project after this stage would prove
expensive.
• A realistic and detailed cost estimate of
the project can be prepared during the
design stage.
Purpose
• The purpose of this stage is to complete the
project summary and determine the
method of construction and estimated
costs so as to obtain necessary approvals
from the client.
Prof. Ashish Makwana 11
Activities (Designing stage)
• To develop the project summary for the
final adoption of the most suitable alternative.
• To carry out technical investigations such
as,
– Soil investigation
– Topographic investigation
– Materials surveys
– Market surveys
• To prepare detailed design, working
drawings, specifications, bill of quantities,
final cost estimate and preliminary
construction programme.
Prof. Ashish Makwana 12
3. Tendering stage
• During this stage tenders are invited and
the contract is awarded at the best
available terms agreed mutually between
the owner’s team and the contractors.
Purpose
• The purpose of the tendering stage is to
appoint a contractor who will undertake
the construction work on the most suitable
terms and conditions of quality, cost and
completion time.
Prof. Ashish Makwana 13
Activities (Tendering stage)
• To invite tenders from the contractors for the
construction work and to award the contract.
• Pre-qualification of contractors involves an
investigation of the potential of contractor’s
financial, managerial and physical resources,
contractor’s experience of handling similar
projects, etc.
• To prepare contract documents, to be
signed by the client and the contractor.
• Holding a pre-bid conference and providing
the necessary information.
Prof. Ashish Makwana 14
Activities (Tendering stage)
• Negotiating contract price with qualified
contractor.
• Reviewing documents submitted by
contractor.
Prof. Ashish Makwana 15
4. Construction stage
• The construction stage involves the
execution of construction work as per
the design, drawing and within agreed
limits of time, cost and specified quality.
Construction Planning Activities
• Construction schedule
• Manpower schedule
• Material delivery schedule
• Plant and equipment schedule
Prof. Ashish Makwana 16
Control of site operations Activities
• Supply of materials and equipment
• Supervision for quality control
• Co-ordination among sub-contractors
• Supervision for quality control
• Supply of necessary drawings
Prof. Ashish Makwana 17
5. Commissioning stage
• It is the stage in which the performance
of the structure is evaluated and the
proposed nature of maintenance and
repair are considered.
Purpose
• The purpose of this stage is to ensure that
the construction work has been carried
out as per the drawing and
specifications and all the facilities
developed function properly as
envisaged in the design.
Prof. Ashish Makwana 18
Activities (Commissioning stage)
• To keep various records of actual work.
• To inspect the construction work
thoroughly and have any defects rectifies.
• To prepare operating instructions and
maintenance manuals.
• To carry out tests for performance, such
as water tightness, strength etc.
Prof. Ashish Makwana 19
IMPORTANCE OF CONSTRUCTION
AND CONSTRUCTION INDUSTRY
• Construction is an important part of real
estate and infrastructure such as:
• Real estate
– Residential
– Industrial
– Corporate
– Commercial
Prof. Ashish Makwana 20
• Infrastructure
– Roads
– Railways
– Urban infrastructure
– Ports
– Airports
– Power
• The importance of construction can be gauged
from the fact that cost of construction of
certain infrastructure projects may be as high
as 60 to 80% of the total project cost.
Prof. Ashish Makwana 21
• Construction is recognized as the basic input
for socio-economic development of a country.
• Since construction industry is dependent on a
number of industries, its growth in other
industries as well.
– Development of building materials industry
– Development of construction equipments
industry
Prof. Ashish Makwana 22
• Construction products such as buildings,
bridges, roads, power plants have a long life
as compared to the products of other
industries.
Prof. Ashish Makwana 23
INDIAN CONSTRUCTION INDUSTRY
Factors in favour of Indian construction industry
• Availability of cheap labour
• Availability of qualified professionals
• Large number of construction companies
• Actual shortage of housing
• Boost from the government
• Growth in industrial sector
Prof. Ashish Makwana 24
INDIAN CONSTRUCTION INDUSTRY (continued..)
Factors against the Indian construction industry
• Low productivity
• Low ratio of skilled to unskilled workers
• High cost of finance
• Complicated tax structure
• Presence of small contractors who lack
financial and technology backup
• Negligible investment in R & D
• Competition from multinational companies
Prof. Ashish Makwana 25
Investment Opportunities in Construction in
India
• Construction development in residential,
retail, commercial and hospitality sectors
• Technology and solutions for smart
sustainable cities
• Technology for the promotion of low cost
housing
• Green building solutions
• Smart cities
• Sustainable and environmental friendly
building materialsProf. Ashish Makwana 26
• Training and Skill development of
construction sector workers
• Urban water supply, Sewage, Sewage
treatment, Solid waste management
Prof. Ashish Makwana 27
CONSTRUCTION MANAGEMENT
• Project Management is the art and science of
mobilising and managing people, materials,
equipment and money to complete the
assigned project work on time, within budgeted
costs and specified technical performance
standards.
• Construction Management may be defined as
the management in which group of people of
different categories works together, to execute
the project economically without affecting the
quality in a well planned and organised manner.Prof. Ashish Makwana 28
Scope of Construction Management
• Planning and estimating
• Execution of works
• Financial management
• Material management
• Equipment management
• Labour management
• Site layout
• Equipments and Materials plant location
• Labour relationships
• Industrial psychology for smooth flow of work
Prof. Ashish Makwana 29
Need of Construction Management
• Co-ordination between different agencies
• Economy in Construction
• Development of management and machinery
• Speed of Construction
• Quality Control of materials and workmanship
Prof. Ashish Makwana 30
Objectives of Construction Management
• Completing the work within estimated budget.
• Completing the work within specified time.
• The Quality and workmanship should be better.
• The work should be executed as per specification.
• Providing safe and satisfactory working conditions
for all personnel and workers.
• Taking sound decisions at the lowest practical
management level through delegation of authority.
• Motivating people to give their best within their
capacities.
• Creating an organisation that works as a team.
• Achieving economy in the construction.Prof. Ashish Makwana 31
Phases / Functions of Construction Management
• Planning and Scheduling
• Organising
• Staffing
• Directing
• Controlling
• Co-ordinating
• Communication
Prof. Ashish Makwana 32
Planning - Planning involves formulation of a number
of alternative of realistic work plans for achieving
specified objectives and finally selecting a plan which is
best suited from the standpoint of available resources
and constraints imposed upon the project.
• Planning is the administrative process which
translates the policy into a method of achieving the
objectives.
• How a project will be carried out?
• What materials will be used?
• What equipment and machineries will be utilized?
• What men and staff will be employed?
‘What to do?’ and ‘How to do?’
Prof. Ashish Makwana 33
Scheduling - Scheduling is the fitting of the final work
plan to a time scale. It shows the duration and order of
various construction activities.
‘When to do?’
• Time plan
• Resources plan
• Plan for controlling project
• Schedule of design and drawing preparation
• Work quantities
• Progress of work planned
• Resource allocations
• Budget costs
Prof. Ashish Makwana 34
Organising – Organising is concerned with division of
the total construction work into manageable sections
and systematically arranging various operations by
delegating specific tasks to individuals.
Staffing – Organising involve the division of the project
work into sections and staffing is the provision of
people to fill the positions so created.
• Staffing functions- Recruiting the right people,
Arranging staff training courses, Carrying out proper
staff assessment
Prof. Ashish Makwana 35
Directing – The directing function is concerned with
training sub-ordinates to carry out assigned tasks,
supervising their work and guiding their efforts.
• The essence of directing lies in the ability to
motivate people individually and as groups to utilize
their creative efforts in achieving specified
objectives.
Controlling – Controlling is necessary for ensuring
effective and efficient working.
• It involves a constant review of the work plan to
check on actual achievements and to discover and
rectify deviations through appropriate corrective
measures.
Prof. Ashish Makwana 36
Co-ordinating – This is a process where the framework
of the organization is made to operate smoothly with
the flow of information, decisions and results in every
direction.
Prof. Ashish Makwana 37
Importance of Planning, Scheduling and
Controlling projects
Prof. Ashish Makwana 38
Planning
• Planning aims at formulation of a time based plan of
action for co-ordinating various activities and
resources to achieve specified objectives.
• Planning is the process of developing the project
plan.
Benefits (Planning)
• Project plan clearly defines project’s scope of work.
• Project plan aids the management in performing its
functions efficiently and effectively.
• Project plan identifies critical activities.
• Project plan provides the yard-stick for measuring
progress and evaluating resources performance.
Prof. Ashish Makwana 39
Benefits (Planning)…
• A project plan maintains continuity of work, specially
when project organisation is temporary and its
staffing is transient in nature.
• Project plans provide the basis of coordinating the
efforts of clients, consultants, architects, designers,
quantity surveyors, suppliers, contractors and the
project staff.
• Project plan creates healthy environment.
• It commits individuals to tasks and motivates them
to achieve challenging targets.
Prof. Ashish Makwana 40
Benefits (Scheduling)
• Schedule simplify a project plan.
• Schedule validates time objectives.
• Schedule aids in the optimization of resources
employed.
• Schedule enables forecasting of input resources like
man, materials and machinery.
• Schedule brings out implications of time and
resources constraints.
Prof. Ashish Makwana 41
Benefits (Controlling)
• The control system aids the management at various
levels to perform its functions efficiently and
effectively for achieving the overall project objectives.
Benefits (At each level of management for Controlling)
(a) Operational control at supervisory level
(b) Administrative control at managerial level
(c) Directional Control at General Manager (GM) /
Project Manager (PM) level
(d) Strategic control at corporate level
Prof. Ashish Makwana 42
Benefits (At each level of management for
Controlling)…
(a) Operational control at supervisory level
• Minimizing unproductive man hours
• Preventing wastage of materials
• Economizing plant and machinery utilization
• Reducing activity execution time
Prof. Ashish Makwana 43
(b) Administrative control at managerial level
• Updating the work quantities status and determining
the balance scope of work
• Analyzing project time status
• Evaluating production cost status and forecasting
future trends
• Calculating income status and forecasting cash
inflows
• Computing budget status and forecasting cash inflows
Prof. Ashish Makwana 44
(c) Directional Control at General Manager (GM) /
Project Manager (PM) level
• Analyzing project time – cost behaviour and making
decisions on time saving when required
• Reviewing project cost and profitability, and making
profitability improvement decisions
• Auditing management’s performance
(d) Strategic control at corporate level
• Determining overall profitability
• Budgeting and allocating funds and resources
• Updating the company’s planning norms and unit
rates for securing future works
Prof. Ashish Makwana 45
Construction Project Categories
• Building construction
• Infrastructure construction
• Industrial construction
• Special – purpose projects
Prof. Ashish Makwana 46
Building construction
• Residential buildings
• Commercial buildings
• Educational buildings
• Recreational buildings
• Hospitals and hotels
• Warehouse and marketing facilities
Prof. Ashish Makwana 47
Infrastructure construction
• Highways and expressways
• Dams and canals
• Airports
• Railways
• Bridges
• Oil / gas pipelines
• Large water supply and sewerage networks
• Docks and harbours
• Nuclear and thermal power plants
Prof. Ashish Makwana 48
Industrial construction
• Construction of steel plants
• Petroleum refineries
• Chemical and Fertilizer plants
• Consumer goods factories
• Automobile and aircraft industry
Prof. Ashish Makwana 49
Special – purpose projects
• Environmental works
• Emergencies
• Remedial works
• Installation and commissioning of equipment
Classification of projects based on completion time
• Large duration projects (over 10 years)
• Medium duration projects (3 to 10 years)
• Short duration projects (few months to 3 years)
• Special short term projects (less than 1 year)
Prof. Ashish Makwana 50
Classification of projects based on project value
• Mega value projects (say over $1000 million)
• Large value projects ($ 100 million to $ 1000 million)
• Medium value projects ($ 10 million to $ 100 million)
• Small value projects (less than $ 10 million)
Prof. Ashish Makwana 51
Classification of projects based on plant and
equipment
Light Construction
• Residential buildings
• Educational buildings
• Recreational buildings
• Commercial buildings
• Schools, hotels
• Small bridges, water tanks
• Shopping centers
Prof. Ashish Makwana 52
Classification of projects based on plant and
equipment…
Heavy Construction
• Dams, barrages, tunnels
• Highways, railways, airports
• Harbours
• Multispan bridges with well / pile foundations
Prof. Ashish Makwana 53
Resources for Construction Industry
• Man power
• Money
• Materials
• Machinery
Prof. Ashish Makwana 54
Resources for Construction Industry
• Man power – Man power in the form of technical and
managerial personnel and work force in various
trades is essential to carry out project activities.
• Money – Adequate funds should be available for
smooth implementation of the project.
• Materials – bricks, steel, stones, timber, aggregate,
scaffolding, cement, water supply and sanitary
fittings, lime, petrol, oil, lubricants
• Machinery – batching and mixing plants, Mixers,
crushers, Trucks, dumpers, tractors, Rollers, Powers,
Cranes, excavators, hoist, Pumps, generators
Prof. Ashish Makwana 55
Stakeholders of a Construction Project
(Construction Team)
• Owner
• Engineers / Architects
• Contractors
Prof. Ashish Makwana 56
Owner – The owner in a building or engineering project
may be an individual, group of individuals, private or
public undertaking.
Responsibilities of the owner
• The owner is supposed to provide necessary site on
which the proposed work is to be constructed.
• The owner should appoint an engineer, to look after
the technical requirements of the work.
• The owner should supply necessary plans and
working drawings through his architect to the
contractor in time so that the work is not
unnecessarily delayed.
Prof. Ashish Makwana 57
Responsibilities of the owner…
• The owner should respect the conditions of contract
concerning his powers and duties.
• The owner should provide necessary work front to
the contractor so that work is not delayed.
• The owner should make necessary arrangement for
the funds required for the construction of the work
so that regular payments shall be made to the
contractor.
• It is desirable that the owner should pass all the
instructions to the contractor through his engineer.
• The owner should supply materials and issue
machinery, if it is a part of the contract.
Prof. Ashish Makwana 58
Responsibilities of the owner…
• The owner should make arrangements to record the
measurement of items in time before they are
covered up in the subsequent execution of work.
• The owner should not interfere with the progress of
the work and should not pass such instructions which
will lead to the problems of extra items, liquidated
damages, etc.
• The owner should not suspend the work temporarily
unless it appears to be in his interest to do so.
• To take over possession of the completed work timely
from the contractor.
Prof. Ashish Makwana 59
Engineers and architects
• This includes structural, mechanical and
electrical engineers, architects, quantity
surveyors, specialists such as structural
consultants, safety and maintenance planners,
soil investigators etc.
Responsibility of engineer
• To organize and supervise the execution of work
and to see that they are suitably and
economically carried out with specified quality
of materials.
Prof. Ashish Makwana 60
Responsibility of engineer…
• It is the duty of the executive engineer to
prepare estimate of proposed works through his
subordinates and submit the same to his
superintending engineer.
• The engineer is responsible for explaining the
plans and provisions of the specifications.
• The engineer is responsible for giving all lines
and levels required in connection with the work.
• It is his duty to invite tenders for works valued
within his power, after obtaining administrative
and technical sanction.
Prof. Ashish Makwana 61
Responsibility of engineer…
• In certain complicated items, the engineer
should give the sequence of operations and
should explain method of construction in detail
to the contractor.
• It is duty of the engineer to prepare
specifications for the work and to see that these
specifications are accurate, proper and
reasonable for the work.
• The assistant engineer is responsible for taking
detailed measurement of works during progress
and to enter the same in M.B. and prepare bills
for payment. Prof. Ashish Makwana 62
Responsibility of engineer…
• To see that machinery likely to be used on works
are properly maintenance and safely house.
• To keep tools and plants in working conditions
and arrange to protect surplus stock from
deterioration.
• To prevent encroachment on government lands
under his division.
• The engineer is responsible for the acts of his
assistants or other agencies employed by him.
• It is also the duty of the engineer to assist the
court of law or the arbitrator during the hearing
of the dispute. Prof. Ashish Makwana 63
Contractor
• The contractor may be an individual undertaking
small or big need the services of qualified
engineers.
Responsibilities of the contractor
• The contractor is responsible to provide all the
materials, labour, equipments, etc. required
under the provisions of the contract for the
execution of the work.
• The contractor should carry out the work as per
plans and specifications and as per directions
given by the engineer.Prof. Ashish Makwana 64
Responsibilities of the contractor…
• The contractor should inform the supervising
engineer before taking up any new item and
before covering up of any work.
• The contractor should appoint a qualified
person on site of the work to whom instructions
and directions can be imparted.
• The contractor is responsible for any damage to
the persons or adjoining properties during
execution of the work.
• The contractor should submit the bills of work
as and when required.
Prof. Ashish Makwana 65
Responsibilities of the contractor…
• The contractor is responsible to respect all the
prevailing labour laws and should make regular
payments to his labourers as well as to the
subcontractors.
• The contractor should give all the required
assistance to the engineer for establishing the
lines and levels of the work.
• The contractor is responsible for arranging for
the permit of the controlled materials and for
paying fees and royalties for the use of patented
articles.
Prof. Ashish Makwana 66
Responsibilities of the contractor…
• The contractor is responsible for the safety of all
the labourers and personnel working at the site
and should provide safety shoes, helmets etc. to
the workmen.
• To handover the completed work in a sound
condition.
• The contractor should submit his claims for extra
items in due time.
Prof. Ashish Makwana 67
Interaction between Owner, Engineer and
Contractor
1. Co-relation between the Owner and an Engineer
• As the owner finances the project and employs an
engineer who agrees to perform his professional
duties with reasonable efforts and skill.
• If an engineer makes an unfortunate mistake, in
spite of due skill, he is not liable for his mistake
unless the owner proves that he failed to perform
his duty carefully.
• It is responsibility of the engineer to plan things
for the owner economically.
Prof. Ashish Makwana 68
2. Co-relation between an Engineer and Contractor
• There is much co-relation between an engineer
and a contractor as the latter executes the work in
strict supervision of the former.
• The contractor has to work as per the design and
drawing in consultation with the engineer to avoid
any dispute.
Prof. Ashish Makwana 69
Causes of delay in construction project
• Unexpected site conditions
• Difficulties in availability of materials
• Difficulties in availability of labours
• Weather conditions – heavy rain
• Delay in issue of construction drawings
• Lack of liaison between contractor and Engineer
• Delay in clarifying bills
• Cash flow and financial constraints
• Dispute between contractor and owner/engineer
Prof. Ashish Makwana 70
Engineer and Construction Economy
• To adopt such construction methods which would
result in the lowest practical cost of the project.
• Using as simple design as possible.
• Making use of locally available materials.
• Encouraging the use of materials of commercial
sizes.
• Making use of cost saving equipments and
adopting proper construction methods.
• Furnishing adequate foundation details, wherever
necessary.
Prof. Ashish Makwana 71
Engineer and Construction Economy…
• Using standard specifications with which the
contractor is familiar.
• Providing suitable checks on costs of labour,
materials, equipments, supervision charges, etc.
• Engaging supervisors who have sufficient
judgement and experience in construction.
• Providing necessary work front to the contractor
to avoid any delay in construction.
Prof. Ashish Makwana 72
Contractor and Construction Economy
• Prebidding studies of the project on the following
aspects will effect economy.
– Topography of the area
– Climate
– Sources of materials
– Geology
– Availability of labour
– Local services, power, fuel, water
– Access to the site
– Storage facilities for materials and equipments
Prof. Ashish Makwana 73
Contractor and Construction Economy
• By employing trained and experienced staff.
• Using alternate construction equipment having
higher capacity and efficiency but lower operating
cost.
• Maintaining the construction equipments in
proper working conditions.
• Maintaining an atmosphere of co-operation with
the labour force.
• Giving liberal incentives to the labour force for
greater output.
• Adopting reliable safety measures to reduce
accidents. Prof. Ashish Makwana 74
Contractor and Construction Economy…
• Holding periodic meeting with key personnel and
concerned design engineers to discuss plans,
procedures and results.
• To satisfy himself with a reasonable percentage of
profit.
• Appointing sub-contractors for the specialized
operations.
Prof. Ashish Makwana 75
THANK YOU
Prof. Ashish Makwana 76

More Related Content

What's hot

Tender
TenderTender
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
GAURAV. H .TANDON
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
akashpadole
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
Muhammad Aljalali
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
johnkirth1898
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
Namrata Agnihotri
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Simarpreet Singh
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
Nikhil Kumar
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
Simarpreet Singh
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
LIJI A
 
Construction management
Construction managementConstruction management
Construction management
Usama Khalid
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 

What's hot (20)

Tender
TenderTender
Tender
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 
Construction management
Construction managementConstruction management
Construction management
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Construction contract
Construction contract Construction contract
Construction contract
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 

Similar to Introduction-construction management_Construction Management (2180611) (Semester-8), Civil Engineering

Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
A Makwana
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
SiharaGallage
 
Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...
A Makwana
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
ShanthaNimalBandaraA
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
ShanthaNimalBandaraA
 
01Overview_2023.pdf overview of project management
01Overview_2023.pdf overview of project management01Overview_2023.pdf overview of project management
01Overview_2023.pdf overview of project management
FiifiMichael
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
emdad bhuiyan
 
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTIONCONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
praveenphalani
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
IJERA Editor
 
Internship presentation.pptx
Internship presentation.pptxInternship presentation.pptx
Internship presentation.pptx
YeMinThant4
 
Kriti ghai project ppt
Kriti ghai project pptKriti ghai project ppt
Kriti ghai project ppt
KritiGhai3
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptx
Jignesh patel
 
construction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptxconstruction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptx
BlackEagles1
 
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
A Makwana
 
module 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfmodule 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdf
keyurcha
 
Resume - Prakash Patil
Resume - Prakash PatilResume - Prakash Patil
Resume - Prakash PatilPrakash Patil
 
CEM unit -I ppt.pptx
CEM unit -I ppt.pptxCEM unit -I ppt.pptx
CEM unit -I ppt.pptx
latestnewsnews
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666
MilkiasMuse
 
Muhammad Hamid Bashir CV
Muhammad Hamid Bashir CVMuhammad Hamid Bashir CV
Muhammad Hamid Bashir CVHamid Bashir
 

Similar to Introduction-construction management_Construction Management (2180611) (Semester-8), Civil Engineering (20)

Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
 
Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
01Overview_2023.pdf overview of project management
01Overview_2023.pdf overview of project management01Overview_2023.pdf overview of project management
01Overview_2023.pdf overview of project management
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTIONCONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
CONSTRUCTION PROJECT MANAGEMENT - INTRODUCTION
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
 
Internship presentation.pptx
Internship presentation.pptxInternship presentation.pptx
Internship presentation.pptx
 
Kriti ghai project ppt
Kriti ghai project pptKriti ghai project ppt
Kriti ghai project ppt
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptx
 
construction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptxconstruction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptx
 
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
Scope management_Infrastructure Engineering and Management (2170611) (Semeste...
 
Appli. for the Const. Mngr
Appli. for the Const. MngrAppli. for the Const. Mngr
Appli. for the Const. Mngr
 
module 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfmodule 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdf
 
Resume - Prakash Patil
Resume - Prakash PatilResume - Prakash Patil
Resume - Prakash Patil
 
CEM unit -I ppt.pptx
CEM unit -I ppt.pptxCEM unit -I ppt.pptx
CEM unit -I ppt.pptx
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666
 
Muhammad Hamid Bashir CV
Muhammad Hamid Bashir CVMuhammad Hamid Bashir CV
Muhammad Hamid Bashir CV
 

More from A Makwana

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
A Makwana
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
A Makwana
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
A Makwana
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
A Makwana
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
A Makwana
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
A Makwana
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
A Makwana
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
A Makwana
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
A Makwana
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
A Makwana
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
A Makwana
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
A Makwana
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
A Makwana
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
A Makwana
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
A Makwana
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
A Makwana
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
A Makwana
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
A Makwana
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
A Makwana
 

More from A Makwana (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
 

Recently uploaded

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

Introduction-construction management_Construction Management (2180611) (Semester-8), Civil Engineering

  • 1. Prepared by Prof. Ashish Makwana Civil Engineering Dept. - MEFGI Prof. Ashish Makwana 1
  • 2. PRESENTATION OUTLINE… 1. Construction Project 2. Phases of a Construction Project 3. Importance of Construction and Construction Industry 4. Indian Construction Industry 5. Construction Management 6. Importance of Planning, Scheduling and Controlling Projects Prof. Ashish Makwana 2
  • 3. CONSTRUCTION PROJECT Project A Project is defined as a temporary endeavour undertaken to create a unique product/service/results. Product The product in case of a construction project is the constructed facility such as a building, a bridge, a highway, a dam, a canal, a factory etc. Prof. Ashish Makwana 3
  • 4. Construction projects Construction projects involve varying manpower and their duration can range from a few weeks to more than five years. Each construction project is ‘unique’ and ‘temporary’ in nature and so is the management involved. Prof. Ashish Makwana 4
  • 5. Construction projects Unique Features of a Construction Project One time activity A start and finish Complexity Involvement of several people on an adhoc basis Limited set of resources High cost A time frame for completion Prof. Ashish Makwana 5
  • 6. High risk of failure Difficulty in defining quality standards Sequencing of activities and phases No practice/rehearsals Uniqueness of people relationship Lack of experience of client/owner Feedback mechanism High level of subcontracting Uncertainty exists Prof. Ashish Makwana 6
  • 7. PHASES OF A CONSTRUCTION PROJECT Briefing stage Designing stage Tendering stage Construction stage Commissioning stage Prof. Ashish Makwana 7
  • 8. 1. Briefing stage • This stage is also called the ‘Report stage’. • It is the stage where ideas originated by individuals are studied with regard to cost and benefits so as to establish the economic viability/social utility of a project. Purpose • The purpose of the briefing stage is to enable the client to specify project functions and permissible costs. Prof. Ashish Makwana 8
  • 9. Activities (Briefing stage) • To appoint a project committee, if necessary. • To appoint a project manager who will have a continuing responsibility to the client through out the construction project. • To carry out technical and non-technical investigation so that alternative proposals may be given due consideration. • To study the various alternatives and identify the most feasible one. • To prepare the project report which is the outcome of the first stage. Prof. Ashish Makwana 9
  • 10. Feasibility report • Technical analysis • Economic analysis • Financial analysis • Ecological analysis Prof. Ashish Makwana 10
  • 11. 2. Designing stage • It is a very important stage in the field of construction because any modification of the project after this stage would prove expensive. • A realistic and detailed cost estimate of the project can be prepared during the design stage. Purpose • The purpose of this stage is to complete the project summary and determine the method of construction and estimated costs so as to obtain necessary approvals from the client. Prof. Ashish Makwana 11
  • 12. Activities (Designing stage) • To develop the project summary for the final adoption of the most suitable alternative. • To carry out technical investigations such as, – Soil investigation – Topographic investigation – Materials surveys – Market surveys • To prepare detailed design, working drawings, specifications, bill of quantities, final cost estimate and preliminary construction programme. Prof. Ashish Makwana 12
  • 13. 3. Tendering stage • During this stage tenders are invited and the contract is awarded at the best available terms agreed mutually between the owner’s team and the contractors. Purpose • The purpose of the tendering stage is to appoint a contractor who will undertake the construction work on the most suitable terms and conditions of quality, cost and completion time. Prof. Ashish Makwana 13
  • 14. Activities (Tendering stage) • To invite tenders from the contractors for the construction work and to award the contract. • Pre-qualification of contractors involves an investigation of the potential of contractor’s financial, managerial and physical resources, contractor’s experience of handling similar projects, etc. • To prepare contract documents, to be signed by the client and the contractor. • Holding a pre-bid conference and providing the necessary information. Prof. Ashish Makwana 14
  • 15. Activities (Tendering stage) • Negotiating contract price with qualified contractor. • Reviewing documents submitted by contractor. Prof. Ashish Makwana 15
  • 16. 4. Construction stage • The construction stage involves the execution of construction work as per the design, drawing and within agreed limits of time, cost and specified quality. Construction Planning Activities • Construction schedule • Manpower schedule • Material delivery schedule • Plant and equipment schedule Prof. Ashish Makwana 16
  • 17. Control of site operations Activities • Supply of materials and equipment • Supervision for quality control • Co-ordination among sub-contractors • Supervision for quality control • Supply of necessary drawings Prof. Ashish Makwana 17
  • 18. 5. Commissioning stage • It is the stage in which the performance of the structure is evaluated and the proposed nature of maintenance and repair are considered. Purpose • The purpose of this stage is to ensure that the construction work has been carried out as per the drawing and specifications and all the facilities developed function properly as envisaged in the design. Prof. Ashish Makwana 18
  • 19. Activities (Commissioning stage) • To keep various records of actual work. • To inspect the construction work thoroughly and have any defects rectifies. • To prepare operating instructions and maintenance manuals. • To carry out tests for performance, such as water tightness, strength etc. Prof. Ashish Makwana 19
  • 20. IMPORTANCE OF CONSTRUCTION AND CONSTRUCTION INDUSTRY • Construction is an important part of real estate and infrastructure such as: • Real estate – Residential – Industrial – Corporate – Commercial Prof. Ashish Makwana 20
  • 21. • Infrastructure – Roads – Railways – Urban infrastructure – Ports – Airports – Power • The importance of construction can be gauged from the fact that cost of construction of certain infrastructure projects may be as high as 60 to 80% of the total project cost. Prof. Ashish Makwana 21
  • 22. • Construction is recognized as the basic input for socio-economic development of a country. • Since construction industry is dependent on a number of industries, its growth in other industries as well. – Development of building materials industry – Development of construction equipments industry Prof. Ashish Makwana 22
  • 23. • Construction products such as buildings, bridges, roads, power plants have a long life as compared to the products of other industries. Prof. Ashish Makwana 23
  • 24. INDIAN CONSTRUCTION INDUSTRY Factors in favour of Indian construction industry • Availability of cheap labour • Availability of qualified professionals • Large number of construction companies • Actual shortage of housing • Boost from the government • Growth in industrial sector Prof. Ashish Makwana 24
  • 25. INDIAN CONSTRUCTION INDUSTRY (continued..) Factors against the Indian construction industry • Low productivity • Low ratio of skilled to unskilled workers • High cost of finance • Complicated tax structure • Presence of small contractors who lack financial and technology backup • Negligible investment in R & D • Competition from multinational companies Prof. Ashish Makwana 25
  • 26. Investment Opportunities in Construction in India • Construction development in residential, retail, commercial and hospitality sectors • Technology and solutions for smart sustainable cities • Technology for the promotion of low cost housing • Green building solutions • Smart cities • Sustainable and environmental friendly building materialsProf. Ashish Makwana 26
  • 27. • Training and Skill development of construction sector workers • Urban water supply, Sewage, Sewage treatment, Solid waste management Prof. Ashish Makwana 27
  • 28. CONSTRUCTION MANAGEMENT • Project Management is the art and science of mobilising and managing people, materials, equipment and money to complete the assigned project work on time, within budgeted costs and specified technical performance standards. • Construction Management may be defined as the management in which group of people of different categories works together, to execute the project economically without affecting the quality in a well planned and organised manner.Prof. Ashish Makwana 28
  • 29. Scope of Construction Management • Planning and estimating • Execution of works • Financial management • Material management • Equipment management • Labour management • Site layout • Equipments and Materials plant location • Labour relationships • Industrial psychology for smooth flow of work Prof. Ashish Makwana 29
  • 30. Need of Construction Management • Co-ordination between different agencies • Economy in Construction • Development of management and machinery • Speed of Construction • Quality Control of materials and workmanship Prof. Ashish Makwana 30
  • 31. Objectives of Construction Management • Completing the work within estimated budget. • Completing the work within specified time. • The Quality and workmanship should be better. • The work should be executed as per specification. • Providing safe and satisfactory working conditions for all personnel and workers. • Taking sound decisions at the lowest practical management level through delegation of authority. • Motivating people to give their best within their capacities. • Creating an organisation that works as a team. • Achieving economy in the construction.Prof. Ashish Makwana 31
  • 32. Phases / Functions of Construction Management • Planning and Scheduling • Organising • Staffing • Directing • Controlling • Co-ordinating • Communication Prof. Ashish Makwana 32
  • 33. Planning - Planning involves formulation of a number of alternative of realistic work plans for achieving specified objectives and finally selecting a plan which is best suited from the standpoint of available resources and constraints imposed upon the project. • Planning is the administrative process which translates the policy into a method of achieving the objectives. • How a project will be carried out? • What materials will be used? • What equipment and machineries will be utilized? • What men and staff will be employed? ‘What to do?’ and ‘How to do?’ Prof. Ashish Makwana 33
  • 34. Scheduling - Scheduling is the fitting of the final work plan to a time scale. It shows the duration and order of various construction activities. ‘When to do?’ • Time plan • Resources plan • Plan for controlling project • Schedule of design and drawing preparation • Work quantities • Progress of work planned • Resource allocations • Budget costs Prof. Ashish Makwana 34
  • 35. Organising – Organising is concerned with division of the total construction work into manageable sections and systematically arranging various operations by delegating specific tasks to individuals. Staffing – Organising involve the division of the project work into sections and staffing is the provision of people to fill the positions so created. • Staffing functions- Recruiting the right people, Arranging staff training courses, Carrying out proper staff assessment Prof. Ashish Makwana 35
  • 36. Directing – The directing function is concerned with training sub-ordinates to carry out assigned tasks, supervising their work and guiding their efforts. • The essence of directing lies in the ability to motivate people individually and as groups to utilize their creative efforts in achieving specified objectives. Controlling – Controlling is necessary for ensuring effective and efficient working. • It involves a constant review of the work plan to check on actual achievements and to discover and rectify deviations through appropriate corrective measures. Prof. Ashish Makwana 36
  • 37. Co-ordinating – This is a process where the framework of the organization is made to operate smoothly with the flow of information, decisions and results in every direction. Prof. Ashish Makwana 37
  • 38. Importance of Planning, Scheduling and Controlling projects Prof. Ashish Makwana 38
  • 39. Planning • Planning aims at formulation of a time based plan of action for co-ordinating various activities and resources to achieve specified objectives. • Planning is the process of developing the project plan. Benefits (Planning) • Project plan clearly defines project’s scope of work. • Project plan aids the management in performing its functions efficiently and effectively. • Project plan identifies critical activities. • Project plan provides the yard-stick for measuring progress and evaluating resources performance. Prof. Ashish Makwana 39
  • 40. Benefits (Planning)… • A project plan maintains continuity of work, specially when project organisation is temporary and its staffing is transient in nature. • Project plans provide the basis of coordinating the efforts of clients, consultants, architects, designers, quantity surveyors, suppliers, contractors and the project staff. • Project plan creates healthy environment. • It commits individuals to tasks and motivates them to achieve challenging targets. Prof. Ashish Makwana 40
  • 41. Benefits (Scheduling) • Schedule simplify a project plan. • Schedule validates time objectives. • Schedule aids in the optimization of resources employed. • Schedule enables forecasting of input resources like man, materials and machinery. • Schedule brings out implications of time and resources constraints. Prof. Ashish Makwana 41
  • 42. Benefits (Controlling) • The control system aids the management at various levels to perform its functions efficiently and effectively for achieving the overall project objectives. Benefits (At each level of management for Controlling) (a) Operational control at supervisory level (b) Administrative control at managerial level (c) Directional Control at General Manager (GM) / Project Manager (PM) level (d) Strategic control at corporate level Prof. Ashish Makwana 42
  • 43. Benefits (At each level of management for Controlling)… (a) Operational control at supervisory level • Minimizing unproductive man hours • Preventing wastage of materials • Economizing plant and machinery utilization • Reducing activity execution time Prof. Ashish Makwana 43
  • 44. (b) Administrative control at managerial level • Updating the work quantities status and determining the balance scope of work • Analyzing project time status • Evaluating production cost status and forecasting future trends • Calculating income status and forecasting cash inflows • Computing budget status and forecasting cash inflows Prof. Ashish Makwana 44
  • 45. (c) Directional Control at General Manager (GM) / Project Manager (PM) level • Analyzing project time – cost behaviour and making decisions on time saving when required • Reviewing project cost and profitability, and making profitability improvement decisions • Auditing management’s performance (d) Strategic control at corporate level • Determining overall profitability • Budgeting and allocating funds and resources • Updating the company’s planning norms and unit rates for securing future works Prof. Ashish Makwana 45
  • 46. Construction Project Categories • Building construction • Infrastructure construction • Industrial construction • Special – purpose projects Prof. Ashish Makwana 46
  • 47. Building construction • Residential buildings • Commercial buildings • Educational buildings • Recreational buildings • Hospitals and hotels • Warehouse and marketing facilities Prof. Ashish Makwana 47
  • 48. Infrastructure construction • Highways and expressways • Dams and canals • Airports • Railways • Bridges • Oil / gas pipelines • Large water supply and sewerage networks • Docks and harbours • Nuclear and thermal power plants Prof. Ashish Makwana 48
  • 49. Industrial construction • Construction of steel plants • Petroleum refineries • Chemical and Fertilizer plants • Consumer goods factories • Automobile and aircraft industry Prof. Ashish Makwana 49
  • 50. Special – purpose projects • Environmental works • Emergencies • Remedial works • Installation and commissioning of equipment Classification of projects based on completion time • Large duration projects (over 10 years) • Medium duration projects (3 to 10 years) • Short duration projects (few months to 3 years) • Special short term projects (less than 1 year) Prof. Ashish Makwana 50
  • 51. Classification of projects based on project value • Mega value projects (say over $1000 million) • Large value projects ($ 100 million to $ 1000 million) • Medium value projects ($ 10 million to $ 100 million) • Small value projects (less than $ 10 million) Prof. Ashish Makwana 51
  • 52. Classification of projects based on plant and equipment Light Construction • Residential buildings • Educational buildings • Recreational buildings • Commercial buildings • Schools, hotels • Small bridges, water tanks • Shopping centers Prof. Ashish Makwana 52
  • 53. Classification of projects based on plant and equipment… Heavy Construction • Dams, barrages, tunnels • Highways, railways, airports • Harbours • Multispan bridges with well / pile foundations Prof. Ashish Makwana 53
  • 54. Resources for Construction Industry • Man power • Money • Materials • Machinery Prof. Ashish Makwana 54
  • 55. Resources for Construction Industry • Man power – Man power in the form of technical and managerial personnel and work force in various trades is essential to carry out project activities. • Money – Adequate funds should be available for smooth implementation of the project. • Materials – bricks, steel, stones, timber, aggregate, scaffolding, cement, water supply and sanitary fittings, lime, petrol, oil, lubricants • Machinery – batching and mixing plants, Mixers, crushers, Trucks, dumpers, tractors, Rollers, Powers, Cranes, excavators, hoist, Pumps, generators Prof. Ashish Makwana 55
  • 56. Stakeholders of a Construction Project (Construction Team) • Owner • Engineers / Architects • Contractors Prof. Ashish Makwana 56
  • 57. Owner – The owner in a building or engineering project may be an individual, group of individuals, private or public undertaking. Responsibilities of the owner • The owner is supposed to provide necessary site on which the proposed work is to be constructed. • The owner should appoint an engineer, to look after the technical requirements of the work. • The owner should supply necessary plans and working drawings through his architect to the contractor in time so that the work is not unnecessarily delayed. Prof. Ashish Makwana 57
  • 58. Responsibilities of the owner… • The owner should respect the conditions of contract concerning his powers and duties. • The owner should provide necessary work front to the contractor so that work is not delayed. • The owner should make necessary arrangement for the funds required for the construction of the work so that regular payments shall be made to the contractor. • It is desirable that the owner should pass all the instructions to the contractor through his engineer. • The owner should supply materials and issue machinery, if it is a part of the contract. Prof. Ashish Makwana 58
  • 59. Responsibilities of the owner… • The owner should make arrangements to record the measurement of items in time before they are covered up in the subsequent execution of work. • The owner should not interfere with the progress of the work and should not pass such instructions which will lead to the problems of extra items, liquidated damages, etc. • The owner should not suspend the work temporarily unless it appears to be in his interest to do so. • To take over possession of the completed work timely from the contractor. Prof. Ashish Makwana 59
  • 60. Engineers and architects • This includes structural, mechanical and electrical engineers, architects, quantity surveyors, specialists such as structural consultants, safety and maintenance planners, soil investigators etc. Responsibility of engineer • To organize and supervise the execution of work and to see that they are suitably and economically carried out with specified quality of materials. Prof. Ashish Makwana 60
  • 61. Responsibility of engineer… • It is the duty of the executive engineer to prepare estimate of proposed works through his subordinates and submit the same to his superintending engineer. • The engineer is responsible for explaining the plans and provisions of the specifications. • The engineer is responsible for giving all lines and levels required in connection with the work. • It is his duty to invite tenders for works valued within his power, after obtaining administrative and technical sanction. Prof. Ashish Makwana 61
  • 62. Responsibility of engineer… • In certain complicated items, the engineer should give the sequence of operations and should explain method of construction in detail to the contractor. • It is duty of the engineer to prepare specifications for the work and to see that these specifications are accurate, proper and reasonable for the work. • The assistant engineer is responsible for taking detailed measurement of works during progress and to enter the same in M.B. and prepare bills for payment. Prof. Ashish Makwana 62
  • 63. Responsibility of engineer… • To see that machinery likely to be used on works are properly maintenance and safely house. • To keep tools and plants in working conditions and arrange to protect surplus stock from deterioration. • To prevent encroachment on government lands under his division. • The engineer is responsible for the acts of his assistants or other agencies employed by him. • It is also the duty of the engineer to assist the court of law or the arbitrator during the hearing of the dispute. Prof. Ashish Makwana 63
  • 64. Contractor • The contractor may be an individual undertaking small or big need the services of qualified engineers. Responsibilities of the contractor • The contractor is responsible to provide all the materials, labour, equipments, etc. required under the provisions of the contract for the execution of the work. • The contractor should carry out the work as per plans and specifications and as per directions given by the engineer.Prof. Ashish Makwana 64
  • 65. Responsibilities of the contractor… • The contractor should inform the supervising engineer before taking up any new item and before covering up of any work. • The contractor should appoint a qualified person on site of the work to whom instructions and directions can be imparted. • The contractor is responsible for any damage to the persons or adjoining properties during execution of the work. • The contractor should submit the bills of work as and when required. Prof. Ashish Makwana 65
  • 66. Responsibilities of the contractor… • The contractor is responsible to respect all the prevailing labour laws and should make regular payments to his labourers as well as to the subcontractors. • The contractor should give all the required assistance to the engineer for establishing the lines and levels of the work. • The contractor is responsible for arranging for the permit of the controlled materials and for paying fees and royalties for the use of patented articles. Prof. Ashish Makwana 66
  • 67. Responsibilities of the contractor… • The contractor is responsible for the safety of all the labourers and personnel working at the site and should provide safety shoes, helmets etc. to the workmen. • To handover the completed work in a sound condition. • The contractor should submit his claims for extra items in due time. Prof. Ashish Makwana 67
  • 68. Interaction between Owner, Engineer and Contractor 1. Co-relation between the Owner and an Engineer • As the owner finances the project and employs an engineer who agrees to perform his professional duties with reasonable efforts and skill. • If an engineer makes an unfortunate mistake, in spite of due skill, he is not liable for his mistake unless the owner proves that he failed to perform his duty carefully. • It is responsibility of the engineer to plan things for the owner economically. Prof. Ashish Makwana 68
  • 69. 2. Co-relation between an Engineer and Contractor • There is much co-relation between an engineer and a contractor as the latter executes the work in strict supervision of the former. • The contractor has to work as per the design and drawing in consultation with the engineer to avoid any dispute. Prof. Ashish Makwana 69
  • 70. Causes of delay in construction project • Unexpected site conditions • Difficulties in availability of materials • Difficulties in availability of labours • Weather conditions – heavy rain • Delay in issue of construction drawings • Lack of liaison between contractor and Engineer • Delay in clarifying bills • Cash flow and financial constraints • Dispute between contractor and owner/engineer Prof. Ashish Makwana 70
  • 71. Engineer and Construction Economy • To adopt such construction methods which would result in the lowest practical cost of the project. • Using as simple design as possible. • Making use of locally available materials. • Encouraging the use of materials of commercial sizes. • Making use of cost saving equipments and adopting proper construction methods. • Furnishing adequate foundation details, wherever necessary. Prof. Ashish Makwana 71
  • 72. Engineer and Construction Economy… • Using standard specifications with which the contractor is familiar. • Providing suitable checks on costs of labour, materials, equipments, supervision charges, etc. • Engaging supervisors who have sufficient judgement and experience in construction. • Providing necessary work front to the contractor to avoid any delay in construction. Prof. Ashish Makwana 72
  • 73. Contractor and Construction Economy • Prebidding studies of the project on the following aspects will effect economy. – Topography of the area – Climate – Sources of materials – Geology – Availability of labour – Local services, power, fuel, water – Access to the site – Storage facilities for materials and equipments Prof. Ashish Makwana 73
  • 74. Contractor and Construction Economy • By employing trained and experienced staff. • Using alternate construction equipment having higher capacity and efficiency but lower operating cost. • Maintaining the construction equipments in proper working conditions. • Maintaining an atmosphere of co-operation with the labour force. • Giving liberal incentives to the labour force for greater output. • Adopting reliable safety measures to reduce accidents. Prof. Ashish Makwana 74
  • 75. Contractor and Construction Economy… • Holding periodic meeting with key personnel and concerned design engineers to discuss plans, procedures and results. • To satisfy himself with a reasonable percentage of profit. • Appointing sub-contractors for the specialized operations. Prof. Ashish Makwana 75