SlideShare a Scribd company logo
22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
FACTORS CONTRIBUTING TO THE RISING
IMPORTANCE OF MODULAR CONSTRUCTION
ADOPTION A CASE STUDY
Ashish Makwana1
*, Mayur Vekariya2
, Dr. Jayeshkumar Pitroda3
1. Assistant Professor, Department of Civil Engineering, Marwadi Education Foundation,
Rajkot, India
2. Assistant Professor, Department of Civil Engineering, Pacific School of Engineering,
Surat, India
3. Assistant Professor, Department of Civil Engineering, Birla Vishvakarma Mahavidyalaya
Engineering College, Vallabh Vidyanagar, India
Email: *ashish.makwana123@yahoo.com
ABSTRACT
In recent times, the trend of modular construction adoption is increasing very fast due to
availability of latest tools and technology, efficient technical manpower and skilled labour
why mainly focus of this area is taken into
consideration through management approach with the help of Relative Importance Index
technique. Modular construction is one type of construction in which modular units are
produced in factory and then delivered to site and assembled as large volumetric
components. The modular units can be produced in any form; it may be service units such as
toilets, lifts, parts of rooms and complete rooms. The existing modular construction approach
is based on survey in Rajkot city. For survey work, Questionnaires is designed and distribute
to Consultants and Contractors. After data collection, rank has been given to the selected
factors of modular construction.
Keywords: Modular construction, Modular units, large volumetric components, Approach
I. INTRODUCTION
A. Modular Construction
Modular construction is a construction process to
produce a building component or modules with the
same design and standard in a manufacturing facility.
A mass production can be achieved then to be
transported and installed to become a building of its
choice.
Modular construction techniques are analogous to
assembly line car manufacturing and are readily
observable on numerous videos on the internet and
modular manufacturer web sites.
Typically, four stages make up a modular construction
project. First, design development by the developer
and plan approval by any regulating authorities;
second, assembly of module components in a factory;
third, transportation of modules to the project site; and
fourth, erection of modular units to form the building.
Modular contractors manufacture buildings at off-site
locations. They may also operate as general
contractors on projects, coordinating the delivery,
installation, site work and finish of the building or the
modular contractor will be responsible for
construction, delivery and installation of only the
modules and an overall general contractor will be
responsible for the entire project. Construction
primarily occurs indoors away from harsh weather
conditions preventing damage to building materials
and allowing builders to work in comfortable
conditions. [17]
B. Modular Coordination
Modular coordination is a concept of dimension and
space, in which building components are dimensioned
and positioned in a term of basic unit or module. The
full benefit of industrialization can be achieved only
by standardization. No effective standardization again
is possible in a building trade without dimensional
coordination. Dimensional coordination is possible if
the coordinating dimensions of all parts, as well as the
dimensions of the building to be erected are in
multiples of one basic dimensional unit - the basic
module. Such dimensional coordination is called
modular coordination. [7]

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
C. History [7]
Figure 1 Figure 2
In 1896, Modular
Construction was first
introduced in Malaysia
but had not been widely
implemented in the
Construction Industry.
Modular bricks and blocks
were introduced in 1983.
Figure 3
Figure 4
Actual sears & roebuck in
Circa 1910 in Portsmouth
Modular coordination
was first studied in
Singapore in the early
seventies. The Housing
and development board
implemented the
concept in 1973 in the
generation flats.
Factory built housing dates
backs to 1900s. Between
1908-1940 more than
75000 Sears s homes were
built. The prices of these
built houses is ranged from
$600 ( 38,436.00) to
$6000 ( 3,84368.00).
Figure 5 Figure 6
After world war II
wartime, factory
production was quickly
changed over to
providing consumer
products to a post war
time economy. Some of
these manufacturing
industries were
converted into the
housing industry.
The 1960s and early 1970s
saw an adaptation of the
manufactured process for
homes to create a
Figure 7 Figure 8
This was basically a site
built or stick built home
completed in two units
or more, transported to
the building site on flat
bed frames and erected
onto a permanent
foundation.
Designs of modular homes
moved from typical ranch
style to more complex and
grew substantially in the
1980s and 1990s.
D. Basics of Modular Coordination [7]
The main purpose of Modular Coordination is to
achieve the Dimensional Compatibility between the
Building Dimensions, Span or Spaces and the Size of
Components and Equipment by using related Modular
Dimensions.
Modular Coordination generally provides the easy
grasped layout of the positioning of the building
components in relation to each other and to the
building and facilitates collaboration between
planners, manufactures, distributors and contractors.
E. Principles of Modular Coordination [7]
 Basic Module
 Modular Dimension
 Planning Module
 Placing of Components
 Modular Grid
 Basic Modular Grid
 Square Grid
 Rectangular Grid
 Multi-Modular Planning Grid
 Preferred Dimensions
 Tolerance
1. Basic Module
The basic module is a fundamental unit of size in
modular coordination.
[1 basic module (M) = 100 mm]
Multi-module: multi-modules are selected in multiples
of the basic module. Different multi-modules will suit
particular application. Using multi-modules, it is
possible to achieve a substantial reduction in the
number of coordinating sizes.
2. Tolerance
Three types of tolerance are generally considered in
modular coordination in the building.

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
 Manufacturing tolerance, which limits the
dimensional deviation in the manufacture of
components.
 Positional tolerances, which limit the deviation of
position for erected components from their
designated position.
 Joint tolerances or gaps, which limit the
variations of joint thickness.
5 mm Rule This rule is applied to all structural parts
of building and components. The wall, slab and
elements which are the structural part of the vertical
and horizontal division are placed on joint proportion
on the boundaries of a modular plane that is the actual
dimension as a rule for the structural elements. This
rule is called as the 5 mm rule for all horizontal &
vertical dimensions.
If size of grid, n1 M x n2 M
Component size = (n1-10 mm) M x (n2 -10 mm) M
The 5 mm rule is given by IS code, it is due to
tolerance because tolerance is required to fit the
component into available grid space.
3. The Structural Grid
The recommended structural grid is 3M or multiples
of 1M. 3M is chosen as most material like the precast
floor slab is in multiple of this dimension. Structural
Grid is used to locate structural component such as a
beam and column.
4. Modular Grids
Plans, sections and elevation are expressed in two
dimensions. These are horizontal and vertical
projections of the modular space grid. Different grids
can be superimposed on the same plan and elevation
for different purpose. The advantage of using grids is
that they provide a continuous reference system in a
project.
5. Planning Grid
Planning Grid is based on any convenient modular
which is multiple for regulating space requirements
such as rooms.
6. Controlling Grid
Controlling Grid is based on any convenient modular
which is multiple for the location of the internal walls,
partition walls etc.
7. Basic Module Grid
This is the smallest planning grid used as a basis for
developing other grids. The basic modular grid is
shown only on a small scale drawing to show the
relationship between the components. Each square is
1M x 1M. These Drawings are in scale of 1:10 and
1:20. Figure 9 to 11 shows various basic modular
grids.
Figure 9
Basic Modular
Grid
Figure 10
Square
Multimodular
Grid
Figure 11
Rectangular
Multimodular
Source: http://www.bca.gov.sg/
8. Tartan Grid
Tartan grid is interrupted modular planning grids in
which the interval or bands of interruption are
regularly spaced in both directions. Figure 12 shows
the tartan grid.
This pattern may be used in very regular plans like
those with columns at constant intervals throughout
the floor. Figure 13 shows the grid for regular column
pattern.
Figure 12
Tartan Grid
Figure 13
Grid for Regular
Column Pattern
Source: http://www.bca.gov.sg/
9. Coordination of the Non-Modular Sizes
The full use of the modular coordination may not be
economical or possible. Sometimes in the components
like slab the thickness of the components may be non-
modular. Such thickness is determined by economic
and functional consideration. In such cases the
determination of sizes shall be based on multi-
modules and sub modules.
10. Reference System
The reference system is a system of points, line and
plane within which a building and its components are
located. A reference system should be used during the
design stage and also during the drawing stage
through which the measurements are taken on the site.
11. Modular Space Grid
The modular space grid is a three dimensional system
within which a building and its components laid. The
distance between each plane in the system is equal to
the basic module.
12. Dimensional Grids
The modular grid network defines the space into
which dimensionally coordinated components must
fit. An important factor is that the component must
always be undersized to allow for the joint which is
sized by the obtainable degree of tolerance and site
assembly.

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
13. Planning Approaches in Modular
Construction
The plan in the modular coordination consists of the
horizontal and vertical planning. There are two basic
approaches to planning in Modular construction is
shown in Figure 14 and symbols of Modular
construction is shown in Table I.
Axial planning Boundary planning
Figure 14
Types of Planning Approaches
[Source: IS 13613:1992 Recommendations for
modular coordination in building industry]
Table I
Symbols of Modular Construction
No Element Symbol
1. Modular Line
2. Modular Space
3. Modular Line (Planning)
4. Modular Reference Line
5.
Centre Line of walls,
Column and Beam
6.
Façade Corner
/ Wall surface
7. Dimension Line
8. Reference Plane
F. Advantages - Modular Construction
 Lightweight
 Easy workability
 Single product solution
 Easy transportation
 Thermal insulation
 Shorter project duration
 Sound insulation
 Modernizing the look with energy efficiency
 Zero waste
 Reliable schedule
 Fast construction work
 Faster return on investment
 Ability to service for remote locations
 Environmentally friendly construction
 Flexibility
G. Disadvantages - Modular Construction
 Limited customization
 Limited service area
 Zoning rules
H. Application of Modular Construction
 Hospital
 Industrial
 Cold Storage
 Single Family Homes
 Hotels, Motels and Restaurants
 Retail and Warehouses
 Auditorium and Theatres
 Education Institute s Construction
 Medical, Clinics and Offices
II. NEED OF STUDY
The study aims at finding the factors which affect the
rising importance of modular construction adoption in
Rajkot city by the perceptions of two different
stakeholders including the Consultants and
Contractors. The work aims at ranking the top 5
factors which most affect the rising importance of
Modular construction adoption.
III. OBJECTIVES OF STUDY
I. To identify the factors contributing to the
rising importance of Modular construction
adoption.
II. To rank the factors by RII (Relative
Importance Index) technique.
IV. LITERATURE REVIEW
E.M. Generalovaa, V.P. Generalova and A.A.
Kuznetsovaa[10]
explain that, the construction of
modular housing is analyzed from overseas nations.
The utilization of modular housing is cost efficient,
safe and ecofriendly. Modular Housing in Russia
based on 3D Reinforced concrete module blocks
which help to achieve quality of building life.
D. Lopeza and T.M. Froesea [12]
, the authors addressed
the research question, concluding that the modular
housing method is a little bit more cost effective than
the panelized construction method. It also provides a
workflow chart of the implications of both
construction methods and a discussion of the
compromise things when choosing the modular
housing method over the panelled method.
J. Molavi and D.L. Barral [11]
, suggested that modular
housing guaranties more control over the safety and
quality of materials. However, some other problems
such as design involvement and coordination of the
factory and plant activities may be easily eroded if an
appropriate procurement technique is not selected.
During precast concrete construction for that period of
time, it requires high skilled labour, complex design
and complex method. To include this managerial task

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
suggests a construction procurement method based on
the project type to achieve sustainable modular
construction.
The main aim of T.U. Ganiron and M. Almarwae [9]
,
was to give information about modular housing and it
is one of the affordable housing for living because it is
much cheaper than conventional housing.
M. Kamali and K. Hewage [13]
, aimed to assess the
factors associated with modular housing performance
throughout its life and also, to find out the comparison
of advantage and constraints from conventional
construction techniques. Consequently, such a
workflow can help the owner to choose the best
methods for the construction without environment
effect and also, to achieve the objective with a suitable
time period.
V. FACTORS
The various factors contributing to the rising
importance of Modular construction adoption are
determined by viewing various literatures.
From that 35 factors considered for this study are
1) Modular Construction on the Rise, 2) Technology,
3) Integrated Planning Approach, 4) Logistics and
Transportation Strategy, 5) Requires lesser time to
build, 6) Cost/schedule risk analysis, 7) Increases
savings, 8) Environmental Benefits, 9) Quicker return
on investment, 10) Increased cost-savings, 11) No
weather-related construction issues, 12) Solution for
difficult sites, 13) Limited site disruption, 14) Lesser
pollution, 15) Lesser waste, 16) Easier quality control,
17) Total delivered cost management, 18) Global
logistics process automation, 19) End-to-end
visibility, 20) Supplier portals, 21) Advance Ship
notice capability, 22) Total product identification and
regulatory compliance, 23) Dynamic routing, 24)
Variability management, 25) Integrated international
and domestic workflow, 26) Integrated Planning and
Execution Platform, 27) Financial supply chain
management, 28) Aspects of logistics planning, 29)
Implementing procurement plans and processes, 30)
Schedule for material and equipment and engineering
deliveries, 31) Integrating and resource loading and
leveling individual schedules, 32) Permits &
Approvals, 33) Site Development, 34) Plant
Fabrication, 35) Installation
VI. RESEARCH METHODOLOGY
Questionnaire was prepared by using above
considered factors for questionnaire survey. The
purpose of questionnaire survey is to gain response by
Consultants and Contractors for ranking the factors
which contributing to the rising importance of
Modular Construction adoption. The Relative
Importance Index (RII) technique is used to rank the
factors.
VII. DATA COLLECTION
First of all, the list of the stakeholders was generated
from local survey and internet through their websites
and accordingly questionnaires were distributed to
various stakeholders by going personally or through
email, personal interview and mail back techniques
where respondents had a clear opportunity to take part
or not; therefore, the voluntary participation in
research was ensured. The telephone number, e-mail
contacts and address of researcher were given in the
questionnaire for contact regarding any query as well
as for sending back the response. The questionnaire
was distributed to various stakeholders by informing
them regarding the purpose of the research and asking
them about their willingness to participate in the
research. Once the initial willingness was shown by
them, a questionnaire was given to them. Total 90
questionnaires were distributed to different
respondents in Rajkot city of Gujarat. They were sent
the reminder for sending their feedback after 7 to 15
days of sending the questionnaire. This study received
38 responses, so the response rate in this research is
62.29 %.
Figure 15
Number of respondents
To obtain a statistically representative sample of the
population, the formula shown in Eq. (1) was used
(Hogg and Tannis, 2009) [16]
... (1)
Where, n, m, and N = the sample size of the limited,
unlimited, and available population, respectively. M is
estimated by Eq. (2)
Where, z = the statistic value for the confidence level
used, i.e., 2.575, 1.96, and 1.645, for 99 %, 95 %, and
90 % confidence levels, respectively; p = the value of
the population proportion that is being estimated; and
the value of p is unknown, Sincich et al. (2002) [1]
suggest a conservative value of 0.50. By using a 90%

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
confidence level, i.e., 10 % significance level, the
unlimited sample size of the population, m is
approximated as follows
m = 67.65
Here, the confidence level is taken as 90 %.
The representative sample size of the population is
determined as shown below
n = 60.51 (say 61)
VIII. DATA ANALYSIS APPROACH
A. Relative Importance Index
Technique
Kometa et al. [15]
It is used determine the relative
importance of the rising importance of Modular
construction adoption. So, this method is adopted in
this study within various groups (i.e. Consultant and
Contractor). The six-point scale [1) No Impact, 2)
Very Low Impact, 3) Low Impact, 4) Moderate
Impact, 5) Moderate Impact, 6) Very high Impact] is
adopted and transformed to relative importance
indices (RII) for each factor as follows
.

... (3)
Where, W is the weightage given to each factor by the
respondents (ranging from 1 to 6), A is the highest
weight (i.e. 6 in this case), and N is the total number
of respondents. Higher the value of RII, more
important is the rising importance of Modular
construction adoption.
The RII was used to rank the different rising
importance of Modular construction adoption. These
rankings made it possible to cross-compare the
relative importance of the factors as perceived by the
two groups of respondents (Consultant and
all respondents should be used to assess the general
and overall rankings in order to give an overall picture
of the rising importance of Modular construction
adoption.
IX. RESULTS AND FINDINGS
As per selected approach,
contributing to the importance of Modular
construction adoption are mentioned in Table II, III &
IV
Table II
Ranking of factors as per C Response
Sr.
No.
Factors
Consultant
RII Rank
1.
Modular Construction on the
Rise
0.46032 30
2. Technology 0.42857 34
3.
Integrated Planning
Approach
0.42857 35
4.
Logistics and Transportation
Strategy
0.61111 6
5. Requires lesser time to build 0.57937 11
6. Cost/schedule risk analysis 0.44444 32
7. Increases savings 0.64286 3
8. Environmental Benefits 0.53175 19
9. Quicker return on investment 0.52381 21
10. Increased cost-savings 0.57937 12
11.
No weather-related
construction issues
0.53175 20
12. Solution for difficult sites 0.48413 28
13. Limited site disruption 0.52381 22
14. Lesser pollution 0.50000 24
15. Lesser waste material 0.53968 18
16. Easier quality control 0.58730 9
17.
Total delivered cost
management
0.57143 15
18.
Global logistics process
automation
0.66667 2
19. End-to-end visibility 0.50000 25
20. Supplier portals 0.64286 4
21.
Advance Ship notice
capability
0.50000 26
22.
Total product identification
and regulatory compliance
0.61905 5
23. Dynamic routing 0.54762 16
24. Variability management 0.46032 31
25.
Integrated international and
domestic workflow
0.48413 29
26.
Integrated Planning and
Execution Platform
0.57937 13
27.
Financial supply chain
management
0.44444 33
28. Aspects of logistics planning 0.69841 1
29.
Implementing procurement
plans and processes
0.58730 10
30.
Schedule for material and
equipment and engineering
deliveries
0.52381 23
31.
Integrating and resource
loading and levelling
individual schedules
0.54762 17
32. Permits & Approvals 0.61111 7
33. Site Development 0.59524 8
34. Plant Fabrication 0.57937 14
35. Installation 0.50000 27

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
Figure 19
Ranking of factors as per C Response
Table III
Ranking of factors as per C Response
Sr.
No.
Factors
Contractor
RII Rank
1.
Modular Construction on the
Rise
0.59804 7
2. Technology 0.49020 31
3.
Integrated Planning
Approach
0.38235 35
4.
Logistics and Transportation
Strategy
0.60784 4
5. Requires lesser time to build 0.44118 34
6. Cost/schedule risk analysis 0.55882 21
7. Increases savings 0.60784 5
8. Environmental Benefits 0.50000 29
9. Quicker return on investment 0.52941 25
10. Increased cost-savings 0.51961 27
11.
No weather-related
construction issues
0.58824 10
12. Solution for difficult sites 0.58824 11
13. Limited site disruption 0.57843 15
14. Lesser pollution 0.60784 6
15. Lesser waste material 0.56863 17
16. Easier quality control 0.52941 26
17.
Total delivered cost
management
0.55882 22
18.
Global logistics process
automation
0.56863 18
19. End-to-end visibility 0.55882 23
20. Supplier portals 0.58824 12
21.
Advance Ship notice
capability
0.58824 13
22.
Total product identification
and regulatory compliance
0.46078 33
23. Dynamic routing 0.61765 2
24. Variability management 0.61765 3
25.
Integrated international and
domestic workflow
0.54902 24
26.
Integrated Planning and
Execution Platform
0.65686 1
27.
Financial supply chain
management
0.49020 32
28. Aspects of logistics planning 0.56863 19
29.
Implementing procurement
plans and processes
0.59804 8
30.
Schedule for material and
equipment and engineering
deliveries
0.56863 20
31.
Integrating and resource
loading and levelling
individual schedules
0.59804 9
32. Permits & Approvals 0.50980 28
33. Site Development 0.57843 16
34. Plant Fabrication 0.58824 14
35. Installation 0.50000 30
30
34
35
6
11
32
3
19
21
12
20
28
22
24
18
9
15
2
25
4
26
5
16
31
29
13
33
1
10
23
17
7
8
14
27
Technology
Increases savings
Environmental Benefits
Increased cost-savings
Limited site disruption
Lesser pollution
Lesser waste material
Easier quality control
End-to-end visibility
Supplier portals
Dynamic routing
Variability management
Permits & Approvals
Site Development
Plant Fabrication
Installation

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
Figure 20
Ranking of factors as per
Table IV
Ranking of factors as per
Sr.
No.
Factors
Overall
RII Rank
1.
Modular Construction on the
Rise
0.52193 27
2. Technology 0.45614 34
3.
Integrated Planning
Approach
0.40789 35
4.
Logistics and Transportation
Strategy
0.60965 6
5. Requires lesser time to build 0.51754 28
6. Cost/schedule risk analysis 0.49561 32
7. Increases savings 0.62719 2
8. Environmental Benefits 0.51754 29
9. Quicker return on investment 0.52632 25
10. Increased cost-savings 0.55263 16
11.
No weather-related
construction issues
0.55702 15
12. Solution for difficult sites 0.53070 23
13. Limited site disruption 0.54825 18
14. Lesser pollution 0.54825 19
15. Lesser waste material 0.55263 17
16. Easier quality control 0.56140 14
17.
Total delivered cost
management
0.56579 12
18.
Global logistics process
automation
0.62281 3
19. End-to-end visibility 0.52632 26
20. Supplier portals 0.61842 4
21.
Advance Ship notice
capability
0.53947 22
22.
Total product identification
and regulatory compliance
0.54825 20
23. Dynamic routing 0.57895 10
24. Variability management 0.53070 24
25.
Integrated international and
domestic workflow
0.51316 30
26.
Integrated Planning and
Execution Platform
0.61404 5
27.
Financial supply chain
management
0.46491 33
28. Aspects of logistics planning 0.64035 1
29.
Implementing procurement
plans and processes
0.59211 7
30.
Schedule for material and
equipment and engineering
deliveries
0.54386 21
31.
Integrating and resource
loading and leveling
individual schedules
0.57018 11
32. Permits & Approvals 0.56579 13
33. Site Development 0.58772 8
34. Plant Fabrication 0.58333 9
35. Installation 0.50000 31
7
31
35
4
34
21
5
29
25
27
10
11
15
6
17
26
22
18
23
12
13
33
2
3
24
1
32
19
8
20
9
28
16
14
30
0 10 20 30 40
Technology
Increases savings
Increased cost-savings
Limited site disruption
Lesser pollution
Lesser waste material
Easier quality control
End-to-end visibility
Supplier portals
Dynamic routing
Permits & Approvals
Site Development
Plant Fabrication
Installation

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
Figure 21
Ranking of factors as per
Overall R Response
X. CONCLUSIONS
Total 35 Factors contributing to the rising importance
of Modular construction adoption were identified
through literature study & expert opinion. As per
population of stakeholder in Rajkot city, total 61
numbers of respondents were required. The response
rate is 62%. Respondents were comprised of 21
consultants and 17 contractors. The collected data
were analyzed through Relative Importance Index
technique. The major conclusions of top five factors
are mentioned below.
As per RII technique, top five factors contributing to
the rising importance of Modular construction
adoption, according (refer
Figure 16)
1. Aspects of logistics planning
2. Global logistics process automation
3. Increases savings
4. Supplier portals
5. Total product identification and regulatory
compliance
Figure 16
Top F as per to C
Response
As per RII technique, top five factors contributing to
the rising importance of Modular construction
adoption, according to
Figure 17)
1. Integrated Planning and Execution Platform
2. Dynamic routing
3. Variability management
4. Logistics and Transportation Strategy
5. Increases savings
Figure 17
Top F C
Response
27
34
35
6
28
32
2
29
25
16
15
23
18
19
17
14
12
3
26
4
22
20
10
24
30
5
33
1
7
21
11
13
8
9
31
0 10 20 30 40
Technology
Increases savings
Increased cost-savings
Limited site disruption
Lesser pollution
Lesser waste material
Easier quality control
End-to-end visibility
Supplier portals
Dynamic routing
Permits & Approvals
Site Development
Plant Fabrication
Installation

22nd
Environmental Development on 30th
December, 2017 at A D Patel Institute of Technology, Karamsad
As per RII technique, top five factors contributing to
the rising importance of Modular construction
adoption, according
(refer Figure 18)
1. Aspects of logistics planning
2. Increases savings
3. Global logistics process automation
4. Supplier portals
5. Integrated Planning and Execution Platform
Figure 18
Top F Overall
R Response
XI. SUGGESTION
Regarding future research, selective study of factors
contributing to the Rising importance of Modular
Construction Adoption would be worthwhile by the
application of Multi Criteria Decision Making
techniques for better educate future scholar with
necessary skills to navigate issues.
REFERENCES
[1]
Statistics by Example using Microsoft Excel and
nd Ed., Prentice Hall, Upper Saddle River,
NJ, 2002.
[2] B. M. Kataria, A. S. Patel, Dr. N. D. Sharma, B. K.
of Fly Ash Brick: A Case Study
of Surat & Tapi District o
International Journal of Innovative Research In
Science, Engineering and Technology, ISSN: 2319-
8753, Vol. 2, Issue 11, Pp.6553-6558, November-2013.
[3] of Delay in
Residential Construction Projects: Case Study of
Central Gujarat Region o
of Engineering Trends and Technology (IJETT), ISSN:
2231-5381, Volume-4, Issue-4, Pp.762-768, April-
2013.
[4] M. Rajgor, P. Chauhan, D. Patel, C. Panchal, D.
e Techniques for
Finding Delay i
Research Journal of Engineering and Technology
(IRJET), E-ISSN: 2395 -0056, P-ISSN: 2395-0072,
Volume: 03, Issue: 01, Pp.1173-1177, Jan-2016.
[5] cated
Technology i
Journal of Advanced Science and Technology, ISSN:
2005-4238, Vol.73, Pp.51-74, 2014.
[6]
System-How t
International Conference on Adaptable Building
Structures, Pp.1-6, Eindhoven The Netherlands 03-05
July 2006.
[7] S. Farhana, J. Pitroda, J. J. Bhavsar, Dr. S. K. Dave,
in
Engineering: Issues, Opportunities and Challenges for
Development, ISBN: 978-81-929339-1-7, S.N. Patel
Institute of Technology & Research Centre, Umrakh,
Bardoli, 11th
April, 2015.
[8] R.I. Khurana, Dr. N. D. Sharma, R. A. Shah,
of Modular Housing Technique in Surat
of Emerging Technologies and
Innovative Research (JETIR), ISSN-2349-5162,
Volume: 4, Issue: 06, June 2017.
[9]
Technology i
Journal of Advanced Science and Technology, Vol.73,
Pp.51-74, 2014.
[10]E. M. Generalova, V. P. Generalova, A. A.
in Modern
Russian Slovak
Seminar Theoretical Foundation of Civil Engineering,
Procedia Engineering, 167 172, 2016.
[11]J. Molavi
Method to Achieve Sustainability In Modular
Construction, International Conference on Sustainable
Engineering, 1362 1369, 2016.
[12] of Costs and
Benefits of Panelized and Modular Prefabricated
on Sustainable
Design, Engineering and Construction, Procedia
Engineering, 1291 1297, 2016.
[13] of
Modular Buildings: A Critical Review, Renewable and
1183, 2016.
[14]
th
ASC
Annual International Conference Proceedings, 2014.
[15]Kom of
UK Construction Clients Influencing Project
1994;12:433 43.
[16] and Statistical
th
Ed., Prentice Hall, Upper Saddle River,
NJ, 2009.
[17] and Challenges of
Modular Construction in High Rise Development in
Massachusetts Institute Of Technology, September,
2012.
[18]Alrogan, R. M. Lawson, N. Bates- and
Benefits Assessment o
Steel Construction Institute, Silwood Park, Ascot,
Berkshire SL5 7QN.
[19]http://www.accerajkot.com/
[20] http://www.rnbgujarat.org/contractors/contractorlist.asp
x


More Related Content

Similar to FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTION A CASE STUDY

B.Arch Dissertation Design in modules
B.Arch Dissertation Design in modulesB.Arch Dissertation Design in modules
B.Arch Dissertation Design in modules
07206771966
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
Shubham Jain
 
Modular cordination
Modular cordinationModular cordination
Modular cordination
Shivangi Saini
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
Atul Verma
 
Design Principles
Design PrinciplesDesign Principles
Design Principles
Nishma2
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A Review
IRJET Journal
 
Pragati towers
Pragati towersPragati towers
Pragati towers
Rajat Nainwal
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
VEMANA INSTITUTE OF TECHNOLOGY, VTU
 
5 modular const.pptx
5 modular const.pptx5 modular const.pptx
5 modular const.pptx
sonu515144
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET Journal
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report
AbhishekM45
 
PEB 2-5.pptx
PEB 2-5.pptxPEB 2-5.pptx
PEB 2-5.pptx
sonu515144
 
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
IAEME Publication
 
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
IRJET Journal
 
Seminar on Robotics in Construction
Seminar on Robotics in ConstructionSeminar on Robotics in Construction
Seminar on Robotics in Construction
UNIVERSAL ENGINEERING COLLEGE
 
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURECOMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
AM Publications
 
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
IRJET Journal
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
Construction Tech. and Mgmt., VNIT Nagpur
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKSameer Malvankar
 

Similar to FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTION A CASE STUDY (20)

B.Arch Dissertation Design in modules
B.Arch Dissertation Design in modulesB.Arch Dissertation Design in modules
B.Arch Dissertation Design in modules
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
Modular cordination
Modular cordinationModular cordination
Modular cordination
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
Design Principles
Design PrinciplesDesign Principles
Design Principles
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A Review
 
Pragati towers
Pragati towersPragati towers
Pragati towers
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
5 modular const.pptx
5 modular const.pptx5 modular const.pptx
5 modular const.pptx
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report
 
PEB 2-5.pptx
PEB 2-5.pptxPEB 2-5.pptx
PEB 2-5.pptx
 
Seminar on modular building
Seminar on modular buildingSeminar on modular building
Seminar on modular building
 
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
 
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”IRJET-  	  Methodology of 3S Construction Method “Prefabrication Technology”
IRJET- Methodology of 3S Construction Method “Prefabrication Technology”
 
Seminar on Robotics in Construction
Seminar on Robotics in ConstructionSeminar on Robotics in Construction
Seminar on Robotics in Construction
 
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURECOMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
COMPARATIVE ANALYSIS WITH CONCREWALL & BRICKWALL STRUCTURE
 
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
IRJET- Performance of High Rise Building under Seismic and Wind Excitation fo...
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
 

More from A Makwana

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
A Makwana
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
A Makwana
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
A Makwana
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
A Makwana
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
A Makwana
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
A Makwana
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
A Makwana
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
A Makwana
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
A Makwana
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
A Makwana
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
A Makwana
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
A Makwana
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
A Makwana
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
A Makwana
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
A Makwana
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
A Makwana
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
A Makwana
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
A Makwana
 
Bricks Selection through Management Approach by AHP, RII, IMP.I.
Bricks Selection through Management Approach by AHP, RII, IMP.I.Bricks Selection through Management Approach by AHP, RII, IMP.I.
Bricks Selection through Management Approach by AHP, RII, IMP.I.
A Makwana
 

More from A Makwana (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
 
Bricks Selection through Management Approach by AHP, RII, IMP.I.
Bricks Selection through Management Approach by AHP, RII, IMP.I.Bricks Selection through Management Approach by AHP, RII, IMP.I.
Bricks Selection through Management Approach by AHP, RII, IMP.I.
 

Recently uploaded

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTION A CASE STUDY

  • 1. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTION A CASE STUDY Ashish Makwana1 *, Mayur Vekariya2 , Dr. Jayeshkumar Pitroda3 1. Assistant Professor, Department of Civil Engineering, Marwadi Education Foundation, Rajkot, India 2. Assistant Professor, Department of Civil Engineering, Pacific School of Engineering, Surat, India 3. Assistant Professor, Department of Civil Engineering, Birla Vishvakarma Mahavidyalaya Engineering College, Vallabh Vidyanagar, India Email: *ashish.makwana123@yahoo.com ABSTRACT In recent times, the trend of modular construction adoption is increasing very fast due to availability of latest tools and technology, efficient technical manpower and skilled labour why mainly focus of this area is taken into consideration through management approach with the help of Relative Importance Index technique. Modular construction is one type of construction in which modular units are produced in factory and then delivered to site and assembled as large volumetric components. The modular units can be produced in any form; it may be service units such as toilets, lifts, parts of rooms and complete rooms. The existing modular construction approach is based on survey in Rajkot city. For survey work, Questionnaires is designed and distribute to Consultants and Contractors. After data collection, rank has been given to the selected factors of modular construction. Keywords: Modular construction, Modular units, large volumetric components, Approach I. INTRODUCTION A. Modular Construction Modular construction is a construction process to produce a building component or modules with the same design and standard in a manufacturing facility. A mass production can be achieved then to be transported and installed to become a building of its choice. Modular construction techniques are analogous to assembly line car manufacturing and are readily observable on numerous videos on the internet and modular manufacturer web sites. Typically, four stages make up a modular construction project. First, design development by the developer and plan approval by any regulating authorities; second, assembly of module components in a factory; third, transportation of modules to the project site; and fourth, erection of modular units to form the building. Modular contractors manufacture buildings at off-site locations. They may also operate as general contractors on projects, coordinating the delivery, installation, site work and finish of the building or the modular contractor will be responsible for construction, delivery and installation of only the modules and an overall general contractor will be responsible for the entire project. Construction primarily occurs indoors away from harsh weather conditions preventing damage to building materials and allowing builders to work in comfortable conditions. [17] B. Modular Coordination Modular coordination is a concept of dimension and space, in which building components are dimensioned and positioned in a term of basic unit or module. The full benefit of industrialization can be achieved only by standardization. No effective standardization again is possible in a building trade without dimensional coordination. Dimensional coordination is possible if the coordinating dimensions of all parts, as well as the dimensions of the building to be erected are in multiples of one basic dimensional unit - the basic module. Such dimensional coordination is called modular coordination. [7] 
  • 2. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad C. History [7] Figure 1 Figure 2 In 1896, Modular Construction was first introduced in Malaysia but had not been widely implemented in the Construction Industry. Modular bricks and blocks were introduced in 1983. Figure 3 Figure 4 Actual sears & roebuck in Circa 1910 in Portsmouth Modular coordination was first studied in Singapore in the early seventies. The Housing and development board implemented the concept in 1973 in the generation flats. Factory built housing dates backs to 1900s. Between 1908-1940 more than 75000 Sears s homes were built. The prices of these built houses is ranged from $600 ( 38,436.00) to $6000 ( 3,84368.00). Figure 5 Figure 6 After world war II wartime, factory production was quickly changed over to providing consumer products to a post war time economy. Some of these manufacturing industries were converted into the housing industry. The 1960s and early 1970s saw an adaptation of the manufactured process for homes to create a Figure 7 Figure 8 This was basically a site built or stick built home completed in two units or more, transported to the building site on flat bed frames and erected onto a permanent foundation. Designs of modular homes moved from typical ranch style to more complex and grew substantially in the 1980s and 1990s. D. Basics of Modular Coordination [7] The main purpose of Modular Coordination is to achieve the Dimensional Compatibility between the Building Dimensions, Span or Spaces and the Size of Components and Equipment by using related Modular Dimensions. Modular Coordination generally provides the easy grasped layout of the positioning of the building components in relation to each other and to the building and facilitates collaboration between planners, manufactures, distributors and contractors. E. Principles of Modular Coordination [7]  Basic Module  Modular Dimension  Planning Module  Placing of Components  Modular Grid  Basic Modular Grid  Square Grid  Rectangular Grid  Multi-Modular Planning Grid  Preferred Dimensions  Tolerance 1. Basic Module The basic module is a fundamental unit of size in modular coordination. [1 basic module (M) = 100 mm] Multi-module: multi-modules are selected in multiples of the basic module. Different multi-modules will suit particular application. Using multi-modules, it is possible to achieve a substantial reduction in the number of coordinating sizes. 2. Tolerance Three types of tolerance are generally considered in modular coordination in the building. 
  • 3. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad  Manufacturing tolerance, which limits the dimensional deviation in the manufacture of components.  Positional tolerances, which limit the deviation of position for erected components from their designated position.  Joint tolerances or gaps, which limit the variations of joint thickness. 5 mm Rule This rule is applied to all structural parts of building and components. The wall, slab and elements which are the structural part of the vertical and horizontal division are placed on joint proportion on the boundaries of a modular plane that is the actual dimension as a rule for the structural elements. This rule is called as the 5 mm rule for all horizontal & vertical dimensions. If size of grid, n1 M x n2 M Component size = (n1-10 mm) M x (n2 -10 mm) M The 5 mm rule is given by IS code, it is due to tolerance because tolerance is required to fit the component into available grid space. 3. The Structural Grid The recommended structural grid is 3M or multiples of 1M. 3M is chosen as most material like the precast floor slab is in multiple of this dimension. Structural Grid is used to locate structural component such as a beam and column. 4. Modular Grids Plans, sections and elevation are expressed in two dimensions. These are horizontal and vertical projections of the modular space grid. Different grids can be superimposed on the same plan and elevation for different purpose. The advantage of using grids is that they provide a continuous reference system in a project. 5. Planning Grid Planning Grid is based on any convenient modular which is multiple for regulating space requirements such as rooms. 6. Controlling Grid Controlling Grid is based on any convenient modular which is multiple for the location of the internal walls, partition walls etc. 7. Basic Module Grid This is the smallest planning grid used as a basis for developing other grids. The basic modular grid is shown only on a small scale drawing to show the relationship between the components. Each square is 1M x 1M. These Drawings are in scale of 1:10 and 1:20. Figure 9 to 11 shows various basic modular grids. Figure 9 Basic Modular Grid Figure 10 Square Multimodular Grid Figure 11 Rectangular Multimodular Source: http://www.bca.gov.sg/ 8. Tartan Grid Tartan grid is interrupted modular planning grids in which the interval or bands of interruption are regularly spaced in both directions. Figure 12 shows the tartan grid. This pattern may be used in very regular plans like those with columns at constant intervals throughout the floor. Figure 13 shows the grid for regular column pattern. Figure 12 Tartan Grid Figure 13 Grid for Regular Column Pattern Source: http://www.bca.gov.sg/ 9. Coordination of the Non-Modular Sizes The full use of the modular coordination may not be economical or possible. Sometimes in the components like slab the thickness of the components may be non- modular. Such thickness is determined by economic and functional consideration. In such cases the determination of sizes shall be based on multi- modules and sub modules. 10. Reference System The reference system is a system of points, line and plane within which a building and its components are located. A reference system should be used during the design stage and also during the drawing stage through which the measurements are taken on the site. 11. Modular Space Grid The modular space grid is a three dimensional system within which a building and its components laid. The distance between each plane in the system is equal to the basic module. 12. Dimensional Grids The modular grid network defines the space into which dimensionally coordinated components must fit. An important factor is that the component must always be undersized to allow for the joint which is sized by the obtainable degree of tolerance and site assembly. 
  • 4. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad 13. Planning Approaches in Modular Construction The plan in the modular coordination consists of the horizontal and vertical planning. There are two basic approaches to planning in Modular construction is shown in Figure 14 and symbols of Modular construction is shown in Table I. Axial planning Boundary planning Figure 14 Types of Planning Approaches [Source: IS 13613:1992 Recommendations for modular coordination in building industry] Table I Symbols of Modular Construction No Element Symbol 1. Modular Line 2. Modular Space 3. Modular Line (Planning) 4. Modular Reference Line 5. Centre Line of walls, Column and Beam 6. Façade Corner / Wall surface 7. Dimension Line 8. Reference Plane F. Advantages - Modular Construction  Lightweight  Easy workability  Single product solution  Easy transportation  Thermal insulation  Shorter project duration  Sound insulation  Modernizing the look with energy efficiency  Zero waste  Reliable schedule  Fast construction work  Faster return on investment  Ability to service for remote locations  Environmentally friendly construction  Flexibility G. Disadvantages - Modular Construction  Limited customization  Limited service area  Zoning rules H. Application of Modular Construction  Hospital  Industrial  Cold Storage  Single Family Homes  Hotels, Motels and Restaurants  Retail and Warehouses  Auditorium and Theatres  Education Institute s Construction  Medical, Clinics and Offices II. NEED OF STUDY The study aims at finding the factors which affect the rising importance of modular construction adoption in Rajkot city by the perceptions of two different stakeholders including the Consultants and Contractors. The work aims at ranking the top 5 factors which most affect the rising importance of Modular construction adoption. III. OBJECTIVES OF STUDY I. To identify the factors contributing to the rising importance of Modular construction adoption. II. To rank the factors by RII (Relative Importance Index) technique. IV. LITERATURE REVIEW E.M. Generalovaa, V.P. Generalova and A.A. Kuznetsovaa[10] explain that, the construction of modular housing is analyzed from overseas nations. The utilization of modular housing is cost efficient, safe and ecofriendly. Modular Housing in Russia based on 3D Reinforced concrete module blocks which help to achieve quality of building life. D. Lopeza and T.M. Froesea [12] , the authors addressed the research question, concluding that the modular housing method is a little bit more cost effective than the panelized construction method. It also provides a workflow chart of the implications of both construction methods and a discussion of the compromise things when choosing the modular housing method over the panelled method. J. Molavi and D.L. Barral [11] , suggested that modular housing guaranties more control over the safety and quality of materials. However, some other problems such as design involvement and coordination of the factory and plant activities may be easily eroded if an appropriate procurement technique is not selected. During precast concrete construction for that period of time, it requires high skilled labour, complex design and complex method. To include this managerial task 
  • 5. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad suggests a construction procurement method based on the project type to achieve sustainable modular construction. The main aim of T.U. Ganiron and M. Almarwae [9] , was to give information about modular housing and it is one of the affordable housing for living because it is much cheaper than conventional housing. M. Kamali and K. Hewage [13] , aimed to assess the factors associated with modular housing performance throughout its life and also, to find out the comparison of advantage and constraints from conventional construction techniques. Consequently, such a workflow can help the owner to choose the best methods for the construction without environment effect and also, to achieve the objective with a suitable time period. V. FACTORS The various factors contributing to the rising importance of Modular construction adoption are determined by viewing various literatures. From that 35 factors considered for this study are 1) Modular Construction on the Rise, 2) Technology, 3) Integrated Planning Approach, 4) Logistics and Transportation Strategy, 5) Requires lesser time to build, 6) Cost/schedule risk analysis, 7) Increases savings, 8) Environmental Benefits, 9) Quicker return on investment, 10) Increased cost-savings, 11) No weather-related construction issues, 12) Solution for difficult sites, 13) Limited site disruption, 14) Lesser pollution, 15) Lesser waste, 16) Easier quality control, 17) Total delivered cost management, 18) Global logistics process automation, 19) End-to-end visibility, 20) Supplier portals, 21) Advance Ship notice capability, 22) Total product identification and regulatory compliance, 23) Dynamic routing, 24) Variability management, 25) Integrated international and domestic workflow, 26) Integrated Planning and Execution Platform, 27) Financial supply chain management, 28) Aspects of logistics planning, 29) Implementing procurement plans and processes, 30) Schedule for material and equipment and engineering deliveries, 31) Integrating and resource loading and leveling individual schedules, 32) Permits & Approvals, 33) Site Development, 34) Plant Fabrication, 35) Installation VI. RESEARCH METHODOLOGY Questionnaire was prepared by using above considered factors for questionnaire survey. The purpose of questionnaire survey is to gain response by Consultants and Contractors for ranking the factors which contributing to the rising importance of Modular Construction adoption. The Relative Importance Index (RII) technique is used to rank the factors. VII. DATA COLLECTION First of all, the list of the stakeholders was generated from local survey and internet through their websites and accordingly questionnaires were distributed to various stakeholders by going personally or through email, personal interview and mail back techniques where respondents had a clear opportunity to take part or not; therefore, the voluntary participation in research was ensured. The telephone number, e-mail contacts and address of researcher were given in the questionnaire for contact regarding any query as well as for sending back the response. The questionnaire was distributed to various stakeholders by informing them regarding the purpose of the research and asking them about their willingness to participate in the research. Once the initial willingness was shown by them, a questionnaire was given to them. Total 90 questionnaires were distributed to different respondents in Rajkot city of Gujarat. They were sent the reminder for sending their feedback after 7 to 15 days of sending the questionnaire. This study received 38 responses, so the response rate in this research is 62.29 %. Figure 15 Number of respondents To obtain a statistically representative sample of the population, the formula shown in Eq. (1) was used (Hogg and Tannis, 2009) [16] ... (1) Where, n, m, and N = the sample size of the limited, unlimited, and available population, respectively. M is estimated by Eq. (2) Where, z = the statistic value for the confidence level used, i.e., 2.575, 1.96, and 1.645, for 99 %, 95 %, and 90 % confidence levels, respectively; p = the value of the population proportion that is being estimated; and the value of p is unknown, Sincich et al. (2002) [1] suggest a conservative value of 0.50. By using a 90% 
  • 6. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad confidence level, i.e., 10 % significance level, the unlimited sample size of the population, m is approximated as follows m = 67.65 Here, the confidence level is taken as 90 %. The representative sample size of the population is determined as shown below n = 60.51 (say 61) VIII. DATA ANALYSIS APPROACH A. Relative Importance Index Technique Kometa et al. [15] It is used determine the relative importance of the rising importance of Modular construction adoption. So, this method is adopted in this study within various groups (i.e. Consultant and Contractor). The six-point scale [1) No Impact, 2) Very Low Impact, 3) Low Impact, 4) Moderate Impact, 5) Moderate Impact, 6) Very high Impact] is adopted and transformed to relative importance indices (RII) for each factor as follows .  ... (3) Where, W is the weightage given to each factor by the respondents (ranging from 1 to 6), A is the highest weight (i.e. 6 in this case), and N is the total number of respondents. Higher the value of RII, more important is the rising importance of Modular construction adoption. The RII was used to rank the different rising importance of Modular construction adoption. These rankings made it possible to cross-compare the relative importance of the factors as perceived by the two groups of respondents (Consultant and all respondents should be used to assess the general and overall rankings in order to give an overall picture of the rising importance of Modular construction adoption. IX. RESULTS AND FINDINGS As per selected approach, contributing to the importance of Modular construction adoption are mentioned in Table II, III & IV Table II Ranking of factors as per C Response Sr. No. Factors Consultant RII Rank 1. Modular Construction on the Rise 0.46032 30 2. Technology 0.42857 34 3. Integrated Planning Approach 0.42857 35 4. Logistics and Transportation Strategy 0.61111 6 5. Requires lesser time to build 0.57937 11 6. Cost/schedule risk analysis 0.44444 32 7. Increases savings 0.64286 3 8. Environmental Benefits 0.53175 19 9. Quicker return on investment 0.52381 21 10. Increased cost-savings 0.57937 12 11. No weather-related construction issues 0.53175 20 12. Solution for difficult sites 0.48413 28 13. Limited site disruption 0.52381 22 14. Lesser pollution 0.50000 24 15. Lesser waste material 0.53968 18 16. Easier quality control 0.58730 9 17. Total delivered cost management 0.57143 15 18. Global logistics process automation 0.66667 2 19. End-to-end visibility 0.50000 25 20. Supplier portals 0.64286 4 21. Advance Ship notice capability 0.50000 26 22. Total product identification and regulatory compliance 0.61905 5 23. Dynamic routing 0.54762 16 24. Variability management 0.46032 31 25. Integrated international and domestic workflow 0.48413 29 26. Integrated Planning and Execution Platform 0.57937 13 27. Financial supply chain management 0.44444 33 28. Aspects of logistics planning 0.69841 1 29. Implementing procurement plans and processes 0.58730 10 30. Schedule for material and equipment and engineering deliveries 0.52381 23 31. Integrating and resource loading and levelling individual schedules 0.54762 17 32. Permits & Approvals 0.61111 7 33. Site Development 0.59524 8 34. Plant Fabrication 0.57937 14 35. Installation 0.50000 27 
  • 7. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad Figure 19 Ranking of factors as per C Response Table III Ranking of factors as per C Response Sr. No. Factors Contractor RII Rank 1. Modular Construction on the Rise 0.59804 7 2. Technology 0.49020 31 3. Integrated Planning Approach 0.38235 35 4. Logistics and Transportation Strategy 0.60784 4 5. Requires lesser time to build 0.44118 34 6. Cost/schedule risk analysis 0.55882 21 7. Increases savings 0.60784 5 8. Environmental Benefits 0.50000 29 9. Quicker return on investment 0.52941 25 10. Increased cost-savings 0.51961 27 11. No weather-related construction issues 0.58824 10 12. Solution for difficult sites 0.58824 11 13. Limited site disruption 0.57843 15 14. Lesser pollution 0.60784 6 15. Lesser waste material 0.56863 17 16. Easier quality control 0.52941 26 17. Total delivered cost management 0.55882 22 18. Global logistics process automation 0.56863 18 19. End-to-end visibility 0.55882 23 20. Supplier portals 0.58824 12 21. Advance Ship notice capability 0.58824 13 22. Total product identification and regulatory compliance 0.46078 33 23. Dynamic routing 0.61765 2 24. Variability management 0.61765 3 25. Integrated international and domestic workflow 0.54902 24 26. Integrated Planning and Execution Platform 0.65686 1 27. Financial supply chain management 0.49020 32 28. Aspects of logistics planning 0.56863 19 29. Implementing procurement plans and processes 0.59804 8 30. Schedule for material and equipment and engineering deliveries 0.56863 20 31. Integrating and resource loading and levelling individual schedules 0.59804 9 32. Permits & Approvals 0.50980 28 33. Site Development 0.57843 16 34. Plant Fabrication 0.58824 14 35. Installation 0.50000 30 30 34 35 6 11 32 3 19 21 12 20 28 22 24 18 9 15 2 25 4 26 5 16 31 29 13 33 1 10 23 17 7 8 14 27 Technology Increases savings Environmental Benefits Increased cost-savings Limited site disruption Lesser pollution Lesser waste material Easier quality control End-to-end visibility Supplier portals Dynamic routing Variability management Permits & Approvals Site Development Plant Fabrication Installation 
  • 8. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad Figure 20 Ranking of factors as per Table IV Ranking of factors as per Sr. No. Factors Overall RII Rank 1. Modular Construction on the Rise 0.52193 27 2. Technology 0.45614 34 3. Integrated Planning Approach 0.40789 35 4. Logistics and Transportation Strategy 0.60965 6 5. Requires lesser time to build 0.51754 28 6. Cost/schedule risk analysis 0.49561 32 7. Increases savings 0.62719 2 8. Environmental Benefits 0.51754 29 9. Quicker return on investment 0.52632 25 10. Increased cost-savings 0.55263 16 11. No weather-related construction issues 0.55702 15 12. Solution for difficult sites 0.53070 23 13. Limited site disruption 0.54825 18 14. Lesser pollution 0.54825 19 15. Lesser waste material 0.55263 17 16. Easier quality control 0.56140 14 17. Total delivered cost management 0.56579 12 18. Global logistics process automation 0.62281 3 19. End-to-end visibility 0.52632 26 20. Supplier portals 0.61842 4 21. Advance Ship notice capability 0.53947 22 22. Total product identification and regulatory compliance 0.54825 20 23. Dynamic routing 0.57895 10 24. Variability management 0.53070 24 25. Integrated international and domestic workflow 0.51316 30 26. Integrated Planning and Execution Platform 0.61404 5 27. Financial supply chain management 0.46491 33 28. Aspects of logistics planning 0.64035 1 29. Implementing procurement plans and processes 0.59211 7 30. Schedule for material and equipment and engineering deliveries 0.54386 21 31. Integrating and resource loading and leveling individual schedules 0.57018 11 32. Permits & Approvals 0.56579 13 33. Site Development 0.58772 8 34. Plant Fabrication 0.58333 9 35. Installation 0.50000 31 7 31 35 4 34 21 5 29 25 27 10 11 15 6 17 26 22 18 23 12 13 33 2 3 24 1 32 19 8 20 9 28 16 14 30 0 10 20 30 40 Technology Increases savings Increased cost-savings Limited site disruption Lesser pollution Lesser waste material Easier quality control End-to-end visibility Supplier portals Dynamic routing Permits & Approvals Site Development Plant Fabrication Installation 
  • 9. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad Figure 21 Ranking of factors as per Overall R Response X. CONCLUSIONS Total 35 Factors contributing to the rising importance of Modular construction adoption were identified through literature study & expert opinion. As per population of stakeholder in Rajkot city, total 61 numbers of respondents were required. The response rate is 62%. Respondents were comprised of 21 consultants and 17 contractors. The collected data were analyzed through Relative Importance Index technique. The major conclusions of top five factors are mentioned below. As per RII technique, top five factors contributing to the rising importance of Modular construction adoption, according (refer Figure 16) 1. Aspects of logistics planning 2. Global logistics process automation 3. Increases savings 4. Supplier portals 5. Total product identification and regulatory compliance Figure 16 Top F as per to C Response As per RII technique, top five factors contributing to the rising importance of Modular construction adoption, according to Figure 17) 1. Integrated Planning and Execution Platform 2. Dynamic routing 3. Variability management 4. Logistics and Transportation Strategy 5. Increases savings Figure 17 Top F C Response 27 34 35 6 28 32 2 29 25 16 15 23 18 19 17 14 12 3 26 4 22 20 10 24 30 5 33 1 7 21 11 13 8 9 31 0 10 20 30 40 Technology Increases savings Increased cost-savings Limited site disruption Lesser pollution Lesser waste material Easier quality control End-to-end visibility Supplier portals Dynamic routing Permits & Approvals Site Development Plant Fabrication Installation 
  • 10. 22nd Environmental Development on 30th December, 2017 at A D Patel Institute of Technology, Karamsad As per RII technique, top five factors contributing to the rising importance of Modular construction adoption, according (refer Figure 18) 1. Aspects of logistics planning 2. Increases savings 3. Global logistics process automation 4. Supplier portals 5. Integrated Planning and Execution Platform Figure 18 Top F Overall R Response XI. SUGGESTION Regarding future research, selective study of factors contributing to the Rising importance of Modular Construction Adoption would be worthwhile by the application of Multi Criteria Decision Making techniques for better educate future scholar with necessary skills to navigate issues. REFERENCES [1] Statistics by Example using Microsoft Excel and nd Ed., Prentice Hall, Upper Saddle River, NJ, 2002. [2] B. M. Kataria, A. S. Patel, Dr. N. D. Sharma, B. K. of Fly Ash Brick: A Case Study of Surat & Tapi District o International Journal of Innovative Research In Science, Engineering and Technology, ISSN: 2319- 8753, Vol. 2, Issue 11, Pp.6553-6558, November-2013. [3] of Delay in Residential Construction Projects: Case Study of Central Gujarat Region o of Engineering Trends and Technology (IJETT), ISSN: 2231-5381, Volume-4, Issue-4, Pp.762-768, April- 2013. [4] M. Rajgor, P. Chauhan, D. Patel, C. Panchal, D. e Techniques for Finding Delay i Research Journal of Engineering and Technology (IRJET), E-ISSN: 2395 -0056, P-ISSN: 2395-0072, Volume: 03, Issue: 01, Pp.1173-1177, Jan-2016. [5] cated Technology i Journal of Advanced Science and Technology, ISSN: 2005-4238, Vol.73, Pp.51-74, 2014. [6] System-How t International Conference on Adaptable Building Structures, Pp.1-6, Eindhoven The Netherlands 03-05 July 2006. [7] S. Farhana, J. Pitroda, J. J. Bhavsar, Dr. S. K. Dave, in Engineering: Issues, Opportunities and Challenges for Development, ISBN: 978-81-929339-1-7, S.N. Patel Institute of Technology & Research Centre, Umrakh, Bardoli, 11th April, 2015. [8] R.I. Khurana, Dr. N. D. Sharma, R. A. Shah, of Modular Housing Technique in Surat of Emerging Technologies and Innovative Research (JETIR), ISSN-2349-5162, Volume: 4, Issue: 06, June 2017. [9] Technology i Journal of Advanced Science and Technology, Vol.73, Pp.51-74, 2014. [10]E. M. Generalova, V. P. Generalova, A. A. in Modern Russian Slovak Seminar Theoretical Foundation of Civil Engineering, Procedia Engineering, 167 172, 2016. [11]J. Molavi Method to Achieve Sustainability In Modular Construction, International Conference on Sustainable Engineering, 1362 1369, 2016. [12] of Costs and Benefits of Panelized and Modular Prefabricated on Sustainable Design, Engineering and Construction, Procedia Engineering, 1291 1297, 2016. [13] of Modular Buildings: A Critical Review, Renewable and 1183, 2016. [14] th ASC Annual International Conference Proceedings, 2014. [15]Kom of UK Construction Clients Influencing Project 1994;12:433 43. [16] and Statistical th Ed., Prentice Hall, Upper Saddle River, NJ, 2009. [17] and Challenges of Modular Construction in High Rise Development in Massachusetts Institute Of Technology, September, 2012. [18]Alrogan, R. M. Lawson, N. Bates- and Benefits Assessment o Steel Construction Institute, Silwood Park, Ascot, Berkshire SL5 7QN. [19]http://www.accerajkot.com/ [20] http://www.rnbgujarat.org/contractors/contractorlist.asp x 