SlideShare a Scribd company logo
Amity School of Engineering & Technology, AUR 
Presentation 
on 
house construction 
submitted by- 
Abhinav saha 
B.Tech CIVIL Vth sem 
1
Amity School of Engineering & Technology, AUR 
2
Amity School of Engineering & Technology, AUR 
3
Amity School of Engineering & Technology, AUR 
4
Amity School of Engineering & Technology, AUR 
5
Amity School of Engineering & Technology, AUR 
• Excavating ground reveals critical knowledge about the soil and therefore 
dictates the design of foundation. For example, for reclaimed land (i.e. ones 
that originally hosted lake and were filled with sand), soil tends to be soft 
and therefore chances of further strengthening the foundation to avoid it 
from setting-in. In some cases, ground may be full of rocks and therefore 
can take longer to excavate. 
• Trick they use with excavation is to excavate about 6-inch and then 
thoroughly soak ground with water. This makes excavation extremely easy. 
For all load bearing areas excavation is done for 4-feet and column area are 
excavated for 6-feet. This building is small-enough that all excavation is 
done manually itself. 
6
Amity School of Engineering & Technology, AUR 
Foundation plan 
• Foundation masonry - Cement building blocks that are about 38cm tall, 15cm wide 
and 15cm deep are the foundation of the building. They are "stuck" together with 
cement concrete masonry. It is recommended that anti-termite treatment be done 
twice - once before placing any cement blocks and next after placing all layers of 
cement blocks. 
• Rain water tank-It was decided to go with what seems like a good size rainwater 
(RWH) tank - 60,000 litres. 
• Columns - Four columns need a bit of special work to get set up. They would 
essentially setup iron columns in those areas and put concrete around them. Once 
columns come up to the plinth level, they would be connected to the rest of the 
house via plinth beam .There are 4 columns to bear the load of the first floor 
balcony and the family room areas. Excavation for columns is about 1500mm. Base 
of the column is filled with mortar. Then a steel column of about 3000mm is 
erected. Rings are tied approx 150mm from each other to hold the column together. 
Finally, they'd pour cement concrete around it to create the actual column structure. 
7
Amity School of Engineering & Technology, AUR 
• Cement building blocks that are about 38cm tall, 15cm wide 
and 15cm deep are the foundation of the building. They are 
"stuck" together with cement concrete masonry. 
• anti-termite treatment be done twice - once before placing 
any cement blocks and next after placing all layers of cement 
blocks. 
• Mixing ratio – 1 part of cement, 4 part of sand, and 8 part of 
aggregate. 
• In my case, ground level at living room side is about 6 to 12 
inches higher than that on the guest bedroom side. Hence, 
they'd do more layers at latter so plinth beam will be at even 
level. 
8
Amity School of Engineering & Technology, AUR 
• Four columns need a bit of special work to get set up. They would 
essentially setup iron columns in those areas and put concrete 
around them. Once columns come up to the plinth level, they would 
be connected to the rest of the house via plinth beam. 
• Foundation around load bearing walls will be done first followed by 
columns and finally by RWH tank structure. Once each component 
is built they will be joined together through plinth beam. Our 
expectation is plinth beam will be about 2.5 feet above the natural 
ground level. This so as to keep house safe from flooding as well as 
provide appropriate elevation. 
9
Amity School of Engineering & Technology, AUR 
Plinth beam 
• Plinth beam is the horizontal cement beam across the house periphery laid 
on top of foundation. 
• PURPOSE 
1. Prevent leaking of water into foundation 
2. Provides support for walls 
3. Holds house together. 
10
Amity School of Engineering & Technology, AUR 
Basic process to construct plinth beam is as follows: 
• Mark-up width - Usually width of plinth is half that of the foundation. In this 
case, foundation is about 45cm wide and so plinth is 23cm aligning with the 
outer edge of the foundation. Inner 23cm of foundation meshes into the floor 
level of the house. 
• Lay down the steel beam - As the adjacent picture shows beams are the 
core of the plinth beam. Beams have a loop every 16cm that holds it 
together. 
• Setup reinforcement - Before concrete is poured, reinforcement has to be 
established to provide rectangular shape to the beam. This takes majority of 
effort as planks have to be nailed properly in place and once concrete is 
poured they need to be removed. 
• Pour the concrete - Next step is to pour the concrete. As concrete is poured, 
mason ensures that it is evenly spread and smoothens out any edges. He 
also needs to ensure the height of the beam is consistent throughout the 
periphery. 
• Remove reinforcement - Concrete turns solid within 24-hour and final step is 
to remove the planks leaving the beam intact. 11
Amity School of Engineering & Technology, AUR 
Planning of exposed brick walls 
• Niches - Position, height and width of each niche that would be 
placed in the wall. 
• Electrical layout - If any ducts have to pass through this wall these 
need to be planned and performed while these walls come up. 
(Note: From aesthetics perspective, it is advisable to not have any 
electrical points in the brick wall itself.) 
• Brick patterns - To avoid monotonous look, border brick patterns 
can be added on a wall. Typically, these are added a few rows 
above the lintel. These have to be decided and upfront planned with 
mason. Some times, masons may not know how to lay patterns 
(especially if they tend to be difficult) and it is wise to allow time for 
these. 
12
Amity School of Engineering & Technology, AUR 
Type of brick used 
Wire cut bricks 
•Dimension : 230*105*75MM (Length*Width*Thickness) 
•Compressive Strength : 300 Kg/Cm2, or 12 N/MM2 
•Water Absorption : 6% of Total Weight 
•Quantity Bricks : 10000 Bricks/Truck 
13
Amity School of Engineering & Technology, AUR 
Lintel beam 
• lintel beam serves the purpose of binding various spaces in the 
house together as well as providing foundation to host brick layers 
extending to roof. Lintel beam is placed typically on top of window 
and door spaces. 
• Put reinforcement in the form of wooden sticks. Then, lay wooden 
sheets on top of window or door space. 
• Do the form work (i.e. lay-down the steel rods that provides the core 
of the beam). 
• Provide shape by reinforcing wooden planks on both sides. Pour the 
concrete and allow it to dry for a few days. 
• Remove the wooden planks on the side as well as wooden sticks 
14
Amity School of Engineering & Technology, AUR 
15
Amity School of Engineering & Technology, AUR 
First Class Brick Work 1:7 
•Brick walls constructed with cement sand mortar in the 
ratio of 1:7 means 1 part of cement and 7 parts of sand. 
This mortar is low in strength and is recommended for 
following works. 
•Toe walls 
•Single storey buildings 
•Temporary structures 
•Light weight walls having no load of beams etc. 
16
Amity School of Engineering & Technology, AUR 
Plastering 
•The joints of the brick work shall raked out to a depth of 12 mm and the surface 
of the wall washed and clean and kept wet for the two days before plastering. The 
material of mortar should be of standard specification. 
•The thickness of the plastering shall be of 12mm to ensure uniform thickness 
of plaster; patches of 15 cm shall be applied first at about 2 m apart to act as 
guide. First mortar shall be dashed and pressed over the surface and then 
brought to a true smooth and uniform surface by means of float and trowel 
•Wall plastering shall be started from top and worked down towards floor,. Ceiling 
plastering shall be completed before starting of wall plaster. 
•All corner and edge shall be rounded. The plastered surface shall be kept wet for 
10days the surface should be protected from rain, sun, frost, etc. 
•For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement 
mortar with coarse sand is used. 
17
Amity School of Engineering & Technology, AUR 
25 cm Cement Concrete floor 
•The cement concrete shall be of proportion 1:2:4 cement shall be fresh Portland cement 
of standard specification. The coarse aggregate shall be hard and tough of 3cm gauge, 
well graded and free from dust, dirt, etc. the sand shall be coarse of 5mm maximum size 
and down, well graded, clean and free from dust, direct and organic matters. 
•The floor shall be leveled and divided into panels or bays of maximums size or 
1.2mx1.2m and the sides of the panels shall be bounded with teak wood battens 2. cm 
thick and 5 cm wide or flat iron of same thickness and fixed with weak mortar, or with 
nails or hooks. Required camber or slope should be given in floor for draining wash 
water. 
•Mixing of concrete shall be down by measuring with boxes to have the required 
proportion as specified. First cement and sand mixed dry and the dry mix of cement and 
sand mixed with ballast dry, and the mixed by adding water slowly and gradually to the 
required quantity, and mixed thoroughly to have a uniform plastic mix. 
•In ground floor the c.c. floor shall be laid on a 7.5cm base of weak cement concrete as 
per standard specifications. 
18
Amity School of Engineering & Technology, AUR 
19

More Related Content

What's hot

DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
jay Rathod
 
specification of Rcc
specification of Rccspecification of Rcc
specification of Rcc
Prabhat chhirolya
 
brick as a building material
brick as a building materialbrick as a building material
brick as a building material
Self employed
 
Brick masonary
Brick masonaryBrick masonary
Brick masonary
Vaibhav Girdhar
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
Vikas Sukhwal
 
Foundation
FoundationFoundation
Foundation
Jitesh Dhule
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
Nabeel Joomun
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
aishwaryasanap
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
Sze Ting Kuek
 
Jacketing
JacketingJacketing
Jacketing
SHAIKH ARSHAD
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
ppt_master
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
Kiran Hadiya
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Udisha15
 
Plastering
PlasteringPlastering
Plastering
Roopa Chikkalgi
 
TYPES OF Foundation
TYPES OF FoundationTYPES OF Foundation
TYPES OF Foundation
Annapurna Sakhardande
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
Sumit Singh
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
Surat Construction PVT LTD
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_design
Pralhad Kore
 
Reinforced cement concrete
Reinforced cement concreteReinforced cement concrete
Reinforced cement concrete
Shourya Puri
 

What's hot (20)

DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
 
specification of Rcc
specification of Rccspecification of Rcc
specification of Rcc
 
brick as a building material
brick as a building materialbrick as a building material
brick as a building material
 
Brick masonary
Brick masonaryBrick masonary
Brick masonary
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
 
Foundation
FoundationFoundation
Foundation
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
 
Jacketing
JacketingJacketing
Jacketing
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Plastering
PlasteringPlastering
Plastering
 
TYPES OF Foundation
TYPES OF FoundationTYPES OF Foundation
TYPES OF Foundation
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
 
Guidelines_for_building_design
Guidelines_for_building_designGuidelines_for_building_design
Guidelines_for_building_design
 
Reinforced cement concrete
Reinforced cement concreteReinforced cement concrete
Reinforced cement concrete
 

Viewers also liked

Farnsworth house Construction Details
Farnsworth house Construction DetailsFarnsworth house Construction Details
Farnsworth house Construction Details
AlHosn University
 
Basic Drafting Week 6 powerpoint section-elevations
Basic Drafting Week 6 powerpoint   section-elevationsBasic Drafting Week 6 powerpoint   section-elevations
Basic Drafting Week 6 powerpoint section-elevations
Freya Van Saun
 
Tuladhar
TuladharTuladhar
Tuladhar
hlksd
 
CITADIL CONSTRUCTION ppt.new
CITADIL CONSTRUCTION ppt.newCITADIL CONSTRUCTION ppt.new
CITADIL CONSTRUCTION ppt.new
Nalinii Acharrya
 
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT NuzvidCuring & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
hema3366
 
BHAGS: Big Hairy Audacious Goals
BHAGS:  Big Hairy Audacious GoalsBHAGS:  Big Hairy Audacious Goals
BHAGS: Big Hairy Audacious Goals
Bonner Foundation
 
Hedgehog & BHAG
Hedgehog & BHAGHedgehog & BHAG
Hedgehog & BHAG
jessicawishart
 
Safe pt design
Safe pt designSafe pt design
Safe pt design
Eldho Peter
 
Fly ash bricks
Fly ash bricks Fly ash bricks
Fly ash bricks
rsbricks2011
 
House History Powerpoint Presentation
House History Powerpoint PresentationHouse History Powerpoint Presentation
House History Powerpoint Presentation
DoverPL
 
House framing guidelines
House framing guidelinesHouse framing guidelines
House framing guidelines
Slawek Dobrowolski
 
Lintels and Beams
Lintels and BeamsLintels and Beams
Lintels and Beams
Steve Jarvis
 
ARCHES AND DOMES
   ARCHES AND DOMES   ARCHES AND DOMES
ARCHES AND DOMES
ahmed lieth
 
LECTURE VI CONST.TEC V Thermal Insulation of Buildings
LECTURE VI CONST.TEC V Thermal Insulation of BuildingsLECTURE VI CONST.TEC V Thermal Insulation of Buildings
LECTURE VI CONST.TEC V Thermal Insulation of Buildings
Darpan Arora
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building construction
Nagma Modi
 
Farnsworth house
Farnsworth houseFarnsworth house
Farnsworth house
Anjali Reghu
 
brick as a building material
brick as a building materialbrick as a building material
brick as a building material
shreenidhi357
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
AmiRul AFiq
 
Brick bonds
Brick bondsBrick bonds
Brick bonds
dezyneecole
 
my_house
my_housemy_house
my_house
Katarína
 

Viewers also liked (20)

Farnsworth house Construction Details
Farnsworth house Construction DetailsFarnsworth house Construction Details
Farnsworth house Construction Details
 
Basic Drafting Week 6 powerpoint section-elevations
Basic Drafting Week 6 powerpoint   section-elevationsBasic Drafting Week 6 powerpoint   section-elevations
Basic Drafting Week 6 powerpoint section-elevations
 
Tuladhar
TuladharTuladhar
Tuladhar
 
CITADIL CONSTRUCTION ppt.new
CITADIL CONSTRUCTION ppt.newCITADIL CONSTRUCTION ppt.new
CITADIL CONSTRUCTION ppt.new
 
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT NuzvidCuring & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
 
BHAGS: Big Hairy Audacious Goals
BHAGS:  Big Hairy Audacious GoalsBHAGS:  Big Hairy Audacious Goals
BHAGS: Big Hairy Audacious Goals
 
Hedgehog & BHAG
Hedgehog & BHAGHedgehog & BHAG
Hedgehog & BHAG
 
Safe pt design
Safe pt designSafe pt design
Safe pt design
 
Fly ash bricks
Fly ash bricks Fly ash bricks
Fly ash bricks
 
House History Powerpoint Presentation
House History Powerpoint PresentationHouse History Powerpoint Presentation
House History Powerpoint Presentation
 
House framing guidelines
House framing guidelinesHouse framing guidelines
House framing guidelines
 
Lintels and Beams
Lintels and BeamsLintels and Beams
Lintels and Beams
 
ARCHES AND DOMES
   ARCHES AND DOMES   ARCHES AND DOMES
ARCHES AND DOMES
 
LECTURE VI CONST.TEC V Thermal Insulation of Buildings
LECTURE VI CONST.TEC V Thermal Insulation of BuildingsLECTURE VI CONST.TEC V Thermal Insulation of Buildings
LECTURE VI CONST.TEC V Thermal Insulation of Buildings
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building construction
 
Farnsworth house
Farnsworth houseFarnsworth house
Farnsworth house
 
brick as a building material
brick as a building materialbrick as a building material
brick as a building material
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
 
Brick bonds
Brick bondsBrick bonds
Brick bonds
 
my_house
my_housemy_house
my_house
 

Similar to house construction

Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
AbhinavSahu45
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & Plastering
Tanvir Araf
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction Techniques
Uday Yadav
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
swethasekhar5
 
working in a building and all the procedures
working in a building and all the proceduresworking in a building and all the procedures
working in a building and all the procedures
azharbhattumz
 
Brickwork and plastering
Brickwork and plasteringBrickwork and plastering
Brickwork and plastering
builtify
 
5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx
AmrithaVijay
 
Sanat Meht's Low cost house - Revised June 2022.pdf
Sanat Meht's Low cost house  - Revised June 2022.pdfSanat Meht's Low cost house  - Revised June 2022.pdf
Sanat Meht's Low cost house - Revised June 2022.pdf
shirish avrani
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
Ajay Kumar
 
Ferrouscementhouse 2
Ferrouscementhouse 2Ferrouscementhouse 2
Ferrouscementhouse 2
poreddy jeevanreddy
 
Building Construction.pdf
Building Construction.pdfBuilding Construction.pdf
Building Construction.pdf
Valmik Mahajan
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
VATSAL PATEL
 
FLOORING
FLOORINGFLOORING
FLOORING
YASH AGRAWAL
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ErLavKushPrasad
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptx
swethaasukumar
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
practicalanswerssl
 
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
ShahbazKhan379018
 

Similar to house construction (20)

Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Bricks & Plastering
Bricks & PlasteringBricks & Plastering
Bricks & Plastering
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction Techniques
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
working in a building and all the procedures
working in a building and all the proceduresworking in a building and all the procedures
working in a building and all the procedures
 
Brickwork and plastering
Brickwork and plasteringBrickwork and plastering
Brickwork and plastering
 
5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx5.2 brick and stone MASONRY.pptx
5.2 brick and stone MASONRY.pptx
 
Sanat Meht's Low cost house - Revised June 2022.pdf
Sanat Meht's Low cost house  - Revised June 2022.pdfSanat Meht's Low cost house  - Revised June 2022.pdf
Sanat Meht's Low cost house - Revised June 2022.pdf
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
 
Ferrouscementhouse 2
Ferrouscementhouse 2Ferrouscementhouse 2
Ferrouscementhouse 2
 
Building Construction.pdf
Building Construction.pdfBuilding Construction.pdf
Building Construction.pdf
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
FLOORING
FLOORINGFLOORING
FLOORING
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptx
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
 
Form Work
Form Work Form Work
Form Work
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 

Recently uploaded

PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 

Recently uploaded (20)

PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 

house construction

  • 1. Amity School of Engineering & Technology, AUR Presentation on house construction submitted by- Abhinav saha B.Tech CIVIL Vth sem 1
  • 2. Amity School of Engineering & Technology, AUR 2
  • 3. Amity School of Engineering & Technology, AUR 3
  • 4. Amity School of Engineering & Technology, AUR 4
  • 5. Amity School of Engineering & Technology, AUR 5
  • 6. Amity School of Engineering & Technology, AUR • Excavating ground reveals critical knowledge about the soil and therefore dictates the design of foundation. For example, for reclaimed land (i.e. ones that originally hosted lake and were filled with sand), soil tends to be soft and therefore chances of further strengthening the foundation to avoid it from setting-in. In some cases, ground may be full of rocks and therefore can take longer to excavate. • Trick they use with excavation is to excavate about 6-inch and then thoroughly soak ground with water. This makes excavation extremely easy. For all load bearing areas excavation is done for 4-feet and column area are excavated for 6-feet. This building is small-enough that all excavation is done manually itself. 6
  • 7. Amity School of Engineering & Technology, AUR Foundation plan • Foundation masonry - Cement building blocks that are about 38cm tall, 15cm wide and 15cm deep are the foundation of the building. They are "stuck" together with cement concrete masonry. It is recommended that anti-termite treatment be done twice - once before placing any cement blocks and next after placing all layers of cement blocks. • Rain water tank-It was decided to go with what seems like a good size rainwater (RWH) tank - 60,000 litres. • Columns - Four columns need a bit of special work to get set up. They would essentially setup iron columns in those areas and put concrete around them. Once columns come up to the plinth level, they would be connected to the rest of the house via plinth beam .There are 4 columns to bear the load of the first floor balcony and the family room areas. Excavation for columns is about 1500mm. Base of the column is filled with mortar. Then a steel column of about 3000mm is erected. Rings are tied approx 150mm from each other to hold the column together. Finally, they'd pour cement concrete around it to create the actual column structure. 7
  • 8. Amity School of Engineering & Technology, AUR • Cement building blocks that are about 38cm tall, 15cm wide and 15cm deep are the foundation of the building. They are "stuck" together with cement concrete masonry. • anti-termite treatment be done twice - once before placing any cement blocks and next after placing all layers of cement blocks. • Mixing ratio – 1 part of cement, 4 part of sand, and 8 part of aggregate. • In my case, ground level at living room side is about 6 to 12 inches higher than that on the guest bedroom side. Hence, they'd do more layers at latter so plinth beam will be at even level. 8
  • 9. Amity School of Engineering & Technology, AUR • Four columns need a bit of special work to get set up. They would essentially setup iron columns in those areas and put concrete around them. Once columns come up to the plinth level, they would be connected to the rest of the house via plinth beam. • Foundation around load bearing walls will be done first followed by columns and finally by RWH tank structure. Once each component is built they will be joined together through plinth beam. Our expectation is plinth beam will be about 2.5 feet above the natural ground level. This so as to keep house safe from flooding as well as provide appropriate elevation. 9
  • 10. Amity School of Engineering & Technology, AUR Plinth beam • Plinth beam is the horizontal cement beam across the house periphery laid on top of foundation. • PURPOSE 1. Prevent leaking of water into foundation 2. Provides support for walls 3. Holds house together. 10
  • 11. Amity School of Engineering & Technology, AUR Basic process to construct plinth beam is as follows: • Mark-up width - Usually width of plinth is half that of the foundation. In this case, foundation is about 45cm wide and so plinth is 23cm aligning with the outer edge of the foundation. Inner 23cm of foundation meshes into the floor level of the house. • Lay down the steel beam - As the adjacent picture shows beams are the core of the plinth beam. Beams have a loop every 16cm that holds it together. • Setup reinforcement - Before concrete is poured, reinforcement has to be established to provide rectangular shape to the beam. This takes majority of effort as planks have to be nailed properly in place and once concrete is poured they need to be removed. • Pour the concrete - Next step is to pour the concrete. As concrete is poured, mason ensures that it is evenly spread and smoothens out any edges. He also needs to ensure the height of the beam is consistent throughout the periphery. • Remove reinforcement - Concrete turns solid within 24-hour and final step is to remove the planks leaving the beam intact. 11
  • 12. Amity School of Engineering & Technology, AUR Planning of exposed brick walls • Niches - Position, height and width of each niche that would be placed in the wall. • Electrical layout - If any ducts have to pass through this wall these need to be planned and performed while these walls come up. (Note: From aesthetics perspective, it is advisable to not have any electrical points in the brick wall itself.) • Brick patterns - To avoid monotonous look, border brick patterns can be added on a wall. Typically, these are added a few rows above the lintel. These have to be decided and upfront planned with mason. Some times, masons may not know how to lay patterns (especially if they tend to be difficult) and it is wise to allow time for these. 12
  • 13. Amity School of Engineering & Technology, AUR Type of brick used Wire cut bricks •Dimension : 230*105*75MM (Length*Width*Thickness) •Compressive Strength : 300 Kg/Cm2, or 12 N/MM2 •Water Absorption : 6% of Total Weight •Quantity Bricks : 10000 Bricks/Truck 13
  • 14. Amity School of Engineering & Technology, AUR Lintel beam • lintel beam serves the purpose of binding various spaces in the house together as well as providing foundation to host brick layers extending to roof. Lintel beam is placed typically on top of window and door spaces. • Put reinforcement in the form of wooden sticks. Then, lay wooden sheets on top of window or door space. • Do the form work (i.e. lay-down the steel rods that provides the core of the beam). • Provide shape by reinforcing wooden planks on both sides. Pour the concrete and allow it to dry for a few days. • Remove the wooden planks on the side as well as wooden sticks 14
  • 15. Amity School of Engineering & Technology, AUR 15
  • 16. Amity School of Engineering & Technology, AUR First Class Brick Work 1:7 •Brick walls constructed with cement sand mortar in the ratio of 1:7 means 1 part of cement and 7 parts of sand. This mortar is low in strength and is recommended for following works. •Toe walls •Single storey buildings •Temporary structures •Light weight walls having no load of beams etc. 16
  • 17. Amity School of Engineering & Technology, AUR Plastering •The joints of the brick work shall raked out to a depth of 12 mm and the surface of the wall washed and clean and kept wet for the two days before plastering. The material of mortar should be of standard specification. •The thickness of the plastering shall be of 12mm to ensure uniform thickness of plaster; patches of 15 cm shall be applied first at about 2 m apart to act as guide. First mortar shall be dashed and pressed over the surface and then brought to a true smooth and uniform surface by means of float and trowel •Wall plastering shall be started from top and worked down towards floor,. Ceiling plastering shall be completed before starting of wall plaster. •All corner and edge shall be rounded. The plastered surface shall be kept wet for 10days the surface should be protected from rain, sun, frost, etc. •For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement mortar with coarse sand is used. 17
  • 18. Amity School of Engineering & Technology, AUR 25 cm Cement Concrete floor •The cement concrete shall be of proportion 1:2:4 cement shall be fresh Portland cement of standard specification. The coarse aggregate shall be hard and tough of 3cm gauge, well graded and free from dust, dirt, etc. the sand shall be coarse of 5mm maximum size and down, well graded, clean and free from dust, direct and organic matters. •The floor shall be leveled and divided into panels or bays of maximums size or 1.2mx1.2m and the sides of the panels shall be bounded with teak wood battens 2. cm thick and 5 cm wide or flat iron of same thickness and fixed with weak mortar, or with nails or hooks. Required camber or slope should be given in floor for draining wash water. •Mixing of concrete shall be down by measuring with boxes to have the required proportion as specified. First cement and sand mixed dry and the dry mix of cement and sand mixed with ballast dry, and the mixed by adding water slowly and gradually to the required quantity, and mixed thoroughly to have a uniform plastic mix. •In ground floor the c.c. floor shall be laid on a 7.5cm base of weak cement concrete as per standard specifications. 18
  • 19. Amity School of Engineering & Technology, AUR 19