SlideShare a Scribd company logo
A
SUMMER TRAINING PRESENTATION
ON
BUILDING CONSTRUCTION
Submitted to
Mr. Hetram Sharma
Asst. Professor & Dy. Head
Department of Civil Engineering
Submitted by
Abhinav Sharma
Roll Number : 20EJCCE004
Submitted in partial fulfillment for the award of the Degree of the
Bachelor of Technology
Rajasthan Technical University, Kota
(2022-2023)
CONTENT
• Introduction
• Site plan & planning
• Building material
• R.C.C.
• Excavation
• Foundation
• Retaining wall
• Walls & Column
• Manufacturing of concrete
• Curing of concrete
• Plastering
• Slump test
• Cube test
• Conclusion
• Reference
Introduction
• The building is defined as any structure what so ever purpose
and of whatsoever materials constructed and ever part thereof
whether used as human habitation or not .
• For this practical training , I reported at SUPERIOR HI-
TECH INFRA PROJECTS LLP, at construction of SUBH
NIKUNJ ( Residential Buildings , Tower & Non-Tower , in
response to Mr. Ashok Sharma (Managing Director) dated In
connection with same, I have reported to Mr. Ajay Sen
(General Manager) at , furthers ordered me to join project site.
The site incharge meet me at the site and gives me brief
introduction of this project as under.
Site plan and planning
• The planning of the building has the most important role in the civil
engineering because well designed building has the comfort and good
working conditions for the people who live and work in it .
• The project on which I take training it is a construction of residential
buildings. This building is designed very carefully by keeping the
following views:
• Swimming pool.
• Aerobics and yoga room.
• Media rooms for watching movies etc. 40-50 seats.
• Sports lounge.
• Community Hall.
• Library.
• Kids play area ,Car Parking..
Building Material
• A building structure is composed of different types of the material these
materials are either called as building material. The material use in the
building on basis of the availability and cost. For construct a building the
essential.
• building material are as follows
• Cement: The cement often called the magic power is a fine ground
material consisting of compound of lime ,silica alumina and iron. When
mixed with water it forms a paste which hardened and bind the aggregates
(sand, gravel ,crushed rock, etc.) together to form a durable mass called the
Concrete.
• Sand :These are cohesion less aggregates of either, rounded sub rounded,
angular, sub angular or flat fragments of more or less unaltered rock of
minerals consisting of 90% of particles of size greater than 0.06 mm and
less than 2 mm.
• Bricks : Bricks are distinguished by their base (row) material and size.
Standard brunt clay bricks come in the size 10" x 5" x 3". Modular bricks,
rarely used because they are not easily available, come in the size 200mm x
100mm x 100mm (including mortar thickness) Fly ash bricks, sometimes
also come in modular form.
EXCAVATION
• Excavation- Foundation trenches shall be dug out to the exact
width of the foundation concrete and the sides shall be vertical.
If the soil is not good and does not permit vertical sides, the
sides should be sloped back or protected with timber shoring.
•
• Finish and Trench- The bottom of the foundation trenches
shall be perfectly leveled both longitudinally and transversally
and the sides of the trench shall be dressed perfectly vertical
from bottom up to least thickness of lose concrete may be laid
to the exact width as per design. The bed of the trench shall be
tightly watered and well rammed. Soft or defective spots shall
be dug out excess digging if done through mistake shall be
filled with concrete
FOUNDATION
• The foundation of the building should
be so planned and the layout of the
foundation should be on the ground
should be correct in the measurement.
• Should not place the concrete in the
foundation before checked by the
Engineer-in charge.
• If building has the basement more than
two raft foundations should be provided.
• In the P.C.C. it should be in the ratio of
1:4:8 and 75 mm thick 75 mm projected
beyond raft foundation.
• The concrete provided in the raft
foundation should be M-25 grade
conforming to IS456.
• The design and thickness of the raft
foundation provided by the soil testing
Retaining Wall
• A retaining wall is a structure designed and constructed to resist the lateral
pressure of soil when there is a desired change in ground elevation that
exceeds the angle of repose of the soil.
• A basement wall is thus one kind of retaining wall. But the term usually
refers to a cantilever retaining wall, which is a freestanding structure
without lateral support at its top. These are cantilevered from a footing and
rise above the grade on one side to retain a higher level grade on the
opposite side. The walls must resist the lateral pressures generated by loose
soils or, in some cases, water pressures.
Manufacturing of concrete
• Batching of the concrete
• After fixing the proportion of different ingredients of concrete for a
particular work, the material C.A., F.A., cement and water measured out in
batches for mixing. The process is known as Batching. This process of
batching may be carried out by weight or by volume.
• (i) Weight batching: - The unit of weight, for material of concrete, is
usually Kilogram. The batching of material by weight is absolutely straight
forward, the cement, sand and coarse aggregate being all weighed directly
in Kilogram.
• (ii) Volume batching: -In batching by volume, all ingredient i.e. water,
cement, sand and coarse aggregate are measured in liters, where the
resulting concrete(being) solid measured in cubic meters.
Curing of concrete
• Curing is one of the most important steps in concrete construction, because
proper curing greatly increase concrete strength and durability. Concrete
hardened as a result of hydration: the chemical reaction between cement
and water. However, hydration occurs only if water is available and if the
concrete temperature stays within a suitable range. During the curing
period from five to seven days after placement for conventional concrete
the concrete surface needs to be kept moist to permit the hydration process.
New concrete can be wet with soaking hoses, sprinklers or covered with
wet burlap, or can be coated with commercially available curing
compounds, which seal in moisture.
• Curing the concrete aids the chemical reaction called hydration. Most
freshly mixed concrete contains considerably more water than is required
for complete hydration of the cement; however, any appreciable loss of
water by evaporation or by otherwise will delay or prevent the hydration.
Plastering
• The joints of the brick work shall raked out to a depth of 12 mm and the surface of
the wall washed and clean and kept wet for the two days before plastering. The
material of mortar should be of standard specification.
• The thickness of the plastering shall be of 12mm to ensure uniform thickness of
plaster; patches of 15 cm shall be applied first at about 2 m apart to act as guide.
• Wall plastering shall be started from top and worked down towards floor,. Ceiling
plastering shall be completed before starting of wall plaster.
• All corner and edge shall be rounded. The plastered surface shall be kept wet for
10days the surface should be protected from rain, sun, frost, etc.
• For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement mortar
with coarse sand is used.
Formwork
• ‘Temporary Supporting
Structure’are those structures,
which are temporarily required in
building construction, either for
supporting the laying of concrete
till it gets matured, such as?
• formwork or forms or
shuttering. As fresh concrete is in
a plastic state, when it is placed
for construction purposes, so it
becomes necessary to provide
some temporary structure to
confine and support the concrete,
till it gains sufficient strength for
self supporting. The temporary
structure is known as formwork or
shuttering
Slump Test
• Dampen inside of cone and place it on a smooth, moist, non-absorbent,
level surface large enough to accommodate both the slumped concrete and
the slump cone. Stand or, foot pieces throughout the test procedure to hold
the cone firmly in place.
• Fill cone 1/3 full by volume and rod 25 times with 5/8-inchdiameter x 24-
inch-longhemispherical tip steel tamping rod. (This is a specification
requirement which will produce nonstandard results unless followed
exactly.) Distribute rodding evenly over the entire cross-section of the
sample.
• Fill cone 2/3 full by volume. Rod this layer 25 times with rod penetrating
into, but not through first layer. Distribute rodding evenly over the entire
cross section of the layer.
• Fill cone to overflowing. Rod this layer 25 times with rod penetrating into
but not through, second layer. Distribute rodding evenly over the entire
cross section of this layer.
• Remove the excess concrete from the top of the cone, using tamping rod as
a screed. Clean overflow from base of cone.
Cube test
• The compressive strength of the concrete cube test provides an idea
about all the characteristics of concrete. By this single test one judge that
whether Concreting has been done properly or not. Concrete compressive
strength for general construction varies from 15 MPa (2200 psi) to 30 MPa
(4400 psi) and higher in commercial and industrial structures.
• Compressive strength formula for any material is the load applied at the
point of failure to the cross-section area of the face on which load was
applied.
• Compressive Strength = Load / Cross-sectional Area
Conclusion
The main aim of studies within this project was to investigate
how a structure is constructed within its desired properties. We
get knowledge about the basic & advanced techniques of
building construction as well as saw the challenges which a
civil engineer have to face during construction i.e. labor
problems, cost management, environmental challenges
etc. We cleared our many doubts regarding building
construction. We had seen dewatering system at project site for
construction which is not used at our state anymore, so it was a
new thing for us...Although are subjects more important for
technicians, in the project .how Project needs a very good
coordination and large quantities of man power, equipment and
funds ..
Reference
• Basic Schedule of Rates (BSR),2019
• Sushil Kumar. (1988). Building Construction. (Pp-). New
Delhi: Standard Publishers Distributors.
• Rangwala , S. C. (1980). Building Construction. (pp-
).New Delhi: R. C. Patel Charotar Bookstall and Anand.
• Mohanty A.B. (1985). Guide to House Building. (Pp-
101-103,103-105). New Delhi: Inter India Publications.
• Tiwari, Piyush. "Energy efficiency and building
construction in India." Building and Environment 36.10
(2001): 1127-1135.
• Basic construction materials - Course (nptel.ac.in)
Thanks

More Related Content

Similar to Sample copy of IT PPT.pptx

Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
CONCRETE PPT SA JBP
CONCRETE PPT SA JBPCONCRETE PPT SA JBP
CONCRETE PPT SA JBP
Suyash Awasthi
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
Sreekutty S
 
Building construction
Building constructionBuilding construction
Building construction
nhmurad
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction TechniquesUday Yadav
 
CONCRETE TECHNOLOGY
CONCRETE TECHNOLOGYCONCRETE TECHNOLOGY
CONCRETE TECHNOLOGY
HitaishiGupta
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
ARUNKUMARC39
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
Seminar Links
 
Group-1-CMT-2.pptx
Group-1-CMT-2.pptxGroup-1-CMT-2.pptx
Group-1-CMT-2.pptx
IvanneFuentesEspinos
 
Cement concrete.pptx
Cement concrete.pptxCement concrete.pptx
Cement concrete.pptx
ReeReena
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
Adv.Construction - assignement.pdf
Adv.Construction - assignement.pdfAdv.Construction - assignement.pdf
Adv.Construction - assignement.pdf
DarshanLimbda
 
Concrete technology and masonry structures
Concrete technology and masonry structuresConcrete technology and masonry structures
Concrete technology and masonry structures
NripeshJha
 
Industrial training ppt bitm
Industrial training ppt bitmIndustrial training ppt bitm
Industrial training ppt bitm
Saikat Nandy
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
VaibhavSoni742163
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
HarshKumarEname
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
ANURAG KASHYAP
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
kavithamegha
 

Similar to Sample copy of IT PPT.pptx (20)

Form Work
Form Work Form Work
Form Work
 
CONCRETE PPT SA JBP
CONCRETE PPT SA JBPCONCRETE PPT SA JBP
CONCRETE PPT SA JBP
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Building construction
Building constructionBuilding construction
Building construction
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction Techniques
 
CONCRETE TECHNOLOGY
CONCRETE TECHNOLOGYCONCRETE TECHNOLOGY
CONCRETE TECHNOLOGY
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Group-1-CMT-2.pptx
Group-1-CMT-2.pptxGroup-1-CMT-2.pptx
Group-1-CMT-2.pptx
 
Cement concrete.pptx
Cement concrete.pptxCement concrete.pptx
Cement concrete.pptx
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Adv.Construction - assignement.pdf
Adv.Construction - assignement.pdfAdv.Construction - assignement.pdf
Adv.Construction - assignement.pdf
 
Concrete technology and masonry structures
Concrete technology and masonry structuresConcrete technology and masonry structures
Concrete technology and masonry structures
 
Industrial training ppt bitm
Industrial training ppt bitmIndustrial training ppt bitm
Industrial training ppt bitm
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
CONCRETE
CONCRETECONCRETE
CONCRETE
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

Sample copy of IT PPT.pptx

  • 1. A SUMMER TRAINING PRESENTATION ON BUILDING CONSTRUCTION Submitted to Mr. Hetram Sharma Asst. Professor & Dy. Head Department of Civil Engineering Submitted by Abhinav Sharma Roll Number : 20EJCCE004 Submitted in partial fulfillment for the award of the Degree of the Bachelor of Technology Rajasthan Technical University, Kota (2022-2023)
  • 2.
  • 3. CONTENT • Introduction • Site plan & planning • Building material • R.C.C. • Excavation • Foundation • Retaining wall • Walls & Column • Manufacturing of concrete • Curing of concrete • Plastering • Slump test • Cube test • Conclusion • Reference
  • 4. Introduction • The building is defined as any structure what so ever purpose and of whatsoever materials constructed and ever part thereof whether used as human habitation or not . • For this practical training , I reported at SUPERIOR HI- TECH INFRA PROJECTS LLP, at construction of SUBH NIKUNJ ( Residential Buildings , Tower & Non-Tower , in response to Mr. Ashok Sharma (Managing Director) dated In connection with same, I have reported to Mr. Ajay Sen (General Manager) at , furthers ordered me to join project site. The site incharge meet me at the site and gives me brief introduction of this project as under.
  • 5.
  • 6. Site plan and planning • The planning of the building has the most important role in the civil engineering because well designed building has the comfort and good working conditions for the people who live and work in it . • The project on which I take training it is a construction of residential buildings. This building is designed very carefully by keeping the following views: • Swimming pool. • Aerobics and yoga room. • Media rooms for watching movies etc. 40-50 seats. • Sports lounge. • Community Hall. • Library. • Kids play area ,Car Parking..
  • 7. Building Material • A building structure is composed of different types of the material these materials are either called as building material. The material use in the building on basis of the availability and cost. For construct a building the essential. • building material are as follows
  • 8. • Cement: The cement often called the magic power is a fine ground material consisting of compound of lime ,silica alumina and iron. When mixed with water it forms a paste which hardened and bind the aggregates (sand, gravel ,crushed rock, etc.) together to form a durable mass called the Concrete. • Sand :These are cohesion less aggregates of either, rounded sub rounded, angular, sub angular or flat fragments of more or less unaltered rock of minerals consisting of 90% of particles of size greater than 0.06 mm and less than 2 mm. • Bricks : Bricks are distinguished by their base (row) material and size. Standard brunt clay bricks come in the size 10" x 5" x 3". Modular bricks, rarely used because they are not easily available, come in the size 200mm x 100mm x 100mm (including mortar thickness) Fly ash bricks, sometimes also come in modular form.
  • 9. EXCAVATION • Excavation- Foundation trenches shall be dug out to the exact width of the foundation concrete and the sides shall be vertical. If the soil is not good and does not permit vertical sides, the sides should be sloped back or protected with timber shoring. • • Finish and Trench- The bottom of the foundation trenches shall be perfectly leveled both longitudinally and transversally and the sides of the trench shall be dressed perfectly vertical from bottom up to least thickness of lose concrete may be laid to the exact width as per design. The bed of the trench shall be tightly watered and well rammed. Soft or defective spots shall be dug out excess digging if done through mistake shall be filled with concrete
  • 10.
  • 11. FOUNDATION • The foundation of the building should be so planned and the layout of the foundation should be on the ground should be correct in the measurement. • Should not place the concrete in the foundation before checked by the Engineer-in charge. • If building has the basement more than two raft foundations should be provided. • In the P.C.C. it should be in the ratio of 1:4:8 and 75 mm thick 75 mm projected beyond raft foundation. • The concrete provided in the raft foundation should be M-25 grade conforming to IS456. • The design and thickness of the raft foundation provided by the soil testing
  • 12. Retaining Wall • A retaining wall is a structure designed and constructed to resist the lateral pressure of soil when there is a desired change in ground elevation that exceeds the angle of repose of the soil. • A basement wall is thus one kind of retaining wall. But the term usually refers to a cantilever retaining wall, which is a freestanding structure without lateral support at its top. These are cantilevered from a footing and rise above the grade on one side to retain a higher level grade on the opposite side. The walls must resist the lateral pressures generated by loose soils or, in some cases, water pressures.
  • 13. Manufacturing of concrete • Batching of the concrete • After fixing the proportion of different ingredients of concrete for a particular work, the material C.A., F.A., cement and water measured out in batches for mixing. The process is known as Batching. This process of batching may be carried out by weight or by volume. • (i) Weight batching: - The unit of weight, for material of concrete, is usually Kilogram. The batching of material by weight is absolutely straight forward, the cement, sand and coarse aggregate being all weighed directly in Kilogram. • (ii) Volume batching: -In batching by volume, all ingredient i.e. water, cement, sand and coarse aggregate are measured in liters, where the resulting concrete(being) solid measured in cubic meters.
  • 14. Curing of concrete • Curing is one of the most important steps in concrete construction, because proper curing greatly increase concrete strength and durability. Concrete hardened as a result of hydration: the chemical reaction between cement and water. However, hydration occurs only if water is available and if the concrete temperature stays within a suitable range. During the curing period from five to seven days after placement for conventional concrete the concrete surface needs to be kept moist to permit the hydration process. New concrete can be wet with soaking hoses, sprinklers or covered with wet burlap, or can be coated with commercially available curing compounds, which seal in moisture. • Curing the concrete aids the chemical reaction called hydration. Most freshly mixed concrete contains considerably more water than is required for complete hydration of the cement; however, any appreciable loss of water by evaporation or by otherwise will delay or prevent the hydration.
  • 15. Plastering • The joints of the brick work shall raked out to a depth of 12 mm and the surface of the wall washed and clean and kept wet for the two days before plastering. The material of mortar should be of standard specification. • The thickness of the plastering shall be of 12mm to ensure uniform thickness of plaster; patches of 15 cm shall be applied first at about 2 m apart to act as guide. • Wall plastering shall be started from top and worked down towards floor,. Ceiling plastering shall be completed before starting of wall plaster. • All corner and edge shall be rounded. The plastered surface shall be kept wet for 10days the surface should be protected from rain, sun, frost, etc. • For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement mortar with coarse sand is used.
  • 16. Formwork • ‘Temporary Supporting Structure’are those structures, which are temporarily required in building construction, either for supporting the laying of concrete till it gets matured, such as? • formwork or forms or shuttering. As fresh concrete is in a plastic state, when it is placed for construction purposes, so it becomes necessary to provide some temporary structure to confine and support the concrete, till it gains sufficient strength for self supporting. The temporary structure is known as formwork or shuttering
  • 17. Slump Test • Dampen inside of cone and place it on a smooth, moist, non-absorbent, level surface large enough to accommodate both the slumped concrete and the slump cone. Stand or, foot pieces throughout the test procedure to hold the cone firmly in place. • Fill cone 1/3 full by volume and rod 25 times with 5/8-inchdiameter x 24- inch-longhemispherical tip steel tamping rod. (This is a specification requirement which will produce nonstandard results unless followed exactly.) Distribute rodding evenly over the entire cross-section of the sample. • Fill cone 2/3 full by volume. Rod this layer 25 times with rod penetrating into, but not through first layer. Distribute rodding evenly over the entire cross section of the layer. • Fill cone to overflowing. Rod this layer 25 times with rod penetrating into but not through, second layer. Distribute rodding evenly over the entire cross section of this layer. • Remove the excess concrete from the top of the cone, using tamping rod as a screed. Clean overflow from base of cone.
  • 18.
  • 19. Cube test • The compressive strength of the concrete cube test provides an idea about all the characteristics of concrete. By this single test one judge that whether Concreting has been done properly or not. Concrete compressive strength for general construction varies from 15 MPa (2200 psi) to 30 MPa (4400 psi) and higher in commercial and industrial structures. • Compressive strength formula for any material is the load applied at the point of failure to the cross-section area of the face on which load was applied. • Compressive Strength = Load / Cross-sectional Area
  • 20.
  • 21. Conclusion The main aim of studies within this project was to investigate how a structure is constructed within its desired properties. We get knowledge about the basic & advanced techniques of building construction as well as saw the challenges which a civil engineer have to face during construction i.e. labor problems, cost management, environmental challenges etc. We cleared our many doubts regarding building construction. We had seen dewatering system at project site for construction which is not used at our state anymore, so it was a new thing for us...Although are subjects more important for technicians, in the project .how Project needs a very good coordination and large quantities of man power, equipment and funds ..
  • 22. Reference • Basic Schedule of Rates (BSR),2019 • Sushil Kumar. (1988). Building Construction. (Pp-). New Delhi: Standard Publishers Distributors. • Rangwala , S. C. (1980). Building Construction. (pp- ).New Delhi: R. C. Patel Charotar Bookstall and Anand. • Mohanty A.B. (1985). Guide to House Building. (Pp- 101-103,103-105). New Delhi: Inter India Publications. • Tiwari, Piyush. "Energy efficiency and building construction in India." Building and Environment 36.10 (2001): 1127-1135. • Basic construction materials - Course (nptel.ac.in)