SlideShare a Scribd company logo
1 of 43
Industrial
Training
L&T SUCG JV Project-CC27(majenta line)
Project Director-Mr. R. G. Saini
Site - Munerika.
Station Manager- Mr. Brijesh Garg
• An endeavour over a period can be successful only
with right guidance and mentorship. I take this
opportunity to express my gratitude to all those
who encouraged me for successful completion of
Project Training.
• I am deeply indebted to Mr RG Saini, Project
Director for providing me this opportunity to work
in such a prestigious organisation.
• I owe my sincere regards to Mr. P.R.Lenka whose
management at site made it possible for me to
learn and gave me a healthy learning environment.
ACKNOWLEDGEMENT
• I express my sincere and profound thanks to Mr. Amrutesh
who acted as a guide map, who steered me throughout my
training through his excellent guidance and knowledge.
• I owe warm hearted acknowledgement of gratitude to Mr.
Sumit Dev who helped me a lot in my initial days clearing my
irritating questions and making myself comfortable in L&T
family.
• I forfeit my respect to Mr. Rajeev Kumar whose guidance
along with encouragement enabled me to work very
efficiently throughout my period of Training.
• The field training can’t be complete through some people. I
also extend my thanks to all other members especially Mr.
Prashant Kumar Pandey whose guidance gave a way to my
learning.
• And last but not the least my co trainees who made the
training like being in a family and for those healthy and
productive discussions.
• Larsen & Toubro is a major Technology,
engineering, construction, manufacturing and
financial services conglomerate. L&T addresses
critical needs in key sectorsInfrastructure, Power,
Process Industries and Defense- for consumers in
over 30 countries around the world.
• CC-27 is L&T SUCG Joint Venture Project. The
project contains five stations (Hauz Khas, Vasant
Vihar, Munirka, and IIT&RK puram)
About the Project
• L&T SUCG CC27 DELHI planned to build a tunnel
from the end of the underground ramp(near the
metro station Shankar Vihar)to metro station Hauz
Khas and underground ramp near the Metro
Station Shankar Vihar and the underground metro
station at Vasant Vihar, Munirka, RK Puram, IIT
,Hauz Khas.
• The project was commenced on November 2012
and was to be completed in 42 months i.e. May
2016 but the deadline has been extended and now
the project is expected to complete by December
2016.
WELDING WORK
FOR CRADDLE
REMOVAL OF SHUTTERING FROM
ES03@ MUNERIKA
• 1. The shortened construction period due to
simultaneous construction of the basement and
the superstructure.
• 2. More operational space gained from the
advanced construction of floor slabs.
• 3. The higher stiffness of floor slab compare to steel
struts improves the safety of excavation.
• 4. It is highly suitable for construction for tall
buildings with deep basements constructed in
urban areas.
• 1. Higher cost (due to the construction of pile
foundation)
• 2. Since the construction period of the basement is
lengthened, the lateral displacement of retaining wall
or ground settlement may possible increase due to the
influence of creep if the soil layers are encountered.
• 3. The construction quality may influence because of
worsened ventilation and illumination under floor slab.
• 4. It requires highly skilled supervision and labour force.
:
Guide wall
Diaphragm wall
Plunge columns
Roof slab
Concourse slab
Base slab Platform
• Construction sequence followed in the
roof slab is as under: Excavation for
the roof slab is done in parts starting
from one side of the station. The
exaction depth for a roof slab of
900mm is kept about 950mm. 50
mm thick layer of plane cement
concrete is poured on the base, PCC
acts as a barrier between soil and the
concrete and also acts as load bearing
surface for the slab. A 3mm thick ply
is placed over the finished PCC surface.
Fe 500D re bars are placed with clear
cover of 50mm.
• Concreting is put in continuous layers not extending more
than 300mm.Each layer is compacted by vibrating needle
before any succeeding layer. Immersion vibrators are 21
operated in vertical position and should not touch the bars
and water stoppers are put at the cutouts. A 5mm thick
water proofing layer is provided. To prevent damage to the
water proofing layer. Over the water proofing layer
another layer of PCC screed is provided 50mm thick, for final
leveling and development of the slope. Backfilling is done
over the finished slab, with sand followed soil. The sand
provides better path for drainage of the water seeping from
ground level.
• Following are the details of the Concourse slab:
• Thickness: 550mm
• The entire area of the concourse has been divided into 39
rooms including the station unpaid and the paid area.
• Following are some of the rooms present in the concourse:
1. ECS plant room (2).
2. Electrical panel room (2).
3. Electrical UPS room.
4. DB room.
5. Ticket office room TOR.
6. EFO 7. Telecom Equipment room TER.
8. Male toilet 9. Female toilet
10. Cleaner’s room.
• 2 It is a nonpublic area under platform consisting of
electric lines, services of drainage, sump (3). PCC of
300mm is done as it will be final coating and no tile
work will be done. It is double walled to
accommodate booster fans. Channels lead to sump.
• Columns for Platform slab (450*300) are given. It
consists of ASS 1&2. Earth mats are installed
underneath. Copper earth electrode: 22.5mm dia.
And 3m long. Size of riser of earth mat is 400 m2.
Copper conductors rise up to platform and are
enclosed in pipe.
• Block works: Block work parallel to
the D-wall is done. The block adds
to the aesthetic look of the station
plus creates path way for the
drainage system and also covers it.
• Block used are made of concrete.
Some of the details of Concrete
blocks used in the station are:
Dimension: 400x200x200 and
400x200x100.
Compressive strength: 7.5 MPa
(N/mm2 )
Density: 1800 kg/m3
• After two layer of block work scupper drain is
constructed between d-wall and block wall.
• PCC of grade M15 with waterproofing admixture is
laid first having 1:200 slope between low point to
high point.
• Then a 200mm half drain scupper drain is
constructed. Afterwards the waterproofing coat is
applied and screed 1:3 is done.
• Figure below shows the section of scupper drain.
• Given below is list of the scope of all finishing works:
• Stone cladding
• Flooring
• Tiles
• painting
• Plumbing
• False ceiling
• Glass
• SS works
• Mild steel railing
• Stone cladding is a thin layer of real or artificial stone
applied to a building or other structure made of a
material other than stone. Here in the station stone
cladding has been done to cover the block work.
• Almost entire area of the walls (except for Rooms in the
concourse and the station unpaid area) is covered with
cladding. Stone cladding may be classified into two
types: Dry stone cladding. The dry stone cladding
method uses fixed or embedded anchors or ties to
attach the stone to the block wall.
Wet stone cladding. Wet cladding uses an adhesive to
adhere the stone to the block wall. Here in the station
dry cladding is done.
• The dry cladding method is safe and
chances of stone falling down at a later
date is remote. b. Method allow for
expansion and contraction of stone in
extreme weather conditions. c. The dry
cladding method creates a gap of
around 50mm in between back wall
and stone lining , providing a layer of
air cushion that acts as a thermal
barrier. d. The appearance of stone
used in dry cladding work looks
aesthetically pleasing. The stone fixed
with mortar may change in color due
to absorption of water from back
mortar layer. The stones are cladded
on the block wall with the help of
clamps that are bolted into the block
wall with the help of drilling machine.
Figure below shows the clamp used in
the station.
Details of the Stones used for
cladding:
For cladding two types of stones
are used namely,
Jhallore Beige Granite (1200x600).
Tan Brown Granite (1200x600).
The thickness of both the stones is
30mm.
The height of wall cladding:
3300mm (as per drawing)
CLAMP USED FOR STONE CLADDING
Flooring is the general term for a permanent covering of
a floor, or for the work of installing such a floor covering.
Floor covering is a term to generically describe any finish
material applied over a floor structure to provide a
walking surface. Here in the station flooring works
include:
Honed Granite stone
Kota stone
GRC tactile
Polished vitrified tiles.
Matt vitrified tiles.
IPS flooring with hardener.
False floor
Glased tiles.
• Typical Steps to be followed during stone lying:
• Leveling and marking.
• Surface preparation.
• Mix preparation.
• Placing of Mix.
• Fixing of granite.
TOTAL STATION
(USED FOR SURVEYING,
PLOTTING OF POINTS ETC.)
Hazard tiles and Directional tactiles
• The plumbing system in the station is for the storage,
collection and the treatment of the waste water
generated. The waste water has been classified into two
categories namely,
• Sewage water.
• Seepage water.
• This waste water will be collected in sumps in the
undercroft level. Sewage water will be collected from
the toilets and stored in the sewage sumps- 160mm dia
and 110mm dia UPVC (Ultra Polyvinyl Chloride) pipes
are used to transport swage from toilets to the sump.
From the sump two 80mm dia
GI sewage riser pipe and one
80mm dia vent pipe lead to
the transportation of raw
water from sewage pit to the
ground level.
Upvc pipes used in plumbing
• The painting works on the station includes the following:
Acrylic Emulsion Paint.
Acrylic Washable Distemper.
Texture Paint.
Synthetic Enamel Paint.
• False Ceiling: Metal false ceiling is done to cover the ducting
and wiring trays on the ceiling and to give an overall
aesthetic look to the station.
Metal false ceiling panels are of dimension 1200x600.
Threaded rods are used to for the fixing of panels to the
ceiling. These threaded rods are fixed at every 1200m
interval.
• Glass Work
• Following are types of glass to be used in the
station:
Toughened Glass of 8mm thick vinyl with intense
magenta color.
Toughened Glass of 8mm thick with frosted film.
13.52mm thick laminated glass.
8mm vinyl glass with intense magenta
•Stainless steel and mild steel works:
• Stainless steel railings The difference between two
SS blancks is 900mm.
• SS sheet cladding
• Mild steel Railing in the ancillary
This is a new technique of crossing underground
dependent on hydraulic system. It is suitable where
intensity of traffic at construction location is too heavy
and can’t be disturbed i.e. conventional open cut
method not possible. However the risk of settlement has
to be taken care of. Construction Sequence:
Utilities passing through the area are identified and
diverted.
Next we install soldier piles. They are spaced @ 1.5m c/c
with wooden leggings fixed in between to act as
retaining wall for further excavation.
Excavation is carried out 1m below strut level .1st layer
and second layer of strut are installed during the course
of excavation.
• After excavation till formation level the bed is
levelled and PCC done. Thrust bed(1m) and thrust
wall is constructed to transfer the thrust of jacking
force to soil at bottom.
• Pin pockets are provided as per drawings for
provision of jacking supports.
• First segment of box will have a cutter shield. Cutter
edge is made of MS plate and fixed to box using
anchor bolts. After completion of work it is cut and
removed. Drag sheet ( GI sheet/galvanised iron) is
provided to reduce drag between soil phase and box
segments. For this purpose anchor and
arrangements on 1st box is made.
• Box is casted in 3 stages.
Bottom slab, walls, top slab. Main feature of it are the
haunches that provide extra support
Thereafter jacking progresses, the front unit with shield
penetrates into soil and after every 200mm of push,
excavation within shield is carried out(manually).
After 1st segment advances to end of thrust bed , 2nd
box is brought in alignment and the procedure
continues. Rate of pushing is around 1-1.5 m/day. There
is intermediate jacking support left between base of
two boxes. forward pushing jacks(150 TN) fill the space.
1st box has additional jacks(wall and roof) for adjusting
the alignment during pushing. 20 mm thick MS plate is
provided at rim of boxes.
• The boring of tunnel line is carried by SUCG JV. It is
fully carried out through TBM ,from boring to
segment fixing as well. Diameter of tunnel is 5.7m.
It starts from launching shaft and ends at retrieval
shaft. Rk Puram had a retrieval shaft where the
tunnel digging ended that was started from
Munirka. Segments are precasted in casting yard at
Mundaka. A ring comprises of 5 segments and a key.
They are made of concrete of M50 grade. This line
of DMRC will have a standard gauge(1435 mm).
It consists of :
• Cutter head
• Front shield to hold cutter
• Mid shield that has jacks and conveyor belt to remove
excavated soil
• End shield deals with segment building .
• At one go length equal to 2 segments(1.2*2m) is excavated
and then ring building starts.
• Tail segment
• Gentry
• These holes are grouted simultaneously and the segments
are interlocked through banana bonds.
•Cross Passage:
• The upside and downside lines are interconnected
through cross passages spaced every 250m providing a
safe access between two tunnels in event of emergency.
It is a pit dug in slab for fitting escalator machinery. Std.
size used for it is 6.5m*1.75m.
• Three holes, 1st for main power cable, 2nd for signal
sensor, 3rd for sprinkler is left while construction. A
drainage pipe is also provided at bottom. Lift: For ease of
PD person, lift is provided at entry structures and within
station from concourse to platform. Its std. size is
2500mm*1900mm. Pit is 1500mm deep. Upper portion
between lift top and roof slab is left for block work. Last
20mm gap is filled with dry mortar packing as a
cushioning material for vibrations.
• Staircase:
Setting of survey points is done with great accuracy. They consist of
riser(140mm) and tread(300mm).
After every 8-15 steps there is a platform. The inside of station consists of
4 staircase, 2 public and 2 non-public.
Ventilation system:
The whole station is underground and it should cater to huge amount of
commuters every day. Also when the metro enters the station area from
tunnel it creates a huge pressure difference. Surely, this has to be dealt
with.
Tunnel Ventilation Shaft (TVS): to ensure adequate air quality in station
area.
Booster fans: In cut N cover. To balance pressure difference when train
enters and leaves station.
Over Track Exhaust (OTE) ducts: Over track area. It is made of precast
concrete segments and is grouted.
Booster fans: At undercroft wall.
Fresh air corridor and exhaust air corridor.
SUBWAY CONSTRUCTION
• Subways will come up at Munirka, Dabri, RK Puram,
IIT, Panchsheel Park, Chirag Delhi and Nehru Enclave.
• The subway planned at the Munirka Metro station is
expected to cater to a large number of people trying
to access Munirka Village and the market. The
station at Munirka will be one of the busiest ones on
the corridor and will cater to approximately 19,000
people per day in 2016.
• The subway will be located near the Munirka flyover
and will be in the unpaid area.
• The subway is being constructed using the box
pushing technology, with which vertical excavation
or large scale digging is not required. This method is
much faster than the conventional cut and cover
technology used generally for construction of
subways. For this subway, had we opted for the
conventional cut and cover technology, we would
have had to excavate the road above, which would
have disrupted traffic movement.
The total length of the
subway will be
approximately 43m. Seven
precast RCC boxes will be
pushed, with an internal size
of 4.2m by 4.7m and length
of each box being 6.3m.
• The condition of the road
above will be monitored
through various high
precision instruments during
the construction period.
Thanking You…..

More Related Content

Similar to training1 (1).pptx

self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsRavi Shankar
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)RAMPRASAD KUMAWAT
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningANURAG KASHYAP
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksKumarS250747
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationKumarS250747
 
Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with backgroundKazim sultani
 

Similar to training1 (1).pptx (20)

self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Finishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinningFinishing and other methods of construction, scaffolding, shoring, underpinning
Finishing and other methods of construction, scaffolding, shoring, underpinning
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Shinchan presentation.pptx
Shinchan presentation.pptxShinchan presentation.pptx
Shinchan presentation.pptx
 
Suraj presentation.pptx
Suraj presentation.pptxSuraj presentation.pptx
Suraj presentation.pptx
 
Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with background
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

training1 (1).pptx

  • 1. Industrial Training L&T SUCG JV Project-CC27(majenta line) Project Director-Mr. R. G. Saini Site - Munerika. Station Manager- Mr. Brijesh Garg
  • 2. • An endeavour over a period can be successful only with right guidance and mentorship. I take this opportunity to express my gratitude to all those who encouraged me for successful completion of Project Training. • I am deeply indebted to Mr RG Saini, Project Director for providing me this opportunity to work in such a prestigious organisation. • I owe my sincere regards to Mr. P.R.Lenka whose management at site made it possible for me to learn and gave me a healthy learning environment. ACKNOWLEDGEMENT
  • 3. • I express my sincere and profound thanks to Mr. Amrutesh who acted as a guide map, who steered me throughout my training through his excellent guidance and knowledge. • I owe warm hearted acknowledgement of gratitude to Mr. Sumit Dev who helped me a lot in my initial days clearing my irritating questions and making myself comfortable in L&T family. • I forfeit my respect to Mr. Rajeev Kumar whose guidance along with encouragement enabled me to work very efficiently throughout my period of Training. • The field training can’t be complete through some people. I also extend my thanks to all other members especially Mr. Prashant Kumar Pandey whose guidance gave a way to my learning. • And last but not the least my co trainees who made the training like being in a family and for those healthy and productive discussions.
  • 4. • Larsen & Toubro is a major Technology, engineering, construction, manufacturing and financial services conglomerate. L&T addresses critical needs in key sectorsInfrastructure, Power, Process Industries and Defense- for consumers in over 30 countries around the world. • CC-27 is L&T SUCG Joint Venture Project. The project contains five stations (Hauz Khas, Vasant Vihar, Munirka, and IIT&RK puram) About the Project
  • 5. • L&T SUCG CC27 DELHI planned to build a tunnel from the end of the underground ramp(near the metro station Shankar Vihar)to metro station Hauz Khas and underground ramp near the Metro Station Shankar Vihar and the underground metro station at Vasant Vihar, Munirka, RK Puram, IIT ,Hauz Khas. • The project was commenced on November 2012 and was to be completed in 42 months i.e. May 2016 but the deadline has been extended and now the project is expected to complete by December 2016.
  • 7. REMOVAL OF SHUTTERING FROM ES03@ MUNERIKA
  • 8.
  • 9. • 1. The shortened construction period due to simultaneous construction of the basement and the superstructure. • 2. More operational space gained from the advanced construction of floor slabs. • 3. The higher stiffness of floor slab compare to steel struts improves the safety of excavation. • 4. It is highly suitable for construction for tall buildings with deep basements constructed in urban areas.
  • 10. • 1. Higher cost (due to the construction of pile foundation) • 2. Since the construction period of the basement is lengthened, the lateral displacement of retaining wall or ground settlement may possible increase due to the influence of creep if the soil layers are encountered. • 3. The construction quality may influence because of worsened ventilation and illumination under floor slab. • 4. It requires highly skilled supervision and labour force. :
  • 11. Guide wall Diaphragm wall Plunge columns Roof slab Concourse slab Base slab Platform
  • 12. • Construction sequence followed in the roof slab is as under: Excavation for the roof slab is done in parts starting from one side of the station. The exaction depth for a roof slab of 900mm is kept about 950mm. 50 mm thick layer of plane cement concrete is poured on the base, PCC acts as a barrier between soil and the concrete and also acts as load bearing surface for the slab. A 3mm thick ply is placed over the finished PCC surface. Fe 500D re bars are placed with clear cover of 50mm.
  • 13. • Concreting is put in continuous layers not extending more than 300mm.Each layer is compacted by vibrating needle before any succeeding layer. Immersion vibrators are 21 operated in vertical position and should not touch the bars and water stoppers are put at the cutouts. A 5mm thick water proofing layer is provided. To prevent damage to the water proofing layer. Over the water proofing layer another layer of PCC screed is provided 50mm thick, for final leveling and development of the slope. Backfilling is done over the finished slab, with sand followed soil. The sand provides better path for drainage of the water seeping from ground level.
  • 14. • Following are the details of the Concourse slab: • Thickness: 550mm • The entire area of the concourse has been divided into 39 rooms including the station unpaid and the paid area. • Following are some of the rooms present in the concourse: 1. ECS plant room (2). 2. Electrical panel room (2). 3. Electrical UPS room. 4. DB room. 5. Ticket office room TOR. 6. EFO 7. Telecom Equipment room TER. 8. Male toilet 9. Female toilet 10. Cleaner’s room.
  • 15.
  • 16. • 2 It is a nonpublic area under platform consisting of electric lines, services of drainage, sump (3). PCC of 300mm is done as it will be final coating and no tile work will be done. It is double walled to accommodate booster fans. Channels lead to sump. • Columns for Platform slab (450*300) are given. It consists of ASS 1&2. Earth mats are installed underneath. Copper earth electrode: 22.5mm dia. And 3m long. Size of riser of earth mat is 400 m2. Copper conductors rise up to platform and are enclosed in pipe.
  • 17. • Block works: Block work parallel to the D-wall is done. The block adds to the aesthetic look of the station plus creates path way for the drainage system and also covers it. • Block used are made of concrete. Some of the details of Concrete blocks used in the station are: Dimension: 400x200x200 and 400x200x100. Compressive strength: 7.5 MPa (N/mm2 ) Density: 1800 kg/m3
  • 18. • After two layer of block work scupper drain is constructed between d-wall and block wall. • PCC of grade M15 with waterproofing admixture is laid first having 1:200 slope between low point to high point. • Then a 200mm half drain scupper drain is constructed. Afterwards the waterproofing coat is applied and screed 1:3 is done. • Figure below shows the section of scupper drain.
  • 19.
  • 20. • Given below is list of the scope of all finishing works: • Stone cladding • Flooring • Tiles • painting • Plumbing • False ceiling • Glass • SS works • Mild steel railing
  • 21. • Stone cladding is a thin layer of real or artificial stone applied to a building or other structure made of a material other than stone. Here in the station stone cladding has been done to cover the block work. • Almost entire area of the walls (except for Rooms in the concourse and the station unpaid area) is covered with cladding. Stone cladding may be classified into two types: Dry stone cladding. The dry stone cladding method uses fixed or embedded anchors or ties to attach the stone to the block wall. Wet stone cladding. Wet cladding uses an adhesive to adhere the stone to the block wall. Here in the station dry cladding is done.
  • 22. • The dry cladding method is safe and chances of stone falling down at a later date is remote. b. Method allow for expansion and contraction of stone in extreme weather conditions. c. The dry cladding method creates a gap of around 50mm in between back wall and stone lining , providing a layer of air cushion that acts as a thermal barrier. d. The appearance of stone used in dry cladding work looks aesthetically pleasing. The stone fixed with mortar may change in color due to absorption of water from back mortar layer. The stones are cladded on the block wall with the help of clamps that are bolted into the block wall with the help of drilling machine. Figure below shows the clamp used in the station.
  • 23. Details of the Stones used for cladding: For cladding two types of stones are used namely, Jhallore Beige Granite (1200x600). Tan Brown Granite (1200x600). The thickness of both the stones is 30mm. The height of wall cladding: 3300mm (as per drawing) CLAMP USED FOR STONE CLADDING
  • 24. Flooring is the general term for a permanent covering of a floor, or for the work of installing such a floor covering. Floor covering is a term to generically describe any finish material applied over a floor structure to provide a walking surface. Here in the station flooring works include: Honed Granite stone Kota stone GRC tactile Polished vitrified tiles. Matt vitrified tiles. IPS flooring with hardener. False floor Glased tiles.
  • 25. • Typical Steps to be followed during stone lying: • Leveling and marking. • Surface preparation. • Mix preparation. • Placing of Mix. • Fixing of granite. TOTAL STATION (USED FOR SURVEYING, PLOTTING OF POINTS ETC.) Hazard tiles and Directional tactiles
  • 26. • The plumbing system in the station is for the storage, collection and the treatment of the waste water generated. The waste water has been classified into two categories namely, • Sewage water. • Seepage water. • This waste water will be collected in sumps in the undercroft level. Sewage water will be collected from the toilets and stored in the sewage sumps- 160mm dia and 110mm dia UPVC (Ultra Polyvinyl Chloride) pipes are used to transport swage from toilets to the sump.
  • 27. From the sump two 80mm dia GI sewage riser pipe and one 80mm dia vent pipe lead to the transportation of raw water from sewage pit to the ground level. Upvc pipes used in plumbing
  • 28. • The painting works on the station includes the following: Acrylic Emulsion Paint. Acrylic Washable Distemper. Texture Paint. Synthetic Enamel Paint. • False Ceiling: Metal false ceiling is done to cover the ducting and wiring trays on the ceiling and to give an overall aesthetic look to the station. Metal false ceiling panels are of dimension 1200x600. Threaded rods are used to for the fixing of panels to the ceiling. These threaded rods are fixed at every 1200m interval.
  • 29. • Glass Work • Following are types of glass to be used in the station: Toughened Glass of 8mm thick vinyl with intense magenta color. Toughened Glass of 8mm thick with frosted film. 13.52mm thick laminated glass. 8mm vinyl glass with intense magenta •Stainless steel and mild steel works: • Stainless steel railings The difference between two SS blancks is 900mm. • SS sheet cladding • Mild steel Railing in the ancillary
  • 30. This is a new technique of crossing underground dependent on hydraulic system. It is suitable where intensity of traffic at construction location is too heavy and can’t be disturbed i.e. conventional open cut method not possible. However the risk of settlement has to be taken care of. Construction Sequence: Utilities passing through the area are identified and diverted. Next we install soldier piles. They are spaced @ 1.5m c/c with wooden leggings fixed in between to act as retaining wall for further excavation. Excavation is carried out 1m below strut level .1st layer and second layer of strut are installed during the course of excavation.
  • 31. • After excavation till formation level the bed is levelled and PCC done. Thrust bed(1m) and thrust wall is constructed to transfer the thrust of jacking force to soil at bottom. • Pin pockets are provided as per drawings for provision of jacking supports. • First segment of box will have a cutter shield. Cutter edge is made of MS plate and fixed to box using anchor bolts. After completion of work it is cut and removed. Drag sheet ( GI sheet/galvanised iron) is provided to reduce drag between soil phase and box segments. For this purpose anchor and arrangements on 1st box is made.
  • 32. • Box is casted in 3 stages. Bottom slab, walls, top slab. Main feature of it are the haunches that provide extra support Thereafter jacking progresses, the front unit with shield penetrates into soil and after every 200mm of push, excavation within shield is carried out(manually). After 1st segment advances to end of thrust bed , 2nd box is brought in alignment and the procedure continues. Rate of pushing is around 1-1.5 m/day. There is intermediate jacking support left between base of two boxes. forward pushing jacks(150 TN) fill the space. 1st box has additional jacks(wall and roof) for adjusting the alignment during pushing. 20 mm thick MS plate is provided at rim of boxes.
  • 33.
  • 34. • The boring of tunnel line is carried by SUCG JV. It is fully carried out through TBM ,from boring to segment fixing as well. Diameter of tunnel is 5.7m. It starts from launching shaft and ends at retrieval shaft. Rk Puram had a retrieval shaft where the tunnel digging ended that was started from Munirka. Segments are precasted in casting yard at Mundaka. A ring comprises of 5 segments and a key. They are made of concrete of M50 grade. This line of DMRC will have a standard gauge(1435 mm).
  • 35.
  • 36. It consists of : • Cutter head • Front shield to hold cutter • Mid shield that has jacks and conveyor belt to remove excavated soil • End shield deals with segment building . • At one go length equal to 2 segments(1.2*2m) is excavated and then ring building starts. • Tail segment • Gentry • These holes are grouted simultaneously and the segments are interlocked through banana bonds.
  • 37.
  • 38. •Cross Passage: • The upside and downside lines are interconnected through cross passages spaced every 250m providing a safe access between two tunnels in event of emergency. It is a pit dug in slab for fitting escalator machinery. Std. size used for it is 6.5m*1.75m. • Three holes, 1st for main power cable, 2nd for signal sensor, 3rd for sprinkler is left while construction. A drainage pipe is also provided at bottom. Lift: For ease of PD person, lift is provided at entry structures and within station from concourse to platform. Its std. size is 2500mm*1900mm. Pit is 1500mm deep. Upper portion between lift top and roof slab is left for block work. Last 20mm gap is filled with dry mortar packing as a cushioning material for vibrations.
  • 39. • Staircase: Setting of survey points is done with great accuracy. They consist of riser(140mm) and tread(300mm). After every 8-15 steps there is a platform. The inside of station consists of 4 staircase, 2 public and 2 non-public. Ventilation system: The whole station is underground and it should cater to huge amount of commuters every day. Also when the metro enters the station area from tunnel it creates a huge pressure difference. Surely, this has to be dealt with. Tunnel Ventilation Shaft (TVS): to ensure adequate air quality in station area. Booster fans: In cut N cover. To balance pressure difference when train enters and leaves station. Over Track Exhaust (OTE) ducts: Over track area. It is made of precast concrete segments and is grouted. Booster fans: At undercroft wall. Fresh air corridor and exhaust air corridor.
  • 40. SUBWAY CONSTRUCTION • Subways will come up at Munirka, Dabri, RK Puram, IIT, Panchsheel Park, Chirag Delhi and Nehru Enclave. • The subway planned at the Munirka Metro station is expected to cater to a large number of people trying to access Munirka Village and the market. The station at Munirka will be one of the busiest ones on the corridor and will cater to approximately 19,000 people per day in 2016.
  • 41. • The subway will be located near the Munirka flyover and will be in the unpaid area. • The subway is being constructed using the box pushing technology, with which vertical excavation or large scale digging is not required. This method is much faster than the conventional cut and cover technology used generally for construction of subways. For this subway, had we opted for the conventional cut and cover technology, we would have had to excavate the road above, which would have disrupted traffic movement.
  • 42. The total length of the subway will be approximately 43m. Seven precast RCC boxes will be pushed, with an internal size of 4.2m by 4.7m and length of each box being 6.3m. • The condition of the road above will be monitored through various high precision instruments during the construction period.