SlideShare a Scribd company logo
By: Malyar Talash
1
2
3
This statement for design or safe system of design work has
been prepared as part of the reserved matters application
submission for the site at Baharak Road which has out limit
approval ref. This report will seek to address condition of
management and planning section of the design. As part of
the basic road design the road has been divided to different
practical stages to use the smart link and objective resources
in case.
This document must read with the conjunction of the drawing
presents.
4
 Typical roadway cross section
 Typical super elevated roadway section with widening
 Typical super elevated roadway cross section
 Typical cross section in hilly area soft cutting
 Typical cross section in hilly area soft cutting (where longitudinal
slop is more than 5%
 Typical roadway cross section in Built up area
 Typical roadway cross section in Bazaar area
 Typical roadway cross section in hard cutting
5
 Typical roadway cross section hard rock cutting
 Typical roadway cross section for cut station where restricted by site
conditions
 Typical roadway cross section with retaining wall (for fill) and trapezoidal lined
ditch
 Typical roadway cross section with retaining wall (River side) and breast wall
 Typical roadway cross section for rock fill (Where water table is less than 0.8m
and water slush)
 Typical roadway cross section with RCC retaining wall (Where river wide is
not enough for Stone masonry wall)
 Typical roadway cross section with Stone Masonry Breast wall
 Typical roadway section for Benching station (Lose materials)
6
 Development plan
 Land surface data (Topographic
and Utilities)
 Photographs
 Lay- byes (Parking)
 Catchment and drainage
 Signposting
 Environmental
 Vegetation and soil
 Transport requirement
7
 Geotechnical
 Previews design
 Crash history
 Design speed
 Operating speed
 Road safety
 Design report and design issues log
 Structures (Bridges, Culverts, Washes,
Retaining walls)
 Construction input
 Pavement design
 Topographic data
 Determine minimum horizontal curve radius
 Determine minimum vertical curve length or K value (for Crest and Sag)
 Determine the maximum Superelvation rate (e%)
 Design values
 Values outside design guideline limits
 Road function
 Speed
 Traffic composition and volume
 Design vehicle
 safety analyze
 Road space allocation
8
 Horizontal curve and alignment
 Vertical alignment
 Traffic facilities
 Bridge structures
 Environment
 Ramps
 Storm water management
 Hydrology
 Property boundaries
 Site issues
 Draft plan output (layout, sections, details)
9
 The proposed Road is located in the South East side of Badakhshan Province. The
alignment of the access road passes through Baharak district. The area is hilly, not
flat or level. There is need for more cases of land donation in this project because it
has surrounded by river mountainous terrain and green land. The road width is
about 11m. The road needs cutting, filling, Sub- base course, base course, Asphalt
carriageway and Double Bituminous Surface Treatment (DBST) with side drain
and construction of structures (Culverts, Retaining and breast walls (Stone
masonry and RCC), Washes, Bridges (RCC, PC) along the road.
 The construction of this road needs, roadway excavation, road way embankment
filling, side cutting (Lose, Soft, Rock and Hard rock materials) asphalt surfacing,
DBST surfacing, gravel surfacing, side drain (earthen, stone pitching, Rip Rap and
lined), culverts (Pre- Cost and cost in place) and fords.
10
 As it is knowing that the road length is 108 km and it passes through three districts
Baharak (1150 m from sea level), Wardooj, Zebaak and Eshkashem (2500 m form
sea level). and the highest elevation is 3000 m form sea level. The elevation
difference from start to end is almost 1350 m, which show high rate of elevation
changes. And the road sections are located in different terrains like flat, rolling and
mountainous.
11
Terrain Classification Table
Terrain Classification Cross Slope % 5m Contour line Per Kilometer
Flat (Level) 0-10 0-10
Rolling 10-25 11-25
Mountainous 25-60 26-60
Super Mountainous (Steep) <60 <60
 The AASHTO “A policy on Geometric Design of Highway and Streets” 2011 and
Overseas Road Note 6 “A Guide to Geometric Design” published by the Transport
Research Laboratory (Overseas Unit), 1988 was also consulted, which gives
guidance on geometric design.
12
 For safe and smooth ride and increasing the safety factor in the entire length of the
road only to the sharp curves based on AASHTO 2011 A policy on Geometric
Design of Highway and Streets widening have applied as per below table. The
design vehicle WB-19 has considered. The widening need to be applied both in
inner and outer side, but due to the mountainous terrain we have consider only the
inner side.
13
14
15
Geometric element Design Type Rural Road
Horizontal Geometry
Desirable Parameters
Design Speed 80 Km/h
Radius, R (min)
Super-elevation, SE
Stopping Sight Distance, SSD
230m,
8%
130m
Desirable minimum parameters
Speed, km/hour 60 Km/h
Radius, R(min) 115m
Super-elevation, SE 8%
Stopping Sight Distance, SSD 85m
Absolute minimum parameters
Speed, km/hour 50
Radius, R(min) 75m
Super-elevation, SE 8%
Stopping Sight Distance, SSD 65m
Minimum crest K value 26
Minimum sag K value 30
Side friction factor 0.18
Longitudinal friction factor 0.4
16
17
Although Superelvation is beneficial for
traffic operations, various factors often
combine to make its use impractical in
low-speed urban areas. These factors
include:
 wide pavement areas;
 the need to meet the grade of adjacent
property;
 surface drainage considerations;
 the desire to maintain low-speed
operation; and
 frequency of intersecting cross streets,
alleys, and driveways.
18
Considering the characteristics of the
soil of the existing embankment and
which is likely t be used for the
construction of the earth embankments.
 Normal Cut 1:1 with no benches on
any stages.
 Lose materials cut 1:1 with benches in
6m height and 3-meter width with 4.0%
to ward earthen drain.
 Hard materials cut 0.4:1 disturb by jack
hummer.
 Hard Rock materials cut 0.1:1 disturb
by blast.
 Composition materials for cutting Big
hard rock exist in Lose materials.
Traffic Composition
19
ESAL Calculation
20
Structural Design Input Data without
Subbase Layer
21
Analysis Period 20 Years
Stages Single Stage
ESALs 7.0*106
Reliability, % 80
Overall Standard Deviation, So 0.45
Design Subgrade CBR, % 14
Roadbed MR, Psi 13,800
Relative Damage Factor, uf 1.0
Effective Roadbed MR, Psi 13,800
Initial Serviceability Index, Po 4.2
Terminal Serviceability Index, Pt 2.0
Serviceability Loss, ΔPSI 2.2
Required Structural Number 3.36
Flexible Pavement Structural Design
without Subbase Layer
22
Layers
Structural Layer
Coefficient
Drainage
Coefficient
Resilient Modulus,
psi (MPa)
Thickness, in. (cm)
Asphalt Surface Course 0.42 1.97 (5.0)
Asphalt Binder Course 0.40 2.36 (6.0)
Granular Untreated Base 0.14 1.0 42,200 (291) 11.41 (29.0)
Subgrade (CBR = 14%) 13,800 (95)
Pavement Section Structural Number 3.37 > 3.36
23
24
25
26
27
28
List of Retaining Walls
Sl. No.
Chainages Dimensions
Remarks
From To L H1
H2
(Foundatio
n)
Total
(Km) (Km) (m) (m) H
1 40+000 40+086 86.0 New R.Wall Non River Side RHS
1 40+000 40+010 10.0 9.00 1.20 10.20 New R.Wall Non River Side RHS
2 40+010 40+020 10.0 10.00 1.20 11.20 New R.Wall Non River Side RHS
3 40+020 40+040 20.0 10.00 1.20 11.20 New R.Wall Non River Side RHS
4 40+040 40+050 10.0 9.50 1.20 10.70 New R.Wall Non River Side RHS
5 40+050 40+060 10.0 9.00 1.20 10.20 New R.Wall Non River Side RHS
6 40+060 40+070 10.0 8.00 1.20 9.20 New R.Wall Non River Side RHS
7 40+070 40+086 16.0 7.00 1.20 8.20 New R.Wall Non River Side RHS
Sub Total 86.0
2 40+346 40+400 54.00
1 40+346 40+350 4.00 6.00 1.20 7.20 New R.Wall Non River Side RHS
2 40+350 40+370 20.00 7.50 1.20 8.70 New R.Wall Non River Side RHS
3 40+370 40+400 30.00 8.00 1.20 9.20 New R.Wall Non River Side RHS
Sub Total 54.0
List of RCC Side Drain & Quantities
Sl. No.
Chainages Dimensions
From To Length Side Total Length Remarks Depth
(Km) (Km) (m) (m)
40+000 43+926 3926.210 2 7852.42
Total Length =
7,852.42
7852.42
List of Guard Rail
Sl. No.
Chainages Dimensions
From To Length Side
Total
Length
Remarks
(Km) (Km) (m) (m)
1 43+610 43+800 190.000 1 190 RHS
2 43+300 43+370 70.000 1 70 LHS
3 42+820 42+915 95.000 1 95 RHS
4 41+870 42+050 180.000 1 180 LHS
5 40+078 40+346 268.000 1 268 RHS
Total Length = 803.00
29
No Description Quantity(Cub-m)
1 Total Cutting 17008.21057
2 Soft Cutting 17008.21057
3 Hard Rock Cutting 0
4 Rock Cutting 0
5 Total Filling 142388.4071
6 Cut to Fill 1700.821057
7 Cut to Spiol 15307.38951
8 Fill from Borrow 140687.586
Center Line Coordinates
Station Easting Northing Elevation Existing Elevation Design Elevation Difference
40+000.00 668901.158 4096673.268 1,470.414m 1,470.414m 0.000m
40+010.00 668892.5316 4096668.21 1,470.322m 1,471.131m -0.808m
40+020.00 668883.9052 4096663.152 1,470.481m 1,471.825m -1.344m
40+030.00 668875.2788 4096658.094 1,471.014m 1,472.491m -1.477m
40+040.00 668866.6526 4096653.035 1,471.581m 1,473.129m -1.548m
40+050.00 668858.1216 4096647.818 1,472.551m 1,473.738m -1.187m
40+060.00 668849.7691 4096642.321 1,473.391m 1,474.318m -0.927m
40+070.00 668841.6045 4096636.547 1,474.234m 1,474.870m -0.636m
40+080.00 668833.6369 4096630.505 1,475.109m 1,475.393m -0.284m
40+090.00 668825.875 4096624.201 1,475.497m 1,475.888m -0.391m
40+100.00 668818.3276 4096617.641 1,475.966m 1,476.354m -0.388m
40+110.00 668811.0029 4096610.834 1,476.346m 1,476.791m -0.445m
40+120.00 668803.9092 4096603.786 1,476.773m 1,477.200m -0.427m
40+130.00 668797.0544 4096596.506 1,477.256m 1,477.580m -0.324m
40+140.00 668790.4453 4096589.002 1,477.502m 1,477.932m -0.430m
40+150.00 668783.9448 4096581.403 1,477.168m 1,478.255m -1.087m
40+160.00 668777.4444 4096573.804 1,477.371m 1,478.550m -1.179m
40+170.00 668770.9439 4096566.205 1,477.523m 1,478.816m -1.294m
40+180.00 668764.4435 4096558.606 1,477.610m 1,479.054m -1.443m
40+190.00 668757.943 4096551.007 1,477.600m 1,479.263m -1.662m
40+200.00 668751.4426 4096543.408 1,477.612m 1,479.454m -1.842m
30
Point Number Easting Northing Point Elevation Raw Description Grid Easting Grid Northing Longitude Latitude Convergence
62829669942.1160m 4093550.7210m 1444.302m BM 1 669942.1160m 4093550.7210m E70° 54' 33.10" N36° 58' 21.84" 1° 08' 54.71"
62830669730.8100m 4093659.2710m 1449.602m BM2 669730.8100m 4093659.2710m E70° 54' 24.65" N36° 58' 25.49" 1° 08' 49.72"
62831669744.3900m 4093698.1770m 1448.833m BM3 669744.3900m 4093698.1770m E70° 54' 25.23" N36° 58' 26.75" 1° 08' 50.11"
62832669616.6450m 4093889.8400m 1449.072m BM 4 669616.6450m 4093889.8400m E70° 54' 20.22" N36° 58' 33.05" 1° 08' 47.26"
62834669328.8990m 4094138.6530m 1493.235m BM 5 669328.8990m 4094138.6530m E70° 54' 08.79" N36° 58' 41.30" 1° 08' 40.60"
62835669283.5300m 4094167.6860m 1463.414m BM 6 669283.5300m 4094167.6860m E70° 54' 06.98" N36° 58' 42.27" 1° 08' 39.53"
62836669153.7020m 4094313.6410m 1463.326m BM 7 669153.7020m 4094313.6410m E70° 54' 01.85" N36° 58' 47.09" 1° 08' 36.57"
62837669039.7300m 4094544.7800m 1464.204m BM 8 669039.7300m 4094544.7800m E70° 53' 57.43" N36° 58' 54.66" 1° 08' 34.11"
31
Daylight Report
Station
Left Daylight
X Left Y Left Z Left
Right Daylight
X Right Y Right Z Right
Offset Offset
40+000.00 -12.602 668,907.53 4,096,662.40 1,474.25 12.602 668,894.78 4,096,684.14 1,464.59
40+020.00 -12.602 668,890.28 4,096,652.28 1,475.39 12.602 668,877.53 4,096,674.02 1,465.34
40+040.00 -12.602 668,873.05 4,096,642.18 1,476.27 12.602 668,860.26 4,096,663.90 1,467.41
40+060.00 -12.602 668,856.87 4,096,631.91 1,475.34 12.602 668,842.67 4,096,652.73 1,470.19
40+080.00 -12.602 668,841.42 4,096,620.59 1,477.46 28.116 668,816.28 4,096,652.62 1,468.06
40+100.00 -12.602 668,826.75 4,096,608.27 1,479.51 16.419 668,807.35 4,096,629.85 1,474.87
40+120.00 -12.602 668,812.94 4,096,595.00 1,478.97 21.733 668,788.34 4,096,618.95 1,473.06
40+140.00 -12.602 668,800.02 4,096,580.81 1,480.52 24.376 668,771.92 4,096,604.85 1,472.47
40+160.00 -12.602 668,787.02 4,096,565.61 1,480.85 26.552 668,757.27 4,096,591.06 1,472.00
40+180.00 -12.602 668,774.02 4,096,550.41 1,480.93 28.113 668,743.08 4,096,576.88 1,471.72
40+200.00 -12.602 668,761.02 4,096,535.22 1,480.62 17.727 668,737.97 4,096,554.93 1,477.32
40+220.00 -12.602 668,748.02 4,096,520.02 1,479.87 29.584 668,715.96 4,096,547.44 1,471.77
40+240.00 -16.05 668,737.20 4,096,502.28 1,482.49 28.112 668,704.58 4,096,532.04 1,472.89
40+260.00 -13.37 668,720.42 4,096,489.10 1,480.64 26.141 668,693.45 4,096,517.98 1,474.26
40+280.00 -12.602 668,703.99 4,096,475.95 1,483.69 25.627 668,680.21 4,096,505.89 1,474.90
40+300.00 -12.602 668,687.03 4,096,463.56 1,482.68 21.017 668,668.29 4,096,491.47 1,477.58
40+320.00 -12.602 668,669.14 4,096,452.56 1,484.48 15.763 668,655.26 4,096,477.29 1,480.59
40+340.00 -12.602 668,650.61 4,096,443.07 1,485.41 15.38 668,638.53 4,096,468.31 1,481.17
40+360.00 -12.602 668,632.57 4,096,434.44 1,485.09 12.602 668,621.69 4,096,457.17 1,477.53
40+380.00 -12.602 668,614.53 4,096,425.80 1,484.84 12.602 668,603.65 4,096,448.54 1,477.24
40+400.00 -12.602 668,596.49 4,096,417.17 1,482.82 35.459 668,575.74 4,096,460.52 1,472.28
40+420.00 -12.602 668,578.45 4,096,408.53 1,483.28 18.147 668,565.18 4,096,436.27 1,481.32
40+440.00 -14.213 668,561.11 4,096,398.45 1,483.67 37.225 668,538.90 4,096,444.84 1,472.16
40+460.00 -13.828 668,542.90 4,096,390.16 1,485.42 35.174 668,521.75 4,096,434.36 1,473.74
32
33

More Related Content

What's hot

Vertical alignment
Vertical alignmentVertical alignment
Vertical alignment
Ghulam Murtaza
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highway
PratikShinde113
 
Horizontal alignment of Roads
Horizontal alignment of RoadsHorizontal alignment of Roads
Horizontal alignment of Roads
Latif Hyder Wadho
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
srinivas2036
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
EWIT
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curves
sachin dass
 
Highway Development & Planning
Highway Development & PlanningHighway Development & Planning
Highway Development & Planning
Ritom Debnath
 
Horizontal curve- IRC 38
Horizontal curve- IRC 38Horizontal curve- IRC 38
Horizontal curve- IRC 38
Surabhi Suman
 
Sight distance .pptx
Sight distance .pptxSight distance .pptx
Sight distance .pptx
Krish Bhavsar
 
Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)
Civil Zone
 
Traffic studies and importance
Traffic studies and importance Traffic studies and importance
Traffic studies and importance
SACHIN NAGAYACH
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
reemajadwani
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
Sachin PatiL
 
Design of highway (Flexible pavement)
Design of highway (Flexible pavement)Design of highway (Flexible pavement)
Design of highway (Flexible pavement)
Raz Gupta
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
Latif Hyder Wadho
 
INTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGINTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERING
jagadeesh prasad
 
Highway Cross Section Elements
Highway Cross Section ElementsHighway Cross Section Elements
Highway Cross Section Elements
RAMPRASAD KUMAWAT
 
Unit 1
Unit 1Unit 1
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
tirath prajapati
 
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Hossam Shafiq I
 

What's hot (20)

Vertical alignment
Vertical alignmentVertical alignment
Vertical alignment
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highway
 
Horizontal alignment of Roads
Horizontal alignment of RoadsHorizontal alignment of Roads
Horizontal alignment of Roads
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curves
 
Highway Development & Planning
Highway Development & PlanningHighway Development & Planning
Highway Development & Planning
 
Horizontal curve- IRC 38
Horizontal curve- IRC 38Horizontal curve- IRC 38
Horizontal curve- IRC 38
 
Sight distance .pptx
Sight distance .pptxSight distance .pptx
Sight distance .pptx
 
Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)
 
Traffic studies and importance
Traffic studies and importance Traffic studies and importance
Traffic studies and importance
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
Design of highway (Flexible pavement)
Design of highway (Flexible pavement)Design of highway (Flexible pavement)
Design of highway (Flexible pavement)
 
Highway And traffic Engineering
Highway And traffic EngineeringHighway And traffic Engineering
Highway And traffic Engineering
 
INTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERINGINTERSECTIONS IN TRAFFIC ENGINEERING
INTERSECTIONS IN TRAFFIC ENGINEERING
 
Highway Cross Section Elements
Highway Cross Section ElementsHighway Cross Section Elements
Highway Cross Section Elements
 
Unit 1
Unit 1Unit 1
Unit 1
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
 

Similar to Highway design presentation (Malyar Talash)

PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
SantoshKapse9
 
Presentation_for_Road.pptx
Presentation_for_Road.pptxPresentation_for_Road.pptx
Presentation_for_Road.pptx
SantoshKapse9
 
design.pptx
design.pptxdesign.pptx
design.pptx
SantoshKapse9
 
Detailed Parameter road.pptx
Detailed Parameter road.pptxDetailed Parameter road.pptx
Detailed Parameter road.pptx
SantoshKapse9
 
Detailed.pptx
Detailed.pptxDetailed.pptx
Detailed.pptx
SantoshKapse9
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
ArAayushGoel
 
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
swaongniyogi
 
HIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docHIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).doc
sydneyaugust1
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
Riaz Zalil
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
KHUSHBU SHAH
 
intro to alignment.pptx
intro to alignment.pptxintro to alignment.pptx
intro to alignment.pptx
CIVILSWATHI
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
Monu Prashar
 
Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
gunjatetm
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
AnshuRaj51911
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
Er. Bam Bhandari
 
Road-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptxRoad-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptx
RagibShuvo1
 

Similar to Highway design presentation (Malyar Talash) (20)

PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
 
Presentation_for_Road.pptx
Presentation_for_Road.pptxPresentation_for_Road.pptx
Presentation_for_Road.pptx
 
design.pptx
design.pptxdesign.pptx
design.pptx
 
Detailed Parameter road.pptx
Detailed Parameter road.pptxDetailed Parameter road.pptx
Detailed Parameter road.pptx
 
Detailed.pptx
Detailed.pptxDetailed.pptx
Detailed.pptx
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
 
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.pptHill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
Hill_Roads_Part -1_Geometric_Design_of_Hill_Road_18817.ppt
 
Diapositivas mod3
Diapositivas mod3Diapositivas mod3
Diapositivas mod3
 
Designing the highway
Designing the highwayDesigning the highway
Designing the highway
 
HIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docHIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).doc
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
intro to alignment.pptx
intro to alignment.pptxintro to alignment.pptx
intro to alignment.pptx
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
Road-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptxRoad-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptx
 

More from Malyar Talash

Railway engineering
Railway engineeringRailway engineering
Railway engineering
Malyar Talash
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
Malyar Talash
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
Malyar Talash
 
1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash
Malyar Talash
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
Malyar Talash
 
Intersection in roads by malyar talash
Intersection in roads by malyar talashIntersection in roads by malyar talash
Intersection in roads by malyar talash
Malyar Talash
 
Key factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar TalashKey factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar Talash
Malyar Talash
 

More from Malyar Talash (7)

Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
 
1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash1 geometric design elements of road by malyar talash
1 geometric design elements of road by malyar talash
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
 
Intersection in roads by malyar talash
Intersection in roads by malyar talashIntersection in roads by malyar talash
Intersection in roads by malyar talash
 
Key factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar TalashKey factors related to traffic crashes by Malyar Talash
Key factors related to traffic crashes by Malyar Talash
 

Recently uploaded

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 

Recently uploaded (20)

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 

Highway design presentation (Malyar Talash)

  • 2. 2
  • 3. 3
  • 4. This statement for design or safe system of design work has been prepared as part of the reserved matters application submission for the site at Baharak Road which has out limit approval ref. This report will seek to address condition of management and planning section of the design. As part of the basic road design the road has been divided to different practical stages to use the smart link and objective resources in case. This document must read with the conjunction of the drawing presents. 4
  • 5.  Typical roadway cross section  Typical super elevated roadway section with widening  Typical super elevated roadway cross section  Typical cross section in hilly area soft cutting  Typical cross section in hilly area soft cutting (where longitudinal slop is more than 5%  Typical roadway cross section in Built up area  Typical roadway cross section in Bazaar area  Typical roadway cross section in hard cutting 5
  • 6.  Typical roadway cross section hard rock cutting  Typical roadway cross section for cut station where restricted by site conditions  Typical roadway cross section with retaining wall (for fill) and trapezoidal lined ditch  Typical roadway cross section with retaining wall (River side) and breast wall  Typical roadway cross section for rock fill (Where water table is less than 0.8m and water slush)  Typical roadway cross section with RCC retaining wall (Where river wide is not enough for Stone masonry wall)  Typical roadway cross section with Stone Masonry Breast wall  Typical roadway section for Benching station (Lose materials) 6
  • 7.  Development plan  Land surface data (Topographic and Utilities)  Photographs  Lay- byes (Parking)  Catchment and drainage  Signposting  Environmental  Vegetation and soil  Transport requirement 7  Geotechnical  Previews design  Crash history  Design speed  Operating speed  Road safety  Design report and design issues log  Structures (Bridges, Culverts, Washes, Retaining walls)  Construction input  Pavement design
  • 8.  Topographic data  Determine minimum horizontal curve radius  Determine minimum vertical curve length or K value (for Crest and Sag)  Determine the maximum Superelvation rate (e%)  Design values  Values outside design guideline limits  Road function  Speed  Traffic composition and volume  Design vehicle  safety analyze  Road space allocation 8
  • 9.  Horizontal curve and alignment  Vertical alignment  Traffic facilities  Bridge structures  Environment  Ramps  Storm water management  Hydrology  Property boundaries  Site issues  Draft plan output (layout, sections, details) 9
  • 10.  The proposed Road is located in the South East side of Badakhshan Province. The alignment of the access road passes through Baharak district. The area is hilly, not flat or level. There is need for more cases of land donation in this project because it has surrounded by river mountainous terrain and green land. The road width is about 11m. The road needs cutting, filling, Sub- base course, base course, Asphalt carriageway and Double Bituminous Surface Treatment (DBST) with side drain and construction of structures (Culverts, Retaining and breast walls (Stone masonry and RCC), Washes, Bridges (RCC, PC) along the road.  The construction of this road needs, roadway excavation, road way embankment filling, side cutting (Lose, Soft, Rock and Hard rock materials) asphalt surfacing, DBST surfacing, gravel surfacing, side drain (earthen, stone pitching, Rip Rap and lined), culverts (Pre- Cost and cost in place) and fords. 10
  • 11.  As it is knowing that the road length is 108 km and it passes through three districts Baharak (1150 m from sea level), Wardooj, Zebaak and Eshkashem (2500 m form sea level). and the highest elevation is 3000 m form sea level. The elevation difference from start to end is almost 1350 m, which show high rate of elevation changes. And the road sections are located in different terrains like flat, rolling and mountainous. 11 Terrain Classification Table Terrain Classification Cross Slope % 5m Contour line Per Kilometer Flat (Level) 0-10 0-10 Rolling 10-25 11-25 Mountainous 25-60 26-60 Super Mountainous (Steep) <60 <60
  • 12.  The AASHTO “A policy on Geometric Design of Highway and Streets” 2011 and Overseas Road Note 6 “A Guide to Geometric Design” published by the Transport Research Laboratory (Overseas Unit), 1988 was also consulted, which gives guidance on geometric design. 12
  • 13.  For safe and smooth ride and increasing the safety factor in the entire length of the road only to the sharp curves based on AASHTO 2011 A policy on Geometric Design of Highway and Streets widening have applied as per below table. The design vehicle WB-19 has considered. The widening need to be applied both in inner and outer side, but due to the mountainous terrain we have consider only the inner side. 13
  • 14. 14
  • 15. 15 Geometric element Design Type Rural Road Horizontal Geometry Desirable Parameters Design Speed 80 Km/h Radius, R (min) Super-elevation, SE Stopping Sight Distance, SSD 230m, 8% 130m Desirable minimum parameters Speed, km/hour 60 Km/h Radius, R(min) 115m Super-elevation, SE 8% Stopping Sight Distance, SSD 85m Absolute minimum parameters Speed, km/hour 50 Radius, R(min) 75m Super-elevation, SE 8% Stopping Sight Distance, SSD 65m Minimum crest K value 26 Minimum sag K value 30 Side friction factor 0.18 Longitudinal friction factor 0.4
  • 16. 16
  • 17. 17 Although Superelvation is beneficial for traffic operations, various factors often combine to make its use impractical in low-speed urban areas. These factors include:  wide pavement areas;  the need to meet the grade of adjacent property;  surface drainage considerations;  the desire to maintain low-speed operation; and  frequency of intersecting cross streets, alleys, and driveways.
  • 18. 18 Considering the characteristics of the soil of the existing embankment and which is likely t be used for the construction of the earth embankments.  Normal Cut 1:1 with no benches on any stages.  Lose materials cut 1:1 with benches in 6m height and 3-meter width with 4.0% to ward earthen drain.  Hard materials cut 0.4:1 disturb by jack hummer.  Hard Rock materials cut 0.1:1 disturb by blast.  Composition materials for cutting Big hard rock exist in Lose materials.
  • 21. Structural Design Input Data without Subbase Layer 21 Analysis Period 20 Years Stages Single Stage ESALs 7.0*106 Reliability, % 80 Overall Standard Deviation, So 0.45 Design Subgrade CBR, % 14 Roadbed MR, Psi 13,800 Relative Damage Factor, uf 1.0 Effective Roadbed MR, Psi 13,800 Initial Serviceability Index, Po 4.2 Terminal Serviceability Index, Pt 2.0 Serviceability Loss, ΔPSI 2.2 Required Structural Number 3.36
  • 22. Flexible Pavement Structural Design without Subbase Layer 22 Layers Structural Layer Coefficient Drainage Coefficient Resilient Modulus, psi (MPa) Thickness, in. (cm) Asphalt Surface Course 0.42 1.97 (5.0) Asphalt Binder Course 0.40 2.36 (6.0) Granular Untreated Base 0.14 1.0 42,200 (291) 11.41 (29.0) Subgrade (CBR = 14%) 13,800 (95) Pavement Section Structural Number 3.37 > 3.36
  • 23. 23
  • 24. 24
  • 25. 25
  • 26. 26
  • 27. 27
  • 28. 28 List of Retaining Walls Sl. No. Chainages Dimensions Remarks From To L H1 H2 (Foundatio n) Total (Km) (Km) (m) (m) H 1 40+000 40+086 86.0 New R.Wall Non River Side RHS 1 40+000 40+010 10.0 9.00 1.20 10.20 New R.Wall Non River Side RHS 2 40+010 40+020 10.0 10.00 1.20 11.20 New R.Wall Non River Side RHS 3 40+020 40+040 20.0 10.00 1.20 11.20 New R.Wall Non River Side RHS 4 40+040 40+050 10.0 9.50 1.20 10.70 New R.Wall Non River Side RHS 5 40+050 40+060 10.0 9.00 1.20 10.20 New R.Wall Non River Side RHS 6 40+060 40+070 10.0 8.00 1.20 9.20 New R.Wall Non River Side RHS 7 40+070 40+086 16.0 7.00 1.20 8.20 New R.Wall Non River Side RHS Sub Total 86.0 2 40+346 40+400 54.00 1 40+346 40+350 4.00 6.00 1.20 7.20 New R.Wall Non River Side RHS 2 40+350 40+370 20.00 7.50 1.20 8.70 New R.Wall Non River Side RHS 3 40+370 40+400 30.00 8.00 1.20 9.20 New R.Wall Non River Side RHS Sub Total 54.0 List of RCC Side Drain & Quantities Sl. No. Chainages Dimensions From To Length Side Total Length Remarks Depth (Km) (Km) (m) (m) 40+000 43+926 3926.210 2 7852.42 Total Length = 7,852.42 7852.42 List of Guard Rail Sl. No. Chainages Dimensions From To Length Side Total Length Remarks (Km) (Km) (m) (m) 1 43+610 43+800 190.000 1 190 RHS 2 43+300 43+370 70.000 1 70 LHS 3 42+820 42+915 95.000 1 95 RHS 4 41+870 42+050 180.000 1 180 LHS 5 40+078 40+346 268.000 1 268 RHS Total Length = 803.00
  • 29. 29 No Description Quantity(Cub-m) 1 Total Cutting 17008.21057 2 Soft Cutting 17008.21057 3 Hard Rock Cutting 0 4 Rock Cutting 0 5 Total Filling 142388.4071 6 Cut to Fill 1700.821057 7 Cut to Spiol 15307.38951 8 Fill from Borrow 140687.586 Center Line Coordinates Station Easting Northing Elevation Existing Elevation Design Elevation Difference 40+000.00 668901.158 4096673.268 1,470.414m 1,470.414m 0.000m 40+010.00 668892.5316 4096668.21 1,470.322m 1,471.131m -0.808m 40+020.00 668883.9052 4096663.152 1,470.481m 1,471.825m -1.344m 40+030.00 668875.2788 4096658.094 1,471.014m 1,472.491m -1.477m 40+040.00 668866.6526 4096653.035 1,471.581m 1,473.129m -1.548m 40+050.00 668858.1216 4096647.818 1,472.551m 1,473.738m -1.187m 40+060.00 668849.7691 4096642.321 1,473.391m 1,474.318m -0.927m 40+070.00 668841.6045 4096636.547 1,474.234m 1,474.870m -0.636m 40+080.00 668833.6369 4096630.505 1,475.109m 1,475.393m -0.284m 40+090.00 668825.875 4096624.201 1,475.497m 1,475.888m -0.391m 40+100.00 668818.3276 4096617.641 1,475.966m 1,476.354m -0.388m 40+110.00 668811.0029 4096610.834 1,476.346m 1,476.791m -0.445m 40+120.00 668803.9092 4096603.786 1,476.773m 1,477.200m -0.427m 40+130.00 668797.0544 4096596.506 1,477.256m 1,477.580m -0.324m 40+140.00 668790.4453 4096589.002 1,477.502m 1,477.932m -0.430m 40+150.00 668783.9448 4096581.403 1,477.168m 1,478.255m -1.087m 40+160.00 668777.4444 4096573.804 1,477.371m 1,478.550m -1.179m 40+170.00 668770.9439 4096566.205 1,477.523m 1,478.816m -1.294m 40+180.00 668764.4435 4096558.606 1,477.610m 1,479.054m -1.443m 40+190.00 668757.943 4096551.007 1,477.600m 1,479.263m -1.662m 40+200.00 668751.4426 4096543.408 1,477.612m 1,479.454m -1.842m
  • 30. 30 Point Number Easting Northing Point Elevation Raw Description Grid Easting Grid Northing Longitude Latitude Convergence 62829669942.1160m 4093550.7210m 1444.302m BM 1 669942.1160m 4093550.7210m E70° 54' 33.10" N36° 58' 21.84" 1° 08' 54.71" 62830669730.8100m 4093659.2710m 1449.602m BM2 669730.8100m 4093659.2710m E70° 54' 24.65" N36° 58' 25.49" 1° 08' 49.72" 62831669744.3900m 4093698.1770m 1448.833m BM3 669744.3900m 4093698.1770m E70° 54' 25.23" N36° 58' 26.75" 1° 08' 50.11" 62832669616.6450m 4093889.8400m 1449.072m BM 4 669616.6450m 4093889.8400m E70° 54' 20.22" N36° 58' 33.05" 1° 08' 47.26" 62834669328.8990m 4094138.6530m 1493.235m BM 5 669328.8990m 4094138.6530m E70° 54' 08.79" N36° 58' 41.30" 1° 08' 40.60" 62835669283.5300m 4094167.6860m 1463.414m BM 6 669283.5300m 4094167.6860m E70° 54' 06.98" N36° 58' 42.27" 1° 08' 39.53" 62836669153.7020m 4094313.6410m 1463.326m BM 7 669153.7020m 4094313.6410m E70° 54' 01.85" N36° 58' 47.09" 1° 08' 36.57" 62837669039.7300m 4094544.7800m 1464.204m BM 8 669039.7300m 4094544.7800m E70° 53' 57.43" N36° 58' 54.66" 1° 08' 34.11"
  • 31. 31 Daylight Report Station Left Daylight X Left Y Left Z Left Right Daylight X Right Y Right Z Right Offset Offset 40+000.00 -12.602 668,907.53 4,096,662.40 1,474.25 12.602 668,894.78 4,096,684.14 1,464.59 40+020.00 -12.602 668,890.28 4,096,652.28 1,475.39 12.602 668,877.53 4,096,674.02 1,465.34 40+040.00 -12.602 668,873.05 4,096,642.18 1,476.27 12.602 668,860.26 4,096,663.90 1,467.41 40+060.00 -12.602 668,856.87 4,096,631.91 1,475.34 12.602 668,842.67 4,096,652.73 1,470.19 40+080.00 -12.602 668,841.42 4,096,620.59 1,477.46 28.116 668,816.28 4,096,652.62 1,468.06 40+100.00 -12.602 668,826.75 4,096,608.27 1,479.51 16.419 668,807.35 4,096,629.85 1,474.87 40+120.00 -12.602 668,812.94 4,096,595.00 1,478.97 21.733 668,788.34 4,096,618.95 1,473.06 40+140.00 -12.602 668,800.02 4,096,580.81 1,480.52 24.376 668,771.92 4,096,604.85 1,472.47 40+160.00 -12.602 668,787.02 4,096,565.61 1,480.85 26.552 668,757.27 4,096,591.06 1,472.00 40+180.00 -12.602 668,774.02 4,096,550.41 1,480.93 28.113 668,743.08 4,096,576.88 1,471.72 40+200.00 -12.602 668,761.02 4,096,535.22 1,480.62 17.727 668,737.97 4,096,554.93 1,477.32 40+220.00 -12.602 668,748.02 4,096,520.02 1,479.87 29.584 668,715.96 4,096,547.44 1,471.77 40+240.00 -16.05 668,737.20 4,096,502.28 1,482.49 28.112 668,704.58 4,096,532.04 1,472.89 40+260.00 -13.37 668,720.42 4,096,489.10 1,480.64 26.141 668,693.45 4,096,517.98 1,474.26 40+280.00 -12.602 668,703.99 4,096,475.95 1,483.69 25.627 668,680.21 4,096,505.89 1,474.90 40+300.00 -12.602 668,687.03 4,096,463.56 1,482.68 21.017 668,668.29 4,096,491.47 1,477.58 40+320.00 -12.602 668,669.14 4,096,452.56 1,484.48 15.763 668,655.26 4,096,477.29 1,480.59 40+340.00 -12.602 668,650.61 4,096,443.07 1,485.41 15.38 668,638.53 4,096,468.31 1,481.17 40+360.00 -12.602 668,632.57 4,096,434.44 1,485.09 12.602 668,621.69 4,096,457.17 1,477.53 40+380.00 -12.602 668,614.53 4,096,425.80 1,484.84 12.602 668,603.65 4,096,448.54 1,477.24 40+400.00 -12.602 668,596.49 4,096,417.17 1,482.82 35.459 668,575.74 4,096,460.52 1,472.28 40+420.00 -12.602 668,578.45 4,096,408.53 1,483.28 18.147 668,565.18 4,096,436.27 1,481.32 40+440.00 -14.213 668,561.11 4,096,398.45 1,483.67 37.225 668,538.90 4,096,444.84 1,472.16 40+460.00 -13.828 668,542.90 4,096,390.16 1,485.42 35.174 668,521.75 4,096,434.36 1,473.74
  • 32. 32
  • 33. 33