SlideShare a Scribd company logo
Fire Risk Assessment
HINDUSTAN UNILEVER LIMITED
ETAH, UTTAR PRADESH
DATE OF ASSESSMENT: 08/06/2022 TO 09/06/2022
ACKNOWLEDGEMENT
Auditor expresses its sincere thanks to the Hindustan Unilever Plant Team for
their co-operation and unstinted help without which this assessment could not
have been possible.
The courtesy and cordiality extended to the auditor is highly appreciated.
I N D E X
Sr. No. Topic
1. General Information
2. Assessment Objectives
3. Assessment Scope
4. Assessment Methodology
5. Audit Team
6. List of Documents Verified
7. Fire Load Calculation
8. Observations and Recommendations
9. Attendance sheet of opening and closing meetings
General Information
 Plant and main product: Hindustan Unilever Limited
 No of Shifts: Multiple Shifts
 Worker Strength: 200
Assessment Objectives
 Identify opportunities to improve operational performance.
 Reduce incident rate.
 Reduce overall costs.
 Recognition to Plant Management.
 Determine the status of statutory documents and necessary compliance.
Assessment Scope
This Assessment was carried out with reference to the following standards:
NBC 2016 (Part 4)
Assessment Methodology
Following methodology adopted for successful completion of the assessment:
 Opening meeting.
 Presentation/Brief by the Plant team.
 Plant walkthrough.
 Discussions with key personnel, verification of statutory records/documents
 Close out meeting.
 Submission of the Report.
Assessment Team
Mirza Baig, Lead Auditor
Qualification: B Tech (Mechanical), PG Diploma (Industrial Safety), Lead Auditor ISO
9001, ISO 14001, ISO 45001, ISO 22001, CSP, NEBOSH, IOSH, OSHA.
Work Experience: 20 + Years (Global EHS Audit and Training)
List of documents Verified
Environment, Health & Safety management system documents
Sr.
No.
Document Name Availability Status
Yes No NA
1. Fire Safety management plan. Yes
2. EHS/Fire Policy. Yes
3. Organization chart Yes
4. Safety Budget Yes
5. EHS Manual Yes
6. Training records Yes
7. Fire Inspection/Internal Audit records Yes
8. Incident/near miss Reporting Records Yes
9. SOP for various activities Yes
10. Record of work permits Yes
11. Maintenance & testing record of fire protection
equipment’s
Yes
12. Accident record register. Yes
13. Safety induction records of workers and staff Yes
14. Pep talk / toolbox session records. Yes
15. Onsite emergency plan Yes
16. HIRA Yes
17. Record of Fire/Mock drills Yes
18. Approval of layouts and approvals from gov. authorities Yes
19. Records of modifications in plant Yes
20. Preventive maintenance logs and records Yes
21. Calibration and testing records Yes
22. Factory inspector register and communication record Yes
23. Factory license and License to Manufacture (Product) Yes
24. Explosive and petroleum license N/A
25. Gas Cylinders Storage License from CCE, if applicable. N/A
26. List of licensed electrician Yes
27. Approval of transformer and DG set Yes
28. Electrical maintenance record (Earth Pit, transformer oil,
lightning arrester, rubber mat etc)
Yes
29. Building stability certificate Yes
30. Fire NOC UP
INTRODUCTION
Fire is one of the major causes in the industrial area and there is increasing rates of fire
accidents which may kill the life of the people. The fire can cause due to three main
components such as Oxygen, Fuel and Heat is also known Fire triangle. When oxygen
supply is increased in the fire area the amount of fire burning rate increases so that heat can
be generated in huge amount. To suppress the fire one of the components must be removed.
The suitable fire extinguishers must be used to suppress the fire triangle so that fire can be
easily put off.
To suppress the fire on of the components such as oxygen, Fuel and Heat must be removed
so that burning rate of fire will be reduced. Fire alarm system is one of the essential needs
and must be installed in the building/factory where there are combustible materials present in
it. In case of fire, it is very useful to migrate and can be detected easily. Fire hydrants and fire
extinguisher must be installed where there is risk of fire. The suitable fire extinguishers must
be kept so that incase of fire it can be easily suppressed. Fire hydrants must be installed
outside to suppress the building of fire.
Classes of Fires and Fire Extinguishers
Classes of Fire Combustible
Materials
Examples Type of
Extinguisher
Class A Solid Wood, Plastic, Rubber etc Water, DCP Type
Class B Liquid Petrol, Diesel, LPG etc Foam Type
Class C Electrical Electrical Appliances CO2 Type
Class D Combustible Metals Magnesium, Potassium etc Water, DCP Type
Fire Load Calculation
Estimation of combustible material of a building can be determined by three methods they
are:
 Direct measurement of mass, with conversion based on the net heat of combustion
 Direct measurement of volume (with conversion based on a combination of density
and net heat of combustion)
 Energy release measurement by calorimetry of an item sufficiently
Fire load density is defined as the amount of heat liberated from a combustible material per
square meter in floor area. Fire load is to determine the severity and building up of fire. Fire
load is useful in determining the growth and severity of fires. The mass of the material is
calculated in kg. The calculated mass is multiplied by its calorific value in MJ/kg to get fire
load. The calculated value is then divided by area of the floor to give fire load density.
Fire load = (combustibles in kg) x calorific value in kcal-kg / Floor area in square
meters.
Calorific value of some common combustible materials
Poly Bags 17.5 Poly Propylene 42.66 Diesel 45.5
Wood 18.6 Carton box 16.9 Plastic 35
Paper (average) 16.3 Sack 16.6 Tea 4.281
Fire Load Calculation for PM Godown
Area: 976 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Carton 92407 16.9 1561678.3
CFC 42028 1.168 49088.704
Poly 70000 17.5 1225000
Sack 16354 16.6 271476.4
Tape 1000 35 35000
Wood Pallet 4800 18.6 89280
Plastic Pallet 3000 35 105000
Fire Load Density= (1561678.3+49088.704+1225000+271476.4+35000+89280+105000)
/976 = 3231630 MJ/M3
Fire Load Calculation for Jumbo Godown
Area: 2973 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Wooden Pallet 1200 18.6 22320
Plastic Pallet 15000 35 525000
Tea 600000 4.281 2568600
Fire Load Density= (22320+525000+2568600) / 2973 = 1048 MJ/M3
Fire Load Calculation for Godown 1
Area: 1394 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Plastic Pallet 11250 35 393750
Tea 250000 4.281 1070250
Fire Load Density= (393750+1070250) / 1394 = 1050 MJ/M3
Fire Load Calculation for Godown 2
Area: 1394 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Plastic Pallet 11250 35 393750
Tea 250000 4.281 1070250
Fire Load Density= (393750+1070250) / 1394 = 1050 MJ/M3
Fire Load Calculation for Shop Floor
Area: 1129 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Carton 2850 16.9 48165
CFC 946 1.168 1104.928
Poly 9600 17.5 168000
Sack 1500 16.6 24900
Tape 10 35 350
Wood Pallet 384 18.6 7142
Plastic Pallet 900 35 31500
Tea 20000 4.281 85620
Ink/Makeup 16 30 480
Fire Load Density= (48165+1104.928+168000+24900+350+7142+31500+85620+480) /
1129 = 325 MJ/M3
Fire Load Calculation for Day PM
Area: 140 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Carton 22648 16.9 382751
CFC 11352 1.168 13259.136
Poly 25000 17.5 437500
Sack 6280 16.6 104248
Tape 120 35 4200
Wood Pallet 4800 18.6 89280
Plastic Pallet 3000 35 105000
Fire Load Density= (382751+13259.136+437500+104248+4200+89280+105000) /140 =
8115 MJ/M3
Fire Load Calculation for Diesel Storage Room
Area: 20 SQM
Combustible
Materials
Weight in KG Calorific Value in
MJ/KG
Fire Load in MJ
Diesel 1900 45.5 86450
Fire Load Density= 86450 / 20 = 4322 MJ/M3
Conclusion
Fire load density is analyzed in the plant and the study gives following conclusion: The
maximum fire load density is found in PM Godown is 3231630 MJ/M3, Minimum is in Shop
Floor 325 MJ/M3 and the average value of fire load density in the plant is given as 463934
MJ/M3. The usage of wooden/Plastic pallets, poly bags and other carton box material can be
reduced to reduce fire load density. The Fire possibilities in the plant are solid/Liquid/Electric
fires. Since, Plant has following fire detection/suppression system in place as per the
requirement of National Building Code (NBC) 2016, part 4 and in adequate numbers;
 Dedicated firefighting/ERT team.
 Fire alarm system.
 Fire Hydrant System with hose reels and pump.
 Fire/smoke detectors.
 Portable fire extinguishers (DCP, Foam and CO2 types).
 One underground and two overhead water tanks.
 Frequent Fire drills as per statutory requirement.
 Frequent fire safety training.
 Sprinkler system.
Existing Capacity Additional Requirement (If any) As per
NBC 2016, Part 4
Water Tank/Pump
Under Ground – 1 Lac Litre
Overhead – 20 Thousand Litre
Not Required
(Ref. NBC 2016, Part 4 Table 23)
Fire hydrant line size- Ring, main and
branches- 4’’
No of Fire hydrant post- 13
No of Fire hose reel- 7
Not Required
(Ref. NBC 2016, Part 4 Table 23 & IS 13039)
Number of Fire Extinguisher (DCP, Foam
and CO2 Type)(5 kg, 9 kg, 20 kg)
Area No. Of FE
productionHall 20
Godown-1 9
Godown-2 8
AdminOffice FF 6
hopperSection 5
SecurityGate 4
Diesel Yard 4
Fire HydrantRoom 3
BlendArea 3
HT/LT Room 2
Scrap Yard 2
CompressorArea 2
ServerRoom 1
RestRoom 1
productionOffice 1
PCC room 1
Inkroom 1
Not Required
(Ref. NBC 2016, Part 4 Clause 5.1)
Manual Call Point- 19
Smoke Detector-196
Heat Detector- 66
Not Required
Fire Sprinklers
Jumbo Godown- 306
Godown 1- 132
Godown 2- 126
PM Store- 91
Not Required
(Ref. NBC 2016, Part 4 Clause 5.1.7)
Emergency Exit
Door Entry/Exists
Area Number
ProductionHall 4
DPMStore 2
QA Lab 2
ProductionOffice 1
Engg Store 1
AdminOffice 2
Change Room 3
Canteen 2
Dispensary 1
Not Required
(Ref. NBC 2016, Part 4 Clause 4.6)
Gate Room 1
PestRoom 2
TrainingRoom 1
Tea 1
PCC room 3
UPS room 2
OldToilet 1
NewToilet 2
LadiesToilet 1
Godown-1 2
Godown-2 2
PMStore 2
JumboGodown 6
Hence, there is no major requirement for fire detection/suppression in existing plant at the
moment. However, following opportunities for improvement identified during site visit.
Correction/modification will further enhance operational excellence as well as meeting
statutory requirements.
Plant falls under Moderate Hazard Industrial Building - G2 Category.
Opportunity for Improvements
Based on NBC 2016, Part 4
Sr.
No
Observation Recommendation Risk Matrix
1 PPE’s - SCBA (Self Contained
Breathing Apparatus) and firefighting
suits not available in the plant.
(Clause 4.1)
SCBA and firefighting suits
should be available in the
plant in adequate numbers.
2 Screening of employees/visitors
belongings/bags at security gate for
fire prone items such as lighter,
match box not evident.
(Clause 4.1)
Screening for bags should be
conducted at security gate to
ensure no fire prone items are
being brought in the plant.
3 Fire Hydrant system has one jockey
pump.
(Clause 4.1)
An additional jockey pump
may be installed to be used in
case of failure of first pump
during emergency.
4 Thermography test not conducted for
detecting electric failures/fires.
(Clause 3.4.10, Good Practices 4(9),
Part 8 section 2)
Thermography test should be
conducted by third party to
determine there is no electric
failure which may lead to
electric fires.
5 Plant has only one operational gate
for entry and exit. Emergency gate is
blocked by vehicles from outside.
(Clause 6.7.3.1)
Emergency gate should
always be free from blockage
for use in emergency
situations.
6 There is only one underground water
tank which fills two overhead tanks.
In fire emergency situation it will get
empty in 1-1.2 Hours.
(Clause 4.1 Ref. NBC Table 23)
It is recommended to have
one more underground water
tank of same capacity to
supply uninterrupted water for
at least two hours.
7 Fire safety is not included in HIRA
Chart.
(Clause 4.1)
Include it in HIRA chart and
communicate it to all
workforces through tool box
talk/induction training.
8 Emergency lighting system has
capacity of 30 minutes only.
(Clause 4.16.10)
It should be increased to 1-3
Hours.
9 PM Storage Area:
 Fire Exit sign not available
 List of trained fire fighters not
available
 Testing of hydrants and
sprinklers not done
 Access blocked partially by
materials
(Clause 4.2.7, 4.1, 5.1.1, 2.27)
 Provide exit sign board
 Display list of trained
fire fighters
 Conduct testing of
hydrants and sprinklers
quarterly
 Keep access free for
blockage all the times
10 Dust Extractor NO 3:
 Emergency ladder not  Provide additional
provided
 Housekeeping is in a very
poor condition
(Clause 4.11, 4.1)
ladder/stair for
emergency evacuation
 Maintain good
housekeeping to avoid
solid fires.
11 PM Plant passageway:
 Passageway obstructed by
materials.
 Fire exit signs not available
(Clause 2.27, 4.2.7)
 Passageway should be
free of obstacles at all
times
 Provide fire exit sign
board
12 Fire extinguishers kept on floor in
compressor area
(Clause 5.1.1)
All fire extinguishers should
be in hanging position, easily
assessable/visible
13 HB 07- access not clear
(Clause 5.1.1)
Clear access should be
provided.
14 Jumbo Godown:
 Fire exit sign not provided
 View of Fire extinguishers
blocked by materials
 Emergency exit gate height is
only 4 feet
(Clause 4.2.7, 5.1.1, 6.7.3.1)
 Provide fire exit sign
board
 Fire extinguishers
should be in hanging
position, easily
assessable/visible
 Either increase gate
height to 7 feet or
provide
additional/alternate
gate
15 VCB Room Area:
 Fire hydrant point missing
 Fire pipeline is 1.5 inch
(Clause 5.1.1, 5.1.1)
 Provide fire hydrant
point
 Change existing
pipeline into 4 inch
16 Transformer yard/DG Set area has
no fire extinguishers
(Clause 4.1)
Provide C type extinguisher
for transformer yard and foam
type extinguisher for DG set.
17 HB FH 11 is under emergency gate
stairs
(Clause 4.1)
Change the location.
18 Godown 2:
 HB/Extinguishers not
visible/access blocked
 Fire exit signs not provided
 No emergency exit/walkway
(Clause 4.1, 4.2.7)
 HB/Fire extinguishers
should be in hanging
position, easily
assessable/visible
 Provide fire exit sign
board
 Either provide
emergency exit gate or
create walkways all
around
19 Fire exit sign not provided in Godown Provide fire exit sign board
1
(Clause 4.2.7)
20 PCC Room:
 Rescue stick and electric hand
gloves not provided
 Fire extinguishers not
provided
(Clause 4.1)
 Provide rescue stick
and electric hand
gloves
 Provide at least 2 CO2
type fire extinguishers
at each gate (Inside)
 Automatic fire
suppression system
may be provided inside
the panels for
additional safety same
as provided in diesel
storage area.
21 Shop Floor:
Contract worker, Manoj Kumar,
Contractor – Shabbir Ahmed found
painting without Induction/tool box
talk, not aware about fire procedure
and use of fire extinguishers.
(Clause 4.1)
All contract workers should go
through induction training,
daily tool box talk and fire
safety awareness training.
Opening Meeting /Closing MeetingAttendanceSheet
Sr.
No.
Name of person Name of Organization Opening
Meeting
08/06/2022
Closing
Meeting
09/06/2022
1. Mirza Baig
(Lead Auditor)
Freelancer √ √
2. Vishal Pawar
(Safety Officer)
Hindustan Uniliver
Limited
√ √
3. Hanamant Kumbhar
Manager
Hindustan Uniliver
Limited
√ √
Report Prepared and Submitted by:
Mirza Baig
--------------------------------------------- END OF REPORT----------------------------------------------

More Related Content

What's hot

Fire Risk Assessment.pdf
Fire Risk Assessment.pdfFire Risk Assessment.pdf
Fire Risk Assessment.pdf
HSEXINYIPROJECT
 
fire_safety
fire_safetyfire_safety
Fire Safety Training
Fire Safety TrainingFire Safety Training
Fire Safety Training
Bhavana Agarwal
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
Gaurav Singh Rajput
 
Emergency Action Plans By OSHA
Emergency Action Plans By OSHAEmergency Action Plans By OSHA
Emergency Action Plans By OSHA
Atlantic Training, LLC.
 
Fire Fighting Theory
Fire Fighting TheoryFire Fighting Theory
2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Fire Extinguisher safety training
Fire Extinguisher safety trainingFire Extinguisher safety training
Fire Extinguisher safety training
Showa Denko Carbon
 
Fire extinguisher monthly checklist report
Fire extinguisher monthly checklist reportFire extinguisher monthly checklist report
Fire extinguisher monthly checklist report
Azmeel Contracting Company
 
Fire fighting course
Fire fighting courseFire fighting course
A Guide to Fire and Safety
A Guide to Fire and SafetyA Guide to Fire and Safety
A Guide to Fire and Safety
Asitava Bose
 
Basic fire safety
Basic fire safetyBasic fire safety
Basic fire safety
Ali Kamal Mostofa Rubel
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
Maffino
 
Fire drill report
Fire drill reportFire drill report
Fire drill report
Seemeeran Messi
 
FIRE MOCK DRILL PPT
FIRE MOCK DRILL PPTFIRE MOCK DRILL PPT
FIRE MOCK DRILL PPT
Aditya Pratap Singh
 
Amn safety induction j 175 - staff rev 4 - s 14
Amn safety induction  j 175 - staff rev 4 - s 14Amn safety induction  j 175 - staff rev 4 - s 14
Amn safety induction j 175 - staff rev 4 - s 14
Mumtaz A. Khan CMIOSH, IDipNEBOSH
 
A fire training hindi
A fire training   hindiA fire training   hindi
A fire training hindi
Er. EHS & Fire Syed Ali
 
Fire safety
Fire  safetyFire  safety
Fire safety
Saurabh Tiwari
 
Fire warden training
Fire warden trainingFire warden training
Fire warden training
Gemstone Fire and Safety
 
Fire Safety & Extinguisher Safety Training
Fire Safety & Extinguisher Safety TrainingFire Safety & Extinguisher Safety Training
Fire Safety & Extinguisher Safety Training
PhillipLaraway
 

What's hot (20)

Fire Risk Assessment.pdf
Fire Risk Assessment.pdfFire Risk Assessment.pdf
Fire Risk Assessment.pdf
 
fire_safety
fire_safetyfire_safety
fire_safety
 
Fire Safety Training
Fire Safety TrainingFire Safety Training
Fire Safety Training
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
Emergency Action Plans By OSHA
Emergency Action Plans By OSHAEmergency Action Plans By OSHA
Emergency Action Plans By OSHA
 
Fire Fighting Theory
Fire Fighting TheoryFire Fighting Theory
Fire Fighting Theory
 
2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx2 Fire Risk Assessment Template Risk Assessment Templates.docx
2 Fire Risk Assessment Template Risk Assessment Templates.docx
 
Fire Extinguisher safety training
Fire Extinguisher safety trainingFire Extinguisher safety training
Fire Extinguisher safety training
 
Fire extinguisher monthly checklist report
Fire extinguisher monthly checklist reportFire extinguisher monthly checklist report
Fire extinguisher monthly checklist report
 
Fire fighting course
Fire fighting courseFire fighting course
Fire fighting course
 
A Guide to Fire and Safety
A Guide to Fire and SafetyA Guide to Fire and Safety
A Guide to Fire and Safety
 
Basic fire safety
Basic fire safetyBasic fire safety
Basic fire safety
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
 
Fire drill report
Fire drill reportFire drill report
Fire drill report
 
FIRE MOCK DRILL PPT
FIRE MOCK DRILL PPTFIRE MOCK DRILL PPT
FIRE MOCK DRILL PPT
 
Amn safety induction j 175 - staff rev 4 - s 14
Amn safety induction  j 175 - staff rev 4 - s 14Amn safety induction  j 175 - staff rev 4 - s 14
Amn safety induction j 175 - staff rev 4 - s 14
 
A fire training hindi
A fire training   hindiA fire training   hindi
A fire training hindi
 
Fire safety
Fire  safetyFire  safety
Fire safety
 
Fire warden training
Fire warden trainingFire warden training
Fire warden training
 
Fire Safety & Extinguisher Safety Training
Fire Safety & Extinguisher Safety TrainingFire Safety & Extinguisher Safety Training
Fire Safety & Extinguisher Safety Training
 

Similar to Fire Risk Assessment.doc

Fire safety
Fire safetyFire safety
Fire safety
farihahmansor
 
Innovative way to develop fire extinguisher
Innovative way to develop fire extinguisherInnovative way to develop fire extinguisher
Innovative way to develop fire extinguisher
Iaetsd Iaetsd
 
Fire protection by K R THANKI
Fire protection by K R THANKIFire protection by K R THANKI
Fire protection by K R THANKI
Krunal Thanki
 
Co2 capture-technologies
Co2 capture-technologiesCo2 capture-technologies
Co2 capture-technologies
Dzung Le
 
Fire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptxFire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptx
VirenPatel528405
 
Final Report
Final ReportFinal Report
Final Report
Zalak Shah
 
Carbon Footprints and Carbon Credit
Carbon Footprints and Carbon CreditCarbon Footprints and Carbon Credit
Carbon Footprints and Carbon Credit
kanhaiya kumawat
 
Chemical fuels
Chemical fuelsChemical fuels
Chemical fuels
Vishnu Thumma
 
100 hse topics.pdf
100 hse topics.pdf100 hse topics.pdf
100 hse topics.pdf
VefadarQasimov
 
100 Safety topics Book.pdf
100 Safety topics Book.pdf100 Safety topics Book.pdf
100 Safety topics Book.pdf
mohamedBelhadj17
 
100 safety topics book
100 safety topics book100 safety topics book
100 safety topics book
Arie Irawan
 
Fire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.pptFire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.ppt
BenounaFert
 
Carbon footprints
Carbon footprintsCarbon footprints
Carbon footprints
kanhaiya kumawat
 
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
Koeppen Halvart
 
“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...
Kyungeun Sung
 
Carbon Accounting Buildings | Sue Roaf
Carbon Accounting Buildings | Sue Roaf Carbon Accounting Buildings | Sue Roaf
Carbon Accounting Buildings | Sue Roaf
icarb
 
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic AgentPyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
IJERA Editor
 
ME4103 Michael Ryan 11323146 4BM
ME4103 Michael Ryan 11323146 4BMME4103 Michael Ryan 11323146 4BM
ME4103 Michael Ryan 11323146 4BM
Michael Ryan
 
Carbon Footprints and Carbon Credits
Carbon Footprints and Carbon CreditsCarbon Footprints and Carbon Credits
Carbon Footprints and Carbon Credits
munisharora
 
State of the art in the pu sub sector-technology options and trends
State of the art in the pu sub sector-technology options and trendsState of the art in the pu sub sector-technology options and trends
State of the art in the pu sub sector-technology options and trends
UNEP OzonAction
 

Similar to Fire Risk Assessment.doc (20)

Fire safety
Fire safetyFire safety
Fire safety
 
Innovative way to develop fire extinguisher
Innovative way to develop fire extinguisherInnovative way to develop fire extinguisher
Innovative way to develop fire extinguisher
 
Fire protection by K R THANKI
Fire protection by K R THANKIFire protection by K R THANKI
Fire protection by K R THANKI
 
Co2 capture-technologies
Co2 capture-technologiesCo2 capture-technologies
Co2 capture-technologies
 
Fire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptxFire Protection Training_QPS_26DEC20_Final.pptx
Fire Protection Training_QPS_26DEC20_Final.pptx
 
Final Report
Final ReportFinal Report
Final Report
 
Carbon Footprints and Carbon Credit
Carbon Footprints and Carbon CreditCarbon Footprints and Carbon Credit
Carbon Footprints and Carbon Credit
 
Chemical fuels
Chemical fuelsChemical fuels
Chemical fuels
 
100 hse topics.pdf
100 hse topics.pdf100 hse topics.pdf
100 hse topics.pdf
 
100 Safety topics Book.pdf
100 Safety topics Book.pdf100 Safety topics Book.pdf
100 Safety topics Book.pdf
 
100 safety topics book
100 safety topics book100 safety topics book
100 safety topics book
 
Fire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.pptFire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.ppt
 
Carbon footprints
Carbon footprintsCarbon footprints
Carbon footprints
 
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
01 Daikin Non Hcfc Alternatives For Ac Split System Hilde Dhont
 
“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...
 
Carbon Accounting Buildings | Sue Roaf
Carbon Accounting Buildings | Sue Roaf Carbon Accounting Buildings | Sue Roaf
Carbon Accounting Buildings | Sue Roaf
 
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic AgentPyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
Pyrolysis of Scrap Tyres and Waste Lube Oil by Using Catalytic Agent
 
ME4103 Michael Ryan 11323146 4BM
ME4103 Michael Ryan 11323146 4BMME4103 Michael Ryan 11323146 4BM
ME4103 Michael Ryan 11323146 4BM
 
Carbon Footprints and Carbon Credits
Carbon Footprints and Carbon CreditsCarbon Footprints and Carbon Credits
Carbon Footprints and Carbon Credits
 
State of the art in the pu sub sector-technology options and trends
State of the art in the pu sub sector-technology options and trendsState of the art in the pu sub sector-technology options and trends
State of the art in the pu sub sector-technology options and trends
 

More from Mirza Saifullah Baig

HSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.pptHSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.ppt
Mirza Saifullah Baig
 
BBS TRAINING.pptx
BBS TRAINING.pptxBBS TRAINING.pptx
BBS TRAINING.pptx
Mirza Saifullah Baig
 
OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.doc
Mirza Saifullah Baig
 
HAZOP STUDY.docx
HAZOP STUDY.docxHAZOP STUDY.docx
HAZOP STUDY.docx
Mirza Saifullah Baig
 
Medical emergency mock drill
Medical emergency mock drillMedical emergency mock drill
Medical emergency mock drill
Mirza Saifullah Baig
 
Legal register
Legal registerLegal register
Legal register
Mirza Saifullah Baig
 
Hazard Identification and Risk Assessment
Hazard Identification and Risk AssessmentHazard Identification and Risk Assessment
Hazard Identification and Risk Assessment
Mirza Saifullah Baig
 
Steel plant process flow
Steel plant process flowSteel plant process flow
Steel plant process flow
Mirza Saifullah Baig
 
Contents of first aid box bocw
Contents of first aid box bocwContents of first aid box bocw
Contents of first aid box bocw
Mirza Saifullah Baig
 
Project EHS Plan
Project EHS PlanProject EHS Plan
Project EHS Plan
Mirza Saifullah Baig
 
Electrical work genral safety precautions
Electrical work genral safety precautionsElectrical work genral safety precautions
Electrical work genral safety precautions
Mirza Saifullah Baig
 
Hirarchy of hazard control
Hirarchy of hazard controlHirarchy of hazard control
Hirarchy of hazard control
Mirza Saifullah Baig
 
Accident pyramid
Accident pyramidAccident pyramid
Accident pyramid
Mirza Saifullah Baig
 
Hse ms elements
Hse ms elementsHse ms elements
Hse ms elements
Mirza Saifullah Baig
 

More from Mirza Saifullah Baig (14)

HSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.pptHSE REPORT 2013-2014.ppt
HSE REPORT 2013-2014.ppt
 
BBS TRAINING.pptx
BBS TRAINING.pptxBBS TRAINING.pptx
BBS TRAINING.pptx
 
OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.doc
 
HAZOP STUDY.docx
HAZOP STUDY.docxHAZOP STUDY.docx
HAZOP STUDY.docx
 
Medical emergency mock drill
Medical emergency mock drillMedical emergency mock drill
Medical emergency mock drill
 
Legal register
Legal registerLegal register
Legal register
 
Hazard Identification and Risk Assessment
Hazard Identification and Risk AssessmentHazard Identification and Risk Assessment
Hazard Identification and Risk Assessment
 
Steel plant process flow
Steel plant process flowSteel plant process flow
Steel plant process flow
 
Contents of first aid box bocw
Contents of first aid box bocwContents of first aid box bocw
Contents of first aid box bocw
 
Project EHS Plan
Project EHS PlanProject EHS Plan
Project EHS Plan
 
Electrical work genral safety precautions
Electrical work genral safety precautionsElectrical work genral safety precautions
Electrical work genral safety precautions
 
Hirarchy of hazard control
Hirarchy of hazard controlHirarchy of hazard control
Hirarchy of hazard control
 
Accident pyramid
Accident pyramidAccident pyramid
Accident pyramid
 
Hse ms elements
Hse ms elementsHse ms elements
Hse ms elements
 

Recently uploaded

Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 

Recently uploaded (20)

Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 

Fire Risk Assessment.doc

  • 1. Fire Risk Assessment HINDUSTAN UNILEVER LIMITED ETAH, UTTAR PRADESH DATE OF ASSESSMENT: 08/06/2022 TO 09/06/2022
  • 2. ACKNOWLEDGEMENT Auditor expresses its sincere thanks to the Hindustan Unilever Plant Team for their co-operation and unstinted help without which this assessment could not have been possible. The courtesy and cordiality extended to the auditor is highly appreciated.
  • 3. I N D E X Sr. No. Topic 1. General Information 2. Assessment Objectives 3. Assessment Scope 4. Assessment Methodology 5. Audit Team 6. List of Documents Verified 7. Fire Load Calculation 8. Observations and Recommendations 9. Attendance sheet of opening and closing meetings
  • 4. General Information  Plant and main product: Hindustan Unilever Limited  No of Shifts: Multiple Shifts  Worker Strength: 200 Assessment Objectives  Identify opportunities to improve operational performance.  Reduce incident rate.  Reduce overall costs.  Recognition to Plant Management.  Determine the status of statutory documents and necessary compliance. Assessment Scope This Assessment was carried out with reference to the following standards: NBC 2016 (Part 4) Assessment Methodology Following methodology adopted for successful completion of the assessment:  Opening meeting.  Presentation/Brief by the Plant team.  Plant walkthrough.  Discussions with key personnel, verification of statutory records/documents  Close out meeting.  Submission of the Report. Assessment Team Mirza Baig, Lead Auditor Qualification: B Tech (Mechanical), PG Diploma (Industrial Safety), Lead Auditor ISO 9001, ISO 14001, ISO 45001, ISO 22001, CSP, NEBOSH, IOSH, OSHA. Work Experience: 20 + Years (Global EHS Audit and Training)
  • 5. List of documents Verified Environment, Health & Safety management system documents Sr. No. Document Name Availability Status Yes No NA 1. Fire Safety management plan. Yes 2. EHS/Fire Policy. Yes 3. Organization chart Yes 4. Safety Budget Yes 5. EHS Manual Yes 6. Training records Yes 7. Fire Inspection/Internal Audit records Yes 8. Incident/near miss Reporting Records Yes 9. SOP for various activities Yes 10. Record of work permits Yes 11. Maintenance & testing record of fire protection equipment’s Yes 12. Accident record register. Yes 13. Safety induction records of workers and staff Yes 14. Pep talk / toolbox session records. Yes 15. Onsite emergency plan Yes 16. HIRA Yes 17. Record of Fire/Mock drills Yes 18. Approval of layouts and approvals from gov. authorities Yes 19. Records of modifications in plant Yes 20. Preventive maintenance logs and records Yes 21. Calibration and testing records Yes 22. Factory inspector register and communication record Yes 23. Factory license and License to Manufacture (Product) Yes 24. Explosive and petroleum license N/A 25. Gas Cylinders Storage License from CCE, if applicable. N/A 26. List of licensed electrician Yes 27. Approval of transformer and DG set Yes 28. Electrical maintenance record (Earth Pit, transformer oil, lightning arrester, rubber mat etc) Yes 29. Building stability certificate Yes 30. Fire NOC UP
  • 6.
  • 7. INTRODUCTION Fire is one of the major causes in the industrial area and there is increasing rates of fire accidents which may kill the life of the people. The fire can cause due to three main components such as Oxygen, Fuel and Heat is also known Fire triangle. When oxygen supply is increased in the fire area the amount of fire burning rate increases so that heat can be generated in huge amount. To suppress the fire one of the components must be removed. The suitable fire extinguishers must be used to suppress the fire triangle so that fire can be easily put off. To suppress the fire on of the components such as oxygen, Fuel and Heat must be removed so that burning rate of fire will be reduced. Fire alarm system is one of the essential needs and must be installed in the building/factory where there are combustible materials present in it. In case of fire, it is very useful to migrate and can be detected easily. Fire hydrants and fire extinguisher must be installed where there is risk of fire. The suitable fire extinguishers must be kept so that incase of fire it can be easily suppressed. Fire hydrants must be installed outside to suppress the building of fire. Classes of Fires and Fire Extinguishers Classes of Fire Combustible Materials Examples Type of Extinguisher Class A Solid Wood, Plastic, Rubber etc Water, DCP Type Class B Liquid Petrol, Diesel, LPG etc Foam Type Class C Electrical Electrical Appliances CO2 Type Class D Combustible Metals Magnesium, Potassium etc Water, DCP Type Fire Load Calculation Estimation of combustible material of a building can be determined by three methods they are:  Direct measurement of mass, with conversion based on the net heat of combustion  Direct measurement of volume (with conversion based on a combination of density and net heat of combustion)  Energy release measurement by calorimetry of an item sufficiently Fire load density is defined as the amount of heat liberated from a combustible material per square meter in floor area. Fire load is to determine the severity and building up of fire. Fire load is useful in determining the growth and severity of fires. The mass of the material is calculated in kg. The calculated mass is multiplied by its calorific value in MJ/kg to get fire load. The calculated value is then divided by area of the floor to give fire load density. Fire load = (combustibles in kg) x calorific value in kcal-kg / Floor area in square meters. Calorific value of some common combustible materials Poly Bags 17.5 Poly Propylene 42.66 Diesel 45.5 Wood 18.6 Carton box 16.9 Plastic 35 Paper (average) 16.3 Sack 16.6 Tea 4.281
  • 8. Fire Load Calculation for PM Godown Area: 976 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Carton 92407 16.9 1561678.3 CFC 42028 1.168 49088.704 Poly 70000 17.5 1225000 Sack 16354 16.6 271476.4 Tape 1000 35 35000 Wood Pallet 4800 18.6 89280 Plastic Pallet 3000 35 105000 Fire Load Density= (1561678.3+49088.704+1225000+271476.4+35000+89280+105000) /976 = 3231630 MJ/M3 Fire Load Calculation for Jumbo Godown Area: 2973 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Wooden Pallet 1200 18.6 22320 Plastic Pallet 15000 35 525000 Tea 600000 4.281 2568600 Fire Load Density= (22320+525000+2568600) / 2973 = 1048 MJ/M3 Fire Load Calculation for Godown 1 Area: 1394 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Plastic Pallet 11250 35 393750 Tea 250000 4.281 1070250 Fire Load Density= (393750+1070250) / 1394 = 1050 MJ/M3 Fire Load Calculation for Godown 2 Area: 1394 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Plastic Pallet 11250 35 393750 Tea 250000 4.281 1070250 Fire Load Density= (393750+1070250) / 1394 = 1050 MJ/M3 Fire Load Calculation for Shop Floor Area: 1129 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Carton 2850 16.9 48165 CFC 946 1.168 1104.928 Poly 9600 17.5 168000 Sack 1500 16.6 24900
  • 9. Tape 10 35 350 Wood Pallet 384 18.6 7142 Plastic Pallet 900 35 31500 Tea 20000 4.281 85620 Ink/Makeup 16 30 480 Fire Load Density= (48165+1104.928+168000+24900+350+7142+31500+85620+480) / 1129 = 325 MJ/M3 Fire Load Calculation for Day PM Area: 140 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Carton 22648 16.9 382751 CFC 11352 1.168 13259.136 Poly 25000 17.5 437500 Sack 6280 16.6 104248 Tape 120 35 4200 Wood Pallet 4800 18.6 89280 Plastic Pallet 3000 35 105000 Fire Load Density= (382751+13259.136+437500+104248+4200+89280+105000) /140 = 8115 MJ/M3 Fire Load Calculation for Diesel Storage Room Area: 20 SQM Combustible Materials Weight in KG Calorific Value in MJ/KG Fire Load in MJ Diesel 1900 45.5 86450 Fire Load Density= 86450 / 20 = 4322 MJ/M3 Conclusion Fire load density is analyzed in the plant and the study gives following conclusion: The maximum fire load density is found in PM Godown is 3231630 MJ/M3, Minimum is in Shop Floor 325 MJ/M3 and the average value of fire load density in the plant is given as 463934 MJ/M3. The usage of wooden/Plastic pallets, poly bags and other carton box material can be reduced to reduce fire load density. The Fire possibilities in the plant are solid/Liquid/Electric fires. Since, Plant has following fire detection/suppression system in place as per the requirement of National Building Code (NBC) 2016, part 4 and in adequate numbers;  Dedicated firefighting/ERT team.  Fire alarm system.  Fire Hydrant System with hose reels and pump.  Fire/smoke detectors.  Portable fire extinguishers (DCP, Foam and CO2 types).  One underground and two overhead water tanks.  Frequent Fire drills as per statutory requirement.  Frequent fire safety training.  Sprinkler system.
  • 10. Existing Capacity Additional Requirement (If any) As per NBC 2016, Part 4 Water Tank/Pump Under Ground – 1 Lac Litre Overhead – 20 Thousand Litre Not Required (Ref. NBC 2016, Part 4 Table 23) Fire hydrant line size- Ring, main and branches- 4’’ No of Fire hydrant post- 13 No of Fire hose reel- 7 Not Required (Ref. NBC 2016, Part 4 Table 23 & IS 13039) Number of Fire Extinguisher (DCP, Foam and CO2 Type)(5 kg, 9 kg, 20 kg) Area No. Of FE productionHall 20 Godown-1 9 Godown-2 8 AdminOffice FF 6 hopperSection 5 SecurityGate 4 Diesel Yard 4 Fire HydrantRoom 3 BlendArea 3 HT/LT Room 2 Scrap Yard 2 CompressorArea 2 ServerRoom 1 RestRoom 1 productionOffice 1 PCC room 1 Inkroom 1 Not Required (Ref. NBC 2016, Part 4 Clause 5.1) Manual Call Point- 19 Smoke Detector-196 Heat Detector- 66 Not Required Fire Sprinklers Jumbo Godown- 306 Godown 1- 132 Godown 2- 126 PM Store- 91 Not Required (Ref. NBC 2016, Part 4 Clause 5.1.7) Emergency Exit Door Entry/Exists Area Number ProductionHall 4 DPMStore 2 QA Lab 2 ProductionOffice 1 Engg Store 1 AdminOffice 2 Change Room 3 Canteen 2 Dispensary 1 Not Required (Ref. NBC 2016, Part 4 Clause 4.6)
  • 11. Gate Room 1 PestRoom 2 TrainingRoom 1 Tea 1 PCC room 3 UPS room 2 OldToilet 1 NewToilet 2 LadiesToilet 1 Godown-1 2 Godown-2 2 PMStore 2 JumboGodown 6 Hence, there is no major requirement for fire detection/suppression in existing plant at the moment. However, following opportunities for improvement identified during site visit. Correction/modification will further enhance operational excellence as well as meeting statutory requirements. Plant falls under Moderate Hazard Industrial Building - G2 Category.
  • 12. Opportunity for Improvements Based on NBC 2016, Part 4 Sr. No Observation Recommendation Risk Matrix 1 PPE’s - SCBA (Self Contained Breathing Apparatus) and firefighting suits not available in the plant. (Clause 4.1) SCBA and firefighting suits should be available in the plant in adequate numbers. 2 Screening of employees/visitors belongings/bags at security gate for fire prone items such as lighter, match box not evident. (Clause 4.1) Screening for bags should be conducted at security gate to ensure no fire prone items are being brought in the plant. 3 Fire Hydrant system has one jockey pump. (Clause 4.1) An additional jockey pump may be installed to be used in case of failure of first pump during emergency. 4 Thermography test not conducted for detecting electric failures/fires. (Clause 3.4.10, Good Practices 4(9), Part 8 section 2) Thermography test should be conducted by third party to determine there is no electric failure which may lead to electric fires. 5 Plant has only one operational gate for entry and exit. Emergency gate is blocked by vehicles from outside. (Clause 6.7.3.1) Emergency gate should always be free from blockage for use in emergency situations. 6 There is only one underground water tank which fills two overhead tanks. In fire emergency situation it will get empty in 1-1.2 Hours. (Clause 4.1 Ref. NBC Table 23) It is recommended to have one more underground water tank of same capacity to supply uninterrupted water for at least two hours. 7 Fire safety is not included in HIRA Chart. (Clause 4.1) Include it in HIRA chart and communicate it to all workforces through tool box talk/induction training. 8 Emergency lighting system has capacity of 30 minutes only. (Clause 4.16.10) It should be increased to 1-3 Hours. 9 PM Storage Area:  Fire Exit sign not available  List of trained fire fighters not available  Testing of hydrants and sprinklers not done  Access blocked partially by materials (Clause 4.2.7, 4.1, 5.1.1, 2.27)  Provide exit sign board  Display list of trained fire fighters  Conduct testing of hydrants and sprinklers quarterly  Keep access free for blockage all the times 10 Dust Extractor NO 3:  Emergency ladder not  Provide additional
  • 13. provided  Housekeeping is in a very poor condition (Clause 4.11, 4.1) ladder/stair for emergency evacuation  Maintain good housekeeping to avoid solid fires. 11 PM Plant passageway:  Passageway obstructed by materials.  Fire exit signs not available (Clause 2.27, 4.2.7)  Passageway should be free of obstacles at all times  Provide fire exit sign board 12 Fire extinguishers kept on floor in compressor area (Clause 5.1.1) All fire extinguishers should be in hanging position, easily assessable/visible 13 HB 07- access not clear (Clause 5.1.1) Clear access should be provided. 14 Jumbo Godown:  Fire exit sign not provided  View of Fire extinguishers blocked by materials  Emergency exit gate height is only 4 feet (Clause 4.2.7, 5.1.1, 6.7.3.1)  Provide fire exit sign board  Fire extinguishers should be in hanging position, easily assessable/visible  Either increase gate height to 7 feet or provide additional/alternate gate 15 VCB Room Area:  Fire hydrant point missing  Fire pipeline is 1.5 inch (Clause 5.1.1, 5.1.1)  Provide fire hydrant point  Change existing pipeline into 4 inch 16 Transformer yard/DG Set area has no fire extinguishers (Clause 4.1) Provide C type extinguisher for transformer yard and foam type extinguisher for DG set. 17 HB FH 11 is under emergency gate stairs (Clause 4.1) Change the location. 18 Godown 2:  HB/Extinguishers not visible/access blocked  Fire exit signs not provided  No emergency exit/walkway (Clause 4.1, 4.2.7)  HB/Fire extinguishers should be in hanging position, easily assessable/visible  Provide fire exit sign board  Either provide emergency exit gate or create walkways all around 19 Fire exit sign not provided in Godown Provide fire exit sign board
  • 14. 1 (Clause 4.2.7) 20 PCC Room:  Rescue stick and electric hand gloves not provided  Fire extinguishers not provided (Clause 4.1)  Provide rescue stick and electric hand gloves  Provide at least 2 CO2 type fire extinguishers at each gate (Inside)  Automatic fire suppression system may be provided inside the panels for additional safety same as provided in diesel storage area. 21 Shop Floor: Contract worker, Manoj Kumar, Contractor – Shabbir Ahmed found painting without Induction/tool box talk, not aware about fire procedure and use of fire extinguishers. (Clause 4.1) All contract workers should go through induction training, daily tool box talk and fire safety awareness training. Opening Meeting /Closing MeetingAttendanceSheet Sr. No. Name of person Name of Organization Opening Meeting 08/06/2022 Closing Meeting 09/06/2022 1. Mirza Baig (Lead Auditor) Freelancer √ √ 2. Vishal Pawar (Safety Officer) Hindustan Uniliver Limited √ √ 3. Hanamant Kumbhar Manager Hindustan Uniliver Limited √ √ Report Prepared and Submitted by: Mirza Baig --------------------------------------------- END OF REPORT----------------------------------------------