SlideShare a Scribd company logo
: PROJECT SITE :
HIDCO CONVENTION CENTRE,
NARKELBAGAN, KOLKATA,
WEST BENGAL
PROJECT UNDERTAKEN BY:
LARSEN & TOUBRO LTD.
The complex at night from the entrance
Plan of the whole project (Schematic diagram)
DMC PILING
PREFACE:
The report is prepared after the training and observation done
at Project-site of WBHIDCO Convention Centre, being an engineer
trainee under Geotreat Ltd.
The project is undertaken by Larsen & Toubro Ltd. A part of
piling works is being conducted by Geotreat Ltd.
The start date of the construction project was 16.06.2014 & the
expected end date is 15.09.2016. Over 2,600 piles are to be
constructed among which 500 number of pilling is conducted by
Geotreat Ltd. All of them are done by DMC piling methods.
The whole project report is subdivided in the following
sections:
1.Introduction
2.Objectives and classification of piles and piling
methods
3. Principle of DMC piling
4.Apparatus used
5.Field procedure DMC piling
6.Conclusion
1. INTRODUCTION
Piles are the columnar structure, the most common type of
deep foundation, that safely transfer loads from the super
structure to more competent subsurface strata by means of
friction, end bearing or a combination of both. Piles can be
broadly classified based on the following parameters.
1. Method of installation of piles – Driven (displacement) piles
or bored (replacement) piles.
2. Type of material used for piling – Concrete, steel, timber
piles etc.
Among these, concrete piles can be classified further as pre-
cast and cast in situ concrete piles. Though there are a variety
of piling options, the most common type of piles used for
majority of construction works in India are bored cast in situ
concrete piles.
2. Objectives and classification of piles and
piling methods
Functions of piles:
The major uses of piles are:
1. To carry vertical compression load, eg. bearing piles,
friction pile. (FIG. 1)
2. To resist uplift pressure, eg. tension piles or uplift piles or
anchor piles. (FIG. 2)
3. To resist horizontal or inclined loads, eg. Batter piles.
(FIG. 3)
Setting up piles
Depending up on the setting up principle, piles can be of two
types, eg. Displacement type and Replacement type, each has its
own advantages and disadvantages. For displacement piling
method, piles are driven into the ground pushing the soil out of its
way. Displacement piling is good for contaminated sites where it
costs a lot to move the soil out.
Using the replacement piling method, muck is dug out and
replaced with the pile. Much bigger piles can be casted by
replacement method.
Direct Mud Circulation (DMC) piling method or simply DMC
Piling method is an example of replacement piling method. This
method is the principle subject of interest in this report.
The advantages of displacement piling are:-
 Self testing as driven to refusal or "set"
 No pile arising to dispose of
 Little disturbance
 Limited access
 High production
The disadvantages of displacement piling are:-
 Cannot penetrate obstructions
 Cannot always penetrate desiccated clay
 Vibration and noise may be an issue
The advantages of replacement piling are:-
 Effectively vibration free
 Installed into non cohesive and water bearing soils
 High production
 Restricted access
The main disadvantage of replacement piling is that:-
 it produces excavated material which requires removal off site
3. Principle of DMC piling
DMC piling is a typical wash bored piling method, ie. the
piles are of REPLACEMENT type. For this type of piling method, the
sub soil must be of cohesive nature. The basic principle of DMC piling
lies in the fact that the soil layers becomes harder to penetrate with
depth, so to soften the hard soil layers deep below the ground level,
water jet streams are used and then a typical chisel cuts the
relatively softer soil. Bore holes of several depths (for example 10m,
15m, 20m, 25m, 30m, etc.) and diameter (for example 500mm
750mm, 1000mm etc.) are dug as per design requirements. It can be
understood quite clearly that the nearby soil can collapse. To prevent
the collapse some special safety measures are considered during the
operation which will be discussed in later sections.
After the bore hole is dug and the collapse of subsoil around
the hole is safely prohibited, a reinforcement cage is entered into the
borehole and concrete is filled from the bottom of the hole with the
help of pipes, typically designed for this operation, called the Tremie
pipes. Usually concrete is left 28 days to harden and gain full
strength, but sometimes using admixtures they are prepared within
21 days.
4. Apparatus used
I. DMC rig
 THE TRIPOD SYSTEM
Main shear leg: it is the longer leg than the other two that
carries the load.
The length is 7.5m.
The length can be adjusted. With the help of 20mm dia pins
The side shear legs: there are two side shear legs, 6.3m long
and they mainly support the tripod system.
The side legs must be placed at least 1.5m away from the centre
of the piles.
 BASE CHANNEL
These are standard I section, 2cm thick and there are grooving
in it that holds the shear legs onto the ground with the help of
base cannel pin.
 SLIP OVER WHEEL
Diameter 450mm
Thickness 50mm
Operation The rope slips over this wheel
or Pulley
 SLIP OVER WEEL HOLDER
Diameter = 500mm
 S.O. WHEEL PIN
Diameter 65mm
Length 200mm
Operation This is very important pin,
because it holds the S.O.
Wheel with the tripod system
and the entire vertical loads
act on it.
 PLUNGE
Inside Diameter = 50mm
 SUSPENSION PLATE – this is called into action if somehow the
chisel is stuck in the borehole. Pulleys are attached here and
the chisel is pulled out.
Suspension Plate
 MAIN SHEAR LEG PIN – 20mm dia.
II. Winch
Capacity 3 Ton (Other capacities can be of
1 Ton 2.5 Ton 5 Ton 7.5 Ton etc.)
Driven wheel diameter 900mm
III. Diesel engine
 USED IN WINCH (RUSTON MAKE)
Number of cylinder 4 3
Diesel consumption 2.1 lit/hr 1.75 lit/hr
Mobil consumption
(fresh engine)
0.5 lit per 7 days 0.5 lit per 7 days
Mobil consumption
(older engine)
0.5 lit per 12 hours 0.5 lit per 12 hours
 USED IN PUMP (KILOSKER MAKE)
Number of cylinder 2
Diesel consumption 1.25 lit/hr
Mobil consumption 250ml per 12 hours
IV. Bailer or Slush Pump
Length 2700mm
Inside Diameter 450mm
Weight 0.5 Ton
V. Guide casing
Length 2750mm
Inside Diameter 550mm
Thickness of casing 30mm
Thickness of collar 20mm
VI. Chisel or Chopper
Thickness of sheet 80mm
Inside Diameter 400mm
Length 2500mm
Number of nozzle 4
7.DMC rod
Length (m) 2.7 3 3.25
Diameter (mm) 95 75 65
Thread length (mm) 120
Thread type Tapered
ID of tapered king end (mm) 80
ID of queen end (mm) 120
Tapered thread end of DMC rods
8.Rope
Diameter – 20mm
9.Tremie pipe
ID 5 inch
OD 6 inch
Thickness of sheet 12mm
10. Vertical pump
Power source Electrically operated
Power 10 Hp
11. Bentonite tank and Bentonite slurry
The Bentonite tank stores the Bentonite water which is of avg.
Density of 1.04gm/cc. The minimum density is 1.03gm/cc and
maximum density is 1.05gm/cc
Vertical Pump in Bentonite tank
12. Wash vat
This is where the muck mix with water gets stored, the muck
gets precipitated and the water becomes reusable.
13. Tremie fork
Used to insert the tremie pipes and taking out DMC rods.
5. Field procedure DMC piling
 For executing DMC piling method which is approved as per IS
2911 under specifications of bored cast in situ piles. The
positioning of points where the piles are proposed to set up,
are checked by the surveyor.
 DMC piling Rig set-up and initiation of boring using the Bailer
 After the point for boring operation is set out by the surveyor
the tripod is paced such that each side legs are at least 1.5m
away from the point, keeping the centre of borehole exactly in
the centre.
 The bailer is then attached with the rope and the boring
operation is initiated.
 After bailer reaches its full length into the soil, the guide casing
is inserted into the hole for farther operations.
Insertion of the guide casing
 To prevent the side collapse and caving in, a guide casing of
550mm dia and of 2750mm length is placed on the top of the
bore hole and hammered by the bailer to insert it into the soil.
This will be withdrawn after concreting is over.
 Boring with Chisel
 Once the guide casing is placed, the boring is started with
chisel.
 The chisel has 4 nozzles from where water jet is forced on the
hard soil layer as the boring progresses.
Progression of boring and addition of DMC rods
 DMC rods are added one after another as the depth increases.
 The DMC head are attached on top of the DMC rods which has
the plunge which receives the water from delivery hose.
 The whole system is pulled up by the rope and the D-Shackle
with the help of the winch system and then left to fall free, so
that the chisel at the bottom cuts the soil and the boring
progresses.
 The loose soil produced by boring, mixes with water and comes
up and is stored in the wash vat, where the soil gets
precipitated and the water is again usable.
Taking out of the DMC rods and Chisel and
Insertion of the reinforcement cage
 After the boring is complete up to the desired depth, the DMC
rods are removed one by one using the DMC fork and the chisel
is also removed.
 Then the steel reinforcement cage is inserted and welded
where ever there are joints.
 Concreting and finalization of the process
 The tremie pipes are inserted one by one using the Tremie fork
and then the bore hole is washed with the Bentonite water and
the Muck is completely removed and the hole is filled with
bentonite slurry.
 The Transit mixer arrives and the Hopper is attached on top of
the tremie pipe.
 The TM puts concrete mix into the hopper and the valve opens.
The bore hole is gradually filled with concrete which is
compacted by gradual vibration of tremie pipes. This filling of
concrete from the bottom is done to avoid segregation of the
concrete mix.
 As the concrete fills the hole from bottom, Bentonite slurry
escapes the hole. The tremie pipes are detached one by one
and thus the hole gets filled completely.
 After the hole is fully filled, the concrete is left 28 days to gain
full strength. After 28 days the guide casing is removed and the
pile is ready.
Concreting
6. Conclusion
DMC piling is the most common piling methods used in India. For
moderate sized piles, that is 450mm to 1000mm diameter and 25m
to 30m depth piles; it is also most convenient and economic way of
piling. Larger piles that are of diameter up to 1500mm can also be
founded by this method, but those are not that convenient. Other
process like Reduced Mud Circulation (RMC) is also in use.
DMC piling

More Related Content

What's hot

Micropile
MicropileMicropile
Micropile
Sameer Thaiyam
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Make Mannan
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored PilesAhmed Zanaty
 
Cofferdam
CofferdamCofferdam
Cofferdam
Shashank Namdeo
 
Caissons
Caissons Caissons
Pile foundations
Pile foundationsPile foundations
Pile foundations
Riya Trivedi
 
Micropiles
Micropiles Micropiles
Micropiles
Sumit Rawat
 
Well foundation
Well foundationWell foundation
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
Self-employed
 
Vacuum dewatered flooring
Vacuum dewatered flooringVacuum dewatered flooring
Vacuum dewatered flooring
Ram Tosniwal
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
guasiya
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
Aglaia Connect
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
AB MAKASANA
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testingSravan Muguda
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
Chaitanya Raval
 
coffer Dam.pptx
coffer Dam.pptxcoffer Dam.pptx
coffer Dam.pptx
Timepass171926
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
Bearing failure
Bearing failureBearing failure
Bearing failure
galaly12345
 

What's hot (20)

Micropile
MicropileMicropile
Micropile
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Caissons
Caissons Caissons
Caissons
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Micropiles
Micropiles Micropiles
Micropiles
 
Well foundation
Well foundationWell foundation
Well foundation
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Vacuum dewatered flooring
Vacuum dewatered flooringVacuum dewatered flooring
Vacuum dewatered flooring
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
 
coffer Dam.pptx
coffer Dam.pptxcoffer Dam.pptx
coffer Dam.pptx
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Bearing failure
Bearing failureBearing failure
Bearing failure
 

Viewers also liked

Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
VARANASI RAMA RAO
 
Bored piles production method
Bored piles   production methodBored piles   production method
Bored piles production methodNguyen Bao
 
Pilework
PileworkPilework
Pilework
Rajiva Gupta
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
Gaurang Kakadiya
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile FoundationSubham Kundu
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
Rituales prohibidos
Rituales prohibidosRituales prohibidos
Rituales prohibidosKey94
 
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Domenico Berardi DestinationSicily DMC Incentives
 
Diesel hammer
Diesel hammer Diesel hammer
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1Er Naveen Kumar
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesSubham Kundu
 
A photographic presentation of the First Indian Port Sector BOT project-A C...
A  photographic  presentation of the First Indian Port Sector BOT project-A C...A  photographic  presentation of the First Indian Port Sector BOT project-A C...
A photographic presentation of the First Indian Port Sector BOT project-A C...
PRABIR DATTA
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14Winter Sonata
 
Slide rabbit pushingpowerpoint_techsummithandout
Slide rabbit pushingpowerpoint_techsummithandoutSlide rabbit pushingpowerpoint_techsummithandout
Slide rabbit pushingpowerpoint_techsummithandout
SlideRabbit
 
Steel reinforcement
Steel reinforcement Steel reinforcement
Steel reinforcement
Subho Mistri
 

Viewers also liked (20)

Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pile
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Bored piles production method
Bored piles   production methodBored piles   production method
Bored piles production method
 
Pilework
PileworkPilework
Pilework
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
SIP- final - LinkedIn
SIP- final - LinkedInSIP- final - LinkedIn
SIP- final - LinkedIn
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
certificate20037782
certificate20037782certificate20037782
certificate20037782
 
Rituales prohibidos
Rituales prohibidosRituales prohibidos
Rituales prohibidos
 
ARIES CURRENT PROFILE
ARIES CURRENT PROFILEARIES CURRENT PROFILE
ARIES CURRENT PROFILE
 
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...Destination sicily dmc mount etna's scary sudden eruption surprising group of...
Destination sicily dmc mount etna's scary sudden eruption surprising group of...
 
Diesel hammer
Diesel hammer Diesel hammer
Diesel hammer
 
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ Piles
 
A photographic presentation of the First Indian Port Sector BOT project-A C...
A  photographic  presentation of the First Indian Port Sector BOT project-A C...A  photographic  presentation of the First Indian Port Sector BOT project-A C...
A photographic presentation of the First Indian Port Sector BOT project-A C...
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
 
Slide rabbit pushingpowerpoint_techsummithandout
Slide rabbit pushingpowerpoint_techsummithandoutSlide rabbit pushingpowerpoint_techsummithandout
Slide rabbit pushingpowerpoint_techsummithandout
 
Steel reinforcement
Steel reinforcement Steel reinforcement
Steel reinforcement
 

Similar to DMC piling

DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
Al Hakam Khan
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
Adib Ramli
 
3 tunnel
3 tunnel3 tunnel
3 tunnel
SUKANTA MONDAL
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
Er.Sunil Wasade
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail projectDocumentStory
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
rutuldave
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
ErLavKushPrasad
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
Pravin Gaurav
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
Chandra Mohan Lodha
 
Cementation jobs.
Cementation jobs.Cementation jobs.
Cementation jobs.
Saba Saif
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
Safdar Ali
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.ppt
DAYANANDWANDRE
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Shaft boring methods
Shaft boring methodsShaft boring methods
Shaft boring methods
Rishabh Ranjan
 
Cementation
CementationCementation
Cementation
Dictor Omien
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Prerak Ka.Patel
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
KRISHNA MURARI
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
KRISHNA MURARI
 

Similar to DMC piling (20)

DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
3 tunnel
3 tunnel3 tunnel
3 tunnel
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail project
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
Cementation jobs.
Cementation jobs.Cementation jobs.
Cementation jobs.
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.ppt
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Shaft boring methods
Shaft boring methodsShaft boring methods
Shaft boring methods
 
Cementation
CementationCementation
Cementation
 
mbl
mblmbl
mbl
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 

Recently uploaded

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 

Recently uploaded (20)

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 

DMC piling

  • 1. : PROJECT SITE : HIDCO CONVENTION CENTRE, NARKELBAGAN, KOLKATA, WEST BENGAL PROJECT UNDERTAKEN BY: LARSEN & TOUBRO LTD.
  • 2. The complex at night from the entrance Plan of the whole project (Schematic diagram)
  • 3. DMC PILING PREFACE: The report is prepared after the training and observation done at Project-site of WBHIDCO Convention Centre, being an engineer trainee under Geotreat Ltd. The project is undertaken by Larsen & Toubro Ltd. A part of piling works is being conducted by Geotreat Ltd. The start date of the construction project was 16.06.2014 & the expected end date is 15.09.2016. Over 2,600 piles are to be constructed among which 500 number of pilling is conducted by Geotreat Ltd. All of them are done by DMC piling methods.
  • 4. The whole project report is subdivided in the following sections: 1.Introduction 2.Objectives and classification of piles and piling methods 3. Principle of DMC piling 4.Apparatus used 5.Field procedure DMC piling 6.Conclusion
  • 5. 1. INTRODUCTION Piles are the columnar structure, the most common type of deep foundation, that safely transfer loads from the super structure to more competent subsurface strata by means of friction, end bearing or a combination of both. Piles can be broadly classified based on the following parameters. 1. Method of installation of piles – Driven (displacement) piles or bored (replacement) piles. 2. Type of material used for piling – Concrete, steel, timber piles etc. Among these, concrete piles can be classified further as pre- cast and cast in situ concrete piles. Though there are a variety of piling options, the most common type of piles used for majority of construction works in India are bored cast in situ concrete piles.
  • 6. 2. Objectives and classification of piles and piling methods Functions of piles: The major uses of piles are: 1. To carry vertical compression load, eg. bearing piles, friction pile. (FIG. 1) 2. To resist uplift pressure, eg. tension piles or uplift piles or anchor piles. (FIG. 2) 3. To resist horizontal or inclined loads, eg. Batter piles. (FIG. 3) Setting up piles Depending up on the setting up principle, piles can be of two types, eg. Displacement type and Replacement type, each has its own advantages and disadvantages. For displacement piling
  • 7. method, piles are driven into the ground pushing the soil out of its way. Displacement piling is good for contaminated sites where it costs a lot to move the soil out. Using the replacement piling method, muck is dug out and replaced with the pile. Much bigger piles can be casted by replacement method. Direct Mud Circulation (DMC) piling method or simply DMC Piling method is an example of replacement piling method. This method is the principle subject of interest in this report. The advantages of displacement piling are:-  Self testing as driven to refusal or "set"  No pile arising to dispose of  Little disturbance  Limited access  High production The disadvantages of displacement piling are:-  Cannot penetrate obstructions  Cannot always penetrate desiccated clay  Vibration and noise may be an issue The advantages of replacement piling are:-  Effectively vibration free  Installed into non cohesive and water bearing soils  High production  Restricted access The main disadvantage of replacement piling is that:-  it produces excavated material which requires removal off site 3. Principle of DMC piling DMC piling is a typical wash bored piling method, ie. the piles are of REPLACEMENT type. For this type of piling method, the
  • 8. sub soil must be of cohesive nature. The basic principle of DMC piling lies in the fact that the soil layers becomes harder to penetrate with depth, so to soften the hard soil layers deep below the ground level, water jet streams are used and then a typical chisel cuts the relatively softer soil. Bore holes of several depths (for example 10m, 15m, 20m, 25m, 30m, etc.) and diameter (for example 500mm 750mm, 1000mm etc.) are dug as per design requirements. It can be understood quite clearly that the nearby soil can collapse. To prevent the collapse some special safety measures are considered during the operation which will be discussed in later sections. After the bore hole is dug and the collapse of subsoil around the hole is safely prohibited, a reinforcement cage is entered into the borehole and concrete is filled from the bottom of the hole with the help of pipes, typically designed for this operation, called the Tremie pipes. Usually concrete is left 28 days to harden and gain full strength, but sometimes using admixtures they are prepared within 21 days. 4. Apparatus used I. DMC rig  THE TRIPOD SYSTEM Main shear leg: it is the longer leg than the other two that carries the load. The length is 7.5m. The length can be adjusted. With the help of 20mm dia pins
  • 9. The side shear legs: there are two side shear legs, 6.3m long and they mainly support the tripod system. The side legs must be placed at least 1.5m away from the centre of the piles.  BASE CHANNEL These are standard I section, 2cm thick and there are grooving in it that holds the shear legs onto the ground with the help of base cannel pin.  SLIP OVER WHEEL Diameter 450mm Thickness 50mm Operation The rope slips over this wheel or Pulley  SLIP OVER WEEL HOLDER Diameter = 500mm
  • 10.  S.O. WHEEL PIN Diameter 65mm Length 200mm Operation This is very important pin, because it holds the S.O. Wheel with the tripod system and the entire vertical loads act on it.  PLUNGE Inside Diameter = 50mm  SUSPENSION PLATE – this is called into action if somehow the chisel is stuck in the borehole. Pulleys are attached here and the chisel is pulled out. Suspension Plate  MAIN SHEAR LEG PIN – 20mm dia.
  • 11. II. Winch Capacity 3 Ton (Other capacities can be of 1 Ton 2.5 Ton 5 Ton 7.5 Ton etc.) Driven wheel diameter 900mm III. Diesel engine  USED IN WINCH (RUSTON MAKE) Number of cylinder 4 3 Diesel consumption 2.1 lit/hr 1.75 lit/hr Mobil consumption (fresh engine) 0.5 lit per 7 days 0.5 lit per 7 days Mobil consumption (older engine) 0.5 lit per 12 hours 0.5 lit per 12 hours  USED IN PUMP (KILOSKER MAKE) Number of cylinder 2 Diesel consumption 1.25 lit/hr Mobil consumption 250ml per 12 hours IV. Bailer or Slush Pump Length 2700mm Inside Diameter 450mm Weight 0.5 Ton
  • 12. V. Guide casing Length 2750mm Inside Diameter 550mm Thickness of casing 30mm Thickness of collar 20mm VI. Chisel or Chopper Thickness of sheet 80mm Inside Diameter 400mm Length 2500mm Number of nozzle 4
  • 13. 7.DMC rod Length (m) 2.7 3 3.25 Diameter (mm) 95 75 65 Thread length (mm) 120 Thread type Tapered ID of tapered king end (mm) 80 ID of queen end (mm) 120 Tapered thread end of DMC rods 8.Rope Diameter – 20mm
  • 14. 9.Tremie pipe ID 5 inch OD 6 inch Thickness of sheet 12mm 10. Vertical pump Power source Electrically operated Power 10 Hp 11. Bentonite tank and Bentonite slurry The Bentonite tank stores the Bentonite water which is of avg. Density of 1.04gm/cc. The minimum density is 1.03gm/cc and maximum density is 1.05gm/cc Vertical Pump in Bentonite tank 12. Wash vat This is where the muck mix with water gets stored, the muck gets precipitated and the water becomes reusable.
  • 15. 13. Tremie fork Used to insert the tremie pipes and taking out DMC rods. 5. Field procedure DMC piling  For executing DMC piling method which is approved as per IS 2911 under specifications of bored cast in situ piles. The positioning of points where the piles are proposed to set up, are checked by the surveyor.  DMC piling Rig set-up and initiation of boring using the Bailer  After the point for boring operation is set out by the surveyor the tripod is paced such that each side legs are at least 1.5m away from the point, keeping the centre of borehole exactly in the centre.  The bailer is then attached with the rope and the boring operation is initiated.  After bailer reaches its full length into the soil, the guide casing is inserted into the hole for farther operations.
  • 16. Insertion of the guide casing  To prevent the side collapse and caving in, a guide casing of 550mm dia and of 2750mm length is placed on the top of the bore hole and hammered by the bailer to insert it into the soil. This will be withdrawn after concreting is over.  Boring with Chisel  Once the guide casing is placed, the boring is started with chisel.  The chisel has 4 nozzles from where water jet is forced on the hard soil layer as the boring progresses. Progression of boring and addition of DMC rods  DMC rods are added one after another as the depth increases.  The DMC head are attached on top of the DMC rods which has the plunge which receives the water from delivery hose.
  • 17.  The whole system is pulled up by the rope and the D-Shackle with the help of the winch system and then left to fall free, so that the chisel at the bottom cuts the soil and the boring progresses.  The loose soil produced by boring, mixes with water and comes up and is stored in the wash vat, where the soil gets precipitated and the water is again usable. Taking out of the DMC rods and Chisel and Insertion of the reinforcement cage  After the boring is complete up to the desired depth, the DMC rods are removed one by one using the DMC fork and the chisel is also removed.  Then the steel reinforcement cage is inserted and welded where ever there are joints.  Concreting and finalization of the process  The tremie pipes are inserted one by one using the Tremie fork and then the bore hole is washed with the Bentonite water and the Muck is completely removed and the hole is filled with bentonite slurry.  The Transit mixer arrives and the Hopper is attached on top of the tremie pipe.  The TM puts concrete mix into the hopper and the valve opens. The bore hole is gradually filled with concrete which is
  • 18. compacted by gradual vibration of tremie pipes. This filling of concrete from the bottom is done to avoid segregation of the concrete mix.  As the concrete fills the hole from bottom, Bentonite slurry escapes the hole. The tremie pipes are detached one by one and thus the hole gets filled completely.  After the hole is fully filled, the concrete is left 28 days to gain full strength. After 28 days the guide casing is removed and the pile is ready. Concreting 6. Conclusion DMC piling is the most common piling methods used in India. For moderate sized piles, that is 450mm to 1000mm diameter and 25m to 30m depth piles; it is also most convenient and economic way of piling. Larger piles that are of diameter up to 1500mm can also be founded by this method, but those are not that convenient. Other process like Reduced Mud Circulation (RMC) is also in use.