ARYA INSTITUTE OF
ENGINEERING TECHNOLOGY
AND MANAGEMENT
CHHABRA THERMAL POWER PLANT
ASH DYKE CONSTRUCTION
SUBMITTED TO SUBMITTED BY
Civil Engineering Department
Chandra Mohan Lodha
4th Year Student
CONTENTS
1. Introduction
2. Ash Dyke
3. Machinery Used In Construction
4. Materials Used In Ash Pond Construction
5. Preparation Of Base
6. Construction Process
7. Drainage System Of Dyke
8. Use Of Dyke
9. Special Features
10. Conclusion
INTRODUCTION
Chhabra Thermal Power Plant is one of Rajasthan coal fired power plant. It is located at
Chowki Motipura (Village) of tehsil Chhabra in Rajasthan Baran district.
The planned capacity of power plant is 2650MW at the end of 12th Five year plan.
The first and 2nd unit at Chhabra super thermal power plant was set up at a cost of Rs2,350
crore. Chhabra is all set to become a power generation hub in the state as in the second phase
two more units with a capacity of 250 MW each will be installed.
Rajasthan Rajya Vidyut Utpadan Nigam Limited (RVUN) has been entrusted with the job of
development of power projects under state sector, in the state along with operation &
maintenance of state owned power stations. Government of Rajasthan constituted the
Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUN) under Companies Act-1956 on 19th July,
2000. The Nigam is since playing lead role in giving highest priority to the power generation for
manifold and rapid development of the state.
The generating Stations of RVUN have acquired a distinctive reputation in the country for their
efficient and economic power generation.
Chhabra Thermal Power Station is a 1000-megawatt (MW) coal-fired power station in
Rajasthan state, India.
A 1320 MW expansion of the power station is under construction.
The power station is owned and operated by Rajasthan Rajya Vidyut Utpadhan Nigam (RVUN or
RRVUN), a government-owned utility. It began as a 500 MW power station, commissioned in
2009-2010. The power station was later expanded by two 250 MW units (Units 3&4). Unit 3 was
commissioned in 2013, and unit 4 in 2014.
ISTALLED CAPACITY
Unit 1 - 250 MW - Operating (commissioned October 30, 2009)
Unit 2 - 250 MW - Operating (commissioned May 4, 2010)
Unit 3 - 250 MW - Operating (commissioned September 14, 2013)
Unit 4 - 250 MW - Operating (commissioned 30 June 2014)
Unit 5 - 660 MW - Construction
Unit 6 - 660 MW - Construction
Ash Dyke/pond
An ash pond is an engineered structure for the disposal of bottom ash and fly ash. The wet
disposal of ash into ash ponds is the most common ash disposal method , but other methods
include dry disposal in landfills. Dry-handled ash is often recycled into useful building materials.
Wet disposal has been preferred due to economic reasons, but increasing environmental
concerns regarding leachate from ponds has decreased the popularity of wet disposal. The wet
method consists of constructing a large "pond" and filling it with fly ash slurry, allowing the
water to drain and evaporate from the fly ash over time. Ash ponds are generally formed using
a ring embankment to enclose the disposal site. The embankments are designed using similar
design parameters as embankment dams, including zoned construction with clay cores. The
design process is primarily focused on handling seepage and ensuring slope stability.
Machinery Used In Construction
Machinery used in ash pond construction like
• Poke Land
• Jcb
• Dozer
• Grader
• Roller
• Trucks
Poke Land :- Poke land is a hydraulic machine which used in the digging.
It is used in the larger project work and speedily constructional work . It
have higher load bearing capacity.
The poke land machine is also available in two types
1.Three hundred poke land
2. Two hundred poke land
Both the machines have different capacity according to the design
capacity .
JCB :- jcb is a earth moving machine which used in the construction work . It give more
importance in the construction filed . It is multi used machine in the construction work .it is
provide faster work .
DOZER :- It is a earth cutting machine which used in the larger project work . Mostly it is used
in the depth of earth about 20m for the harder stone cutting/collection of stone particles.
It have front larger size part which is very used and have higher capacity.
GRADER :-A grader, also commonly referred to as a road grader, a blade, a maintainer, or a
motor grader, is a construction machine with a long blade used to create a flat surface during
the grading process. second blade that is placed in front of the front axle. Some construction
personnel refer to the entire machine as "the blade". Capacities range from a blade width of
2.50 to 7.30 m and engines from 93–373 kW(125–500 hp).
ROLLER :-A road roller (sometimes called a roller-compactor, or just roller) is a compactor
type engineering vehicle used to compact soil, gravel, concrete, or asphalt in the construction of
roads and foundations, similar rollers are used also at landfills or in agriculture.
In some parts of the world, road rollers are still known colloquially as steam rollers, regardless of
their method of propulsion. This typically only applies to the largest examples (used for road-
making).
Trucks :-Normally trucks are used for the transportation but in the construction field it is used
for sand , soil, stone, cement etc material dumping/supply. From one place to another place.
Modern trucks are largely powered by diesel engines, although small to medium size trucks with
gasoline engines.
Material Used In Ash Pond Construction
For the ash pond construction many materials required .
Some materials are :-
Concrete (M7.5, M25)
Bricks (Fly Ash )
Cement
Soil
LDPE ( 150&270 micron thick geomembrane )
Black cotton ( Black Sand 300mm )
Preparation Of Base
The preparation of base for the ash pond construction is simplest process. Firstly survey of the
all area and test of field like soil test , ground water level of area .marked the area required for
the ash pond construction . After that dig the depth about 12meter depth all area by machinery
used . Finished the base surface clearly with 0 degree angles. The ash pond all sides having
width 12 to 15 meter for vehicle travelling and transportation . The ash pond all walls having
slope 60 degree.
Cutting the all walls with 60 degree slope and finish properly . Around the ash pond drainage
system must required so drainage base also cut by machines.
Now base is complete for the ash pond design process.
Construction Process Of Ash Dyke
The Construction of ash dyke required special skills and engineering knowledge .
The Construction of ash dyke in the parts like
1. Construction of trench beam
2. Construction of base
3. Construction of sloping walls
4. Construction of bad
1. Construction Of Trench Beam :- The design of trench beam according to the drawing all the
measurements used according to the drawing. The trench beam located nearly the sloping wall
base point. The beam having size 500mm height , 230 mm width (500*230)mm and concrete
M7.5 used in the construction.
2. Construction Of Base :- After cut and finishing the surface 150mm depth soil fill in the all base
area and then soil covered by175 micron thick LDPE spread in all the area . And then LDPE jointed
by the electric jointing machine.
STEP -3
CONSTRUCTION OF BASE
STEP -1 STEP -2
3.Construction Of Sloping Walls:- The design of sloping walls of ash dyke required technical
specifications . Design according to the given drawing .
The concrete used in the wall construction is M25.
Construction of sloping walls are as follows given dimensions.
Length 9m , width 3m , thickness 75mm.
4. Construction Of Bad :- the construction of ash dyke bad is similar process as like
dams bad process.
The width of bad is equal to 15metere with flat surface. It is also used for transportation in the
construction time .
It is made up of sand with compaction , compaction should be completed by the vibration roller.
The length of bad is depends upon the size of dyke.
Construction Of Drainage System
The drainage system of ash dyke is outer side of the dyke. With special supervision and according to
the given drawing.
The drainage system base completed by using of concrete M7.5 and walls having dimensions height
800mm , width 350mm and length depends upon the drain length.
The slope between starting point of wall and end point of wall is 1:0.5
The drain walls constructed by the cement , sand , bricks with proper ratio of cement sand and water.
PRIMARILY, THE FLY ASH IS DISPOSED OFF USING EITHER DRY OR WET DISPOSAL
SCHEME.
IN DRY DISPOSAL, THE FLY ASH IS TRANSPORTED BY TRUCK, CHUTE OR CONVEYOR AT
THE SITE AND DISPOSED OFF BY CONSTRUCTING A DRY EMBANKMENT (DYKE).
IN WET DISPOSAL, THE FLY ASH IS TRANSPORTED AS SLURRY THROUGH PIPE AND
DISPOSED OFF IN IMPOUNDMENT CALLED "ASH POND".
Use of Ash Dyke
Special Features
• Use Of LDPE (175 micron thick membrane) to protect under ground water.
• Use of trench beam to maintain black cotton (Black Soil).
• Use of sloping walls with concrete to protect seepage of water.
• Use of proper drainage system around the ash dyke.
CONCLUSION
The construction of ash dyke for the fly ash disposal and utilization in the thermal
power plants is compulsory.
But in the ctpp power plant ash dyke construction is something different as
compare to other ash dykes.
Comparison clarify by the special features of the dyke.
The engineering summer internship time is very good for my practical knowledge
of the field.
Chhabra Thermal Power plant ppt by Cm lodha

More Related Content

What's hot

Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Aniket Raj
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid designsusanta das
 
Seminar Report Writing
Seminar Report WritingSeminar Report Writing
Seminar Report WritingJahannaviSingh
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installationAmitesh Kumar
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant vishal patel
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plantpranavn007
 
Solar photovoltaic system design
Solar photovoltaic system designSolar photovoltaic system design
Solar photovoltaic system designJay Ranvir
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantShaik Afzal
 
Power Generation by Non Conventional Energy Sources
Power Generation by Non Conventional Energy  Sources 	Power Generation by Non Conventional Energy  Sources
Power Generation by Non Conventional Energy Sources Niraj Solanki
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plantSatish Taji
 
Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive workvipin rai
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant pptMohammad Nafey
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSRAJ BAIRWA
 
Hydrogen electrolyser capacity investment in the Australian context: optimiza...
Hydrogen electrolyser capacity investment in the Australian context: optimiza...Hydrogen electrolyser capacity investment in the Australian context: optimiza...
Hydrogen electrolyser capacity investment in the Australian context: optimiza...IEA-ETSAP
 

What's hot (20)

Tidal Energy
Tidal EnergyTidal Energy
Tidal Energy
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Hydraulic power plant
Hydraulic power plantHydraulic power plant
Hydraulic power plant
 
Seminar Report Writing
Seminar Report WritingSeminar Report Writing
Seminar Report Writing
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installation
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Solar photovoltaic system design
Solar photovoltaic system designSolar photovoltaic system design
Solar photovoltaic system design
 
Training report on thermal power plant
Training report on thermal power plantTraining report on thermal power plant
Training report on thermal power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
HYDRO POWER PLANT
HYDRO POWER PLANT HYDRO POWER PLANT
HYDRO POWER PLANT
 
Power Generation by Non Conventional Energy Sources
Power Generation by Non Conventional Energy  Sources 	Power Generation by Non Conventional Energy  Sources
Power Generation by Non Conventional Energy Sources
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Diesel locomotive work
Diesel locomotive workDiesel locomotive work
Diesel locomotive work
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant ppt
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTS
 
Hydrogen electrolyser capacity investment in the Australian context: optimiza...
Hydrogen electrolyser capacity investment in the Australian context: optimiza...Hydrogen electrolyser capacity investment in the Australian context: optimiza...
Hydrogen electrolyser capacity investment in the Australian context: optimiza...
 
Train lighting
Train lightingTrain lighting
Train lighting
 

Viewers also liked

Intelligent building project report
Intelligent building project reportIntelligent building project report
Intelligent building project reportBeing Deepak
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTShivam Sharma
 
Chhabra Thermal Power Plant Report By Chandra Mohan Lodha
Chhabra Thermal Power Plant Report By Chandra Mohan LodhaChhabra Thermal Power Plant Report By Chandra Mohan Lodha
Chhabra Thermal Power Plant Report By Chandra Mohan LodhaChandra Mohan Lodha
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Continuously reinforced concrete pavement seminar ppt by chandramohan lodha
Continuously reinforced concrete pavement seminar ppt by chandramohan lodhaContinuously reinforced concrete pavement seminar ppt by chandramohan lodha
Continuously reinforced concrete pavement seminar ppt by chandramohan lodhaChandra Mohan Lodha
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportBeing Deepak
 
syringe actuated mechanical arm
syringe actuated mechanical armsyringe actuated mechanical arm
syringe actuated mechanical armSuchit Moon
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance pptBeing Deepak
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant00veerchauhan
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plantsagar20jain
 
syringe actuated mechanical arm
syringe actuated mechanical armsyringe actuated mechanical arm
syringe actuated mechanical armSuchit Moon
 
Mechanical projects
Mechanical projects Mechanical projects
Mechanical projects Abi Nesan
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training reportEr. Aman Agrawal
 
Project report format
Project report formatProject report format
Project report formatrohtb2010
 
Continuously reinforced concrete pavement seminar report by chandramohan lodha
Continuously reinforced concrete pavement seminar report by chandramohan lodhaContinuously reinforced concrete pavement seminar report by chandramohan lodha
Continuously reinforced concrete pavement seminar report by chandramohan lodhaChandra Mohan Lodha
 
Multistorey residential building construction training report
Multistorey residential building construction training  reportMultistorey residential building construction training  report
Multistorey residential building construction training reportBeing Deepak
 

Viewers also liked (20)

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Intelligent building project report
Intelligent building project reportIntelligent building project report
Intelligent building project report
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Chhabra Thermal Power Plant Report By Chandra Mohan Lodha
Chhabra Thermal Power Plant Report By Chandra Mohan LodhaChhabra Thermal Power Plant Report By Chandra Mohan Lodha
Chhabra Thermal Power Plant Report By Chandra Mohan Lodha
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Continuously reinforced concrete pavement seminar ppt by chandramohan lodha
Continuously reinforced concrete pavement seminar ppt by chandramohan lodhaContinuously reinforced concrete pavement seminar ppt by chandramohan lodha
Continuously reinforced concrete pavement seminar ppt by chandramohan lodha
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
syringe actuated mechanical arm
syringe actuated mechanical armsyringe actuated mechanical arm
syringe actuated mechanical arm
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
syringe actuated mechanical arm
syringe actuated mechanical armsyringe actuated mechanical arm
syringe actuated mechanical arm
 
jcb
jcbjcb
jcb
 
Mechanical projects
Mechanical projects Mechanical projects
Mechanical projects
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
 
Project report format
Project report formatProject report format
Project report format
 
Continuously reinforced concrete pavement seminar report by chandramohan lodha
Continuously reinforced concrete pavement seminar report by chandramohan lodhaContinuously reinforced concrete pavement seminar report by chandramohan lodha
Continuously reinforced concrete pavement seminar report by chandramohan lodha
 
MECHANICAL PROJECT
MECHANICAL PROJECTMECHANICAL PROJECT
MECHANICAL PROJECT
 
Multistorey residential building construction training report
Multistorey residential building construction training  reportMultistorey residential building construction training  report
Multistorey residential building construction training report
 

Similar to Chhabra Thermal Power plant ppt by Cm lodha

Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with backgroundKazim sultani
 
Pebbles II site report
Pebbles II site reportPebbles II site report
Pebbles II site reportkalyani kadam
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907yogesh pal
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...IRJET Journal
 
Rmc plant
Rmc plantRmc plant
Rmc plantKp Ahm
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementNIWASHISH VISWAS
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 

Similar to Chhabra Thermal Power plant ppt by Cm lodha (20)

Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with background
 
Persentation on "ELEVATED ROAD"
 Persentation on "ELEVATED ROAD" Persentation on "ELEVATED ROAD"
Persentation on "ELEVATED ROAD"
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
DMC Piling
DMC PilingDMC Piling
DMC Piling
 
DMC piling
DMC pilingDMC piling
DMC piling
 
Pebbles II site report
Pebbles II site reportPebbles II site report
Pebbles II site report
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907
 
Field work
Field workField work
Field work
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...IRJET-  	  Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
IRJET- Use of Solar Energy for Pumping Out Groundwater for Irrigation in ...
 
SACHIN CIVIL.docx
SACHIN CIVIL.docxSACHIN CIVIL.docx
SACHIN CIVIL.docx
 
Rmc plant
Rmc plantRmc plant
Rmc plant
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
SPCL
SPCLSPCL
SPCL
 

Recently uploaded

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 

Recently uploaded (20)

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 

Chhabra Thermal Power plant ppt by Cm lodha

  • 1. ARYA INSTITUTE OF ENGINEERING TECHNOLOGY AND MANAGEMENT CHHABRA THERMAL POWER PLANT ASH DYKE CONSTRUCTION SUBMITTED TO SUBMITTED BY Civil Engineering Department Chandra Mohan Lodha 4th Year Student
  • 2. CONTENTS 1. Introduction 2. Ash Dyke 3. Machinery Used In Construction 4. Materials Used In Ash Pond Construction 5. Preparation Of Base 6. Construction Process 7. Drainage System Of Dyke 8. Use Of Dyke 9. Special Features 10. Conclusion
  • 3. INTRODUCTION Chhabra Thermal Power Plant is one of Rajasthan coal fired power plant. It is located at Chowki Motipura (Village) of tehsil Chhabra in Rajasthan Baran district. The planned capacity of power plant is 2650MW at the end of 12th Five year plan. The first and 2nd unit at Chhabra super thermal power plant was set up at a cost of Rs2,350 crore. Chhabra is all set to become a power generation hub in the state as in the second phase two more units with a capacity of 250 MW each will be installed. Rajasthan Rajya Vidyut Utpadan Nigam Limited (RVUN) has been entrusted with the job of development of power projects under state sector, in the state along with operation & maintenance of state owned power stations. Government of Rajasthan constituted the Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUN) under Companies Act-1956 on 19th July, 2000. The Nigam is since playing lead role in giving highest priority to the power generation for manifold and rapid development of the state. The generating Stations of RVUN have acquired a distinctive reputation in the country for their efficient and economic power generation. Chhabra Thermal Power Station is a 1000-megawatt (MW) coal-fired power station in Rajasthan state, India. A 1320 MW expansion of the power station is under construction.
  • 4. The power station is owned and operated by Rajasthan Rajya Vidyut Utpadhan Nigam (RVUN or RRVUN), a government-owned utility. It began as a 500 MW power station, commissioned in 2009-2010. The power station was later expanded by two 250 MW units (Units 3&4). Unit 3 was commissioned in 2013, and unit 4 in 2014. ISTALLED CAPACITY Unit 1 - 250 MW - Operating (commissioned October 30, 2009) Unit 2 - 250 MW - Operating (commissioned May 4, 2010) Unit 3 - 250 MW - Operating (commissioned September 14, 2013) Unit 4 - 250 MW - Operating (commissioned 30 June 2014) Unit 5 - 660 MW - Construction Unit 6 - 660 MW - Construction
  • 5.
  • 6. Ash Dyke/pond An ash pond is an engineered structure for the disposal of bottom ash and fly ash. The wet disposal of ash into ash ponds is the most common ash disposal method , but other methods include dry disposal in landfills. Dry-handled ash is often recycled into useful building materials. Wet disposal has been preferred due to economic reasons, but increasing environmental concerns regarding leachate from ponds has decreased the popularity of wet disposal. The wet method consists of constructing a large "pond" and filling it with fly ash slurry, allowing the water to drain and evaporate from the fly ash over time. Ash ponds are generally formed using a ring embankment to enclose the disposal site. The embankments are designed using similar design parameters as embankment dams, including zoned construction with clay cores. The design process is primarily focused on handling seepage and ensuring slope stability.
  • 7. Machinery Used In Construction Machinery used in ash pond construction like • Poke Land • Jcb • Dozer • Grader • Roller • Trucks
  • 8. Poke Land :- Poke land is a hydraulic machine which used in the digging. It is used in the larger project work and speedily constructional work . It have higher load bearing capacity. The poke land machine is also available in two types 1.Three hundred poke land 2. Two hundred poke land Both the machines have different capacity according to the design capacity .
  • 9. JCB :- jcb is a earth moving machine which used in the construction work . It give more importance in the construction filed . It is multi used machine in the construction work .it is provide faster work . DOZER :- It is a earth cutting machine which used in the larger project work . Mostly it is used in the depth of earth about 20m for the harder stone cutting/collection of stone particles. It have front larger size part which is very used and have higher capacity. GRADER :-A grader, also commonly referred to as a road grader, a blade, a maintainer, or a motor grader, is a construction machine with a long blade used to create a flat surface during the grading process. second blade that is placed in front of the front axle. Some construction personnel refer to the entire machine as "the blade". Capacities range from a blade width of 2.50 to 7.30 m and engines from 93–373 kW(125–500 hp).
  • 10. ROLLER :-A road roller (sometimes called a roller-compactor, or just roller) is a compactor type engineering vehicle used to compact soil, gravel, concrete, or asphalt in the construction of roads and foundations, similar rollers are used also at landfills or in agriculture. In some parts of the world, road rollers are still known colloquially as steam rollers, regardless of their method of propulsion. This typically only applies to the largest examples (used for road- making). Trucks :-Normally trucks are used for the transportation but in the construction field it is used for sand , soil, stone, cement etc material dumping/supply. From one place to another place. Modern trucks are largely powered by diesel engines, although small to medium size trucks with gasoline engines.
  • 11. Material Used In Ash Pond Construction For the ash pond construction many materials required . Some materials are :- Concrete (M7.5, M25) Bricks (Fly Ash ) Cement Soil LDPE ( 150&270 micron thick geomembrane ) Black cotton ( Black Sand 300mm )
  • 12. Preparation Of Base The preparation of base for the ash pond construction is simplest process. Firstly survey of the all area and test of field like soil test , ground water level of area .marked the area required for the ash pond construction . After that dig the depth about 12meter depth all area by machinery used . Finished the base surface clearly with 0 degree angles. The ash pond all sides having width 12 to 15 meter for vehicle travelling and transportation . The ash pond all walls having slope 60 degree. Cutting the all walls with 60 degree slope and finish properly . Around the ash pond drainage system must required so drainage base also cut by machines. Now base is complete for the ash pond design process.
  • 13. Construction Process Of Ash Dyke The Construction of ash dyke required special skills and engineering knowledge . The Construction of ash dyke in the parts like 1. Construction of trench beam 2. Construction of base 3. Construction of sloping walls 4. Construction of bad 1. Construction Of Trench Beam :- The design of trench beam according to the drawing all the measurements used according to the drawing. The trench beam located nearly the sloping wall base point. The beam having size 500mm height , 230 mm width (500*230)mm and concrete M7.5 used in the construction. 2. Construction Of Base :- After cut and finishing the surface 150mm depth soil fill in the all base area and then soil covered by175 micron thick LDPE spread in all the area . And then LDPE jointed by the electric jointing machine.
  • 14. STEP -3 CONSTRUCTION OF BASE STEP -1 STEP -2
  • 15. 3.Construction Of Sloping Walls:- The design of sloping walls of ash dyke required technical specifications . Design according to the given drawing . The concrete used in the wall construction is M25. Construction of sloping walls are as follows given dimensions. Length 9m , width 3m , thickness 75mm.
  • 16. 4. Construction Of Bad :- the construction of ash dyke bad is similar process as like dams bad process. The width of bad is equal to 15metere with flat surface. It is also used for transportation in the construction time . It is made up of sand with compaction , compaction should be completed by the vibration roller. The length of bad is depends upon the size of dyke.
  • 17. Construction Of Drainage System The drainage system of ash dyke is outer side of the dyke. With special supervision and according to the given drawing. The drainage system base completed by using of concrete M7.5 and walls having dimensions height 800mm , width 350mm and length depends upon the drain length. The slope between starting point of wall and end point of wall is 1:0.5 The drain walls constructed by the cement , sand , bricks with proper ratio of cement sand and water.
  • 18. PRIMARILY, THE FLY ASH IS DISPOSED OFF USING EITHER DRY OR WET DISPOSAL SCHEME. IN DRY DISPOSAL, THE FLY ASH IS TRANSPORTED BY TRUCK, CHUTE OR CONVEYOR AT THE SITE AND DISPOSED OFF BY CONSTRUCTING A DRY EMBANKMENT (DYKE). IN WET DISPOSAL, THE FLY ASH IS TRANSPORTED AS SLURRY THROUGH PIPE AND DISPOSED OFF IN IMPOUNDMENT CALLED "ASH POND". Use of Ash Dyke
  • 19. Special Features • Use Of LDPE (175 micron thick membrane) to protect under ground water. • Use of trench beam to maintain black cotton (Black Soil). • Use of sloping walls with concrete to protect seepage of water. • Use of proper drainage system around the ash dyke.
  • 20. CONCLUSION The construction of ash dyke for the fly ash disposal and utilization in the thermal power plants is compulsory. But in the ctpp power plant ash dyke construction is something different as compare to other ash dykes. Comparison clarify by the special features of the dyke. The engineering summer internship time is very good for my practical knowledge of the field.