Oil Well cementing is the process of mixing
a slurry of cement and water and displacing
it down the casing, tubing or drill pipe to a
pre specified point in the well
Two types of cementing process
 Primary cementing
 Secondary cementing
CEMENTATION
PRIMARY CEMENTATION
The cementing takes place soon after the
lowering of casing is called primary cementation.
It is the process of mixing a slurry of cement
and water and pumping it down through steel
casing of the critical points in the annulus
between casing and open hole.
MAIN FUNCTIONS
• To bond and support the casing
• Protect the casing from corrosion.
• To restrict fluid movement between formations
• Protecting the casing from shock loads
• Sealing-off problematic zones.
High Press Gas
Fresh Water
Gas
Oil
Water
Oil
Surface Casing
Intermediate Casing
Production Casing
Conductor Casing
PRIMARY CEMENTING
Three most commonly used techniques :-
1. Single stage cementation
2. Multi stage cementation
3. Liner cementation
TECHNIQUES
SINGLE STAGE CEMENTING
It is the Most common technique
Normally accomplished by pumping
one batch of cement down the
casing between two rubber plugs.
The bottom plug is placed in the
casing, followed by cement slurry.
When the batch of cement has
been pumped into the casing, a top
plug is released.
The top plug is pumped down until
it lands on the top of float collar,
thus completing the cement job.
Float Shoe
Float collar
Bottom Plug
Top Plug
Centralizers
Cement Slurry
Well Fluid (Mud)
Pre-flush/ Spacer
FLOAT COLLARGUIDE SHOE
CEMENTING PLUGS
CENTRALIZERS
MULTI STAGE CEMENTATION
STAGE COLLAR FOR
MULTI STAGE CEMENTATION
13-3/8” C/Shoe
(1200 M)
LINER
CEMENTATION
9-5/8” C/Shoe
(2800 M)
7” Liner Shoe
(3800 M)
POST JOB CONSIDERATION
WAITING ON CEMENT (WOC)
Compressive strength
500psi Resuming drilling
2000psi Perforation
CEMENT AND ADDITIVES
Cement
• Class ‘G’ Oil Well Cement
Chemicals & Additives
Used to change the properties of cement slurries.
• Accelerators
• Retarders
• Fluid Loss Additives
• Friction Reducer
• Defoamer
ANY CEMENTING OPERATION THAT OCCUR
AFTER THE PRIMARY CEMENTING OPERATION.
TYPES OF SECONDARY CEMENTATION
 PLUG CEMENTING
 SQUEEZE CEMENTING
SECONDARY CEMENTATION
PLUG CEMENTING
In plug cementing, a cement plug of a
specified length is placed across a
selected interval in an open or a cased
hole.
The cement is normally pumped through
open-ended drill pipe or tubing.
TECHNIQUE
BALANCE PLUG METHOD
Reasons for setting a cement plug
1. To stop lost circulation during drilling.
2. Directional drilling and side tracking.
3. To plug back a depleted zone.
4. Abandonment.
5. To provide anchor for open hole test tool.
SQUEEZE CEMENTING
The most common remedial method
used today is squeeze cementing.
In squeeze cementing -
The slurry is forced by pressure to a
specified point in the annulus to cause
a seal at the point of squeeze.
CLASSIFICATION BY PRESSURE
1. LOW PRESSURE SQUEEZING.
2. HIGH PRESSURE SQUEEZING.
SQUEEZING TECHNIQUES
1. BRADENHEAD.
2. PACKER SQUEEZE.
SQUEEZE TECHNIQUES
SQUEEZE TECHNIQUES
CLASIFICATION BY PRESSURE
LOW PRESSURE SQUEEZING
 Injection pressure < formation
fracture pressure
 Cavities and interconnected voids
filled with dehydrated cement
 Volume of cement small
 Perforation and channel clear of
mud and other solids
 Small node of cement filter cake
with properly designed slurries
 Highest success rate
CLASIFICATION BY PRESSURE
HIGH PRESSURE SQUEEZE
 Injection pressure > formation
fracture pressure
 Channels not directly connected to
perforations
 Impossible to remove plugging
material inside perforations
 Placement accomplished by
breaking down formation
 Location & orientation of fracture
not controlled.
SQUEEZE DEFINITION
Applications :
1. Supplement a faulty primary cement job.
2. Reduce water/oil, water/gas, or gas/oil ratio.
3. Repair casing leaks.
4. Stop lost circulation in open hole while drilling.
5. Supplement primary cement around a liner by
squeezing the top of the liner (during primary
cementation)
6. Sealing leakage of the liner top (in case of failure
after primary cementation).
7. Abandonment of single zones.
RE-CEMENT SQUEEZE
CHANNEL SQUEEZING
CASING SPLIT
LINER SQUEEZE
CEMENTING: PLANNING & JOB EXECUTION
•SLURRY DESIGN
•BLENDING & LOADING OF CEMENT
•WELL PREPARATION
Space for placement
Clean water
Mud pumps
Pressure gauges & stroke counter
Centralizer
Connection from stand pipe
Mobilization of equipment
JOB EXECUTION
POST JOB CONSIDERATION
• Casing pressure
• Waiting on cement
Cementation

More Related Content

What's hot

Cementing
CementingCementing
Cementing
SadeqRajabi
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation kaleem ullah
 
Cementing
CementingCementing
Cementing
M.T.H Group
 
Casing design
Casing designCasing design
Casing design
SYED NAWAZ
 
Drilling Engineering - Primary Cementing
Drilling Engineering - Primary CementingDrilling Engineering - Primary Cementing
Drilling Engineering - Primary Cementing
James Craig
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
amrhaggag
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
DagogoGreenFurosigha
 
Pressure Draw Down Test
Pressure Draw Down TestPressure Draw Down Test
Pressure Draw Down Test
Mubarik Rao
 
Well completion fundamentals
Well completion fundamentalsWell completion fundamentals
Well completion fundamentals
Ogbarode Napoleon Ogbon
 
Q922+de2+l07 v1
Q922+de2+l07 v1Q922+de2+l07 v1
Q922+de2+l07 v1AFATous
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
Narendra Kumar Dewangan
 
Secondary cementing
Secondary cementingSecondary cementing
Secondary cementing
kareem Hassan
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
TinaMarey
 
Casing
CasingCasing
Petroleum Production Engineering - Perforation
Petroleum Production Engineering - PerforationPetroleum Production Engineering - Perforation
Petroleum Production Engineering - Perforation
James Craig
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT EnvironmentNikhil Barshettiwar
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
AAPG SU SC
 
Drilling Fluids Mud
Drilling Fluids MudDrilling Fluids Mud
Drilling Fluids Mud
M.T.H Group
 
Well completion
Well completionWell completion

What's hot (20)

Cementing
CementingCementing
Cementing
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation
 
Cementing
CementingCementing
Cementing
 
Squeeze cementing
Squeeze cementingSqueeze cementing
Squeeze cementing
 
Casing design
Casing designCasing design
Casing design
 
Drilling Engineering - Primary Cementing
Drilling Engineering - Primary CementingDrilling Engineering - Primary Cementing
Drilling Engineering - Primary Cementing
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
 
Pressure Draw Down Test
Pressure Draw Down TestPressure Draw Down Test
Pressure Draw Down Test
 
Well completion fundamentals
Well completion fundamentalsWell completion fundamentals
Well completion fundamentals
 
Q922+de2+l07 v1
Q922+de2+l07 v1Q922+de2+l07 v1
Q922+de2+l07 v1
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Secondary cementing
Secondary cementingSecondary cementing
Secondary cementing
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
 
Casing
CasingCasing
Casing
 
Petroleum Production Engineering - Perforation
Petroleum Production Engineering - PerforationPetroleum Production Engineering - Perforation
Petroleum Production Engineering - Perforation
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT Environment
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Drilling Fluids Mud
Drilling Fluids MudDrilling Fluids Mud
Drilling Fluids Mud
 
Well completion
Well completionWell completion
Well completion
 

Viewers also liked

7'' liner running and cementing
7'' liner running and cementing7'' liner running and cementing
7'' liner running and cementing
Kamel Elsayed
 
Cementing Technique in Arthroplasty - tips, tricks and Traps
Cementing Technique in Arthroplasty - tips, tricks and TrapsCementing Technique in Arthroplasty - tips, tricks and Traps
Cementing Technique in Arthroplasty - tips, tricks and Traps
Vaibhav Bagaria
 
Packers
PackersPackers
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge coursesCEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
Indian dental academy
 
Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)
James Craig
 
Dental cement dental material
Dental cement dental materialDental cement dental material
Dental cement dental material
Dr-Faisal Al-Qahtani
 
Petroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of PetroleumPetroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of Petroleum
James Craig
 
Modern Cementing Technique: Acetabulum
Modern Cementing Technique: AcetabulumModern Cementing Technique: Acetabulum
Modern Cementing Technique: AcetabulumArun Shanbhag
 
Cement production line
Cement production lineCement production line
Cement production line
Evita Lee
 
ABB_Podilsky_Reprint_WorldCement_lowres
ABB_Podilsky_Reprint_WorldCement_lowresABB_Podilsky_Reprint_WorldCement_lowres
ABB_Podilsky_Reprint_WorldCement_lowresDmitry Trikoz
 
Casing Centralizers: Are We Using Too Many or Too Few?
Casing Centralizers: Are We Using Too Many or Too Few?Casing Centralizers: Are We Using Too Many or Too Few?
Casing Centralizers: Are We Using Too Many or Too Few?
pvisoftware
 
Ilustrated drilling dictionary (1)
Ilustrated drilling dictionary (1)Ilustrated drilling dictionary (1)
Ilustrated drilling dictionary (1)Mouloud Issaad
 
Stability /certified fixed orthodontic courses by Indian dental academy
Stability /certified fixed orthodontic courses by Indian dental academy Stability /certified fixed orthodontic courses by Indian dental academy
Stability /certified fixed orthodontic courses by Indian dental academy
Indian dental academy
 

Viewers also liked (14)

Cementation
CementationCementation
Cementation
 
7'' liner running and cementing
7'' liner running and cementing7'' liner running and cementing
7'' liner running and cementing
 
Cementing Technique in Arthroplasty - tips, tricks and Traps
Cementing Technique in Arthroplasty - tips, tricks and TrapsCementing Technique in Arthroplasty - tips, tricks and Traps
Cementing Technique in Arthroplasty - tips, tricks and Traps
 
Packers
PackersPackers
Packers
 
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge coursesCEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
CEMENTATION PROCEDURES IN FIXED PARTIAL DENTURES/ dental crown & bridge courses
 
Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)
 
Dental cement dental material
Dental cement dental materialDental cement dental material
Dental cement dental material
 
Petroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of PetroleumPetroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of Petroleum
 
Modern Cementing Technique: Acetabulum
Modern Cementing Technique: AcetabulumModern Cementing Technique: Acetabulum
Modern Cementing Technique: Acetabulum
 
Cement production line
Cement production lineCement production line
Cement production line
 
ABB_Podilsky_Reprint_WorldCement_lowres
ABB_Podilsky_Reprint_WorldCement_lowresABB_Podilsky_Reprint_WorldCement_lowres
ABB_Podilsky_Reprint_WorldCement_lowres
 
Casing Centralizers: Are We Using Too Many or Too Few?
Casing Centralizers: Are We Using Too Many or Too Few?Casing Centralizers: Are We Using Too Many or Too Few?
Casing Centralizers: Are We Using Too Many or Too Few?
 
Ilustrated drilling dictionary (1)
Ilustrated drilling dictionary (1)Ilustrated drilling dictionary (1)
Ilustrated drilling dictionary (1)
 
Stability /certified fixed orthodontic courses by Indian dental academy
Stability /certified fixed orthodontic courses by Indian dental academy Stability /certified fixed orthodontic courses by Indian dental academy
Stability /certified fixed orthodontic courses by Indian dental academy
 

Similar to Cementation

Cement additives
Cement additivesCement additives
Cement additives
OYLex LMS
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
ErankajKumar
 
Coring casing and cementation and drilling fluids
Coring casing and cementation and drilling fluidsCoring casing and cementation and drilling fluids
Coring casing and cementation and drilling fluids
SANJAY KRISHNA BHUYAN
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
ErankajKumar
 
Grouting
GroutingGrouting
1.9 GROUTING.ppt
1.9 GROUTING.ppt1.9 GROUTING.ppt
1.9 GROUTING.ppt
Venkatesh Baskar
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
Raghavendra Rachamadugu
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
Amol Pawar
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
Akshay kumar
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
ktx500
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
ChristopherThomas578171
 
4. cement
4. cement4. cement
Concrete
ConcreteConcrete
EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDFMoises Nava
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
ARUNKUMARC39
 

Similar to Cementation (20)

Cement additives
Cement additivesCement additives
Cement additives
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
Coring casing and cementation and drilling fluids
Coring casing and cementation and drilling fluidsCoring casing and cementation and drilling fluids
Coring casing and cementation and drilling fluids
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
 
Grouting
GroutingGrouting
Grouting
 
1.9 GROUTING.ppt
1.9 GROUTING.ppt1.9 GROUTING.ppt
1.9 GROUTING.ppt
 
Kellingray
KellingrayKellingray
Kellingray
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
 
Defining Well completion
Defining Well completionDefining Well completion
Defining Well completion
 
4. cement
4. cement4. cement
4. cement
 
Cip
CipCip
Cip
 
Concrete
ConcreteConcrete
Concrete
 
precast manholes
precast manholesprecast manholes
precast manholes
 
EP- August 2015.PDF
EP- August 2015.PDFEP- August 2015.PDF
EP- August 2015.PDF
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 

Recently uploaded

basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 

Recently uploaded (20)

basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 

Cementation

  • 2. Oil Well cementing is the process of mixing a slurry of cement and water and displacing it down the casing, tubing or drill pipe to a pre specified point in the well Two types of cementing process  Primary cementing  Secondary cementing CEMENTATION
  • 3.
  • 4. PRIMARY CEMENTATION The cementing takes place soon after the lowering of casing is called primary cementation. It is the process of mixing a slurry of cement and water and pumping it down through steel casing of the critical points in the annulus between casing and open hole.
  • 5. MAIN FUNCTIONS • To bond and support the casing • Protect the casing from corrosion. • To restrict fluid movement between formations • Protecting the casing from shock loads • Sealing-off problematic zones.
  • 6. High Press Gas Fresh Water Gas Oil Water Oil Surface Casing Intermediate Casing Production Casing Conductor Casing PRIMARY CEMENTING
  • 7.
  • 8. Three most commonly used techniques :- 1. Single stage cementation 2. Multi stage cementation 3. Liner cementation TECHNIQUES
  • 9. SINGLE STAGE CEMENTING It is the Most common technique Normally accomplished by pumping one batch of cement down the casing between two rubber plugs. The bottom plug is placed in the casing, followed by cement slurry. When the batch of cement has been pumped into the casing, a top plug is released. The top plug is pumped down until it lands on the top of float collar, thus completing the cement job.
  • 10. Float Shoe Float collar Bottom Plug Top Plug Centralizers Cement Slurry Well Fluid (Mud) Pre-flush/ Spacer
  • 15. STAGE COLLAR FOR MULTI STAGE CEMENTATION
  • 16. 13-3/8” C/Shoe (1200 M) LINER CEMENTATION 9-5/8” C/Shoe (2800 M) 7” Liner Shoe (3800 M)
  • 17. POST JOB CONSIDERATION WAITING ON CEMENT (WOC) Compressive strength 500psi Resuming drilling 2000psi Perforation
  • 18. CEMENT AND ADDITIVES Cement • Class ‘G’ Oil Well Cement Chemicals & Additives Used to change the properties of cement slurries. • Accelerators • Retarders • Fluid Loss Additives • Friction Reducer • Defoamer
  • 19.
  • 20. ANY CEMENTING OPERATION THAT OCCUR AFTER THE PRIMARY CEMENTING OPERATION. TYPES OF SECONDARY CEMENTATION  PLUG CEMENTING  SQUEEZE CEMENTING SECONDARY CEMENTATION
  • 21.
  • 22. PLUG CEMENTING In plug cementing, a cement plug of a specified length is placed across a selected interval in an open or a cased hole. The cement is normally pumped through open-ended drill pipe or tubing.
  • 24. Reasons for setting a cement plug 1. To stop lost circulation during drilling. 2. Directional drilling and side tracking. 3. To plug back a depleted zone. 4. Abandonment. 5. To provide anchor for open hole test tool.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. SQUEEZE CEMENTING The most common remedial method used today is squeeze cementing. In squeeze cementing - The slurry is forced by pressure to a specified point in the annulus to cause a seal at the point of squeeze.
  • 31. CLASSIFICATION BY PRESSURE 1. LOW PRESSURE SQUEEZING. 2. HIGH PRESSURE SQUEEZING. SQUEEZING TECHNIQUES 1. BRADENHEAD. 2. PACKER SQUEEZE.
  • 34. CLASIFICATION BY PRESSURE LOW PRESSURE SQUEEZING  Injection pressure < formation fracture pressure  Cavities and interconnected voids filled with dehydrated cement  Volume of cement small  Perforation and channel clear of mud and other solids  Small node of cement filter cake with properly designed slurries  Highest success rate
  • 35. CLASIFICATION BY PRESSURE HIGH PRESSURE SQUEEZE  Injection pressure > formation fracture pressure  Channels not directly connected to perforations  Impossible to remove plugging material inside perforations  Placement accomplished by breaking down formation  Location & orientation of fracture not controlled.
  • 37. Applications : 1. Supplement a faulty primary cement job. 2. Reduce water/oil, water/gas, or gas/oil ratio. 3. Repair casing leaks. 4. Stop lost circulation in open hole while drilling. 5. Supplement primary cement around a liner by squeezing the top of the liner (during primary cementation) 6. Sealing leakage of the liner top (in case of failure after primary cementation). 7. Abandonment of single zones.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 47. CEMENTING: PLANNING & JOB EXECUTION •SLURRY DESIGN •BLENDING & LOADING OF CEMENT •WELL PREPARATION Space for placement Clean water Mud pumps Pressure gauges & stroke counter Centralizer Connection from stand pipe Mobilization of equipment JOB EXECUTION POST JOB CONSIDERATION • Casing pressure • Waiting on cement