JAIPUR METRO RAIL PROJECT 
The Metro Way Of Life 
2012-2013 
(01 June 2012 – 30 June 2012) 
Presented By: 
Anchal Meena , Asha Chaudhary 
Arpit Hada, Poonam Shekhawat 
PriyankaMeena, Narendra Singh 
Shruti Shilpi 
Submitted To: 
Dr. B.P.Suneja 
(Head of PTP)
Introduction 
 Jaipur Metro Rail project, a company under the name Jaipur Metro Rail 
Corporation Limited was incorporated on 01.01.2010 under Companies 
Act,1956. 
 DSC Limited is an infrastructure group started as an Indian Construction 
Company 70 years ago. 
 It has full capabilities from developing, financing constructing and operating 
infrastructure projects across various infrastructure sectors in India and 
abroad. 
Vision 
To be the leading infrastructure developer of choice. 
Mission 
Efficient, rapid and innovative development of quality infrastructure to 
create infrawealth for the nation.
Introduction 
Jaipur Metro Rail project, aIcomnpatnyrunodedr thue ncamte Jiaoipunr Metro Rail Corporation 
Limited was incorporated on 01.01.2010 under Companies Act,1956.
STAGES 
• Mansarover to Chandpole: 9.25 km 
Chandpole to badichopad : 2.3 km 
(approx.) 
• Executed by : D.M.R.C 
• Est. cost : Rs 1250 Crores 
• Est. D.O.C : Febrary 2013 
• Operational Comission of the stage : 
June 2013 
• Ambabari to Sitapura : 23.5 km 
• Executed by : P.P.P 
• Est. cost : Rs 8750 Crores 
• East. D.O.C : Febrary 2015 
• Operational Comission of the stage : 
June 2015
Pile Foundation 
Pile location by Surveyor 
Excavation done by Augger 
Casing wall around Pile Bore
Layout plan of pile group
Piling 
Digging bucket used for drilling 
Bentonite water for dense soil
Pile Location 
Cage Lowering 
Tremie Pipe used for Conc. 
Flushing Head attached
Pile Casting 
1. Hopper is used for 
concreting in the 
piles. 
2. From the transit 
mixer concrete 
discharge into the 
hopper directly. 
3. Tremie pipe is 
always dipped into 
the concrete.
Excavation for pile cap. 
1. After concreting is 
done casing is taken 
out. 
2. In the Chipping 
process top concrete 
of the pile is 
removed. 
3. Chipping is done to 
the cut off level.
Pile Cap 
1. Reinforcement is laid 
into the trench and 
shuttering is provided 
on the sides. 
2. Pier reinforcement is 
laid with the pile cap 
reinforcement. 
3. Concreting is done by 
the boom pipe.
Chipping of Pile 
1. Top of the pile is 
removed manually. 
2. Cause:- At the top of 
the pile silt is 
collected which make 
it weak. 
3. After chipping p.c.c 
provide a bed to the 
pile cap.
Pier 
1. The size of pier is 1.8 m 
to 2.0 m dia. of cir. shape. 
2. A required clearance of 
5.5 m on road side. 
3. The min. ht. of rail above 
the existing road is 8.4 m. 
4. An outward slope of 
1:200 will be provided at 
the pier top for the 
drainage due to spilling of 
rain water.
Crash barrier 
1. A wall is cast around the 
pier at the road level, 
which is known as Crash 
barrier. 
2. The gap of 25 mm is 
maintained between pier 
and crash barrier 
3. It works as a shock 
absorber. And to protect 
the pier from the damage 
by the road accident.
Pier Cap 
On the pier Pier Cap is 
casted, than shear key 
is casted. 
Grade of Concrete- 
M45
Span Laying 
1. Precast Segments lifted 
& layed by Launching 
Girder. 
2.Than Gluing, Threading, 
Prestressing & Grouting is 
done.
Side View of a span 
1. Span of the segment 
varies according to 
the design i.e.21, 
24, 28, 31, 34, 
37m. 
2. Each Segment has a 
different shape & 
weight.
Auto Launching 
1. Shifting of Launching 
Girder to next span 
is called Auto 
Launching. 
2. Launching Girder 
consists of- 
∙Main Box Girder 
∙Front Support 
∙Middle Support 
∙Rear Support 
∙Rear Trolley 
∙Slider Beams
Gluing,prestressing, grouting
Parapet Segment Launching 
1. After the Grouting, 
Parapet Segment 
Launching is done. 
2. Parapet Segment 
weight 3.8 ton. 
3. Segment is launched 
by Gantry by means 
of a vellar or lifter.
Cut & Cover method 
1. Procedure used for 
construction of 
Chandpole Metro 
Station. 
2. D-Wall cage is 
inserted into the 
ground. 
3. Work is done from 
top to bottom.
Ramp section 
1. Ramp Section is 
provided for 
access of metro 
from elevated to 
underground 
metro station. 
2. In ramp section, they 
were using 
timbering process 
to retain the soil.
23
24

Jaipur metro rail project

  • 1.
    JAIPUR METRO RAILPROJECT The Metro Way Of Life 2012-2013 (01 June 2012 – 30 June 2012) Presented By: Anchal Meena , Asha Chaudhary Arpit Hada, Poonam Shekhawat PriyankaMeena, Narendra Singh Shruti Shilpi Submitted To: Dr. B.P.Suneja (Head of PTP)
  • 2.
    Introduction  JaipurMetro Rail project, a company under the name Jaipur Metro Rail Corporation Limited was incorporated on 01.01.2010 under Companies Act,1956.  DSC Limited is an infrastructure group started as an Indian Construction Company 70 years ago.  It has full capabilities from developing, financing constructing and operating infrastructure projects across various infrastructure sectors in India and abroad. Vision To be the leading infrastructure developer of choice. Mission Efficient, rapid and innovative development of quality infrastructure to create infrawealth for the nation.
  • 3.
    Introduction Jaipur MetroRail project, aIcomnpatnyrunodedr thue ncamte Jiaoipunr Metro Rail Corporation Limited was incorporated on 01.01.2010 under Companies Act,1956.
  • 4.
    STAGES • Mansaroverto Chandpole: 9.25 km Chandpole to badichopad : 2.3 km (approx.) • Executed by : D.M.R.C • Est. cost : Rs 1250 Crores • Est. D.O.C : Febrary 2013 • Operational Comission of the stage : June 2013 • Ambabari to Sitapura : 23.5 km • Executed by : P.P.P • Est. cost : Rs 8750 Crores • East. D.O.C : Febrary 2015 • Operational Comission of the stage : June 2015
  • 5.
    Pile Foundation Pilelocation by Surveyor Excavation done by Augger Casing wall around Pile Bore
  • 6.
    Layout plan ofpile group
  • 7.
    Piling Digging bucketused for drilling Bentonite water for dense soil
  • 8.
    Pile Location CageLowering Tremie Pipe used for Conc. Flushing Head attached
  • 9.
    Pile Casting 1.Hopper is used for concreting in the piles. 2. From the transit mixer concrete discharge into the hopper directly. 3. Tremie pipe is always dipped into the concrete.
  • 10.
    Excavation for pilecap. 1. After concreting is done casing is taken out. 2. In the Chipping process top concrete of the pile is removed. 3. Chipping is done to the cut off level.
  • 11.
    Pile Cap 1.Reinforcement is laid into the trench and shuttering is provided on the sides. 2. Pier reinforcement is laid with the pile cap reinforcement. 3. Concreting is done by the boom pipe.
  • 12.
    Chipping of Pile 1. Top of the pile is removed manually. 2. Cause:- At the top of the pile silt is collected which make it weak. 3. After chipping p.c.c provide a bed to the pile cap.
  • 13.
    Pier 1. Thesize of pier is 1.8 m to 2.0 m dia. of cir. shape. 2. A required clearance of 5.5 m on road side. 3. The min. ht. of rail above the existing road is 8.4 m. 4. An outward slope of 1:200 will be provided at the pier top for the drainage due to spilling of rain water.
  • 14.
    Crash barrier 1.A wall is cast around the pier at the road level, which is known as Crash barrier. 2. The gap of 25 mm is maintained between pier and crash barrier 3. It works as a shock absorber. And to protect the pier from the damage by the road accident.
  • 15.
    Pier Cap Onthe pier Pier Cap is casted, than shear key is casted. Grade of Concrete- M45
  • 16.
    Span Laying 1.Precast Segments lifted & layed by Launching Girder. 2.Than Gluing, Threading, Prestressing & Grouting is done.
  • 17.
    Side View ofa span 1. Span of the segment varies according to the design i.e.21, 24, 28, 31, 34, 37m. 2. Each Segment has a different shape & weight.
  • 18.
    Auto Launching 1.Shifting of Launching Girder to next span is called Auto Launching. 2. Launching Girder consists of- ∙Main Box Girder ∙Front Support ∙Middle Support ∙Rear Support ∙Rear Trolley ∙Slider Beams
  • 19.
  • 20.
    Parapet Segment Launching 1. After the Grouting, Parapet Segment Launching is done. 2. Parapet Segment weight 3.8 ton. 3. Segment is launched by Gantry by means of a vellar or lifter.
  • 21.
    Cut & Covermethod 1. Procedure used for construction of Chandpole Metro Station. 2. D-Wall cage is inserted into the ground. 3. Work is done from top to bottom.
  • 22.
    Ramp section 1.Ramp Section is provided for access of metro from elevated to underground metro station. 2. In ramp section, they were using timbering process to retain the soil.
  • 23.
  • 24.