SlideShare a Scribd company logo
CONSTRUCTION OF HIGH LEVEL
 BRIDGE OVER SUTLEJ RIVER

       WELL FOUNDATION
PROJECT BREIFING

 This bridge forms a part of a bye-pass project near Ropar
     The project is undertaken by B&R division of PWD.
     Total cost of the bridge over Sutlej is 63 crs.
     The contract is given to the company on the lump sum basis.


    Length                                       982 m
    Lanes                                        4 lane
    Spans                                        28
    Length of span                               36.5 m ( middle 23 spans)
                                                 24 m (end spans)
    Formation level                              273.5 m
    High flood level                             264.2 m
Alignment
•Alignment of the
bridge passes through :

New I.I.T. Road

Sutlej river

Nwansheher highway

•Alignment crosses river
at an angle therefore it
is a Skew alignment
Height of Bridge

 Bridge is high level bridge i.e. formation
  level is above H.F.L.
 Height if bridge is determined by
  examining the clearance of bridge over
  highway
 As per IRC 5:1998
Min. clearance needed = 5 m
Road level =267
Width of beam and slab =1.7 m
Req. formation level= 273.7 m
Actual formation level=274.7 m
Extent of exploration

 The exploration shall cover the entire length of the bridge and also
  extend at either side for a distance of about twice the depth below bed
  of the last main foundations i.e. if depth of foundation below bed is
  24mts. then exploration will be done up to 48mts away from ends.

 The depth of exploration should be at least 1 ½ times the minimum
  width of the foundation below the proposed foundation level in case of
  open foundations and deep well foundation

 Where such investigation end in any unsuitable or questionable foundation
  material, the exploration shall be extended to a sufficient depth into firm and
  stable soil or rock but not less than four times the minimum depth of
  foundation below the earlier contemplated foundation level.
Scour depth

 Depth of scour below the high flood level.
 Scour depth has important in determination depth of
  foundation.
Determination
 The maximum depth of scour should be measured with
  reference to existing structures near the proposed bridge
  site, if this is possible. Such soundings are best done
  during or immediately after a flood.
 Mean scour depth (dsm )= 9.2 m
 Max. scour depth for piers = 2 dsm = 18.4 m
Depth of foundation

 Well foundation are taken up to depth such that min.
  grip of foundation below max. scour depth is 1/3 rd
  of max. scour depth.
 The max. Bearing pressure on the subsoil under the
  foundation resulting from any combination of the
  loads and forces except wind and seismic forces
  should not exceed the safe bearing capacity of the
  subsoil, after taking into account the effect of scour.
WELL
FOUNDATION
•Well foundation lies
under the category of
open caisson

•They are open at both
ends
Well
Components
Cutting edge

Well curb

Well steining

Bottom plug

Sand fill

Top plug

Well cap
Cutting edge

•Cutting edge is the lowermost
part of a well It is the part
which cuts through the earth.
•The mild steel cutting edge
shall be made from structural
steel sections.
• The cutting edge shall weigh
not less than 40 kg per metre
length and be properly
anchored into the well curb
• sections are bent into shape
by cold bended no heating is
                                 The picture above shows a three 160mm MS
done.                            Sections curved and welded to form Cutting
                                                    Edge.
Well curb

•Well curb is a structure with
outer wall of curb being straight
and inner at an appropriate angle
which is fabricated over cutting
edge.
•The internal angle of curb can be
kept between 30O to 37o .
•It serves the purpose of
transferring
•Load from steining to bottom
plug.
•Thickness of well curb is 75mm
more than that of steining to
prevent tilts
                                     A fabricated well curb set atop wooden planks
Well curb



 Reinforcements in a
      well curb

 Vertical bars -20 dia.
Triangular bars -20 dia.
Well steining
 It is the longest part of well and it transfers load from
     well cap to the well curb at desired depth.
    Track of length is taken by marking wells on 4 sides
     by gauges.
    Steining is built in lifts of 2.15m and each lift is
     aligned with previous one.
    As per IRC 78:200
1.      The amount of vertical reinforcement provided
        should not be less than .2% of cross sectional area
        of steining.
2.      At the inner face reinforcement must not be less
        than .06% of area.
3.      Transverse reinforcement must not be less than
        .04% of volume/unit length of steining.
Reinforcements in steining


 For wells 12 to 23
 Outer dia.= 5.35 m inner dia. = 3.4 m
 Area of steining= 13.394
 Min. reinforcement for steining (20 dia.
  Bars)= .02*area/area of bar = 85.3 = 86
  bars
  Actual no. =62+26 =88 bars
 Min. reinforcements for inner wall(20
  dia.)=.oo6*area/area of bar =25.59 = 26
  bars
  Actual no. =26 bars
Well steining

 Determination of thickness of steining
 The min. thickness should not be less than 500mm and should be
    according:
                 h=kd√l     where : h- min. thickness in m
                                    d=external dia. Of well
                                    l=depth of well below well cap
                                    k= a constant = 0.03
 At the site:   avg. depth of well = 25m
                              dia. = 5.2m
 So        Min. thickness required = .78 m
Well steining

 But some adjustments are needed in thickness according to
    the strata as given by the table:
        Strata                                   Adjustment
        Very soft clay strata                    -10%
        Hard clay strata                         +10%
        Boulder strata or well resting on rock   +10%

 As the strata is sand with boulders
             final thickness is = .858 m
 Original thickness =.78 m (well no. 1-11 and 24 -29)
                    = .88m (well no. 12-23)
 Bottom plug- transfers the load of structure from well to the
  ground. It is cast under water after the final depth of well is
  reached. No reinforcement is provided. The mix should have min.
  cement content of 330Kg/m3

 Sand filling : Sand filling shall commence after a period of 3 days of
  laying of bottom plug. It helps in increasing the weight of the
  foundation which provides more stability to the structure. It also
  counteract buoyant force of water.

 Intermediate plug :The function of the plug is to keep the sand
  filling sandwiched & undisturbed. The concrete used for
  intermediate plugging is also M25.

 Top plug :After filling sand up to the required level a plug of
  concrete is provided over it as shown on the drawing. It at least
  serves as a shuttering for laying well cap.

 Well cap- It is needed to transfer the loads and moments from the
  pier to the well or wells below. It is designed as two way slab.
Well parameters

Parameters                                                   Data

                                                             59 n0.
  1.   Total no. of wells to be sunk
                                                             M 30
  2.   Grade of concrete used for well curb and steinning:
                                                             M 25
  3. Grade of concrete used for bottom, intermediate
  and top plugging
                                                             OPC 43-G
  4.   Type of Cement used
                                                             FE 500
  5.   Grade of steel used for reinforcement:
                                                             9m
  7.   Scouring levels from previous years data:
                                                             16 mm
  9.   Thickness of the cutting edge:
Well parameters

Parameters                            Data

   Depth of the wells below ground:   Well no. 1 to 11:24.0 m
                                      Well no. 12 to 23: 26.5 m

                                      Well no. 24 to 29: 24.0 m

  Height of well curb:                well no. 1 to 11 and 24,25: 1.410 m
                                      Well no. 12 to 25: 1.530

  Thickness of the well steinning:    Well no. 1 to 11: 780 mm

                                      Well no. 12 to 23: 880 mm

                                      Well no. 24 to 29: 780 mm
Construction of well


Setting of well curb

  Sinking of well

     Bottom plugging

       Sand filling

          Closing of top by well cap
Setting of well curb

 The centre of the well is marked
  accurately with help of theodolite.
 Cutting edge is placed on the wooden
  sleepers such that centre of cutting
  edge coincide with the marked centre.
 Reinforcements and formwork for
  curb is fabricated on the cutting edge
  and concreting is done.
 After curing of well curb is complete
  the wooden slippers below the curb
  are removed by making soil below
  them diluted by water and is allowed
  to sink under its own weight.
                                           In this picture a well curb is resting
                                                  on the wooden slippers
Sinking of well/Construction of steinning


                                  1. Fabrication
        3. Dredging of
                                   of formwork
           earth to
                                        and
       support sinking
                                 reinforcements




                     2. Concreting
Sinking of Well
                     Fabrication of Formwork

      Fabrication                                 Concreting

 The formwork for
  casting are                              Concreting is done by
  supported on the                         pumping the concrete to
  channels bolted with                     the mould by concrete
  steining on both                         pump.
  sides.                                   The concrete is placed
                                           in 400mm thick layers
 As per design lap is
                                           along with continues
  provided after every
                                           vibrations.
  fourth
                                           On avg. about 23m3 of
  reinforcement at
                                           concrete is needed for
  same section.
                                           casting of one lift.
Sinking of Well

  Dredging
 In order to sink the well,
  continuous dredging is done.
  Soil is excavated from the
  dredge hole inside the well.
 The dredging operation is
  performed evenly along the
  hole circular hole
Construction of well

 Bottom plugging : it is done after the well
  has reached the founding level. Concreting
  is done inside water. For this tremie pipe is
  used. A tremie is long funnel made of mild
  steel . A flap door is provided at its bottom.
 Well cap:After water filling, a truss system
  consisting of three trusses supported in
  well steining and cribs welded with it in
  criss-cross manner are used for top
  plugging. This system is covered with
  strong plywood and sealed with concrete
  slurry so that nothing can enter inside the
  well. Hence preparing it for the casting of
  well cap.
Methods to promote sinking

 Kentledge -Total of 125 concrete cubes of 1m3 in size
  are made for kentledge loading which is
  approximately equal to 25t × 125.
 Chiseling- When the boulders are very firmly
  cemented then chiselling is done. In this soil is hit
  hard by sharp end chisel.
 Dewatering- dewatering of dredge hole is done to
  reduce buyout force on well thus promoting sinking.
 Flushing with jet of water on the outside face of well
  reducing skin friction
Tilt and shift

 Tilt and shift are deviation of well from its proposed position
  and orientation.
 Max. tilt allowed is 1/80
 Max. shift allowed is 150mm
Measures to avoid tilt and shift
 The outer surface of steining and curb should be kept as
  smooth as possible.
 The radius of well curb should be kept more than the steining.
 The dredging should be done on all sides of well uniformly.
Causes
 Eccentric dredging
 Can be caused due to boulder under one side
Method of checking tilt and shift

 Tilt and shift are calculated with the help of
  a level and total station.
Method
 Difference between height of points (1& 3)=
  R.L.(1)-R.L.(3)
 Tilt
  = [ R.L.(1)-R.L.(3)]/diameter
 Shift at bottom from top position
  = tilt/ length
 Note : this process is repeated on sides (2 & 4)
  and in similar manner tilt is obtained and
  then combined tilt and shift is reported.
 Shift of well at top is measured by total
  station.
Correcting tilt and shift

 Regulation of Grabbing
 Eccentric Loading
 Strutting The well
 Water jetting or Digging Pit outside the higher side
  of well
 Pulling the well or caisson
 Excavation on the higher side outside the well
Problems

 Sand blowing- This problem occurs when well bottom rests on
  sandy strata and dewatering is done below water table. In this
  sand from ground gushes into the well and there is sudden
  sinking of well. This sudden sinking is very dangerous and is
  very difficult to rectify.
 Bridge scour -is the removal of sediment from bed such as
  sand and rocks from around bridge, abutments or piers.
  Scour, caused by swiftly moving water, can scoop out scour
  holes, compromising the integrity of a structure.
 Sand heaving-When a well passes through soft strata over a
  considerable depth, the upward resistance acting on the
  outside surface of the well is less than the weight of the well.
  In that situation the well sinks down and quite often a heap is
  formed inside the dredge hole.
Problems

Bridge scour        Sand heaving
Thank You

More Related Content

What's hot

Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
Rushikesh Kolhe
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
vishal prakash
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile FoundationSubham Kundu
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
Dar Hilal
 
Bearing capacity of soil final
Bearing capacity of soil  final Bearing capacity of soil  final
Bearing capacity of soil final
Harigovind Sreekumar
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
Aglaia Connect
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
Latif Hyder Wadho
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
Abhinay Saraswat
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
Tajul Islam
 
CNS layer (usefulsearch.org) (useful search)
CNS layer  (usefulsearch.org) (useful search) CNS layer  (usefulsearch.org) (useful search)
CNS layer (usefulsearch.org) (useful search)
Make Mannan
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Tunnelling
TunnellingTunnelling
Tunnelling
Usama Zia
 
Grouting
Grouting Grouting
Grouting
Chaitanya Raval
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
pradip dangar
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
Sivasai Pratap Reddy
 

What's hot (20)

Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Bearing capacity of soil final
Bearing capacity of soil  final Bearing capacity of soil  final
Bearing capacity of soil final
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
CNS layer (usefulsearch.org) (useful search)
CNS layer  (usefulsearch.org) (useful search) CNS layer  (usefulsearch.org) (useful search)
CNS layer (usefulsearch.org) (useful search)
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Grouting
Grouting Grouting
Grouting
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
 
Dewatering by well point system
Dewatering by well point systemDewatering by well point system
Dewatering by well point system
 

Similar to Well Foundation

Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
SachinThakre10
 
19021 d2004 well foundation design ppt
19021 d2004 well foundation design ppt19021 d2004 well foundation design ppt
19021 d2004 well foundation design ppt
Bala Balaji
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
FAISAL ANSARI
 
unit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptxunit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptx
va234143347
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Tonyamis
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
RajeshKumar25548
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
PRASANTHI PETLURU
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
KumarS250747
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
KumarS250747
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tank
Nagma Modi
 
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdfPile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
DharmPalJangra1
 
346260332-Under-Reamed-Piles-1-10-09.pptx
346260332-Under-Reamed-Piles-1-10-09.pptx346260332-Under-Reamed-Piles-1-10-09.pptx
346260332-Under-Reamed-Piles-1-10-09.pptx
DevPadhiyar1
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ABHISHEK THAKKAE
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Method Statement D Wall
Method Statement D WallMethod Statement D Wall

Similar to Well Foundation (20)

Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Anantpur Report
Anantpur ReportAnantpur Report
Anantpur Report
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
 
19021 d2004 well foundation design ppt
19021 d2004 well foundation design ppt19021 d2004 well foundation design ppt
19021 d2004 well foundation design ppt
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
 
unit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptxunit-4 design drawing of steel stru.pptx
unit-4 design drawing of steel stru.pptx
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tank
 
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdfPile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
Pile&Wellfoundation_ManualUpdated as on 20.5.16.pdf
 
346260332-Under-Reamed-Piles-1-10-09.pptx
346260332-Under-Reamed-Piles-1-10-09.pptx346260332-Under-Reamed-Piles-1-10-09.pptx
346260332-Under-Reamed-Piles-1-10-09.pptx
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Method Statement D Wall
Method Statement D WallMethod Statement D Wall
Method Statement D Wall
 

Recently uploaded

Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 

Recently uploaded (20)

Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 

Well Foundation

  • 1. CONSTRUCTION OF HIGH LEVEL BRIDGE OVER SUTLEJ RIVER WELL FOUNDATION
  • 2. PROJECT BREIFING  This bridge forms a part of a bye-pass project near Ropar  The project is undertaken by B&R division of PWD.  Total cost of the bridge over Sutlej is 63 crs.  The contract is given to the company on the lump sum basis. Length 982 m Lanes 4 lane Spans 28 Length of span 36.5 m ( middle 23 spans) 24 m (end spans) Formation level 273.5 m High flood level 264.2 m
  • 3. Alignment •Alignment of the bridge passes through : New I.I.T. Road Sutlej river Nwansheher highway •Alignment crosses river at an angle therefore it is a Skew alignment
  • 4. Height of Bridge  Bridge is high level bridge i.e. formation level is above H.F.L.  Height if bridge is determined by examining the clearance of bridge over highway  As per IRC 5:1998 Min. clearance needed = 5 m Road level =267 Width of beam and slab =1.7 m Req. formation level= 273.7 m Actual formation level=274.7 m
  • 5. Extent of exploration  The exploration shall cover the entire length of the bridge and also extend at either side for a distance of about twice the depth below bed of the last main foundations i.e. if depth of foundation below bed is 24mts. then exploration will be done up to 48mts away from ends.  The depth of exploration should be at least 1 ½ times the minimum width of the foundation below the proposed foundation level in case of open foundations and deep well foundation  Where such investigation end in any unsuitable or questionable foundation material, the exploration shall be extended to a sufficient depth into firm and stable soil or rock but not less than four times the minimum depth of foundation below the earlier contemplated foundation level.
  • 6. Scour depth  Depth of scour below the high flood level.  Scour depth has important in determination depth of foundation. Determination  The maximum depth of scour should be measured with reference to existing structures near the proposed bridge site, if this is possible. Such soundings are best done during or immediately after a flood.  Mean scour depth (dsm )= 9.2 m  Max. scour depth for piers = 2 dsm = 18.4 m
  • 7. Depth of foundation  Well foundation are taken up to depth such that min. grip of foundation below max. scour depth is 1/3 rd of max. scour depth.  The max. Bearing pressure on the subsoil under the foundation resulting from any combination of the loads and forces except wind and seismic forces should not exceed the safe bearing capacity of the subsoil, after taking into account the effect of scour.
  • 8. WELL FOUNDATION •Well foundation lies under the category of open caisson •They are open at both ends
  • 9. Well Components Cutting edge Well curb Well steining Bottom plug Sand fill Top plug Well cap
  • 10. Cutting edge •Cutting edge is the lowermost part of a well It is the part which cuts through the earth. •The mild steel cutting edge shall be made from structural steel sections. • The cutting edge shall weigh not less than 40 kg per metre length and be properly anchored into the well curb • sections are bent into shape by cold bended no heating is The picture above shows a three 160mm MS done. Sections curved and welded to form Cutting Edge.
  • 11. Well curb •Well curb is a structure with outer wall of curb being straight and inner at an appropriate angle which is fabricated over cutting edge. •The internal angle of curb can be kept between 30O to 37o . •It serves the purpose of transferring •Load from steining to bottom plug. •Thickness of well curb is 75mm more than that of steining to prevent tilts A fabricated well curb set atop wooden planks
  • 12. Well curb Reinforcements in a well curb Vertical bars -20 dia. Triangular bars -20 dia.
  • 13. Well steining  It is the longest part of well and it transfers load from well cap to the well curb at desired depth.  Track of length is taken by marking wells on 4 sides by gauges.  Steining is built in lifts of 2.15m and each lift is aligned with previous one.  As per IRC 78:200 1. The amount of vertical reinforcement provided should not be less than .2% of cross sectional area of steining. 2. At the inner face reinforcement must not be less than .06% of area. 3. Transverse reinforcement must not be less than .04% of volume/unit length of steining.
  • 14. Reinforcements in steining  For wells 12 to 23  Outer dia.= 5.35 m inner dia. = 3.4 m  Area of steining= 13.394  Min. reinforcement for steining (20 dia. Bars)= .02*area/area of bar = 85.3 = 86 bars Actual no. =62+26 =88 bars  Min. reinforcements for inner wall(20 dia.)=.oo6*area/area of bar =25.59 = 26 bars Actual no. =26 bars
  • 15. Well steining  Determination of thickness of steining  The min. thickness should not be less than 500mm and should be according:  h=kd√l where : h- min. thickness in m d=external dia. Of well l=depth of well below well cap k= a constant = 0.03  At the site: avg. depth of well = 25m dia. = 5.2m  So Min. thickness required = .78 m
  • 16. Well steining  But some adjustments are needed in thickness according to the strata as given by the table: Strata Adjustment Very soft clay strata -10% Hard clay strata +10% Boulder strata or well resting on rock +10%  As the strata is sand with boulders  final thickness is = .858 m  Original thickness =.78 m (well no. 1-11 and 24 -29)  = .88m (well no. 12-23)
  • 17.  Bottom plug- transfers the load of structure from well to the ground. It is cast under water after the final depth of well is reached. No reinforcement is provided. The mix should have min. cement content of 330Kg/m3  Sand filling : Sand filling shall commence after a period of 3 days of laying of bottom plug. It helps in increasing the weight of the foundation which provides more stability to the structure. It also counteract buoyant force of water.  Intermediate plug :The function of the plug is to keep the sand filling sandwiched & undisturbed. The concrete used for intermediate plugging is also M25.  Top plug :After filling sand up to the required level a plug of concrete is provided over it as shown on the drawing. It at least serves as a shuttering for laying well cap.  Well cap- It is needed to transfer the loads and moments from the pier to the well or wells below. It is designed as two way slab.
  • 18. Well parameters Parameters Data 59 n0. 1. Total no. of wells to be sunk M 30 2. Grade of concrete used for well curb and steinning: M 25 3. Grade of concrete used for bottom, intermediate and top plugging OPC 43-G 4. Type of Cement used FE 500 5. Grade of steel used for reinforcement: 9m 7. Scouring levels from previous years data: 16 mm 9. Thickness of the cutting edge:
  • 19. Well parameters Parameters Data Depth of the wells below ground: Well no. 1 to 11:24.0 m Well no. 12 to 23: 26.5 m Well no. 24 to 29: 24.0 m Height of well curb: well no. 1 to 11 and 24,25: 1.410 m Well no. 12 to 25: 1.530 Thickness of the well steinning: Well no. 1 to 11: 780 mm Well no. 12 to 23: 880 mm Well no. 24 to 29: 780 mm
  • 20. Construction of well Setting of well curb Sinking of well Bottom plugging Sand filling Closing of top by well cap
  • 21. Setting of well curb  The centre of the well is marked accurately with help of theodolite.  Cutting edge is placed on the wooden sleepers such that centre of cutting edge coincide with the marked centre.  Reinforcements and formwork for curb is fabricated on the cutting edge and concreting is done.  After curing of well curb is complete the wooden slippers below the curb are removed by making soil below them diluted by water and is allowed to sink under its own weight. In this picture a well curb is resting on the wooden slippers
  • 22. Sinking of well/Construction of steinning 1. Fabrication 3. Dredging of of formwork earth to and support sinking reinforcements 2. Concreting
  • 23. Sinking of Well Fabrication of Formwork Fabrication Concreting  The formwork for casting are Concreting is done by supported on the pumping the concrete to channels bolted with the mould by concrete steining on both pump. sides. The concrete is placed in 400mm thick layers  As per design lap is along with continues provided after every vibrations. fourth On avg. about 23m3 of reinforcement at concrete is needed for same section. casting of one lift.
  • 24. Sinking of Well Dredging  In order to sink the well, continuous dredging is done. Soil is excavated from the dredge hole inside the well.  The dredging operation is performed evenly along the hole circular hole
  • 25. Construction of well  Bottom plugging : it is done after the well has reached the founding level. Concreting is done inside water. For this tremie pipe is used. A tremie is long funnel made of mild steel . A flap door is provided at its bottom.  Well cap:After water filling, a truss system consisting of three trusses supported in well steining and cribs welded with it in criss-cross manner are used for top plugging. This system is covered with strong plywood and sealed with concrete slurry so that nothing can enter inside the well. Hence preparing it for the casting of well cap.
  • 26. Methods to promote sinking  Kentledge -Total of 125 concrete cubes of 1m3 in size are made for kentledge loading which is approximately equal to 25t × 125.  Chiseling- When the boulders are very firmly cemented then chiselling is done. In this soil is hit hard by sharp end chisel.  Dewatering- dewatering of dredge hole is done to reduce buyout force on well thus promoting sinking.  Flushing with jet of water on the outside face of well reducing skin friction
  • 27. Tilt and shift  Tilt and shift are deviation of well from its proposed position and orientation.  Max. tilt allowed is 1/80  Max. shift allowed is 150mm Measures to avoid tilt and shift  The outer surface of steining and curb should be kept as smooth as possible.  The radius of well curb should be kept more than the steining.  The dredging should be done on all sides of well uniformly. Causes  Eccentric dredging  Can be caused due to boulder under one side
  • 28. Method of checking tilt and shift  Tilt and shift are calculated with the help of a level and total station. Method  Difference between height of points (1& 3)= R.L.(1)-R.L.(3)  Tilt = [ R.L.(1)-R.L.(3)]/diameter  Shift at bottom from top position = tilt/ length  Note : this process is repeated on sides (2 & 4) and in similar manner tilt is obtained and then combined tilt and shift is reported.  Shift of well at top is measured by total station.
  • 29. Correcting tilt and shift  Regulation of Grabbing  Eccentric Loading  Strutting The well  Water jetting or Digging Pit outside the higher side of well  Pulling the well or caisson  Excavation on the higher side outside the well
  • 30. Problems  Sand blowing- This problem occurs when well bottom rests on sandy strata and dewatering is done below water table. In this sand from ground gushes into the well and there is sudden sinking of well. This sudden sinking is very dangerous and is very difficult to rectify.  Bridge scour -is the removal of sediment from bed such as sand and rocks from around bridge, abutments or piers. Scour, caused by swiftly moving water, can scoop out scour holes, compromising the integrity of a structure.  Sand heaving-When a well passes through soft strata over a considerable depth, the upward resistance acting on the outside surface of the well is less than the weight of the well. In that situation the well sinks down and quite often a heap is formed inside the dredge hole.
  • 31. Problems Bridge scour Sand heaving