SlideShare a Scribd company logo
Cast-in-situ Bored Pile
by
Dayanand Wandre
B.E.Civil, PGDCM-Nicmar,MBA-Finance*
Discover Engineering
Introduction
• Pile foundations consist of piles that are dug into soil till a layer of
stable soil is reached.
• Pile foundations transfer building load to the bearing ground with
the greater bearing capacity.
• Pile foundations are useful in regions with unstable upper soil that
may erode, or for large structures.
Displacement Pile (A/D)
Advantage Disadvantages
Pile material can be inspected for
quality before driving
May break during driving
Construction operation affect by
ground water
Noise and vibration problems
Can driven in very long lengths Cannot be driven in condition of low
headroom
Construction operation not affected by
ground water
Noise may prove unacceptable. Noise
permit may be required
Soil disposal is not necessary Vibration may prove unacceptable due
to presence of sensitive structures,
utility installation or machinery
Content
Bored Pile Procedure :
1. Set up the Location of Bored Pile
2. Insert Casing
3. Drilling
4. Removing Slime/muck
5. Flushing –Testing Specific Gravity /Viscosity
6. Insert of Steel Cage
7. Insert Tremmie Pipe
8. Pouring the Concrete
9. Removing Casing
Cycle Time of a Bored Pile
Types of Pile
• The pile installation procedure varies considerably, and has an
important influence on the subsequent response
• Three categories of piles are classified by method of
installation as below:
• Large displacement piles
• They encompass all solid driven piles including precast concrete piles, steel
or concrete tubes closed at the lower end
• Small displacement piles
• They include rolled steel sections such as H-pile and open-end tubular piles
• Replacement piles
• They are formed by machine boring, grabbing or hand-digging.
Pile Materilas
Precast pile
Location based piling
Deep foundation
End Bearing Piles
ROCK
SOFT SOILPILES
End bearing pile rests on a relative firm
soil . The load of the structure is
transmitted through the pile into this firm
soil or rock because the base of the pile
bears the load of the structure, this type
of pile is called end bearing pile
Most of the piles used in
Hong Kong are end
bearing piles. This is
because the majority of
new developments are
on reclaimed land
SOFT SOILPILES
Friction Piles
If the firm soil is at a considerable depth,
it may be very expensive to use end
bearing piles. In such situations, the
piles are driven through the penetrable
soil for some distance. The piles
transmit the load of structure to the
penetrable soil by means of skin friction
between the soil.
W
Qu
Qb
Qs
Qu = Qs + Qb - W
Basic Concept
The ultimate bearing capacity (Qu )of a pile may
be assessed using soil mechanics principles. The
capacity is assumed to be the sum of skin friction
and end-bearing resistance, i.e
Qu =Qb+Qs-W ……………………….(1)
where
Qu total pile resistance,
Qb is the end bearing resistance and
Qs is side friction resistance
General behaviour
Shaft resistance fully mobilized at small pile
movement (<0.01D)
Base resistance mobilized at large movement
(0.1D)
Loading
Settlement
Behaviour of Frictional Pile
Loading
Settlement
Behaviour of End Bearing Pile
Qu
QS
QB
Qu
QB
QS
• Piles founded on strong stratum
• Not much benefit in enhancing base
resistance
• Important to adopt good construction
practice to enhance shaft friction
• Shaft grouting useful in enhancing pile
capacity
 Piles founded on dense soils
 Important to adopt good construction
practice to enhance shaft friction and
base resistance
 Shaft and base grouting useful in
enhancing pile capacity
BoredPileProcedure
1. Set up the location of Bored Pile
BoredPileProcedure
We use Total Station instrument to survey each
pile point.
BoredPileProcedure
2. Insert casing
 casing must be stand vertical
( by checking verticality of casing when
insert casing )
Bored Pile Procedure
 use Vibrodriver or Vibrohamer to insert casing
Bored Pile Procedure
3. Drilling
 Drilling Machine :
weight :
130tons
BG - 40 drilling depth : 49m
diameter : 3m
weight : 96tons
BG - 28 drilling depth : 39m
diameter : 2.5m
weight : 91tons
SD - 515 drilling depth : 36m
diameter : 2.5m
BG - 40
BG - 28
SD - 515
Bored Pile Procedure
4. Removing slime
when finish drilling , we use Mechanical pump
equipment to remove slime .
Bored Pile Procedure
6. Insert of steel cage
Bored Pile Procedure
7. Insert Tremie
Bored Pile Procedure
Type of tremie pipe :
we have 3 types of tremie : 1m, 2m and 3m Length
3mLength
1mLength
2mLength
Bored Pile Procedure
How to insert tremie pipe :
1. Use mobile crane to hang the hopper
2. Then connect each tremie pipe
3. After that put it into the bored pile hole
until bottom
When we pour concrete, we have to bury
the tremie pipe into concrete as below :
Diameter of Bored
Pile
Buried Length of
Tremie
Ø1000 3 to 3.5m
Ø1800 2 to 2.5m
Bored Pile Procedure
8. Pouring the concrete
Quality of Concrete :
 Max. size of Aggregate : 2.5cm
 Workability : 55cm ( Flow )
Bored Pile Procedure
9. Remove casing
CycleTime of a Bored Pile
Step of Bored Pile
Cycle time of each step
( hour)
1. Set up location of Bored Pile 0.3
2. Inserting Casing 2
3. Drilling 8
4. Removing slime/Muck 1
5. Test(Flushing) 1
6. Inserting Steel Cage 2
7. Inserting Tremie Pipe 1
8. Pouring the concrete 2
9. Remove casing 1.5
Total Cycle Time 18.8
Thanks for kind attention

More Related Content

What's hot

Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
Safdar Ali
 
construction procedure of DMC piling
construction procedure of DMC pilingconstruction procedure of DMC piling
construction procedure of DMC piling
Nikhil Kumar
 
Steel arches and cerchar test
Steel arches and cerchar testSteel arches and cerchar test
Steel arches and cerchar test
Simon Madiro
 
compaction equipment
compaction equipmentcompaction equipment
compaction equipment
shailesh chauhan
 
Types Of Roller Used For Construction
Types Of Roller Used For Construction Types Of Roller Used For Construction
Types Of Roller Used For Construction
Er Vivek Sampat
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
Er.Sunil Wasade
 
Pilework
PileworkPilework
Pilework
Rajiva Gupta
 
John Zeni - Developments in mine shafts
John Zeni - Developments in mine shaftsJohn Zeni - Developments in mine shafts
John Zeni - Developments in mine shafts
NSW Environment and Planning
 
Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pile
Rizwan Khurram
 
Deep Foundations
Deep FoundationsDeep Foundations
Deep Foundations
Sri Ram Srinivas Dudala
 
Underground mine
Underground mineUnderground mine
Underground mine
Saurabh Jain
 
Pile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying CapacityPile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying Capacity
SHAZEBALIKHAN1
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
kamariya keyur
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Dr. Malek Smadi
 
Types of excavating tools and machine
Types of excavating tools and machineTypes of excavating tools and machine
Types of excavating tools and machine
Practicing In Some Infra Company
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
Safdar Ali
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipment
swetha110
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
Sharmeesh Arvind
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
Safdar Ali
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
SATYANARAYANA I
 

What's hot (20)

Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
 
construction procedure of DMC piling
construction procedure of DMC pilingconstruction procedure of DMC piling
construction procedure of DMC piling
 
Steel arches and cerchar test
Steel arches and cerchar testSteel arches and cerchar test
Steel arches and cerchar test
 
compaction equipment
compaction equipmentcompaction equipment
compaction equipment
 
Types Of Roller Used For Construction
Types Of Roller Used For Construction Types Of Roller Used For Construction
Types Of Roller Used For Construction
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Pilework
PileworkPilework
Pilework
 
John Zeni - Developments in mine shafts
John Zeni - Developments in mine shaftsJohn Zeni - Developments in mine shafts
John Zeni - Developments in mine shafts
 
Problem in bored pile
Problem in bored pileProblem in bored pile
Problem in bored pile
 
Deep Foundations
Deep FoundationsDeep Foundations
Deep Foundations
 
Underground mine
Underground mineUnderground mine
Underground mine
 
Pile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying CapacityPile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying Capacity
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
 
Types of excavating tools and machine
Types of excavating tools and machineTypes of excavating tools and machine
Types of excavating tools and machine
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipment
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
 

Similar to 2.pile foundation 2.ppt

Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
Daphne Tan
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatra
SUNIL KUMAR MOHAPATRA
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
bryankalindo888
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
Subham Kundu
 
Pilefoundation
PilefoundationPilefoundation
Pilefoundation
Arpan Patel
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Shivam Gandhi
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
avibose4
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
Riya Trivedi
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
PRASANTHI PETLURU
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Fatihoktr
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
LovelyLavakumarLK
 
any
anyany
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
vietcgxd
 
Pile Foundations v1.00 Oct2010.pdf
Pile Foundations v1.00 Oct2010.pdfPile Foundations v1.00 Oct2010.pdf
Pile Foundations v1.00 Oct2010.pdf
MehdiEbadi10
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
avibose4
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
LaxmiNarayanGurung
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
ssuser4ec34c1
 
POWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.pptPOWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.ppt
MdDiluarHossain1
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
Gaurang Kakadiya
 

Similar to 2.pile foundation 2.ppt (20)

Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatra
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
Pilefoundation
PilefoundationPilefoundation
Pilefoundation
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
any
anyany
any
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Pile Foundations v1.00 Oct2010.pdf
Pile Foundations v1.00 Oct2010.pdfPile Foundations v1.00 Oct2010.pdf
Pile Foundations v1.00 Oct2010.pdf
 
deep foundation.ppt
deep foundation.pptdeep foundation.ppt
deep foundation.ppt
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
POWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.pptPOWER POINT PRESENTATION ON pile_foundation_1.ppt
POWER POINT PRESENTATION ON pile_foundation_1.ppt
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 

Recently uploaded

Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
PIMR BHOPAL
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
Yasser Mahgoub
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 

Recently uploaded (20)

Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 08 Doors and Windows.pdf
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 

2.pile foundation 2.ppt

  • 1. Cast-in-situ Bored Pile by Dayanand Wandre B.E.Civil, PGDCM-Nicmar,MBA-Finance* Discover Engineering
  • 2. Introduction • Pile foundations consist of piles that are dug into soil till a layer of stable soil is reached. • Pile foundations transfer building load to the bearing ground with the greater bearing capacity. • Pile foundations are useful in regions with unstable upper soil that may erode, or for large structures.
  • 3. Displacement Pile (A/D) Advantage Disadvantages Pile material can be inspected for quality before driving May break during driving Construction operation affect by ground water Noise and vibration problems Can driven in very long lengths Cannot be driven in condition of low headroom Construction operation not affected by ground water Noise may prove unacceptable. Noise permit may be required Soil disposal is not necessary Vibration may prove unacceptable due to presence of sensitive structures, utility installation or machinery
  • 4. Content Bored Pile Procedure : 1. Set up the Location of Bored Pile 2. Insert Casing 3. Drilling 4. Removing Slime/muck 5. Flushing –Testing Specific Gravity /Viscosity 6. Insert of Steel Cage 7. Insert Tremmie Pipe 8. Pouring the Concrete 9. Removing Casing Cycle Time of a Bored Pile
  • 5. Types of Pile • The pile installation procedure varies considerably, and has an important influence on the subsequent response • Three categories of piles are classified by method of installation as below: • Large displacement piles • They encompass all solid driven piles including precast concrete piles, steel or concrete tubes closed at the lower end • Small displacement piles • They include rolled steel sections such as H-pile and open-end tubular piles • Replacement piles • They are formed by machine boring, grabbing or hand-digging.
  • 10. End Bearing Piles ROCK SOFT SOILPILES End bearing pile rests on a relative firm soil . The load of the structure is transmitted through the pile into this firm soil or rock because the base of the pile bears the load of the structure, this type of pile is called end bearing pile Most of the piles used in Hong Kong are end bearing piles. This is because the majority of new developments are on reclaimed land
  • 11. SOFT SOILPILES Friction Piles If the firm soil is at a considerable depth, it may be very expensive to use end bearing piles. In such situations, the piles are driven through the penetrable soil for some distance. The piles transmit the load of structure to the penetrable soil by means of skin friction between the soil.
  • 12. W Qu Qb Qs Qu = Qs + Qb - W Basic Concept The ultimate bearing capacity (Qu )of a pile may be assessed using soil mechanics principles. The capacity is assumed to be the sum of skin friction and end-bearing resistance, i.e Qu =Qb+Qs-W ……………………….(1) where Qu total pile resistance, Qb is the end bearing resistance and Qs is side friction resistance General behaviour Shaft resistance fully mobilized at small pile movement (<0.01D) Base resistance mobilized at large movement (0.1D)
  • 13. Loading Settlement Behaviour of Frictional Pile Loading Settlement Behaviour of End Bearing Pile Qu QS QB Qu QB QS • Piles founded on strong stratum • Not much benefit in enhancing base resistance • Important to adopt good construction practice to enhance shaft friction • Shaft grouting useful in enhancing pile capacity  Piles founded on dense soils  Important to adopt good construction practice to enhance shaft friction and base resistance  Shaft and base grouting useful in enhancing pile capacity
  • 14. BoredPileProcedure 1. Set up the location of Bored Pile
  • 15. BoredPileProcedure We use Total Station instrument to survey each pile point.
  • 16. BoredPileProcedure 2. Insert casing  casing must be stand vertical ( by checking verticality of casing when insert casing )
  • 17. Bored Pile Procedure  use Vibrodriver or Vibrohamer to insert casing
  • 18. Bored Pile Procedure 3. Drilling  Drilling Machine : weight : 130tons BG - 40 drilling depth : 49m diameter : 3m weight : 96tons BG - 28 drilling depth : 39m diameter : 2.5m weight : 91tons SD - 515 drilling depth : 36m diameter : 2.5m BG - 40 BG - 28 SD - 515
  • 19. Bored Pile Procedure 4. Removing slime when finish drilling , we use Mechanical pump equipment to remove slime .
  • 20. Bored Pile Procedure 6. Insert of steel cage
  • 21. Bored Pile Procedure 7. Insert Tremie
  • 22. Bored Pile Procedure Type of tremie pipe : we have 3 types of tremie : 1m, 2m and 3m Length 3mLength 1mLength 2mLength
  • 23. Bored Pile Procedure How to insert tremie pipe : 1. Use mobile crane to hang the hopper 2. Then connect each tremie pipe 3. After that put it into the bored pile hole until bottom When we pour concrete, we have to bury the tremie pipe into concrete as below : Diameter of Bored Pile Buried Length of Tremie Ø1000 3 to 3.5m Ø1800 2 to 2.5m
  • 24. Bored Pile Procedure 8. Pouring the concrete Quality of Concrete :  Max. size of Aggregate : 2.5cm  Workability : 55cm ( Flow )
  • 25. Bored Pile Procedure 9. Remove casing
  • 26. CycleTime of a Bored Pile Step of Bored Pile Cycle time of each step ( hour) 1. Set up location of Bored Pile 0.3 2. Inserting Casing 2 3. Drilling 8 4. Removing slime/Muck 1 5. Test(Flushing) 1 6. Inserting Steel Cage 2 7. Inserting Tremie Pipe 1 8. Pouring the concrete 2 9. Remove casing 1.5 Total Cycle Time 18.8
  • 27.
  • 28.
  • 29.
  • 30. Thanks for kind attention