SlideShare a Scribd company logo
1 of 18
Narration, slides and
graphics by:
J. Banzon
What is a project?

Project, as defined in the PMBOK
Guide, is a “temporary endeavor
undertaken to create a unique product,
service or result.”

All projects vary in complexity but they
all follow similar life cycles

All projects have deliverables (meaning
they always produce something)

Project examples:
− New product development
− Building renovation
− Wedding
− Dinner party
What is a project life cycle?

Project life cycle is a series of phases of a project from initiation
to completion.

The life cycle gives a practical approach to problem solving
applied to all aspects of a project.

Phases in a project life cycle encompasses sequential and
overlapping phases.

A project life cycle typically has 4 major phases:
− Initiation Phase
− Planning Phase
− Implementation/ Execution Phase
− Closure Phase
Project life cycle phases
Initiation Phase
The project need is
identified in the initiation
phase. It signals the start
of a project.
Planning phase
This phase is where the project
solution is further explored and
the steps necessary to achieve
their goals.
Closure phase
This phase is the final
closing of all project
processes and handing
over deliverables to the
customer.
Implementation phase
The project plan is put
into action. This phase
is when people are
carrying out the tasks of
their plan.
Initiation phase

The first phase explores the project concept.

Scope is defined during this phase.

Feasibility studies are made in order to identify if there
is a business need and justification to pursue the
project. Project charter is developed for approval.

This is the phase that the project team is assembled
and the project manager is identified.
Planning phase

This phase further details the scope of the project.

Tasks and resources are identified and assigned during
this phase

Project manager coordinates the preparation of the
schedule and project budget

Risks are identified ahead to anticipate any project threats

Quality plan is developed to maintain proper standards
throughout project

Communications plan is created in order to ensure
everyone is constantly informed of project status
Implementation phase

This phase is where the work outlined in the project
plan is performed.

This phase consumes the most resources and
energy.

Constant and close monitoring of the work should be
done to ensure efficiency of the project execution.

Status reports are important for all stakeholders
involved.

Deliverables are measured against the set metrics to
ensure quality is acceptable
Closure phase

This is the last phase of the project life cycle and
involves handing over final deliverable to the
customer.

Contracts are properly terminated for equipment,
vendors and staff.

All stakeholders are to be informed of project
closure.

This phase is when the team reviews the overall
project and identify lessons learned for future
projects.
Processes

Processes are the tasks and methodologies
that occur within a phase.

Although they sound like phases, processes
are not phases.

The PMBOK arrange processes into groups
according to when they typically occur in a
project.

However, different processes can occur any
time during a project phase
Processes

This graphic is a representation of when these
processes typically occur over the project life
cycle
Processes
Initiating process group

Typically occurring during the
initiation phase of a project.

These process groups define
the new project or phase
objectives and what is needed
to achieve it.

Involves obtaining
authorization for the project or
phase.

Process group main output is
the project charter and
stakeholder register.
Initiation processes:
4.1 Develop Project Charter
13.1 Identify Stakeholders
From PMBOK, 5th
edition
Planning process group

Typically occurring during the
planning phase of a project.

Planning process group does not
just apply to the planning phase.
Planning is an activity that continues
to almost the end of a project, as
projects tend to change as it
progresses.

A skilled project manager knows
how much time and effort to put into
each stage of planning as the project
changes
Planning processes:
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Duration
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management
From PMBOK, 5th
edition
Executing process group

Typically occurring during the
implementation/execution
phase of a project.

This process group involves a
lot of management tasks and
coordination with staff while the
project plan is being executed.

The outputs produced during
this process group is the actual
project deliverable.
Execution processes:
4.3 Direct and Manage Project Work
8.2 Perform Quality Assurance
9.2 Acquire Project Team
9.3 Develop Project Team
9.4 Manage Project Team
10.2 Manage Communications
12.2 Conduct Procurements
13.3 Manage Stakeholder Engagement
From PMBOK, 5th
edition
Closing process group

Typically occurring during
the closure phase of a
project.

Formal transfer of
deliverable to customer

Administrative closure and
contract closure is
performed to formally close
out project.
Closing processes:
4.6 Close Project or Phase
12.4 Close Procurements
From PMBOK, 5th
edition
Monitoring and controlling
process group

This process group occurs on
all phases of the project life
cycle.

Ensures that the project is on
track and flags issues to
maintain project course
direction.

Collects performance data
through constant reports from
team such as status reports
and team meetings.
Monitoring and Controlling processes:
4.4 Monitor and Control Project Work
4.5 Perform Integrated Change Control
5.5 Validate Scope
5.6 Control Scope
6.7 Control Schedule
7.4 Control Costs
8.3 Control Quality
10.3 Control Communications
11.6 Control Risks
12.3 Control Procurements
13.4 Control Stakeholder Engagement
From PMBOK, 5th
edition
Final thoughts

While the PMBOK and PMI gives an outline of a
typical project, no two projects are the same.

A good project manager knows how to choose which
processes are needed for their project.

Practicality and pragmatism is the best approach to
any project. (keep it simple)
References

https://opentextbc.ca/projectmanagement/chapter/chapter-3-the-project-life-cycle-phases-p

http://www.method123.com/project-lifecycle.php

http://www.free-management-ebooks.com/faqpm/processes-01.htm

Duncan, William ( 1996 ). AGuide to the Pro je ct Manag e m e nt Bo dy o f
Kno wle dg e . Newtown Square, Pennsylvania: PMI Publishing Division.

More Related Content

What's hot

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in DetailNIILM University Online
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Managerkanti choudhary
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager ProofHub
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycleMegha BHardwaj
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Project life cycle
Project life cycleProject life cycle
Project life cycleAbhishek Raj
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 

What's hot (20)

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in Detail
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Manager
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Roles of project managers in oe
Roles of project managers in oeRoles of project managers in oe
Roles of project managers in oe
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project planning
Project planning Project planning
Project planning
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Project selection
Project selection Project selection
Project selection
 

Viewers also liked

札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」
札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」
札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」Yusuke Suzuki
 
Reflection a pwr.pt
Reflection a pwr.ptReflection a pwr.pt
Reflection a pwr.ptpat21donv
 
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント Yoichi Tamamaki
 
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824masashi takehara
 
初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門尚 鈴木
 
Schoo web campus「相手に伝わる」文章を書く技術 3限目
 Schoo web campus「相手に伝わる」文章を書く技術 3限目 Schoo web campus「相手に伝わる」文章を書く技術 3限目
Schoo web campus「相手に伝わる」文章を書く技術 3限目schoowebcampus
 
新人プロジェクトリーダーが抑えるべき勘所
新人プロジェクトリーダーが抑えるべき勘所新人プロジェクトリーダーが抑えるべき勘所
新人プロジェクトリーダーが抑えるべき勘所schoowebcampus
 
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳schoowebcampus
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
PJマネジメント初級
PJマネジメント初級PJマネジメント初級
PJマネジメント初級Masaru Kimura
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Executionpajames36
 

Viewers also liked (17)

札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」
札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」
札幌Javaカンファレンス2012 C3「顧客とPMとPGの話は、なぜ噛み合わないのか」
 
Reflection a pwr.pt
Reflection a pwr.ptReflection a pwr.pt
Reflection a pwr.pt
 
Designing Culture at #LeanUXja
Designing Culture at #LeanUXjaDesigning Culture at #LeanUXja
Designing Culture at #LeanUXja
 
Lean UX Workshop at Movida Japan #3
Lean UX Workshop at Movida Japan #3Lean UX Workshop at Movida Japan #3
Lean UX Workshop at Movida Japan #3
 
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント
リーン思考に学ぶ失敗で終わらせないプロジェクトマネージメント
 
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824
[Slide] プロジェクトマネジメント勉強会(PMBOK概要)20100824
 
初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門
 
Schoo web campus「相手に伝わる」文章を書く技術 3限目
 Schoo web campus「相手に伝わる」文章を書く技術 3限目 Schoo web campus「相手に伝わる」文章を書く技術 3限目
Schoo web campus「相手に伝わる」文章を書く技術 3限目
 
新人プロジェクトリーダーが抑えるべき勘所
新人プロジェクトリーダーが抑えるべき勘所新人プロジェクトリーダーが抑えるべき勘所
新人プロジェクトリーダーが抑えるべき勘所
 
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳
プロジェクトリーダーになったら学ぶべき、プロジェクト・マネジメント入門 先生:芝本 秀徳
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
PJマネジメント初級
PJマネジメント初級PJマネジメント初級
PJマネジメント初級
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Execution
 
Project management
Project managementProject management
Project management
 

Similar to Project life cycle

Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOswebuploader
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Simplilearn
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approachMurali Venkatesh
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Project Delivery Lifecycle
Project Delivery LifecycleProject Delivery Lifecycle
Project Delivery LifecycleMousumi Borah
 
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptxharisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptxFaizanGul6
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfLe Duong
 
Project Audit and Closure.pptx
Project Audit and Closure.pptxProject Audit and Closure.pptx
Project Audit and Closure.pptxSerkinBaleros
 
PA-210-G1-Participatory Project Development Management.pdf
 PA-210-G1-Participatory Project Development Management.pdf PA-210-G1-Participatory Project Development Management.pdf
PA-210-G1-Participatory Project Development Management.pdfMarivicPenarubia1
 

Similar to Project life cycle (20)

Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Project lifecycle in IT industry
Project lifecycle in IT industryProject lifecycle in IT industry
Project lifecycle in IT industry
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOs
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Project lifecycle
Project lifecycleProject lifecycle
Project lifecycle
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
Project Delivery Lifecycle
Project Delivery LifecycleProject Delivery Lifecycle
Project Delivery Lifecycle
 
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptxharisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
harisjaswal_1132_17052_1_Lecture 03 - 06th March2021.pptx
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdf
 
Project Audit and Closure.pptx
Project Audit and Closure.pptxProject Audit and Closure.pptx
Project Audit and Closure.pptx
 
PA-210-G1-Participatory Project Development Management.pdf
 PA-210-G1-Participatory Project Development Management.pdf PA-210-G1-Participatory Project Development Management.pdf
PA-210-G1-Participatory Project Development Management.pdf
 

Recently uploaded

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxSocio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxtrishalcan8
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docxRodelinaLaud
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 

Recently uploaded (20)

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxSocio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docx
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 

Project life cycle

  • 2. What is a project?  Project, as defined in the PMBOK Guide, is a “temporary endeavor undertaken to create a unique product, service or result.”  All projects vary in complexity but they all follow similar life cycles  All projects have deliverables (meaning they always produce something)  Project examples: − New product development − Building renovation − Wedding − Dinner party
  • 3. What is a project life cycle?  Project life cycle is a series of phases of a project from initiation to completion.  The life cycle gives a practical approach to problem solving applied to all aspects of a project.  Phases in a project life cycle encompasses sequential and overlapping phases.  A project life cycle typically has 4 major phases: − Initiation Phase − Planning Phase − Implementation/ Execution Phase − Closure Phase
  • 4. Project life cycle phases Initiation Phase The project need is identified in the initiation phase. It signals the start of a project. Planning phase This phase is where the project solution is further explored and the steps necessary to achieve their goals. Closure phase This phase is the final closing of all project processes and handing over deliverables to the customer. Implementation phase The project plan is put into action. This phase is when people are carrying out the tasks of their plan.
  • 5. Initiation phase  The first phase explores the project concept.  Scope is defined during this phase.  Feasibility studies are made in order to identify if there is a business need and justification to pursue the project. Project charter is developed for approval.  This is the phase that the project team is assembled and the project manager is identified.
  • 6. Planning phase  This phase further details the scope of the project.  Tasks and resources are identified and assigned during this phase  Project manager coordinates the preparation of the schedule and project budget  Risks are identified ahead to anticipate any project threats  Quality plan is developed to maintain proper standards throughout project  Communications plan is created in order to ensure everyone is constantly informed of project status
  • 7. Implementation phase  This phase is where the work outlined in the project plan is performed.  This phase consumes the most resources and energy.  Constant and close monitoring of the work should be done to ensure efficiency of the project execution.  Status reports are important for all stakeholders involved.  Deliverables are measured against the set metrics to ensure quality is acceptable
  • 8. Closure phase  This is the last phase of the project life cycle and involves handing over final deliverable to the customer.  Contracts are properly terminated for equipment, vendors and staff.  All stakeholders are to be informed of project closure.  This phase is when the team reviews the overall project and identify lessons learned for future projects.
  • 9. Processes  Processes are the tasks and methodologies that occur within a phase.  Although they sound like phases, processes are not phases.
  • 10.  The PMBOK arrange processes into groups according to when they typically occur in a project.  However, different processes can occur any time during a project phase Processes
  • 11.  This graphic is a representation of when these processes typically occur over the project life cycle Processes
  • 12. Initiating process group  Typically occurring during the initiation phase of a project.  These process groups define the new project or phase objectives and what is needed to achieve it.  Involves obtaining authorization for the project or phase.  Process group main output is the project charter and stakeholder register. Initiation processes: 4.1 Develop Project Charter 13.1 Identify Stakeholders From PMBOK, 5th edition
  • 13. Planning process group  Typically occurring during the planning phase of a project.  Planning process group does not just apply to the planning phase. Planning is an activity that continues to almost the end of a project, as projects tend to change as it progresses.  A skilled project manager knows how much time and effort to put into each stage of planning as the project changes Planning processes: 4.2 Develop Project Management Plan 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Duration 6.6 Develop Schedule 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 8.1 Plan Quality Management 9.1 Plan Human Resource Management 10.1 Plan Communications Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 12.1 Plan Procurement Management 13.2 Plan Stakeholder Management From PMBOK, 5th edition
  • 14. Executing process group  Typically occurring during the implementation/execution phase of a project.  This process group involves a lot of management tasks and coordination with staff while the project plan is being executed.  The outputs produced during this process group is the actual project deliverable. Execution processes: 4.3 Direct and Manage Project Work 8.2 Perform Quality Assurance 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.2 Manage Communications 12.2 Conduct Procurements 13.3 Manage Stakeholder Engagement From PMBOK, 5th edition
  • 15. Closing process group  Typically occurring during the closure phase of a project.  Formal transfer of deliverable to customer  Administrative closure and contract closure is performed to formally close out project. Closing processes: 4.6 Close Project or Phase 12.4 Close Procurements From PMBOK, 5th edition
  • 16. Monitoring and controlling process group  This process group occurs on all phases of the project life cycle.  Ensures that the project is on track and flags issues to maintain project course direction.  Collects performance data through constant reports from team such as status reports and team meetings. Monitoring and Controlling processes: 4.4 Monitor and Control Project Work 4.5 Perform Integrated Change Control 5.5 Validate Scope 5.6 Control Scope 6.7 Control Schedule 7.4 Control Costs 8.3 Control Quality 10.3 Control Communications 11.6 Control Risks 12.3 Control Procurements 13.4 Control Stakeholder Engagement From PMBOK, 5th edition
  • 17. Final thoughts  While the PMBOK and PMI gives an outline of a typical project, no two projects are the same.  A good project manager knows how to choose which processes are needed for their project.  Practicality and pragmatism is the best approach to any project. (keep it simple)