SlideShare a Scribd company logo
Department of Metallurgical Engineering
Gandhi Institute of Engineering and Technology, Gunupur
BIKASH RANJAN PRADHAN
11MET018
By
 Introduction
 Classification
 Equipments
 Materials required
 Process
 Defects
 Modern developments
 Advantages
 Disadvantages
 Earlier 1950s steel was poured into stationary
moulds to form ‘ingots’ since then “continuous
casting” has evolved to achieve improved yield,
quality, productivity & cost efficiency
 Continuous casting may be defined as teeming of
liquid metal in short mould with a false bottom
through which partially solidified ingot
(billet ,bloom or slab) is continuously withdrawn at
the same rate at which metal is poured in the mould.
 Which are subsequently rolled to get finished
products.
 Three main types of machines are in use in practice
namely
 Vertical mould
 Vertical mould with bending
 Curved mould or S-type
 This type of mould is very
tall and hence needs either a
tall shop or a large pit to
accommodate the equipments.
The problem is acute if high
casting speed are employed
& consequence longer cooling
zone is required.
 Used for large and medium sections
 It is easy to repair and restart the machine.
 It is a modification over the vertical design to reduce
the overall height of the machine.
 The roller apron and pinch rolls are similar to those
in vertical machine.
 After the product emerges from the pinch rolls it is
bent to obtain the discharge horizontal.
 A horizontal set of straightening rolls becomes
necessary.
 Heavy sections being difficult to bend .
 30% height is saved by this design.
 This is the latest design now almost universally
adopted for continuous casting of almost all sections
like billets, blooms and slabs.
 Characteristics-
 The mould is itself curved mould.
 The strands comes out of the mould in curvilinear
fashion with a fixed radius.
 It is bent before entire cross-section is solidified.
 The curved strand is in fact straightened after it is
fully solidified.
Curved mould(s-type)
 Ladle
 Tundish
 Mould
 Dummy bar
 Roller apron
 Withdrawal rolls
 Bending and straightening rolls
 Cooling sprays
 Cutting devices
 Auxiliary electrical and/or mechanical gears to help
run the machine smoothly.
Ladle & turret-
Steel from EAF or BOF is tapped into a ladle and
taken to the continuous casting platform.
The ladle is raised into a turret that rotate the ladle
into the casting position above the tundish
 Tundish-
 Shroud
 Turbo blower
 Mono block Stopper rod
 SEN
It is a container which collects liquid steel from ladle
through shroud.
Here a turbo blower is fixed which converts the turbulant
flow of liquid steel to laminar flow.
Then by opening the stopper rod metal flows through the
submerged entry nozzle.
 Mould
It is made of copper, copper & silver(cu 99.95%) due to
its high thermal conductivity.
Nickel plate is used inside the mould to protect the
mould wall from eroding.
Mould of 220mm to 300mm thick and 2500mm wide
900mm height is used.
Now a days the mould width is decreased at any time
when required during casting.
4500 -5000 ltrs/min of water is flow through the mould.
Life of the mould is about 1000 heats.
 Dummy bar-
To begin with, the bottom of the mould is temporarily
Closed by what is known as dummy bar.
It lead the product through the roller apron and
withdrawal rolls.
The head of dummy bar is supposed to nearly close
the bottom of the mould and whatever gap is left is
packed with asbestos to obtain a temporarily fully
closed bottom of the mould.
 Withdrawal rolls-
These are one or two pairs of rolls meant to finally grip
the ingot and pull it out at a pre fixed rate without
deforming the product.
The pressure exerted by rolls on product should neither
be excessive to cause deformation nor less to allow
slip.
 Bending & straightening rolls-
 Single bending roller is used in vertical mould with
horizontal discharge machine.
 In s-type machine multi point bending rollers are
used.
 A straightening roller table is provided for straighten
the product.
 Cutting devices-
Torch cutter with 4 torches(two for normal cutting
& two for sample cutting in line)
Oxy-fuel cutter is used , where LPG or acetylene
are used as fuel.
 Liquid steel
 Asbestos
 Fluxes
 Chiller
 Steel rods
Tundish preparation Tundish and
sen preheating
Dummy bar
insertion
Mould setting
Dummy bar
sealing
Ladle & tundish
in casting position
Teeming
Start the machine Cutting
 To start a cast the mould bottom is sealed by a
steel dummy bar which is held in place
hydraulically by the straightener withdrawal units.
 The gap between the mould bottom and the
dummy bar head is filled by asbestos. After that
chiller & steel rods are provided for rapid
solidification of the steel and it stick to the dummy
bar head.
 The steel is partially solidified in mould and
producing a steel strand with a solid outer shell
and a liquid core.
 In this primary cooling area once the steel shell has a
sufficient thickness about 10-20mm, the straightener
withdrawal units are started and proceeds to
withdraw the partially solidified strand out of the
mould along with the dummy bar. Liquid steel
continues to pour into the mould to replenish the
withdrawn steel at an equal rate.
 The withdrawal rate depends on the cross-section,
grade, quality of steel being produced and may vary
from 30 cm to 100cm per minute.
 Casting time is typically 45 minutes to 90 minutes
per heat to avoid excessive ladle heat losses.
 Open exiting the mould the strands enters a roller
containment section and secondary cooling chamber
in which the solidifying strand is sprayed with water
to promote solidification. This area preserves cast
shape integrity and product quality.
 Once the strand is fully solidified and has passed
through the straightener withdrawal units the
dummy bar is disconnected. Following the
straightener the strand is cut into individual pieces of
the following as-cast products: slabs, blooms, billets,
rounds or beam blanks depending on machine
design.
 Mould stroke in the range of 5-10 mm.
 Frequency of stroke , which is 150-200/min
 Casting speed normally in the range of
2m/min
 Negative strip time .1-.2 sec
 Total cycle time of the order of .3-.4 sec
 Positive strip time .15-.3% of cycle time
 Powder consumption in the range of .17-
.40kg/m2 of strand area.
 Break out
 Edge cracks
 Longitudinal cracks
 Primary scales
 Random surface defects arising due to fluctuations of
surfaces
 Variations in width
 Non-uniform thickness and flatness
 Non-uniform microstructure in either direction
 Segregation
 Slag particle sticking the surface- entrapment of lubricant
slag particle at the surface.
 Remote adjustable mould
 Air mist cooling
 Dynamic spray cooling
 BOPS
 AMLC
 Sprue, runner, riser etc. are not used. Hence ,
no waste metal this leads to casting yield.
 Process is automatic
 Product has good consistent soundness.
 Mechanical properties are very high and very
reproducible.
 Not suitable for small quantity production.
 Continuous and efficient cooling of mould is
required, else, centre line shrinkage develops.
 Requires large floor space.
 Continuous casting has evolved from a batch
process into a sophisticated continuous process.
This transformation has occurred through
understanding principle of mechanical design ,
heat transfer , steel metallurgical properties and
stress strain relationships, to produce a product
with excellent shape and quality.
 In recent year the process has been optimized
through careful integration of electro-mechanical
sensors, computer-controls, & planning to provide
a highly automated system designed for new
millenia.
Continious casting of steel

More Related Content

What's hot

Welding metallurgy
Welding metallurgyWelding metallurgy
Welding metallurgy
Kapil dev Pandey
 
Secondary steel making
Secondary steel making Secondary steel making
Secondary steel making
Abhishek Kumar
 
Steel making
Steel makingSteel making
Steel making
Sirish Satyavolu
 
Copper Mould
Copper MouldCopper Mould
Copper Mould
Cameron KL
 
Breakouts Problem during continuous casting of steel
Breakouts Problem during continuous casting of steelBreakouts Problem during continuous casting of steel
Breakouts Problem during continuous casting of steel
Sonal Kothari Runwal
 
Inclusion control for clean steel
Inclusion control for clean steelInclusion control for clean steel
Inclusion control for clean steelSANTOSH KUMAR
 
Iron making
Iron makingIron making
Iron makingguddu_92
 
Dual phase steels (1)
Dual phase steels (1)Dual phase steels (1)
Dual phase steels (1)
Payal Priyadarshini
 
Continuous casting.PPT
Continuous casting.PPTContinuous casting.PPT
Continuous casting.PPTthiru1mech
 
Hot Rolling And cold rolling process
Hot Rolling And cold rolling processHot Rolling And cold rolling process
Hot Rolling And cold rolling process
Dhyey Shukla
 
Ductile iron
Ductile ironDuctile iron
Ductile iron
NIAJ AHMED
 
Study of breakouts in thin slab caster
Study of breakouts in thin slab casterStudy of breakouts in thin slab caster
Study of breakouts in thin slab caster
Shubham Thakur
 
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
NED University of Engineering and Technology
 
Continuous casting
Continuous castingContinuous casting
Continuous casting
Saurabh Negi
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
temkin abdlkader
 
Heat affected zone
Heat affected zoneHeat affected zone
Heat affected zone
jay prakash
 

What's hot (20)

Welding metallurgy
Welding metallurgyWelding metallurgy
Welding metallurgy
 
Secondary steel making
Secondary steel making Secondary steel making
Secondary steel making
 
Steel Making Continuous casting I
Steel Making Continuous casting ISteel Making Continuous casting I
Steel Making Continuous casting I
 
Steel making
Steel makingSteel making
Steel making
 
Copper Mould
Copper MouldCopper Mould
Copper Mould
 
Breakouts Problem during continuous casting of steel
Breakouts Problem during continuous casting of steelBreakouts Problem during continuous casting of steel
Breakouts Problem during continuous casting of steel
 
Ainsm
AinsmAinsm
Ainsm
 
Inclusion control for clean steel
Inclusion control for clean steelInclusion control for clean steel
Inclusion control for clean steel
 
Iron making
Iron makingIron making
Iron making
 
Bos
BosBos
Bos
 
Dual phase steels (1)
Dual phase steels (1)Dual phase steels (1)
Dual phase steels (1)
 
Continuous casting.PPT
Continuous casting.PPTContinuous casting.PPT
Continuous casting.PPT
 
Hot Rolling And cold rolling process
Hot Rolling And cold rolling processHot Rolling And cold rolling process
Hot Rolling And cold rolling process
 
Ductile iron
Ductile ironDuctile iron
Ductile iron
 
Study of breakouts in thin slab caster
Study of breakouts in thin slab casterStudy of breakouts in thin slab caster
Study of breakouts in thin slab caster
 
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
Steel Making: Lecture 1 Introduction to the subject and review of Iron Making
 
Continuous casting
Continuous castingContinuous casting
Continuous casting
 
Heat treatment
Heat treatmentHeat treatment
Heat treatment
 
Heat affected zone
Heat affected zoneHeat affected zone
Heat affected zone
 
Steel Making: Ingot casting
Steel Making: Ingot casting Steel Making: Ingot casting
Steel Making: Ingot casting
 

Viewers also liked

Continuous Casting Steel
Continuous Casting SteelContinuous Casting Steel
Continuous Casting Steel
Er Soumyabrata Basak
 
Continuous Casting: Get more from your Caster
Continuous Casting: Get more from your CasterContinuous Casting: Get more from your Caster
Continuous Casting: Get more from your Caster
Rakesh Niranjan
 
Billet defects pinhole and blowhole formation, prevention and evolution
Billet defects   pinhole and blowhole formation, prevention and evolutionBillet defects   pinhole and blowhole formation, prevention and evolution
Billet defects pinhole and blowhole formation, prevention and evolution
Jorge Madias
 
BSP Project (Based on Continuous Casting) [Final]
BSP Project (Based on Continuous Casting) [Final]BSP Project (Based on Continuous Casting) [Final]
BSP Project (Based on Continuous Casting) [Final]Subham Shit
 
Casting
CastingCasting
Casting
Manoj Yadav
 
casting ppt
casting pptcasting ppt
casting ppt
Tayyab Warraich
 
Tundish & tundish car
Tundish & tundish carTundish & tundish car
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEEL
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEELEFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEEL
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEELSurya Teja Botu
 
Billet defects pinhole and blowhole formation prevention and evolution
Billet defects   pinhole and blowhole formation prevention and evolutionBillet defects   pinhole and blowhole formation prevention and evolution
Billet defects pinhole and blowhole formation prevention and evolution
Jorge Madias
 
End splitting during long products rolling billet quality of rolling process
End splitting during long products rolling   billet quality of rolling processEnd splitting during long products rolling   billet quality of rolling process
End splitting during long products rolling billet quality of rolling process
Jorge Madias
 
Steel melting shop (sms) - 2
Steel melting shop (sms) - 2Steel melting shop (sms) - 2
Steel melting shop (sms) - 2
NIT - ROURKELA
 
Casting and its types
Casting and its typesCasting and its types
Casting and its types
Waqas Ahmed
 
Reduced nonmetallic inclusions in steel using next generation disposable tund...
Reduced nonmetallic inclusions in steel using next generation disposable tund...Reduced nonmetallic inclusions in steel using next generation disposable tund...
Reduced nonmetallic inclusions in steel using next generation disposable tund...
Bill Porter
 
Introduction to Steelmaking 2012
Introduction to Steelmaking 2012Introduction to Steelmaking 2012
Introduction to steelmaking
Introduction to steelmakingIntroduction to steelmaking
Introduction to steelmaking
Pambudi Pajar Pratama
 
Iron & Steel sector
Iron & Steel sectorIron & Steel sector
Iron & Steel sector
dipesh_86
 
Full Mould Casting Process
Full Mould Casting ProcessFull Mould Casting Process
Full Mould Casting Process
pradeepkumarunnithan
 
A resposta dos metais aos desafios do projeto automotivo
A resposta dos metais aos desafios do projeto automotivoA resposta dos metais aos desafios do projeto automotivo
A resposta dos metais aos desafios do projeto automotivoAgencia G ABC
 
Copper continuous casting
Copper continuous castingCopper continuous casting
Copper continuous casting
Rautomead Limited
 

Viewers also liked (20)

Continuous Casting Steel
Continuous Casting SteelContinuous Casting Steel
Continuous Casting Steel
 
Continuous Casting: Get more from your Caster
Continuous Casting: Get more from your CasterContinuous Casting: Get more from your Caster
Continuous Casting: Get more from your Caster
 
Billet defects pinhole and blowhole formation, prevention and evolution
Billet defects   pinhole and blowhole formation, prevention and evolutionBillet defects   pinhole and blowhole formation, prevention and evolution
Billet defects pinhole and blowhole formation, prevention and evolution
 
BSP Project (Based on Continuous Casting) [Final]
BSP Project (Based on Continuous Casting) [Final]BSP Project (Based on Continuous Casting) [Final]
BSP Project (Based on Continuous Casting) [Final]
 
Casting
CastingCasting
Casting
 
casting ppt
casting pptcasting ppt
casting ppt
 
Tundish & tundish car
Tundish & tundish carTundish & tundish car
Tundish & tundish car
 
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEEL
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEELEFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEEL
EFFECT OF CASTING PARAMETERS ON MACROSTRUCTURE OF STEEL
 
Billet defects pinhole and blowhole formation prevention and evolution
Billet defects   pinhole and blowhole formation prevention and evolutionBillet defects   pinhole and blowhole formation prevention and evolution
Billet defects pinhole and blowhole formation prevention and evolution
 
End splitting during long products rolling billet quality of rolling process
End splitting during long products rolling   billet quality of rolling processEnd splitting during long products rolling   billet quality of rolling process
End splitting during long products rolling billet quality of rolling process
 
Steel melting shop (sms) - 2
Steel melting shop (sms) - 2Steel melting shop (sms) - 2
Steel melting shop (sms) - 2
 
Metal casting process
Metal casting processMetal casting process
Metal casting process
 
Casting and its types
Casting and its typesCasting and its types
Casting and its types
 
Reduced nonmetallic inclusions in steel using next generation disposable tund...
Reduced nonmetallic inclusions in steel using next generation disposable tund...Reduced nonmetallic inclusions in steel using next generation disposable tund...
Reduced nonmetallic inclusions in steel using next generation disposable tund...
 
Introduction to Steelmaking 2012
Introduction to Steelmaking 2012Introduction to Steelmaking 2012
Introduction to Steelmaking 2012
 
Introduction to steelmaking
Introduction to steelmakingIntroduction to steelmaking
Introduction to steelmaking
 
Iron & Steel sector
Iron & Steel sectorIron & Steel sector
Iron & Steel sector
 
Full Mould Casting Process
Full Mould Casting ProcessFull Mould Casting Process
Full Mould Casting Process
 
A resposta dos metais aos desafios do projeto automotivo
A resposta dos metais aos desafios do projeto automotivoA resposta dos metais aos desafios do projeto automotivo
A resposta dos metais aos desafios do projeto automotivo
 
Copper continuous casting
Copper continuous castingCopper continuous casting
Copper continuous casting
 

Similar to Continious casting of steel

Extrusion
ExtrusionExtrusion
Extrusion
Gulfam Hussain
 
UNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.pptUNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.ppt
Praveen Kumar
 
UNIT3-Special casting processcasting.ppt
UNIT3-Special casting processcasting.pptUNIT3-Special casting processcasting.ppt
UNIT3-Special casting processcasting.ppt
Praveen Kumar
 
UNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.pptUNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.ppt
Praveen Kumar
 
Extrusion and Drawing.ppt
Extrusion and Drawing.pptExtrusion and Drawing.ppt
Extrusion and Drawing.ppt
rmrm64
 
Conclave of rolling processs
Conclave of rolling processsConclave of rolling processs
Conclave of rolling processs
Hitesh Basitti
 
Forging document for mechanical engineering students
Forging document for mechanical engineering studentsForging document for mechanical engineering students
Forging document for mechanical engineering students
Martin939812
 
Module 3.pdf
Module 3.pdfModule 3.pdf
Module 3.pdf
gamadabegna
 
extrusion-amanufacturingprocess-140623001143-phpapp01.pdf
extrusion-amanufacturingprocess-140623001143-phpapp01.pdfextrusion-amanufacturingprocess-140623001143-phpapp01.pdf
extrusion-amanufacturingprocess-140623001143-phpapp01.pdf
ninjasquad
 
Rolling Process
Rolling ProcessRolling Process
Rolling Process
M Siva Kumar
 
Rolling slides
Rolling slidesRolling slides
Rolling slides
Ziad Salem
 
Unit iii METAL FORMING PROCESSES
Unit   iii METAL FORMING PROCESSESUnit   iii METAL FORMING PROCESSES
Unit iii METAL FORMING PROCESSES
SelvamV17
 
Extrusion
ExtrusionExtrusion
Extrusion
Deepam Goyal
 
Extrusion amanufacturingprocess-140623001143-phpapp01
Extrusion amanufacturingprocess-140623001143-phpapp01Extrusion amanufacturingprocess-140623001143-phpapp01
Extrusion amanufacturingprocess-140623001143-phpapp01
mohmedx
 
03 rolling of metals
03 rolling of metals03 rolling of metals
03 rolling of metals
Mahmoud Hassan
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
VAIBHAV SINGH
 
Metal Forming Processes
Metal Forming ProcessesMetal Forming Processes
Metal Forming Processes
Muthukumar V
 
Aluminium_Extrusion.pdf
Aluminium_Extrusion.pdfAluminium_Extrusion.pdf
Aluminium_Extrusion.pdf
GowthamS464425
 

Similar to Continious casting of steel (20)

Seminar-II
Seminar-IISeminar-II
Seminar-II
 
Extrusion
ExtrusionExtrusion
Extrusion
 
Rolling
RollingRolling
Rolling
 
UNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.pptUNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.ppt
 
UNIT3-Special casting processcasting.ppt
UNIT3-Special casting processcasting.pptUNIT3-Special casting processcasting.ppt
UNIT3-Special casting processcasting.ppt
 
UNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.pptUNIT3-Special casting processmechanica.ppt
UNIT3-Special casting processmechanica.ppt
 
Extrusion and Drawing.ppt
Extrusion and Drawing.pptExtrusion and Drawing.ppt
Extrusion and Drawing.ppt
 
Conclave of rolling processs
Conclave of rolling processsConclave of rolling processs
Conclave of rolling processs
 
Forging document for mechanical engineering students
Forging document for mechanical engineering studentsForging document for mechanical engineering students
Forging document for mechanical engineering students
 
Module 3.pdf
Module 3.pdfModule 3.pdf
Module 3.pdf
 
extrusion-amanufacturingprocess-140623001143-phpapp01.pdf
extrusion-amanufacturingprocess-140623001143-phpapp01.pdfextrusion-amanufacturingprocess-140623001143-phpapp01.pdf
extrusion-amanufacturingprocess-140623001143-phpapp01.pdf
 
Rolling Process
Rolling ProcessRolling Process
Rolling Process
 
Rolling slides
Rolling slidesRolling slides
Rolling slides
 
Unit iii METAL FORMING PROCESSES
Unit   iii METAL FORMING PROCESSESUnit   iii METAL FORMING PROCESSES
Unit iii METAL FORMING PROCESSES
 
Extrusion
ExtrusionExtrusion
Extrusion
 
Extrusion amanufacturingprocess-140623001143-phpapp01
Extrusion amanufacturingprocess-140623001143-phpapp01Extrusion amanufacturingprocess-140623001143-phpapp01
Extrusion amanufacturingprocess-140623001143-phpapp01
 
03 rolling of metals
03 rolling of metals03 rolling of metals
03 rolling of metals
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
 
Metal Forming Processes
Metal Forming ProcessesMetal Forming Processes
Metal Forming Processes
 
Aluminium_Extrusion.pdf
Aluminium_Extrusion.pdfAluminium_Extrusion.pdf
Aluminium_Extrusion.pdf
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 

Continious casting of steel

  • 1. Department of Metallurgical Engineering Gandhi Institute of Engineering and Technology, Gunupur BIKASH RANJAN PRADHAN 11MET018 By
  • 2.  Introduction  Classification  Equipments  Materials required  Process  Defects  Modern developments  Advantages  Disadvantages
  • 3.  Earlier 1950s steel was poured into stationary moulds to form ‘ingots’ since then “continuous casting” has evolved to achieve improved yield, quality, productivity & cost efficiency  Continuous casting may be defined as teeming of liquid metal in short mould with a false bottom through which partially solidified ingot (billet ,bloom or slab) is continuously withdrawn at the same rate at which metal is poured in the mould.  Which are subsequently rolled to get finished products.
  • 4.  Three main types of machines are in use in practice namely  Vertical mould  Vertical mould with bending  Curved mould or S-type
  • 5.  This type of mould is very tall and hence needs either a tall shop or a large pit to accommodate the equipments. The problem is acute if high casting speed are employed & consequence longer cooling zone is required.  Used for large and medium sections  It is easy to repair and restart the machine.
  • 6.  It is a modification over the vertical design to reduce the overall height of the machine.  The roller apron and pinch rolls are similar to those in vertical machine.  After the product emerges from the pinch rolls it is bent to obtain the discharge horizontal.  A horizontal set of straightening rolls becomes necessary.  Heavy sections being difficult to bend .  30% height is saved by this design.
  • 7.
  • 8.  This is the latest design now almost universally adopted for continuous casting of almost all sections like billets, blooms and slabs.  Characteristics-  The mould is itself curved mould.  The strands comes out of the mould in curvilinear fashion with a fixed radius.  It is bent before entire cross-section is solidified.  The curved strand is in fact straightened after it is fully solidified.
  • 10.  Ladle  Tundish  Mould  Dummy bar  Roller apron  Withdrawal rolls  Bending and straightening rolls  Cooling sprays  Cutting devices  Auxiliary electrical and/or mechanical gears to help run the machine smoothly.
  • 11. Ladle & turret- Steel from EAF or BOF is tapped into a ladle and taken to the continuous casting platform. The ladle is raised into a turret that rotate the ladle into the casting position above the tundish
  • 12.  Tundish-  Shroud  Turbo blower  Mono block Stopper rod  SEN It is a container which collects liquid steel from ladle through shroud. Here a turbo blower is fixed which converts the turbulant flow of liquid steel to laminar flow. Then by opening the stopper rod metal flows through the submerged entry nozzle.
  • 13.
  • 14.  Mould It is made of copper, copper & silver(cu 99.95%) due to its high thermal conductivity. Nickel plate is used inside the mould to protect the mould wall from eroding. Mould of 220mm to 300mm thick and 2500mm wide 900mm height is used. Now a days the mould width is decreased at any time when required during casting. 4500 -5000 ltrs/min of water is flow through the mould. Life of the mould is about 1000 heats.
  • 15.
  • 16.  Dummy bar- To begin with, the bottom of the mould is temporarily Closed by what is known as dummy bar. It lead the product through the roller apron and withdrawal rolls. The head of dummy bar is supposed to nearly close the bottom of the mould and whatever gap is left is packed with asbestos to obtain a temporarily fully closed bottom of the mould.
  • 17.  Withdrawal rolls- These are one or two pairs of rolls meant to finally grip the ingot and pull it out at a pre fixed rate without deforming the product. The pressure exerted by rolls on product should neither be excessive to cause deformation nor less to allow slip.  Bending & straightening rolls-  Single bending roller is used in vertical mould with horizontal discharge machine.  In s-type machine multi point bending rollers are used.  A straightening roller table is provided for straighten the product.
  • 18.  Cutting devices- Torch cutter with 4 torches(two for normal cutting & two for sample cutting in line) Oxy-fuel cutter is used , where LPG or acetylene are used as fuel.
  • 19.  Liquid steel  Asbestos  Fluxes  Chiller  Steel rods
  • 20. Tundish preparation Tundish and sen preheating Dummy bar insertion Mould setting Dummy bar sealing Ladle & tundish in casting position Teeming Start the machine Cutting
  • 21.  To start a cast the mould bottom is sealed by a steel dummy bar which is held in place hydraulically by the straightener withdrawal units.  The gap between the mould bottom and the dummy bar head is filled by asbestos. After that chiller & steel rods are provided for rapid solidification of the steel and it stick to the dummy bar head.  The steel is partially solidified in mould and producing a steel strand with a solid outer shell and a liquid core.
  • 22.  In this primary cooling area once the steel shell has a sufficient thickness about 10-20mm, the straightener withdrawal units are started and proceeds to withdraw the partially solidified strand out of the mould along with the dummy bar. Liquid steel continues to pour into the mould to replenish the withdrawn steel at an equal rate.  The withdrawal rate depends on the cross-section, grade, quality of steel being produced and may vary from 30 cm to 100cm per minute.  Casting time is typically 45 minutes to 90 minutes per heat to avoid excessive ladle heat losses.
  • 23.  Open exiting the mould the strands enters a roller containment section and secondary cooling chamber in which the solidifying strand is sprayed with water to promote solidification. This area preserves cast shape integrity and product quality.  Once the strand is fully solidified and has passed through the straightener withdrawal units the dummy bar is disconnected. Following the straightener the strand is cut into individual pieces of the following as-cast products: slabs, blooms, billets, rounds or beam blanks depending on machine design.
  • 24.  Mould stroke in the range of 5-10 mm.  Frequency of stroke , which is 150-200/min  Casting speed normally in the range of 2m/min  Negative strip time .1-.2 sec  Total cycle time of the order of .3-.4 sec  Positive strip time .15-.3% of cycle time  Powder consumption in the range of .17- .40kg/m2 of strand area.
  • 25.
  • 26.
  • 27.  Break out  Edge cracks  Longitudinal cracks  Primary scales  Random surface defects arising due to fluctuations of surfaces  Variations in width  Non-uniform thickness and flatness  Non-uniform microstructure in either direction  Segregation  Slag particle sticking the surface- entrapment of lubricant slag particle at the surface.
  • 28.
  • 29.  Remote adjustable mould  Air mist cooling  Dynamic spray cooling  BOPS  AMLC
  • 30.  Sprue, runner, riser etc. are not used. Hence , no waste metal this leads to casting yield.  Process is automatic  Product has good consistent soundness.  Mechanical properties are very high and very reproducible.
  • 31.  Not suitable for small quantity production.  Continuous and efficient cooling of mould is required, else, centre line shrinkage develops.  Requires large floor space.
  • 32.  Continuous casting has evolved from a batch process into a sophisticated continuous process. This transformation has occurred through understanding principle of mechanical design , heat transfer , steel metallurgical properties and stress strain relationships, to produce a product with excellent shape and quality.  In recent year the process has been optimized through careful integration of electro-mechanical sensors, computer-controls, & planning to provide a highly automated system designed for new millenia.