The document discusses two issues regarding a construction contract:
1) Whether a contractor is entitled to an extension of time if a project is suspended by a stop work order from local authorities. The answer depends on whether the stop work was due to the contractor's fault.
2) Whether an employer can take over a project from the contractor and appoint a third party to finish without terminating the original contract. Generally no, unless the contract allows termination for convenience or there is a breach by the contractor. Simply facing delays does not allow the employer to replace the contractor.