2. Contract claims in Construction
A contractual claim is an entitlement under the contract itself
where specific provisions or implied conditions of the contract
can be invoked to support the entitlement.
In construction contract, parties can pursue his rights to
implications of time and cost.
3. The Standard Form of Contract provides
provision empowering the Architect to
change or vary the contracted works, either
additions or omissions.
There is nothing in the contract to prevent
both parties from agreeing that the varied
work should be undertaken under a
separate contract.
Variation Claims
PAM 2006/2018 Clause 11.2
A successful claim,
Valid variation order
The Architect must be authorised under the
Conditions of Contract to issue such
instructions and that the instruction carries
an express or implied promise that the
Contractor will be paid for the work.
Extra work or work executed
under different conditions
Subject of varied work must fall within the
scope of work.
4. A successful claim,
Valid variation order
The Architect must be authorised under the
Conditions of Contract to issue such
instructions and that the instruction carries
an express or implied promise that the
Contractor will be paid for the work.
Extra work or work executed
under different conditions
Subject of varied work must fall within the
scope of work.
A variation order need not be issued but implied, so
the first test may be dispensed with:
â Differences between the quantity
of the executed works and
quantity shown in the Bills of
Quantities.
â Discrepancies between different
Contract Drawing.
â Changes in construction
methods.
5. The Contractor can request the Architect to specify which provision of
the Conditions empowers the issuance of said instruction.
Clause 1.4 Discrepancy or divergence between documents
Clause 3.4 Further drawings or details
Clause 3.5 Revised Works Programme
Clause 4.2 Inconsistencies with statutory requirements
Clause 4.4 Fees, Levies and charges
Clause 5.1 Setting Out
Clause 6.2 Provision of Vouchers
Clause 6.3 Inspection and Testing
Clause 6.5 Works not in accordance with the Contract
Clause 8.3 Exclusion of Person employed on the Works
Clause 11.2 No variation issued by the Architect shall vitiate Contract/Instruction ordering a Variation
Clause 11.3 Issue of Variations after Practical Completion
Clause 11.4 AI on P.C. Sums and Provisional Sum
Clause 12.2 Correction of errors or omissions
Clause 15.4 Schedule of Defects
Clause 16.3 Contractor to remove equipment upon Partial Possession by Employer
Clause 21.1 Commencement and Completion
Clause 21.4 Postponement or suspension of the Works
Clause 23.3 Insufficient information for EOT
Clause 25.4 Contractorâs duty to remove temporary buildings, plant, tool, equipment upon determination of
Contractorâs employment
Clause 25.7 Instruction to remove temporary buildings, plant, tool, equipment upon determination of Contractorâs
employment
Clause 27.1 Nominated Subcontractor
Clause 27.4 Action following objection to nomination of Subcontractor
Clause 27.11 Re-nomination of subcontractor due to determination of contractor
Clause 27.12 Re-nomination of subcontractor due to determination of subcontractor
Clause 28.1 Nominated Supplier
Clause 28.4 Actions following objection of suppliers
Clause 31.3 Protective work in event of outbreak of hostilities
Clause 32.1 Removal or disposal of debris or damaged works following war damage or protective
Clause 33.1 Antiquities - discovery on site
6. The Power to Issue Variation Order
A variation order which is issued outside the scope of
the power or which contradict the terms of the power is
not a valid order.
Architect
has no implied power to:
â Vary the terms of the contract
â Order extras
â Vary quantity or nature of work
âŚexcept only those powers derived from the
Conditions.
Contractor
cannot be compelled to
comply with the order.
He can totally disregard
it.
Employer
rigorously insists that
the Contractor comply
with the instruction
Treat as repudiating the contract
Should the Contractor chose to comply with the order and execute the variation work as ordered,
there is no corresponding obligation on the part of the Employer to pay for such works.
7. The Power to Issue Variation Order
Stockport MBC v OâReilly (1978)
Instructions were not empowered by any of the
Conditions of the Contract.
Ultra vires
âbeyond the powersâ
The English Court found that the Architect has acted beyond his remit
in issuing such instructions.
It was held that an Architectâs ultra vires acts
do not saddle the Employer with liability.
However, the Contractor is entitled to protest and to ignore them.
â The Architect is not the Employerâs agent in that respect. He has no authority to vary the contract. â
8. Person given the powers
Employer
Architect Quantity SurveyorEngineer
PAM
2006/2018
The Employer agrees to accept liability
for all the contractual consequences of
a valid variation order.
Engineerâs Instruction to be formalized as Architectâs Instruction
9. Extent of powers
Architectâs power cannot order
works beyond the scope of the
original work.
Extra work
The Contractor may be able to recover a
reasonable price for such work on a fresh
contract.
Case: Astilleros Canarios v Cape Hatteras Shipping (1982)
The Employer cannot be saddled with the
responsibility for unauthorised instruction issued
by the Architect.
Case: Stockport MBC v OâReilly (1978)
Without Employerâs knowledge
With Employerâs knowledge
10. Extent of powers
Power to vary works is intended to give flexibility and convenience during course of the works but
must be controlled to avoid unnecessary risk of additional cost being factored into the contract price.
During the tender stage, the Contractor can anticipate
potential variation upon studying the drawings, and
factor such variation into the schedule of rates or
contract price.
Hence, Contractor has the profit opportunity when such
variation arises.
Rationalisation of rates
to be conducted by
Quantity Surveyor.
11. Extent of powers
What recourse does a Contractor have if after carrying out an Architectâs Instruction only to find out
that the variation order exceeded his authority under the contract?
When the Architect issues an order for variations, he
warrants by implication that he is authorised to do so and
it is reasonable for the Contractor to act on the order.
Therefore, based of general principle,
Breach of warranty
of his authority
ArchitectContractor
12. Written instruction
PAM 2006/2018 Clause 2.2
All instructions issued by the Architect
shall be in writing expressly entitled
âArchitectâs Instructionâ (âAIâ).
Upon written confirmation from the
Contractor entitled âConfirmation of
Architectâs Instructionâ (âCAIâ).
Upon subsequent confirmation of the written
instructions by the Architect with an AI.
PAM 2006/2018 Clause 2.2(a)
PAM 2006/2018 Clause 2.2(b)
â Oral instruction
â Architectâs team members: Engineer, Clerk of Work
13. Written instruction
If the Contractor proceed and complete variation work without a written instruction,
Complain
Ask for a
reasonable sum
...notwithstanding that the Employer has benefited from the variation work.
14. Written instruction
Justifications
Enable changes to be better
understood.
Provide adequate attention by the
Employerâs consultant to
investigate, measure, and verify
the change.
Where the change is significant and
has huge cost implication, it serves
the interest of both parties for the
specific detail of the change to be
recorded.
Alert the other Consultants
to start gathering details and
records of the change before
they are covered up.
15. Written instruction
Tharsis Sulphur and Copper Co. v McElroy & Sons (1878)
The contract expressly provided that no extra work is
to be paid for unless there is a written order for the
same by the appellantâs agent or engineer.
The House of Lords held that the interim certificates
did not constitute written orders and that the claimant
was not entitled to claim for the additional tonnage of
steel work.
Facts Judgement
The claimant contractor found that it was unable to make certain
girders, due to the thinness of the metal specified by the defendant.
Claim for payment
Interim Certificate
16. Written instruction
Oral instruction
Quantum Meruit
Subject that the Contractor is able to
prove and justify.
If the Contractor fails to claim
for the extra works orally
ordered under PAM, he can
proceed to claim outside the
terms of the contract for
implied promise to pay
for work done.
17. Written instruction
Molloy v Liebe (1910)
Proper inferences:
â that the Employer had
actual knowledge of the
extra works as they were
being done
â that the Employer knew
that they were outside the
contract
â that the Employer knew
that the builder expected to
be paid for them as extras
...then a contract to pay for could
properly be implied.
Extra work
There had been no writing for these works as required by the Contract.
They had been ordered by the Architect, either in writing signed by him alone, or orally.
The Contractor submitted that the Employer had entered into an implied contract to pay the fair
value of the works âas extra worksâ.
19. 1. Work which is indispensably necessary
The courts are likely to require the Contractor to
perform all work which is indispensably
necessary for completion of the work, even if
each and every minor item of work involved is
not specifically referred to in the Contract.
Additional works are those not contemplated
by the parties at the time of execution of the
Contract and are not provided for.
Indispensably necessary
works are not a variation.
Specifications
did not
specifically
refer to any
hinges on
doors
Supplying the
hinges will be
found to be
part of the
scope
20. 2. Warranty that works can be built
When the Contractor undertakes a
contract for a lump sum price, he
basically warrants that the Works as
shown in the Drawings and
Specifications can be constructed.
Warranty found in Construction
Express warranties Implied warranties
Warranty is written
directly into the
Contract
The law provides
contracts with certain
protections regardless if
it is included in the
Contract or not
21. 2. Warranty that works can be built
When the Contractor undertakes a
contract for a lump sum price, he
basically warrants that the Works as
shown in the Drawings and
Specifications can be constructed.
Tharsis Sulphur and Copper Co. v McElroy & Sons (1878)
At all events, if the girders could not be made of the
precise thickness specified, that was a matter which
the Contractor ought to have known beforehand.
Casting girders of precise
thickness specified
22. 3. Items not specifically mentioned
An item specifically
provided for in the
Contract is not an extra. With todayâs Bills of
Quantities, any item of
work which is not
expressly mentioned in
the Contract Documents
becomes a
âpayable variationâ.
?
23. Loss of profit
The variation in the changes of the requirement can be paid easily but
4. Changes in employerâs requirement
Contractor
Loss of productivity
the variation works delay the project or prevent the optimal deployment of resources on site
Change Order Procedure
Provide for price of variation works be agreed upon before the contractor proceed
with it - to monitor closely the additional expenditure and project budget
24. No no⌠the contract specification
didn't state that I have to use this
Poor drafting of contract specification allows the contractor discretion in the choice of
construction materials or component for some work.
5. Poorly drafted contract documents
25. Treating it as variation and pays the contractor
6. Omission and discrepancies in contract documents
Variation
Contract price
Content that it has been included as part of the work covered under contract price
Leavell-Morrison Knudsen v United States (1971)
An air conditioning contract states that ducts shall be insulated
Flexible connector from ducts to ceiling diffuser were not insulated
Contractor contended that flexible connectors are not duct and not provision to
the contract
To do so constitute to variation and a payable extra
The court held in favour of the contractor
26. PAM 2018
Measurement of building works
Shall be prepared in accordance with the principles of
Standard Method of Measurement of Building Works.
PAM 2018 Clause 12.1
PAM 2018 Clause 12.2
7. Deviation from standard method of measurement
Correction of errors or omission
Non-compliance with standard method measurement,
Architect shall correct the error & treat it as variation.
Error shall not vitiate the contract.
27. The bills contained stipulation that the price inserted for
excavation work were to include âremoving natural stone
or rock excavationâ
Standard method - âE.O excavation in rockâ
The court held that by the virtue of the clause 12.1 -
contract bills cannot modify the conditions of the contract
Thus, the item of the work has to be paid for as variation
or extra
Bryant & Sons Ltd v Birmingham Hospital Saturday Fund (1938)
28. 8. Differences in quantities
Where a contract is based on Bills of Quantities, the principle is that the price is contracted for the
quantity of works as described in the bills.
Actual quantity of works > Quantities shown in the BQ
Contractor is entitled to claim
the additional as variation
Clause 12.2
Whether the parties intended the contract to be
a) Lump sum contract - additional quantity of work
undertaken to be measured and paid for accordingly
to bill rates
a) Re-measurement contract - envisages that the
entire quantity of work undertaken is to be re-
measured and paid accordingly to bill rates
Corrected by Architect
29. 9. Tender errors
PAM 2006/18 Clause 13.1
Shall be corrected and/or rationalised by the Architect or
Consultant without any change to the Contract Sum before the
signing of the Contract.
Contract sum shall not be adjusted or altered.
30. 10. Advice by Architect, Engineers and Consultant
Architect Quantity SurveyorEngineer
Contractor
Can I have the advice on the project by
suggesting alternative working method?
Care must be taken to ensure that such
advices are not interpreted as variation
instruction where the contractor is then
entitled to claim for additional expenditure
involved in implementing the solution,
even though he was only assisting the
contractor to discharge his obligations.
31. 11. Approval of construction method
Architect Engineer
Contractor
Submit construction method for approval
before commencement of work
Instruct the contractor to modify his method of
construction or use another method
Contractor may able to claim for additional cost if
a) The engineer was not honest in his decision; or
a) The contract expressly provides for price adjustment
if an unreasonable onerous or uneconomical method
of construction in selected
Neodox Ltd v Swinton & Pendlebury
Borough Council (1958)
32. Conditions of contract
Carr v JA Berriman Pty Ltd (1953)
Court held that the architect powers to omit works are for those works that
are desirable to be omitted in the course of the construction. The clause did
not authorise him to omit a particular item of work so that they can be
carried out by other party.
without intention to deceive or legal
Bona fide omission
Award to another contractor
Architect to omit part of work with
attendance adjustment on the
contract price
12. Valid omission
33. 13. Variation that changes the scope of contract
must not change the scope of the contract
or the works character which is
fundamentally different from that
contemplated by the parties at the time of
contract
Variation order
Employer ordered greatly in excess of the amount
contemplated
The court of Appeal held that the additional work
executed exceed the contemplation of the party
BQ cannot be applied but had to paid in quantum meruit
Sir Lindsay Parkinson & Co Ltd v Commissioners of
Her Majestyâs Works and Public Buildings (1950)
34. What can the Contractor do if he cannot precisely determine the variation order is valid or invalid?
The contractor cannot be forced to carry out an invalid
variation order
Breach of contract
ArchitectContractor
Proceed with the disputed work first and state that he is
working under protest on the basis
Entitled to be compensated if it is not in the scope of
contract
Original contract price Quantum meruit
Effect of changes to scope of contract
35.
36. 1
Damaged
roof to be
repaired
Upon acknowledging the damage, the Employer made instructions to the Contractor to repair.
Which provision under the PAM Contract can be uphold to justify the scope of work specified?
Under PAM Contract 2018 Article 7(be),
means the works described in the
Articles of Agreement and referred to in
the Contract Documents and include any
changes made to these works in
accordance with the Contract.
It is an extra work and the Contractor is
not obligated to comply with.
Works
37. 2 Can a Contractor claim extras in respect of items of work not mentioned in the Contract Bills?
Chittick V. Taylor An item specifically provided for in the contract is not an "extra."
Without any instructions
- Supplied material of a better quality than the minimum quality
necessary for the fulfilment of the contract
- Did work or supplied materials not called by the contract (plans of
specifications)
not entitled to charge this additional work or materials as an "extra."
If the employer, without giving definite instructions, knew the contractor was doing extra work or
supplying extra materials and stood by and approved of what was being done, and encouraged the contractor
to do it, that, amounts to an implied instruction to the contractor.
A contractual claim is an entitlement under the contract itself with specific provisions or implied conditions.
In construction contract, it is the entitlement to time and cost implications.
For variation claims, the PAM contract empowered the architect to issue variation, either additions, omissions or substitutions.
Therefore, such varied work is not required to be undertaken under a separate contract.
For a successful claim, the contractor must show that the variation work satisfy two tests:
Contractor must show that the instruction to change the works constitutes a valid variation order, in which the Architect is given the authorisation and thereâs an express or implied promise to pay
Contractor also need to show that the variation is an extra work or work executed under different conditions, subject that the variation must fall within the scope of work.
A variation order need not be issued but implied, so the first test may be dispensed with:
Differences between the actual quantity and BQ
Discrepancies between different contract drawings
And
Changes in construction methods
When the Architect issues an instruction, the contractor can request to specify the provision of the conditions* that empowers the issuance
And thereâs a total of 30 provisions under the PAM contract.
The Architect has no implied power to vary the terms of the contract, order extras, or vary quantity or nature of work, except those derived from the conditions.
A variation order which is issued outside the scope of the power or which contradict the terms of the power is not a valid order, and therefore the contractor cannot be forced to comply.
If the Employer insist upon the instruction, the Contractor may be entitled to treat the employer as repudiating the contract.
In the event that the contractor chose to comply with the order, the employer has no corresponding obligation to pay.
In the case of Stockport, the architect imposed instructions which were not empowered by any of the conditions of the contract.
It was held that the architect acted beyond the scope of his authority and ultra vires do not saddle the employer with liability.
However, the contractor is entitled to protest and ignore them.
https://www.isurv.com/directory_record/4562/stockport_mbc_v_oreilly
http://what-when-how.com/Tutorial/topic-865l3k3p/Building-Contract-319.html
Under the PAM contract, the power to issue variation order is given to the Architect by the Employer and by implication; the Employer agrees to accept liability for all the contractual consequences of a valid variation order.
Hence, the engineer and qs are not empowered to issue variation under their own name.
*
In the event thereâs Engineerâs instruction, it needs to be formalized as Architectâs instruction.
The architectâs power cannot order works beyond the scope of the original work, which is also known as extra work.
When the architect conducted otherwise and the employer is unaware of it, the employer cannot be saddled with the responsibility;
Whereas if the employer knew about it, the contractor may be able to recover a reasonable price on a fresh contract.
The power to vary works is intended to give flexibility and convenience, but it must be controlled to avoid unnecessary risk
For example, during the tender stage, the contractor can foresee potential variation when studying the drawings, and factor additional cost into the contract price.
So, it is important for the qs to conduct rationalisation of rates.
When the architect issues a variation order, he warrants by implication that he is authorised to do so, and it is reasonable for the contractor to act on the order.
But when the contractor carried out the work after only to find out that the order exceeded the architectâs authority,
The contractor may be entitled to proceed against the architect for breach of warranty of his authority.
Clause 2.2 in the pam contract provided that all instructions issued by the architect shall be in writing expressly entitled architectâs instruction.
Say if it is an oral instruction, or by the architectâs team member, the contractor can request for confirmation of architectâs instruction as stated under clause 2.2(a) and receive subsequent confirmation with an AI.
If the contractor proceed and complete variation work without a written instruction*, he cannot complain or ask for a reasonable sum despite that the employer has benefited from the work.
The purpose of written instruction is to allow better understanding of the changes, alert parties concerned to take appropriate actions and also serve as a record.
In the case of tharsis sulphur,
The contractor found that it was unable to make certain girders due to the thinness of the metal and took the risk of changing it.
In a claim for payment for the extra, the contractor relied on the fact that it was reflected in the interim certificate.
As a judgement, it was held that the interim certificate is not a written order and the contractor is not entitled to recover the extra cost.
https://lawcarenigeria.com/tharsis-sulphur-and-copper-co-v-melroy-sons-1878-ukhl-777-4-june-1878/
https://www.isurv.com/directory_record/4592/tharsis_sulphur_and_copper_company_v_mcelroy_and_sons
If the contractor fails to claim for the extra work orally ordered, he can proceed to claim outside the terms of the contract for implied promise on the basis of quantum meruit.
Subject that the contractor is able to prove and justify.
* As for the implied promise to pay
*
The proper inference is that the employer had actual knowledge of the extra works, that it is outside the contract, and the contractor expected to be paid for as extra
In the case of molloy v liebe,
The contractor wished to claim payment for certain extra works, but there was no valid variation order.
Given that the employer fit the three inference, there was an implied promise to pay and the contractor may recover on the basis of quantum meruit.
https://mosaicprojects.com.au/PDF-Casewatch/1038_Liebe-v-Molloy.pdf
The courts are likely to require the Contractor to perform all work which is indispensably necessary for completion of the work, even if each and every minor item of work involved is not specifically referred to in the Contract.
*
For example, the specifications did not specifically refer to any hinges on the doors, supplying the hinges will be found to be part of the scope, as it is work which is indispensably necessary for the completion of that work.
http://www.constructionlawmadeeasy.com/chapter4
As indicated, whether a particular work is a variation will depend on whether it comes within the general scope of the contract. Some works, although not specifically described, are nevertheless considered as implied or form a necessary part of the contract. An early case on this point is Williams v Fitzmaurice (1858) 157 ER 709. In that case, the contractor undertook to provide 'the whole of the material mentioned or otherwise in the foregoing particulars necessary for the completion of the work' and 'to perform all works of every kind mentioned and contained in the foregoing specifications for the sum of 100.00 pounds'. Flooring was not specifically mentioned and the issue was whether it was included in the contract. The court held that it was.
Similarly, in Walker v Randwick Municipal Council (1929) SR (NSW) 84 the contractor agreed to 'do and perform the whole of the works required in or about the construction of a concrete retaining wall'. In performing the works, Walker had to remove a sandbank to construct the retaining wall. The plan (which was not incorporated in the contract) showed the bank to be 6 feet wide. Walker claimed the bank was in fact 12 feet wide and claimed for work and labour in removing the extra 6 feet. The majority of the court held that the contract was an entire one to build a retaining wall at a fixed price and that the risk lay with contractor. Rogers J said (at page 87):
The contract is not to perform the work set out in any plan; all work necessarily required for the construction must be done whether set out in the plan or not.
When the Contractor undertakes a lump sum contract, he basically warrants that the Works as shown in the Drawings and Specifications can be constructed.
In construction, there are 2 main types of warranty, which are express and implied.
https://www.levelset.com/blog/workmanship-warranty/
Every contractor impliedly warrants that his work will be built in a good and workmanlike manner and that it will be sufficiently free of any major defects.
* From the previous case of tharsis sulphur, the contractor should have known beforehand if the girders could not be made of the precise thickness specified.
https://www.levelset.com/blog/workmanship-warranty/
in casting certain iron girders, owing to the unequal cooling of the iron, it was found difficult to make the girders of the precise thickness specified.
it requires greater care to cast the girders of the thickness specified in the contract than it would require to cast them thicker. In fact it would have been by no means difficult to cast the girders of the required thickness if the right course had been taken.
An item specifically provided for in the Contract is not an extra.
While, those that are not expressly mentioned in the Contract Documents becomes a
âpayable variationâ.
When there is changes in employerâs requirement, it is easy for the employer to pay for the variation but the contractor may claim for compensation of loss of profit and productivity if he can prove that the variation works delay the project or prevent the optimal deployment of resources on site
Some contract are modified to have change order procedure to Provide for price of variation works be agreed upon before the contractor proceed with it but it can work against the employer as not always easy to agree prices
Loss of productivity https://www.adroitprojectconsultants.com/2018/12/17/loss-of-productivity-in-construction-some-considerations/
Poor drafted contract documents caused variation arise. Common problem like poor drafting of contract specification allows the contractor discretion in the choice of construction materials or component for some work.
When there is omission and discrepancies in contract documents, the architect can resolve the problem by either Treating it as variation and pays the contractor
or argue that it has been included as part of the work covered under contract price
example the case of leavell morrison knudsen v united state (1971) An air conditioning contract states that ducts shall be insulated. During inspection, it was found that Flexible connector from ducts were not insulated. Contractor contended that flexible connectors are not duct and not provision to the contract. To do so constitute to variation and a payable extra. In the end, The court held in favour of the contractor
Leavell morrison case law https://law.justia.com/cases/federal/appellate-courts/F2/436/451/210184/
Deviation from standard method of measurement is one of the variation work
Here you can see that as per PAM 2018 clause 12.1 stated that Measurement of building works shall be prepared in accordance with the principles of SMM Which also means that the contract conditions prioritise over the contract BQ in the event of document conflicts
Moving on, the clause 12.2 stated that if there is non compliances of with SMM, Architect shall correct the error & treat it as variation. The Error shall not vitiate the contract.
Heres an example. In the case of Bryant & Sons Ltd v Birmingham Hospital Saturday Fund (1938)
The bills contained stipulation that the price inserted for excavation work were to include âremoving natural stone or rock excavationâ
but in the SMM stated that the excavation of rock have to be measurement separately and treated as an extra over
So in the end the rock was encountered on site & as aforementioned clause 12.1 stated that contract bills cannot modify the conditions of the contract
Thus, the item of the work has to be paid for as variation or extra
when the actual quantity of works executed by the contractor is more than the Quantities shown in the BQ then the Contractor is entitled to claim the additional as variation and The differences are to be corrected by the Architect
When there's differences in quantities, it is important that the parties determine whether the contract to be lump sum contract or remeasurement contract As it will determine how the remeasurement works
Extra info : Under a lump sum contract, a single âlump sumâ price for all the works is agreed before the works begin. It is defined as a fixed price contract, where the contractors agree to execute the work for a stated total sum of money. Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
Measurement contracts (sometimes called âre-measurementâ or âmeasure and valueâ contracts) are generally used in situations where the design (or type of works) can be described in reasonable detail, but the amount cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
Variation arise when there is error or mistake in the price or rates entered in the Contract Bills so based on PAM 2018 clause 13.1 . Any error aforementioned shall be correct by the Architect without any change to the Contract Sum before the signing of the Contract.
Contract sum shall not be adjusted or altered.
When contractor encounters problems during construction and ask the Architect/Consultant for advice,
*
You can give advice but take note that Care must be taken to ensure that such advices are not interpreted as variation instruction where the contractor is then entitled to claim for additional expenditure involved in implementing the solution,
*
Therefore Architect/Engineer responding to such requests should ensure that the contractor understand that the directions given are intended to assist him in his obligations under the contract
Before the commencement of work, the contractor has to submit method of approval before commencement of work
If the Architect/Engineer instruct the contractor to modify his method of construction or use another method, the contractor may able to claim for additional cost if
The engineer was not honest in his decision; or
The contract expressly provides for price adjustment if an unreasonable or uneconomical method of construction in selected
See Neodox Ltd v Swinton & Pendlebury Borough Council (1958) as an example where the contractor's claim failed because the court held that the engineer was honest in his decision of the method of
working.
Conditions of contract usually give powers to the Architect to omit part of work with attendance adjustment on the contract price in respect of bona fide omission
But he cannot omit work from the contract in order to award to another contractor which is supported by the case of Carr v JA Berriman Pty Ltd (1953)
Last, The power to vary works is limited by the rule that the variation order not change the scope of the contract or the works character which is fundamentally different from that contemplated by the parties at the time of contract
In the case of Sir Lindsay Parkinson v Commissioners of Her Majestyâs Works. The court of Appeal held that the additional work executed exceed the contemplation of the party thus BQ cannot be applied but had to paid in quantum meruit
So in the effect of changes to scope of contract
The contractor cannot be forced to carry out an invalid variation order as Such action is a breach of contract
However, most of situations the contractor cannot be precisely determine if the vo is valid or invalid during construction
So what the contractor can do is to proceed with the disputed work first and state that he is working under protest on the basis
if later established that THE WORK does not fall within the scope of contract, the contractor are entitled to be compensated based on quantum meruit as the original contract price cannot be apply to work that is outside of the scoop of contract
An item specifically provided for in the contract is not an "extra."
The contractor supplied material of a better quality than the minimum quality necessary for the fulfilment of the contract, or did work or supplied materials not called by the contract (plans of specifications)
without any instructions, express or implied, from the employer to do so, he is not entitled to charge the extra cost as an "extra."
When the contractor did work or supplied material not called for by the contract on the instructions, express to implied of the employer, he is entitled to charge for the additional work or materials as an "extra."
If the employer, without giving definite instructions, knew the plaintiff was doing extra work or supplying extra materials and stood by and approved of what was being done, and encouraged the contractor to do it, that, in my opinion amounts to an implied instruction to the contractor.