SlideShare a Scribd company logo
1 of 38
Chapter 7
Construction Contractual Claims
0330764 WAN YEE LEN 0327653 WONG WEN NEE
Contract claims in Construction
A contractual claim is an entitlement under the contract itself
where specific provisions or implied conditions of the contract
can be invoked to support the entitlement.
In construction contract, parties can pursue his rights to
implications of time and cost.
The Standard Form of Contract provides
provision empowering the Architect to
change or vary the contracted works, either
additions or omissions.
There is nothing in the contract to prevent
both parties from agreeing that the varied
work should be undertaken under a
separate contract.
Variation Claims
PAM 2006/2018 Clause 11.2
A successful claim,
Valid variation order
The Architect must be authorised under the
Conditions of Contract to issue such
instructions and that the instruction carries
an express or implied promise that the
Contractor will be paid for the work.
Extra work or work executed
under different conditions
Subject of varied work must fall within the
scope of work.
A successful claim,
Valid variation order
The Architect must be authorised under the
Conditions of Contract to issue such
instructions and that the instruction carries
an express or implied promise that the
Contractor will be paid for the work.
Extra work or work executed
under different conditions
Subject of varied work must fall within the
scope of work.
A variation order need not be issued but implied, so
the first test may be dispensed with:
● Differences between the quantity
of the executed works and
quantity shown in the Bills of
Quantities.
● Discrepancies between different
Contract Drawing.
● Changes in construction
methods.
The Contractor can request the Architect to specify which provision of
the Conditions empowers the issuance of said instruction.
Clause 1.4 Discrepancy or divergence between documents
Clause 3.4 Further drawings or details
Clause 3.5 Revised Works Programme
Clause 4.2 Inconsistencies with statutory requirements
Clause 4.4 Fees, Levies and charges
Clause 5.1 Setting Out
Clause 6.2 Provision of Vouchers
Clause 6.3 Inspection and Testing
Clause 6.5 Works not in accordance with the Contract
Clause 8.3 Exclusion of Person employed on the Works
Clause 11.2 No variation issued by the Architect shall vitiate Contract/Instruction ordering a Variation
Clause 11.3 Issue of Variations after Practical Completion
Clause 11.4 AI on P.C. Sums and Provisional Sum
Clause 12.2 Correction of errors or omissions
Clause 15.4 Schedule of Defects
Clause 16.3 Contractor to remove equipment upon Partial Possession by Employer
Clause 21.1 Commencement and Completion
Clause 21.4 Postponement or suspension of the Works
Clause 23.3 Insufficient information for EOT
Clause 25.4 Contractor’s duty to remove temporary buildings, plant, tool, equipment upon determination of
Contractor’s employment
Clause 25.7 Instruction to remove temporary buildings, plant, tool, equipment upon determination of Contractor’s
employment
Clause 27.1 Nominated Subcontractor
Clause 27.4 Action following objection to nomination of Subcontractor
Clause 27.11 Re-nomination of subcontractor due to determination of contractor
Clause 27.12 Re-nomination of subcontractor due to determination of subcontractor
Clause 28.1 Nominated Supplier
Clause 28.4 Actions following objection of suppliers
Clause 31.3 Protective work in event of outbreak of hostilities
Clause 32.1 Removal or disposal of debris or damaged works following war damage or protective
Clause 33.1 Antiquities - discovery on site
The Power to Issue Variation Order
A variation order which is issued outside the scope of
the power or which contradict the terms of the power is
not a valid order.
Architect
has no implied power to:
● Vary the terms of the contract
● Order extras
● Vary quantity or nature of work
…except only those powers derived from the
Conditions.
Contractor
cannot be compelled to
comply with the order.
He can totally disregard
it.
Employer
rigorously insists that
the Contractor comply
with the instruction
Treat as repudiating the contract
Should the Contractor chose to comply with the order and execute the variation work as ordered,
there is no corresponding obligation on the part of the Employer to pay for such works.
The Power to Issue Variation Order
Stockport MBC v O’Reilly (1978)
Instructions were not empowered by any of the
Conditions of the Contract.
Ultra vires
“beyond the powers”
The English Court found that the Architect has acted beyond his remit
in issuing such instructions.
It was held that an Architect’s ultra vires acts
do not saddle the Employer with liability.
However, the Contractor is entitled to protest and to ignore them.
‘ The Architect is not the Employer’s agent in that respect. He has no authority to vary the contract. ’
Person given the powers
Employer
Architect Quantity SurveyorEngineer
PAM
2006/2018
The Employer agrees to accept liability
for all the contractual consequences of
a valid variation order.
Engineer’s Instruction to be formalized as Architect’s Instruction
Extent of powers
Architect’s power cannot order
works beyond the scope of the
original work.
Extra work
The Contractor may be able to recover a
reasonable price for such work on a fresh
contract.
Case: Astilleros Canarios v Cape Hatteras Shipping (1982)
The Employer cannot be saddled with the
responsibility for unauthorised instruction issued
by the Architect.
Case: Stockport MBC v O’Reilly (1978)
Without Employer’s knowledge
With Employer’s knowledge
Extent of powers
Power to vary works is intended to give flexibility and convenience during course of the works but
must be controlled to avoid unnecessary risk of additional cost being factored into the contract price.
During the tender stage, the Contractor can anticipate
potential variation upon studying the drawings, and
factor such variation into the schedule of rates or
contract price.
Hence, Contractor has the profit opportunity when such
variation arises.
Rationalisation of rates
to be conducted by
Quantity Surveyor.
Extent of powers
What recourse does a Contractor have if after carrying out an Architect’s Instruction only to find out
that the variation order exceeded his authority under the contract?
When the Architect issues an order for variations, he
warrants by implication that he is authorised to do so and
it is reasonable for the Contractor to act on the order.
Therefore, based of general principle,
Breach of warranty
of his authority
ArchitectContractor
Written instruction
PAM 2006/2018 Clause 2.2
All instructions issued by the Architect
shall be in writing expressly entitled
“Architect’s Instruction” (‘AI’).
Upon written confirmation from the
Contractor entitled “Confirmation of
Architect’s Instruction” (‘CAI’).
Upon subsequent confirmation of the written
instructions by the Architect with an AI.
PAM 2006/2018 Clause 2.2(a)
PAM 2006/2018 Clause 2.2(b)
● Oral instruction
● Architect’s team members: Engineer, Clerk of Work
Written instruction
If the Contractor proceed and complete variation work without a written instruction,
Complain
Ask for a
reasonable sum
...notwithstanding that the Employer has benefited from the variation work.
Written instruction
Justifications
Enable changes to be better
understood.
Provide adequate attention by the
Employer’s consultant to
investigate, measure, and verify
the change.
Where the change is significant and
has huge cost implication, it serves
the interest of both parties for the
specific detail of the change to be
recorded.
Alert the other Consultants
to start gathering details and
records of the change before
they are covered up.
Written instruction
Tharsis Sulphur and Copper Co. v McElroy & Sons (1878)
The contract expressly provided that no extra work is
to be paid for unless there is a written order for the
same by the appellant’s agent or engineer.
The House of Lords held that the interim certificates
did not constitute written orders and that the claimant
was not entitled to claim for the additional tonnage of
steel work.
Facts Judgement
The claimant contractor found that it was unable to make certain
girders, due to the thinness of the metal specified by the defendant.
Claim for payment
Interim Certificate
Written instruction
Oral instruction
Quantum Meruit
Subject that the Contractor is able to
prove and justify.
If the Contractor fails to claim
for the extra works orally
ordered under PAM, he can
proceed to claim outside the
terms of the contract for
implied promise to pay
for work done.
Written instruction
Molloy v Liebe (1910)
Proper inferences:
● that the Employer had
actual knowledge of the
extra works as they were
being done
● that the Employer knew
that they were outside the
contract
● that the Employer knew
that the builder expected to
be paid for them as extras
...then a contract to pay for could
properly be implied.
Extra work
There had been no writing for these works as required by the Contract.
They had been ordered by the Architect, either in writing signed by him alone, or orally.
The Contractor submitted that the Employer had entered into an implied contract to pay the fair
value of the works “as extra works”.
Variation Works and Common Claims
1. Work which is indispensably necessary
The courts are likely to require the Contractor to
perform all work which is indispensably
necessary for completion of the work, even if
each and every minor item of work involved is
not specifically referred to in the Contract.
Additional works are those not contemplated
by the parties at the time of execution of the
Contract and are not provided for.
Indispensably necessary
works are not a variation.
Specifications
did not
specifically
refer to any
hinges on
doors
Supplying the
hinges will be
found to be
part of the
scope
2. Warranty that works can be built
When the Contractor undertakes a
contract for a lump sum price, he
basically warrants that the Works as
shown in the Drawings and
Specifications can be constructed.
Warranty found in Construction
Express warranties Implied warranties
Warranty is written
directly into the
Contract
The law provides
contracts with certain
protections regardless if
it is included in the
Contract or not
2. Warranty that works can be built
When the Contractor undertakes a
contract for a lump sum price, he
basically warrants that the Works as
shown in the Drawings and
Specifications can be constructed.
Tharsis Sulphur and Copper Co. v McElroy & Sons (1878)
At all events, if the girders could not be made of the
precise thickness specified, that was a matter which
the Contractor ought to have known beforehand.
Casting girders of precise
thickness specified
3. Items not specifically mentioned
An item specifically
provided for in the
Contract is not an extra. With today’s Bills of
Quantities, any item of
work which is not
expressly mentioned in
the Contract Documents
becomes a
‘payable variation’.
?
Loss of profit
The variation in the changes of the requirement can be paid easily but
4. Changes in employer’s requirement
Contractor
Loss of productivity
the variation works delay the project or prevent the optimal deployment of resources on site
Change Order Procedure
Provide for price of variation works be agreed upon before the contractor proceed
with it - to monitor closely the additional expenditure and project budget
No no… the contract specification
didn't state that I have to use this
Poor drafting of contract specification allows the contractor discretion in the choice of
construction materials or component for some work.
5. Poorly drafted contract documents
Treating it as variation and pays the contractor
6. Omission and discrepancies in contract documents
Variation
Contract price
Content that it has been included as part of the work covered under contract price
Leavell-Morrison Knudsen v United States (1971)
An air conditioning contract states that ducts shall be insulated
Flexible connector from ducts to ceiling diffuser were not insulated
Contractor contended that flexible connectors are not duct and not provision to
the contract
To do so constitute to variation and a payable extra
The court held in favour of the contractor
PAM 2018
Measurement of building works
Shall be prepared in accordance with the principles of
Standard Method of Measurement of Building Works.
PAM 2018 Clause 12.1
PAM 2018 Clause 12.2
7. Deviation from standard method of measurement
Correction of errors or omission
Non-compliance with standard method measurement,
Architect shall correct the error & treat it as variation.
Error shall not vitiate the contract.
The bills contained stipulation that the price inserted for
excavation work were to include ‘removing natural stone
or rock excavation’
Standard method - “E.O excavation in rock”
The court held that by the virtue of the clause 12.1 -
contract bills cannot modify the conditions of the contract
Thus, the item of the work has to be paid for as variation
or extra
Bryant & Sons Ltd v Birmingham Hospital Saturday Fund (1938)
8. Differences in quantities
Where a contract is based on Bills of Quantities, the principle is that the price is contracted for the
quantity of works as described in the bills.
Actual quantity of works > Quantities shown in the BQ
Contractor is entitled to claim
the additional as variation
Clause 12.2
Whether the parties intended the contract to be
a) Lump sum contract - additional quantity of work
undertaken to be measured and paid for accordingly
to bill rates
a) Re-measurement contract - envisages that the
entire quantity of work undertaken is to be re-
measured and paid accordingly to bill rates
Corrected by Architect
9. Tender errors
PAM 2006/18 Clause 13.1
Shall be corrected and/or rationalised by the Architect or
Consultant without any change to the Contract Sum before the
signing of the Contract.
Contract sum shall not be adjusted or altered.
10. Advice by Architect, Engineers and Consultant
Architect Quantity SurveyorEngineer
Contractor
Can I have the advice on the project by
suggesting alternative working method?
Care must be taken to ensure that such
advices are not interpreted as variation
instruction where the contractor is then
entitled to claim for additional expenditure
involved in implementing the solution,
even though he was only assisting the
contractor to discharge his obligations.
11. Approval of construction method
Architect Engineer
Contractor
Submit construction method for approval
before commencement of work
Instruct the contractor to modify his method of
construction or use another method
Contractor may able to claim for additional cost if
a) The engineer was not honest in his decision; or
a) The contract expressly provides for price adjustment
if an unreasonable onerous or uneconomical method
of construction in selected
Neodox Ltd v Swinton & Pendlebury
Borough Council (1958)
Conditions of contract
Carr v JA Berriman Pty Ltd (1953)
Court held that the architect powers to omit works are for those works that
are desirable to be omitted in the course of the construction. The clause did
not authorise him to omit a particular item of work so that they can be
carried out by other party.
without intention to deceive or legal
Bona fide omission
Award to another contractor
Architect to omit part of work with
attendance adjustment on the
contract price
12. Valid omission
13. Variation that changes the scope of contract
must not change the scope of the contract
or the works character which is
fundamentally different from that
contemplated by the parties at the time of
contract
Variation order
Employer ordered greatly in excess of the amount
contemplated
The court of Appeal held that the additional work
executed exceed the contemplation of the party
BQ cannot be applied but had to paid in quantum meruit
Sir Lindsay Parkinson & Co Ltd v Commissioners of
Her Majesty’s Works and Public Buildings (1950)
What can the Contractor do if he cannot precisely determine the variation order is valid or invalid?
The contractor cannot be forced to carry out an invalid
variation order
Breach of contract
ArchitectContractor
Proceed with the disputed work first and state that he is
working under protest on the basis
Entitled to be compensated if it is not in the scope of
contract
Original contract price Quantum meruit
Effect of changes to scope of contract
1
Damaged
roof to be
repaired
Upon acknowledging the damage, the Employer made instructions to the Contractor to repair.
Which provision under the PAM Contract can be uphold to justify the scope of work specified?
Under PAM Contract 2018 Article 7(be),
means the works described in the
Articles of Agreement and referred to in
the Contract Documents and include any
changes made to these works in
accordance with the Contract.
It is an extra work and the Contractor is
not obligated to comply with.
Works
2 Can a Contractor claim extras in respect of items of work not mentioned in the Contract Bills?
Chittick V. Taylor An item specifically provided for in the contract is not an "extra."
Without any instructions
- Supplied material of a better quality than the minimum quality
necessary for the fulfilment of the contract
- Did work or supplied materials not called by the contract (plans of
specifications)
not entitled to charge this additional work or materials as an "extra."
If the employer, without giving definite instructions, knew the contractor was doing extra work or
supplying extra materials and stood by and approved of what was being done, and encouraged the contractor
to do it, that, amounts to an implied instruction to the contractor.
End of presentation
Thank You

More Related Content

What's hot

Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerTrace96
 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation Jaey Chai
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminarwendyteosy
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project managementNilesh Dhotre
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMPÂŽ, CCPÂŽ
 

What's hot (20)

Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Construction contract
Construction contract Construction contract
Construction contract
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Fidic
FidicFidic
Fidic
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 

Similar to Construction Law - Presentation - Construction Contractual Claims

Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omittedAMILA GAYAN
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangEmilia Chian Chee Yong
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)mohammedAlmusawi11
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdfHASMANIRA
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Francis Ho
 
ICM.pptx
ICM.pptxICM.pptx
ICM.pptxKoul5
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction ProjectMelissa Brumback
 

Similar to Construction Law - Presentation - Construction Contractual Claims (20)

Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omitted
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
ICM.pptx
ICM.pptxICM.pptx
ICM.pptx
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction Project
 

More from Yee Len Wan

Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationYee Len Wan
 
Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Yee Len Wan
 
Value Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeValue Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeYee Len Wan
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalYee Len Wan
 
Development Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchDevelopment Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchYee Len Wan
 
Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Yee Len Wan
 
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Yee Len Wan
 
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowStructures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowYee Len Wan
 
Integrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportIntegrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportYee Len Wan
 
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergLeading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergYee Len Wan
 
Construction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationConstruction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationYee Len Wan
 
Professional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsProfessional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsYee Len Wan
 
Construction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingConstruction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingYee Len Wan
 
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMBuilding Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMYee Len Wan
 
Financial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisFinancial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisYee Len Wan
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationYee Len Wan
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)Yee Len Wan
 
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingValue Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingYee Len Wan
 

More from Yee Len Wan (20)

Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentation
 
Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...
 
Value Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeValue Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcome
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisal
 
Development Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchDevelopment Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market Research
 
Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO
 
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
 
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowStructures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
 
Integrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportIntegrated Assignment - Site Visit Report
Integrated Assignment - Site Visit Report
 
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergLeading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
 
Construction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationConstruction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavation
 
Professional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsProfessional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional Ethics
 
Construction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingConstruction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - Scaffolding
 
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMBuilding Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
 
Financial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisFinancial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial Analysis
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)
 
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingValue Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
 

Recently uploaded

Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 

Recently uploaded (20)

Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 

Construction Law - Presentation - Construction Contractual Claims

  • 1. Chapter 7 Construction Contractual Claims 0330764 WAN YEE LEN 0327653 WONG WEN NEE
  • 2. Contract claims in Construction A contractual claim is an entitlement under the contract itself where specific provisions or implied conditions of the contract can be invoked to support the entitlement. In construction contract, parties can pursue his rights to implications of time and cost.
  • 3. The Standard Form of Contract provides provision empowering the Architect to change or vary the contracted works, either additions or omissions. There is nothing in the contract to prevent both parties from agreeing that the varied work should be undertaken under a separate contract. Variation Claims PAM 2006/2018 Clause 11.2 A successful claim, Valid variation order The Architect must be authorised under the Conditions of Contract to issue such instructions and that the instruction carries an express or implied promise that the Contractor will be paid for the work. Extra work or work executed under different conditions Subject of varied work must fall within the scope of work.
  • 4. A successful claim, Valid variation order The Architect must be authorised under the Conditions of Contract to issue such instructions and that the instruction carries an express or implied promise that the Contractor will be paid for the work. Extra work or work executed under different conditions Subject of varied work must fall within the scope of work. A variation order need not be issued but implied, so the first test may be dispensed with: ● Differences between the quantity of the executed works and quantity shown in the Bills of Quantities. ● Discrepancies between different Contract Drawing. ● Changes in construction methods.
  • 5. The Contractor can request the Architect to specify which provision of the Conditions empowers the issuance of said instruction. Clause 1.4 Discrepancy or divergence between documents Clause 3.4 Further drawings or details Clause 3.5 Revised Works Programme Clause 4.2 Inconsistencies with statutory requirements Clause 4.4 Fees, Levies and charges Clause 5.1 Setting Out Clause 6.2 Provision of Vouchers Clause 6.3 Inspection and Testing Clause 6.5 Works not in accordance with the Contract Clause 8.3 Exclusion of Person employed on the Works Clause 11.2 No variation issued by the Architect shall vitiate Contract/Instruction ordering a Variation Clause 11.3 Issue of Variations after Practical Completion Clause 11.4 AI on P.C. Sums and Provisional Sum Clause 12.2 Correction of errors or omissions Clause 15.4 Schedule of Defects Clause 16.3 Contractor to remove equipment upon Partial Possession by Employer Clause 21.1 Commencement and Completion Clause 21.4 Postponement or suspension of the Works Clause 23.3 Insufficient information for EOT Clause 25.4 Contractor’s duty to remove temporary buildings, plant, tool, equipment upon determination of Contractor’s employment Clause 25.7 Instruction to remove temporary buildings, plant, tool, equipment upon determination of Contractor’s employment Clause 27.1 Nominated Subcontractor Clause 27.4 Action following objection to nomination of Subcontractor Clause 27.11 Re-nomination of subcontractor due to determination of contractor Clause 27.12 Re-nomination of subcontractor due to determination of subcontractor Clause 28.1 Nominated Supplier Clause 28.4 Actions following objection of suppliers Clause 31.3 Protective work in event of outbreak of hostilities Clause 32.1 Removal or disposal of debris or damaged works following war damage or protective Clause 33.1 Antiquities - discovery on site
  • 6. The Power to Issue Variation Order A variation order which is issued outside the scope of the power or which contradict the terms of the power is not a valid order. Architect has no implied power to: ● Vary the terms of the contract ● Order extras ● Vary quantity or nature of work …except only those powers derived from the Conditions. Contractor cannot be compelled to comply with the order. He can totally disregard it. Employer rigorously insists that the Contractor comply with the instruction Treat as repudiating the contract Should the Contractor chose to comply with the order and execute the variation work as ordered, there is no corresponding obligation on the part of the Employer to pay for such works.
  • 7. The Power to Issue Variation Order Stockport MBC v O’Reilly (1978) Instructions were not empowered by any of the Conditions of the Contract. Ultra vires “beyond the powers” The English Court found that the Architect has acted beyond his remit in issuing such instructions. It was held that an Architect’s ultra vires acts do not saddle the Employer with liability. However, the Contractor is entitled to protest and to ignore them. ‘ The Architect is not the Employer’s agent in that respect. He has no authority to vary the contract. ’
  • 8. Person given the powers Employer Architect Quantity SurveyorEngineer PAM 2006/2018 The Employer agrees to accept liability for all the contractual consequences of a valid variation order. Engineer’s Instruction to be formalized as Architect’s Instruction
  • 9. Extent of powers Architect’s power cannot order works beyond the scope of the original work. Extra work The Contractor may be able to recover a reasonable price for such work on a fresh contract. Case: Astilleros Canarios v Cape Hatteras Shipping (1982) The Employer cannot be saddled with the responsibility for unauthorised instruction issued by the Architect. Case: Stockport MBC v O’Reilly (1978) Without Employer’s knowledge With Employer’s knowledge
  • 10. Extent of powers Power to vary works is intended to give flexibility and convenience during course of the works but must be controlled to avoid unnecessary risk of additional cost being factored into the contract price. During the tender stage, the Contractor can anticipate potential variation upon studying the drawings, and factor such variation into the schedule of rates or contract price. Hence, Contractor has the profit opportunity when such variation arises. Rationalisation of rates to be conducted by Quantity Surveyor.
  • 11. Extent of powers What recourse does a Contractor have if after carrying out an Architect’s Instruction only to find out that the variation order exceeded his authority under the contract? When the Architect issues an order for variations, he warrants by implication that he is authorised to do so and it is reasonable for the Contractor to act on the order. Therefore, based of general principle, Breach of warranty of his authority ArchitectContractor
  • 12. Written instruction PAM 2006/2018 Clause 2.2 All instructions issued by the Architect shall be in writing expressly entitled “Architect’s Instruction” (‘AI’). Upon written confirmation from the Contractor entitled “Confirmation of Architect’s Instruction” (‘CAI’). Upon subsequent confirmation of the written instructions by the Architect with an AI. PAM 2006/2018 Clause 2.2(a) PAM 2006/2018 Clause 2.2(b) ● Oral instruction ● Architect’s team members: Engineer, Clerk of Work
  • 13. Written instruction If the Contractor proceed and complete variation work without a written instruction, Complain Ask for a reasonable sum ...notwithstanding that the Employer has benefited from the variation work.
  • 14. Written instruction Justifications Enable changes to be better understood. Provide adequate attention by the Employer’s consultant to investigate, measure, and verify the change. Where the change is significant and has huge cost implication, it serves the interest of both parties for the specific detail of the change to be recorded. Alert the other Consultants to start gathering details and records of the change before they are covered up.
  • 15. Written instruction Tharsis Sulphur and Copper Co. v McElroy & Sons (1878) The contract expressly provided that no extra work is to be paid for unless there is a written order for the same by the appellant’s agent or engineer. The House of Lords held that the interim certificates did not constitute written orders and that the claimant was not entitled to claim for the additional tonnage of steel work. Facts Judgement The claimant contractor found that it was unable to make certain girders, due to the thinness of the metal specified by the defendant. Claim for payment Interim Certificate
  • 16. Written instruction Oral instruction Quantum Meruit Subject that the Contractor is able to prove and justify. If the Contractor fails to claim for the extra works orally ordered under PAM, he can proceed to claim outside the terms of the contract for implied promise to pay for work done.
  • 17. Written instruction Molloy v Liebe (1910) Proper inferences: ● that the Employer had actual knowledge of the extra works as they were being done ● that the Employer knew that they were outside the contract ● that the Employer knew that the builder expected to be paid for them as extras ...then a contract to pay for could properly be implied. Extra work There had been no writing for these works as required by the Contract. They had been ordered by the Architect, either in writing signed by him alone, or orally. The Contractor submitted that the Employer had entered into an implied contract to pay the fair value of the works “as extra works”.
  • 18. Variation Works and Common Claims
  • 19. 1. Work which is indispensably necessary The courts are likely to require the Contractor to perform all work which is indispensably necessary for completion of the work, even if each and every minor item of work involved is not specifically referred to in the Contract. Additional works are those not contemplated by the parties at the time of execution of the Contract and are not provided for. Indispensably necessary works are not a variation. Specifications did not specifically refer to any hinges on doors Supplying the hinges will be found to be part of the scope
  • 20. 2. Warranty that works can be built When the Contractor undertakes a contract for a lump sum price, he basically warrants that the Works as shown in the Drawings and Specifications can be constructed. Warranty found in Construction Express warranties Implied warranties Warranty is written directly into the Contract The law provides contracts with certain protections regardless if it is included in the Contract or not
  • 21. 2. Warranty that works can be built When the Contractor undertakes a contract for a lump sum price, he basically warrants that the Works as shown in the Drawings and Specifications can be constructed. Tharsis Sulphur and Copper Co. v McElroy & Sons (1878) At all events, if the girders could not be made of the precise thickness specified, that was a matter which the Contractor ought to have known beforehand. Casting girders of precise thickness specified
  • 22. 3. Items not specifically mentioned An item specifically provided for in the Contract is not an extra. With today’s Bills of Quantities, any item of work which is not expressly mentioned in the Contract Documents becomes a ‘payable variation’. ?
  • 23. Loss of profit The variation in the changes of the requirement can be paid easily but 4. Changes in employer’s requirement Contractor Loss of productivity the variation works delay the project or prevent the optimal deployment of resources on site Change Order Procedure Provide for price of variation works be agreed upon before the contractor proceed with it - to monitor closely the additional expenditure and project budget
  • 24. No no… the contract specification didn't state that I have to use this Poor drafting of contract specification allows the contractor discretion in the choice of construction materials or component for some work. 5. Poorly drafted contract documents
  • 25. Treating it as variation and pays the contractor 6. Omission and discrepancies in contract documents Variation Contract price Content that it has been included as part of the work covered under contract price Leavell-Morrison Knudsen v United States (1971) An air conditioning contract states that ducts shall be insulated Flexible connector from ducts to ceiling diffuser were not insulated Contractor contended that flexible connectors are not duct and not provision to the contract To do so constitute to variation and a payable extra The court held in favour of the contractor
  • 26. PAM 2018 Measurement of building works Shall be prepared in accordance with the principles of Standard Method of Measurement of Building Works. PAM 2018 Clause 12.1 PAM 2018 Clause 12.2 7. Deviation from standard method of measurement Correction of errors or omission Non-compliance with standard method measurement, Architect shall correct the error & treat it as variation. Error shall not vitiate the contract.
  • 27. The bills contained stipulation that the price inserted for excavation work were to include ‘removing natural stone or rock excavation’ Standard method - “E.O excavation in rock” The court held that by the virtue of the clause 12.1 - contract bills cannot modify the conditions of the contract Thus, the item of the work has to be paid for as variation or extra Bryant & Sons Ltd v Birmingham Hospital Saturday Fund (1938)
  • 28. 8. Differences in quantities Where a contract is based on Bills of Quantities, the principle is that the price is contracted for the quantity of works as described in the bills. Actual quantity of works > Quantities shown in the BQ Contractor is entitled to claim the additional as variation Clause 12.2 Whether the parties intended the contract to be a) Lump sum contract - additional quantity of work undertaken to be measured and paid for accordingly to bill rates a) Re-measurement contract - envisages that the entire quantity of work undertaken is to be re- measured and paid accordingly to bill rates Corrected by Architect
  • 29. 9. Tender errors PAM 2006/18 Clause 13.1 Shall be corrected and/or rationalised by the Architect or Consultant without any change to the Contract Sum before the signing of the Contract. Contract sum shall not be adjusted or altered.
  • 30. 10. Advice by Architect, Engineers and Consultant Architect Quantity SurveyorEngineer Contractor Can I have the advice on the project by suggesting alternative working method? Care must be taken to ensure that such advices are not interpreted as variation instruction where the contractor is then entitled to claim for additional expenditure involved in implementing the solution, even though he was only assisting the contractor to discharge his obligations.
  • 31. 11. Approval of construction method Architect Engineer Contractor Submit construction method for approval before commencement of work Instruct the contractor to modify his method of construction or use another method Contractor may able to claim for additional cost if a) The engineer was not honest in his decision; or a) The contract expressly provides for price adjustment if an unreasonable onerous or uneconomical method of construction in selected Neodox Ltd v Swinton & Pendlebury Borough Council (1958)
  • 32. Conditions of contract Carr v JA Berriman Pty Ltd (1953) Court held that the architect powers to omit works are for those works that are desirable to be omitted in the course of the construction. The clause did not authorise him to omit a particular item of work so that they can be carried out by other party. without intention to deceive or legal Bona fide omission Award to another contractor Architect to omit part of work with attendance adjustment on the contract price 12. Valid omission
  • 33. 13. Variation that changes the scope of contract must not change the scope of the contract or the works character which is fundamentally different from that contemplated by the parties at the time of contract Variation order Employer ordered greatly in excess of the amount contemplated The court of Appeal held that the additional work executed exceed the contemplation of the party BQ cannot be applied but had to paid in quantum meruit Sir Lindsay Parkinson & Co Ltd v Commissioners of Her Majesty’s Works and Public Buildings (1950)
  • 34. What can the Contractor do if he cannot precisely determine the variation order is valid or invalid? The contractor cannot be forced to carry out an invalid variation order Breach of contract ArchitectContractor Proceed with the disputed work first and state that he is working under protest on the basis Entitled to be compensated if it is not in the scope of contract Original contract price Quantum meruit Effect of changes to scope of contract
  • 35.
  • 36. 1 Damaged roof to be repaired Upon acknowledging the damage, the Employer made instructions to the Contractor to repair. Which provision under the PAM Contract can be uphold to justify the scope of work specified? Under PAM Contract 2018 Article 7(be), means the works described in the Articles of Agreement and referred to in the Contract Documents and include any changes made to these works in accordance with the Contract. It is an extra work and the Contractor is not obligated to comply with. Works
  • 37. 2 Can a Contractor claim extras in respect of items of work not mentioned in the Contract Bills? Chittick V. Taylor An item specifically provided for in the contract is not an "extra." Without any instructions - Supplied material of a better quality than the minimum quality necessary for the fulfilment of the contract - Did work or supplied materials not called by the contract (plans of specifications) not entitled to charge this additional work or materials as an "extra." If the employer, without giving definite instructions, knew the contractor was doing extra work or supplying extra materials and stood by and approved of what was being done, and encouraged the contractor to do it, that, amounts to an implied instruction to the contractor.

Editor's Notes

  1. A contractual claim is an entitlement under the contract itself with specific provisions or implied conditions. In construction contract, it is the entitlement to time and cost implications.
  2. For variation claims, the PAM contract empowered the architect to issue variation, either additions, omissions or substitutions. Therefore, such varied work is not required to be undertaken under a separate contract. For a successful claim, the contractor must show that the variation work satisfy two tests: Contractor must show that the instruction to change the works constitutes a valid variation order, in which the Architect is given the authorisation and there’s an express or implied promise to pay Contractor also need to show that the variation is an extra work or work executed under different conditions, subject that the variation must fall within the scope of work.
  3. A variation order need not be issued but implied, so the first test may be dispensed with: Differences between the actual quantity and BQ Discrepancies between different contract drawings And Changes in construction methods
  4. When the Architect issues an instruction, the contractor can request to specify the provision of the conditions* that empowers the issuance And there’s a total of 30 provisions under the PAM contract.
  5. The Architect has no implied power to vary the terms of the contract, order extras, or vary quantity or nature of work, except those derived from the conditions. A variation order which is issued outside the scope of the power or which contradict the terms of the power is not a valid order, and therefore the contractor cannot be forced to comply. If the Employer insist upon the instruction, the Contractor may be entitled to treat the employer as repudiating the contract. In the event that the contractor chose to comply with the order, the employer has no corresponding obligation to pay.
  6. In the case of Stockport, the architect imposed instructions which were not empowered by any of the conditions of the contract. It was held that the architect acted beyond the scope of his authority and ultra vires do not saddle the employer with liability. However, the contractor is entitled to protest and ignore them. https://www.isurv.com/directory_record/4562/stockport_mbc_v_oreilly http://what-when-how.com/Tutorial/topic-865l3k3p/Building-Contract-319.html
  7. Under the PAM contract, the power to issue variation order is given to the Architect by the Employer and by implication; the Employer agrees to accept liability for all the contractual consequences of a valid variation order. Hence, the engineer and qs are not empowered to issue variation under their own name. * In the event there’s Engineer’s instruction, it needs to be formalized as Architect’s instruction.
  8. The architect’s power cannot order works beyond the scope of the original work, which is also known as extra work. When the architect conducted otherwise and the employer is unaware of it, the employer cannot be saddled with the responsibility; Whereas if the employer knew about it, the contractor may be able to recover a reasonable price on a fresh contract.
  9. The power to vary works is intended to give flexibility and convenience, but it must be controlled to avoid unnecessary risk For example, during the tender stage, the contractor can foresee potential variation when studying the drawings, and factor additional cost into the contract price. So, it is important for the qs to conduct rationalisation of rates.
  10. When the architect issues a variation order, he warrants by implication that he is authorised to do so, and it is reasonable for the contractor to act on the order. But when the contractor carried out the work after only to find out that the order exceeded the architect’s authority, The contractor may be entitled to proceed against the architect for breach of warranty of his authority.
  11. Clause 2.2 in the pam contract provided that all instructions issued by the architect shall be in writing expressly entitled architect’s instruction. Say if it is an oral instruction, or by the architect’s team member, the contractor can request for confirmation of architect’s instruction as stated under clause 2.2(a) and receive subsequent confirmation with an AI.
  12. If the contractor proceed and complete variation work without a written instruction*, he cannot complain or ask for a reasonable sum despite that the employer has benefited from the work.
  13. The purpose of written instruction is to allow better understanding of the changes, alert parties concerned to take appropriate actions and also serve as a record.
  14. In the case of tharsis sulphur, The contractor found that it was unable to make certain girders due to the thinness of the metal and took the risk of changing it. In a claim for payment for the extra, the contractor relied on the fact that it was reflected in the interim certificate. As a judgement, it was held that the interim certificate is not a written order and the contractor is not entitled to recover the extra cost. https://lawcarenigeria.com/tharsis-sulphur-and-copper-co-v-melroy-sons-1878-ukhl-777-4-june-1878/ https://www.isurv.com/directory_record/4592/tharsis_sulphur_and_copper_company_v_mcelroy_and_sons
  15. If the contractor fails to claim for the extra work orally ordered, he can proceed to claim outside the terms of the contract for implied promise on the basis of quantum meruit. Subject that the contractor is able to prove and justify. * As for the implied promise to pay *
  16. The proper inference is that the employer had actual knowledge of the extra works, that it is outside the contract, and the contractor expected to be paid for as extra In the case of molloy v liebe, The contractor wished to claim payment for certain extra works, but there was no valid variation order. Given that the employer fit the three inference, there was an implied promise to pay and the contractor may recover on the basis of quantum meruit. https://mosaicprojects.com.au/PDF-Casewatch/1038_Liebe-v-Molloy.pdf
  17. The courts are likely to require the Contractor to perform all work which is indispensably necessary for completion of the work, even if each and every minor item of work involved is not specifically referred to in the Contract. * For example, the specifications did not specifically refer to any hinges on the doors, supplying the hinges will be found to be part of the scope, as it is work which is indispensably necessary for the completion of that work. http://www.constructionlawmadeeasy.com/chapter4 As indicated, whether a particular work is a variation will depend on whether it comes within the general scope of the contract. Some works, although not specifically described, are nevertheless considered as implied or form a necessary part of the contract. An early case on this point is Williams v Fitzmaurice (1858) 157 ER 709. In that case, the contractor undertook to provide 'the whole of the material mentioned or otherwise in the foregoing particulars necessary for the completion of the work' and 'to perform all works of every kind mentioned and contained in the foregoing specifications for the sum of 100.00 pounds'. Flooring was not specifically mentioned and the issue was whether it was included in the contract. The court held that it was. Similarly, in Walker v Randwick Municipal Council (1929) SR (NSW) 84 the contractor agreed to 'do and perform the whole of the works required in or about the construction of a concrete retaining wall'. In performing the works, Walker had to remove a sandbank to construct the retaining wall. The plan (which was not incorporated in the contract) showed the bank to be 6 feet wide. Walker claimed the bank was in fact 12 feet wide and claimed for work and labour in removing the extra 6 feet. The majority of the court held that the contract was an entire one to build a retaining wall at a fixed price and that the risk lay with contractor. Rogers J said (at page 87): The contract is not to perform the work set out in any plan; all work necessarily required for the construction must be done whether set out in the plan or not.
  18. When the Contractor undertakes a lump sum contract, he basically warrants that the Works as shown in the Drawings and Specifications can be constructed. In construction, there are 2 main types of warranty, which are express and implied. https://www.levelset.com/blog/workmanship-warranty/ Every contractor impliedly warrants that his work will be built in a good and workmanlike manner and that it will be sufficiently free of any major defects.
  19. * From the previous case of tharsis sulphur, the contractor should have known beforehand if the girders could not be made of the precise thickness specified. https://www.levelset.com/blog/workmanship-warranty/ in casting certain iron girders, owing to the unequal cooling of the iron, it was found difficult to make the girders of the precise thickness specified. it requires greater care to cast the girders of the thickness specified in the contract than it would require to cast them thicker. In fact it would have been by no means difficult to cast the girders of the required thickness if the right course had been taken.
  20. An item specifically provided for in the Contract is not an extra. While, those that are not expressly mentioned in the Contract Documents becomes a ‘payable variation’.
  21. When there is changes in employer’s requirement, it is easy for the employer to pay for the variation but the contractor may claim for compensation of loss of profit and productivity if he can prove that the variation works delay the project or prevent the optimal deployment of resources on site Some contract are modified to have change order procedure to Provide for price of variation works be agreed upon before the contractor proceed with it but it can work against the employer as not always easy to agree prices Loss of productivity https://www.adroitprojectconsultants.com/2018/12/17/loss-of-productivity-in-construction-some-considerations/
  22. Poor drafted contract documents caused variation arise. Common problem like poor drafting of contract specification allows the contractor discretion in the choice of construction materials or component for some work.
  23. When there is omission and discrepancies in contract documents, the architect can resolve the problem by either Treating it as variation and pays the contractor or argue that it has been included as part of the work covered under contract price example the case of leavell morrison knudsen v united state (1971) An air conditioning contract states that ducts shall be insulated. During inspection, it was found that Flexible connector from ducts were not insulated. Contractor contended that flexible connectors are not duct and not provision to the contract. To do so constitute to variation and a payable extra. In the end, The court held in favour of the contractor Leavell morrison case law https://law.justia.com/cases/federal/appellate-courts/F2/436/451/210184/
  24. Deviation from standard method of measurement is one of the variation work Here you can see that as per PAM 2018 clause 12.1 stated that Measurement of building works shall be prepared in accordance with the principles of SMM Which also means that the contract conditions prioritise over the contract BQ in the event of document conflicts Moving on, the clause 12.2 stated that if there is non compliances of with SMM, Architect shall correct the error & treat it as variation. The Error shall not vitiate the contract.
  25. Heres an example. In the case of Bryant & Sons Ltd v Birmingham Hospital Saturday Fund (1938) The bills contained stipulation that the price inserted for excavation work were to include ‘removing natural stone or rock excavation’ but in the SMM stated that the excavation of rock have to be measurement separately and treated as an extra over So in the end the rock was encountered on site & as aforementioned clause 12.1 stated that contract bills cannot modify the conditions of the contract Thus, the item of the work has to be paid for as variation or extra
  26. when the actual quantity of works executed by the contractor is more than the Quantities shown in the BQ then the Contractor is entitled to claim the additional as variation and The differences are to be corrected by the Architect When there's differences in quantities, it is important that the parties determine whether the contract to be lump sum contract or remeasurement contract As it will determine how the remeasurement works Extra info : Under a lump sum contract, a single ‘lump sum’ price for all the works is agreed before the works begin. It is defined as a fixed price contract, where the contractors agree to execute the work for a stated total sum of money. Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out. Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) are generally used in situations where the design (or type of works) can be described in reasonable detail, but the amount cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
  27. Variation arise when there is error or mistake in the price or rates entered in the Contract Bills so based on PAM 2018 clause 13.1 . Any error aforementioned shall be correct by the Architect without any change to the Contract Sum before the signing of the Contract. Contract sum shall not be adjusted or altered.
  28. When contractor encounters problems during construction and ask the Architect/Consultant for advice, * You can give advice but take note that Care must be taken to ensure that such advices are not interpreted as variation instruction where the contractor is then entitled to claim for additional expenditure involved in implementing the solution, * Therefore Architect/Engineer responding to such requests should ensure that the contractor understand that the directions given are intended to assist him in his obligations under the contract
  29. Before the commencement of work, the contractor has to submit method of approval before commencement of work If the Architect/Engineer instruct the contractor to modify his method of construction or use another method, the contractor may able to claim for additional cost if The engineer was not honest in his decision; or The contract expressly provides for price adjustment if an unreasonable or uneconomical method of construction in selected See Neodox Ltd v Swinton & Pendlebury Borough Council (1958) as an example where the contractor's claim failed because the court held that the engineer was honest in his decision of the method of working.
  30. Conditions of contract usually give powers to the Architect to omit part of work with attendance adjustment on the contract price in respect of bona fide omission But he cannot omit work from the contract in order to award to another contractor which is supported by the case of Carr v JA Berriman Pty Ltd (1953)
  31. Last, The power to vary works is limited by the rule that the variation order not change the scope of the contract or the works character which is fundamentally different from that contemplated by the parties at the time of contract In the case of Sir Lindsay Parkinson v Commissioners of Her Majesty’s Works. The court of Appeal held that the additional work executed exceed the contemplation of the party thus BQ cannot be applied but had to paid in quantum meruit
  32. So in the effect of changes to scope of contract The contractor cannot be forced to carry out an invalid variation order as Such action is a breach of contract However, most of situations the contractor cannot be precisely determine if the vo is valid or invalid during construction So what the contractor can do is to proceed with the disputed work first and state that he is working under protest on the basis if later established that THE WORK does not fall within the scope of contract, the contractor are entitled to be compensated based on quantum meruit as the original contract price cannot be apply to work that is outside of the scoop of contract
  33. An item specifically provided for in the contract is not an "extra." The contractor supplied material of a better quality than the minimum quality necessary for the fulfilment of the contract, or did work or supplied materials not called by the contract (plans of specifications) without any instructions, express or implied, from the employer to do so, he is not entitled to charge the extra cost as an "extra." When the contractor did work or supplied material not called for by the contract on the instructions, express to implied of the employer, he is entitled to charge for the additional work or materials as an "extra." If the employer, without giving definite instructions, knew the plaintiff was doing extra work or supplying extra materials and stood by and approved of what was being done, and encouraged the contractor to do it, that, in my opinion amounts to an implied instruction to the contractor.