2. The Team:
Director: Mok Po Yi
Members:
Chin Weng Lok
Darren Loong Chi Yoong
Lee Jian Ru
Pang Khai Shuen
Sherlyn Ang Tse Yun
3. Project Description
❖ Freehold land
❖ 10 acres 1 rood 10 pole = 449,213 ft2
❖ Bought 3 years ago
❖ RM15/ft2
❖ Bank loan: RM6,500,000.00
❖ Development Area = 449,213 ft2 x 60%
= 269,528 ft2
4. Strength & Weaknesses
Strengths
1. Strategic location
a. In close proximity to the city centre, shopping complex and
universities.
2. High population density
a. According to world population review (2018), Subang Jaya is
home to as many as 708,296 people.
5. Strength & Weaknesses
3. High effective demand for houses and shop/ office lots
a. High student population as there are a lot of universities nearby.
b. Food and beverage businesses would opt for the shop lots in the
proposed site as it would be able to cater to the student.
6. Strength & Weaknesses
Weaknesses:
1. Inadequate Ingress/Egress
a. Only one ingress from LDP highway, one egress to Bandar Sunway
b. Two other high density developments that share the same main road
2. Limited Parking Facilities
a. Risk of excessive roadside parking unless development is gated & guarded
8. Benchmark Project (Cont’d)
Price of double-storey
terraced house
RM 350,000
Size per unit 20ft x 70 ft
Number of double-storey
terraced houses
600 units
Total area of double-storey
terraced houses
1400 ft2 x 600 units
= 840,000 ft2
Unit price per square feet RM 250.00
GDV RM250.00 x 840,000
= RM 210,000,000.00
11. Pre-construction stage
Identification of project goal :
● Best value for money
● Expected gross profit - 30% from GDV
● Expected completion - end of December of 2014
● Expected budget - RM38 million
Procurement method: Traditional Procurement Method
12. Pre-construction stage
Design review
● Aim:
○ To keep design changes to a
minimum
○ To achieve high quality design
● Done by project team
● Using a design review checklist
13. Pre-construction stage
● Tender document and specification
Quality Assessment System in
Construction (QLASSIC)
Must score above 70%
British Standard (BS) Standardise the technical specification
Building Information Modelling (BIM) ● Visualise building design
● Detect clash
● Enable contractor to understand the complexity of the project
Value Engineering Change Proposal
(VECP)
● Allow contractor to have alternative proposal
● Reduce construction cost
● Improve quality
● Grant incentive to contractors
15. Construction Stage
● A Project Quality Plan (PQP) to ensure a smooth execution of works
during construction stage is essential.
● Our PQP was prepared to satisfy the requirements in ISO 9001:2015
- Quality Management System Requirements.
16. Construction Stage
Quality Objectives:
✓ Proper planning of construction activities within a realistic timeframe and
control delays within 10%.
✓ Continuous review and control of costs to ensure completion of works
are within +/- 5% of budget.
✓ Constantly meeting with health and safety requirements in accordance to
the Occupational Health and Safety Assessment Series (OHSAS) 18000.
✓ Achieving minimum 80% client satisfaction in all construction activities to
maintain healthy relationship.
17. Construction Stage
Quality Policies:
1. Establish clearly defined responsibility and authority for compliance.
2. Translate client’s goals and objectives from the Contract Documents to top quality completed
facility while meeting the applicable standards.
3. Ensure the highest level of quality by maintaining supervised controls and written instructions
governing Quality Control procedures and practices.
4. Complete and maintain accurate records of inspections and tests.
5. Clearly specify procedures to ensure that quality requirements are communicated to all levels of
the field organization.
6. Identify and take corrective measures against non-conformance of quality related aspects and
ensuring all corrective measures are properly implemented and documented.
19. Construction Stage
Inspection and Test Plans (ITP):
● To identify, plan and provide a record of project specific inspections
and tests from project commencement to completion.
● Responsibility of the QC Coordinator and Consultant Inspectors.
● 4 Types of ITP:
1. Field inspection
2. Approved material inspection
3. Material test inspection
4. Re-work procedure
20. Post Construction Stage
Operation and Maintenance
-Maintenance is the process to be done to prevent the deterioration in the building and to
repair the damages towards the building.
-The life cycle cost of project should be taken into consideration during feasibility study,
such as operation and maintenance cost.
-It could create a great impact on the overall life cycle cost of the construction project during
post construction stage.
-Once the project is completed and the building is ready to function and occupied, it
becomes part of the operating system.
-The operation and maintenance (O&M) includes repair and replacement
(R&R), usually associated with the quality of the constructed project.
21. Post Construction Stage
Operation and Maintenance
Documents required to operate and maintain the completed facility, which are
submitted by the contractor during the testing, commissioning and handover phase of
the construction project:
I. As-built Drawings
II. Operation and Maintenance Manuals
III. Operating Procedures
IV. Source Information for Availability of Spare Parts of the Installed Works
22. Post Construction Stage
Operation and Maintenance Program
-The operation and maintenance personnel should be engaged and involved in
determining maintenance requirements which to be included into the design.
-The following procedures must be followed to create an effective and efficient
Operation and Maintenance Program:
● Ensure that as-built drawings for all systems are up to date and readily
available
● Ensure that operational procedures and manuals for the installed
equipments are readily available
● A master schedule for operation and preventive/predictive maintenance
must be prepared
23. Post Construction Stage
Operation and Maintenance Program
● Follow the manufacturer’s recommendations for maintenance of
equipment and systems
● Implement preventive maintenance programs complete with
maintenance schedules and records of all maintenance performed
for the equipment and systems installed in the facility or project
● Ensure the maintenance personnels are well trained and have full
knowledge of the equipment and systems installed which he is
responsible to operate and maintain
● Implement a monitoring program that provides function of
tracking documenting of equipment performance to identify and
diagnose potential problems
26. Identification of Risks
External Risks:
1. Political – Government Regulations, GST, Change of Government
2. Economic – Exchange Rate, GDP Growth
3. Social – Demographics, Cultural Trends, Population Size
4. Technological – IBS Scoring System 50%
5. Environmental – Pollution, Traffic planning
6. Legal – Local Authority
27. Identification of Risks
Internal Risks:
1. Pre-construction
a. Technical – Poor Buildability
b. Financial – Funding
2. Construction
a. Safety – Safety Officer
b. Material – Material Testing
c. Personnel – Unregistered Foreign Workers
3. Post-construction
a. Operation & Maintenance – After Sales Service
28. Assessment/ Analysis of Risk
Qualitative
- Delphi Technique
(brainstorming)
- SWIFT
- Bow-tie analysis
- Probability Consequence
Quantitative
- Sensitivity Analysis
- Expected Monetary Value
(EMV)
- Monte Carlo Simulation
- Decision Tree analysis
29. Recommendation of Risk Assessment
- We have chosen to use probability/consequence risk matrix.
- This is because the risk matrix showcases the probability as well as the
impact of a risk. This will enable us to shift our focus on the main driver of
the risk and mitigate the risk.
30. Response/Controlling Risks
❖ Avoidance/Prevention/Elimination
Eliminate project’s risk is to change the scope of project or, worst scenario, cancel it
❖ Reduction/Mitigation
Hire experts to manage high-risk activities in construction projects
❖ Transfer/Insure
Purchasing an insurance policy, warranties, performance bonds, guarantees or by outsourcing the work
❖ Retention/Tolerate
Changing of law which contemplated in the Uniform Building By-Laws (UBBL)
31. Monitoring Risks
- Continuous operative control of the effectiveness of the risk control
measures
- Helps to discover new risks, keep track of identified risks and eliminate
past risks from the risk assessment and project
- Monitoring of the risk is to supervise the status of the risks and take
corrective actions if needed
- Risk reassessment, status meetings and risk register updates must be
carried out continuously in order to improve the project work as the pros
and cons will be established