SlideShare a Scribd company logo
Determination of 
Building Contracts
 Determination by Employer 
 Determination by Contractor 
 Pre-mature determination
Pre-mature determination 
 The main cause for pre-mature determination is 
frustration 
 Generally, a ct is frustrated when further 
performance has become illegal/impossible due 
to subsequent or supervening event which 
rendered the contract : 
 (i) illegal 
 (ii) impossible 
 (iii) commercial sterile
 A frustration event must be of such a 
nature as to have been unforeseeable, 
irresistible and not due to fault of either 
contractual party.
Goh Yew Chew & Anor v 
Soh Kian Tee 
The plf entered a ct with the def 
(contractor) for the construction of two 
storey shop houses in Malacca. The plf 
paid $5000 of earnest deposit. The def 
later discovered that the building could not 
be completed according to plan because 
of the proximity to an adjacent house. The 
plf claimed for the deposit.
Federal court: The contractor claimed that 
the plf can not claim for the deposit as the 
ct has become frustrated. The ct was not a 
frustrated contract where a change of 
circumstances vitiated it, but one which 
rendered void by initial impossibility. There 
was no evidence that construction work on 
the buildings had actually started.
Force-majeure 
 Another circumstances for pre mature 
determination. 
 The contract shall be determined if the force 
majeure event render the contract to become 
impossible or illegal to perform. 
 The scope of force majeure includes two other 
terms: 
(i) Act of God 
(ii) Vis major 
( Refer to notes on EoT)
Commercially Sterile 
 This circumstances occur when the essential 
commercial purpose of the contract has become 
frustrated 
Bush v Whitehaven Port & Town Trustees 
The contract was entered by the parties in summer. 
However, due to some fault of the employer, the 
performance of the contract was delayed. The delay 
resulted higher cost as the works had to be extended 
until winter. The contractor claimed for QM. 
Held: The contractor is entitled to the QM claim as if 
there had been frustrated.
Determination by the Employer 
 Clause 25.0 PAM 2006 
 Cl 25.1-Grounds which give rights to the 
employer to determine the contract : 
(a) –(f)
Duties of contractors upon of 
determination of contract by employer 
 Clause 25.4(a)-(d)
Duties of employers upon 
determination of the contract by them 
 Clause 25.5-Records of works 
 Clause 25.6-Final account
Determination by Contractors 
 Clause 26: Contractor may determine his 
own employment if the employer defaults 
in any of the following- cl 26.1 (a)- (d)
 Duties of contractors - cl 26.4(a) 
- cl 26.5 
- cl 26.6 
 Duties of employer-cl 26.4(b)
Insolvency 
 Insolvency is a ground for determination of 
the contract: 
Insolvency of the contractor- employment of 
the contractor shall be automatically 
determine-cl 25.3 
Insolvency of the employer- employment of 
the contractor shall be automatically 
determine- cl 26.3

More Related Content

What's hot

Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
Kai Yun Pang
 
PP1 report
PP1 reportPP1 report
PP1 report
Doreen Yeo
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
lucaschinsheng
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
Trace96
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
Hafizul Mukhlis
 
ECA presentation
ECA presentationECA presentation
ECA presentation
Shze Hwa Lee
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
마 이환
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
lohwenjun
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Liquidated damages
Liquidated damagesLiquidated damages
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation
Jaey Chai
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
Kai Yun Pang
 
Eca presentation
Eca presentationEca presentation
Eca presentation
wendyteosy
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Hasif Alias
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
Farah Sham
 

What's hot (20)

Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation PP1Tutorial 5 Presentation
PP1Tutorial 5 Presentation
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 

Viewers also liked

Duty of Care in Federal Agencies
Duty of Care in Federal AgenciesDuty of Care in Federal Agencies
Duty of Care in Federal Agencies
Gov BizCouncil
 
Building a Knowledge-Based Practice in the Digital Age
Building a Knowledge-Based Practice in the Digital AgeBuilding a Knowledge-Based Practice in the Digital Age
Building a Knowledge-Based Practice in the Digital Age
Carl Davis
 
Story To Reflect Upon 101, 102
Story To Reflect Upon 101, 102Story To Reflect Upon 101, 102
Story To Reflect Upon 101, 102
OH TEIK BIN
 
New Age Link Building
New Age Link BuildingNew Age Link Building
New Age Link Building
Performics.Convonix
 
G05732933
G05732933G05732933
G05732933
IOSR-JEN
 
A Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
A Quick Crack Stitching Wall Repair Guide by Thor Helical AustraliaA Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
A Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
Thor Helical Australia
 
Experiences concerning Stone age building constructions in Finland - OpenArch...
Experiences concerning Stone age building constructions in Finland - OpenArch...Experiences concerning Stone age building constructions in Finland - OpenArch...
Experiences concerning Stone age building constructions in Finland - OpenArch...
EXARC
 
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITY Collaborative initiative of WHO-S...
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITYCollaborative initiative of WHO-S...TOWARDS BUILDING AN AGE FRIENDLY COMMUNITYCollaborative initiative of WHO-S...
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITY Collaborative initiative of WHO-S...
Alakananda Banerjee
 
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
Sandia National Laboratories: Energy & Climate: Renewables
 
Comparison of Mesh Type Seismic Retrofitting for Masonry Structures
Comparison of Mesh Type Seismic Retrofitting for Masonry StructuresComparison of Mesh Type Seismic Retrofitting for Masonry Structures
Comparison of Mesh Type Seismic Retrofitting for Masonry Structures
chali090
 
Comparision of building for sesmic response by using base isolation
Comparision of building for sesmic response by using base isolationComparision of building for sesmic response by using base isolation
Comparision of building for sesmic response by using base isolation
eSAT Journals
 
PROJECT
PROJECTPROJECT
PROJECT
Udit Roy
 
retrofitting
retrofittingretrofitting
retrofitting
SRUTHI K
 
Insurance Provisions in Commercial Contracts
Insurance Provisions in Commercial ContractsInsurance Provisions in Commercial Contracts
Insurance Provisions in Commercial Contracts
Bradley Arant Boult Cummings LLP
 
Hop dong solar
Hop dong solarHop dong solar
Hop dong solarHeo Rừng
 
What I Wish I Knew Before I Signed that Contract
What I Wish I Knew Before I Signed that ContractWhat I Wish I Knew Before I Signed that Contract
What I Wish I Knew Before I Signed that Contract
InnoTech
 
UNIT 10 TOLES. IP rights, ROT clause, Force Majeure
UNIT 10 TOLES. IP rights, ROT clause, Force MajeureUNIT 10 TOLES. IP rights, ROT clause, Force Majeure
UNIT 10 TOLES. IP rights, ROT clause, Force Majeure
Adela Perez del Viso
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3Joy Irman
 

Viewers also liked (20)

Design liability
Design liabilityDesign liability
Design liability
 
Duty of Care in Federal Agencies
Duty of Care in Federal AgenciesDuty of Care in Federal Agencies
Duty of Care in Federal Agencies
 
Building a Knowledge-Based Practice in the Digital Age
Building a Knowledge-Based Practice in the Digital AgeBuilding a Knowledge-Based Practice in the Digital Age
Building a Knowledge-Based Practice in the Digital Age
 
Story To Reflect Upon 101, 102
Story To Reflect Upon 101, 102Story To Reflect Upon 101, 102
Story To Reflect Upon 101, 102
 
New Age Link Building
New Age Link BuildingNew Age Link Building
New Age Link Building
 
G05732933
G05732933G05732933
G05732933
 
A Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
A Quick Crack Stitching Wall Repair Guide by Thor Helical AustraliaA Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
A Quick Crack Stitching Wall Repair Guide by Thor Helical Australia
 
my cv
my cvmy cv
my cv
 
Experiences concerning Stone age building constructions in Finland - OpenArch...
Experiences concerning Stone age building constructions in Finland - OpenArch...Experiences concerning Stone age building constructions in Finland - OpenArch...
Experiences concerning Stone age building constructions in Finland - OpenArch...
 
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITY Collaborative initiative of WHO-S...
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITYCollaborative initiative of WHO-S...TOWARDS BUILDING AN AGE FRIENDLY COMMUNITYCollaborative initiative of WHO-S...
TOWARDS BUILDING AN AGE FRIENDLY COMMUNITY Collaborative initiative of WHO-S...
 
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
Wind Turbine Blade Reliability, Effects of Manufacturing Defects and Composit...
 
Comparison of Mesh Type Seismic Retrofitting for Masonry Structures
Comparison of Mesh Type Seismic Retrofitting for Masonry StructuresComparison of Mesh Type Seismic Retrofitting for Masonry Structures
Comparison of Mesh Type Seismic Retrofitting for Masonry Structures
 
Comparision of building for sesmic response by using base isolation
Comparision of building for sesmic response by using base isolationComparision of building for sesmic response by using base isolation
Comparision of building for sesmic response by using base isolation
 
PROJECT
PROJECTPROJECT
PROJECT
 
retrofitting
retrofittingretrofitting
retrofitting
 
Insurance Provisions in Commercial Contracts
Insurance Provisions in Commercial ContractsInsurance Provisions in Commercial Contracts
Insurance Provisions in Commercial Contracts
 
Hop dong solar
Hop dong solarHop dong solar
Hop dong solar
 
What I Wish I Knew Before I Signed that Contract
What I Wish I Knew Before I Signed that ContractWhat I Wish I Knew Before I Signed that Contract
What I Wish I Knew Before I Signed that Contract
 
UNIT 10 TOLES. IP rights, ROT clause, Force Majeure
UNIT 10 TOLES. IP rights, ROT clause, Force MajeureUNIT 10 TOLES. IP rights, ROT clause, Force Majeure
UNIT 10 TOLES. IP rights, ROT clause, Force Majeure
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3
 

Similar to Determination of building_contracts

Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of Contract
Arissa Loh
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10
Jessyca Than
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
SeanGibbs12
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
mohammedAlmusawi11
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
SONU61709
 
VA Sup Ct Opinion 11232016
VA Sup Ct Opinion 11232016VA Sup Ct Opinion 11232016
VA Sup Ct Opinion 11232016Louis Antonacci
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
 
Contract Law II Group Assignment Presentation
Contract Law II Group Assignment PresentationContract Law II Group Assignment Presentation
Contract Law II Group Assignment Presentation
Tineshvaar
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
Eversheds Sutherland
 
L7 Rights to discharge and disolve contracts.pptx
L7 Rights to discharge and disolve contracts.pptxL7 Rights to discharge and disolve contracts.pptx
L7 Rights to discharge and disolve contracts.pptx
thắm ngọc
 
Defining Necessity: implied terms revisited
Defining Necessity: implied terms revisitedDefining Necessity: implied terms revisited
Defining Necessity: implied terms revisited
Rachel Tandy
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsSamantha Ip
 
5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions
msstephanielord
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
Robert MacDonald
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introduction
Hafizul Mukhlis
 
Chapter 21 – Performance of Sales Contracts
Chapter 21 – Performance of Sales Contracts Chapter 21 – Performance of Sales Contracts
Chapter 21 – Performance of Sales Contracts UAF_BA330
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
Pang Khai Shuen
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performance
Hafizul Mukhlis
 
The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019
Parsons Behle & Latimer
 

Similar to Determination of building_contracts (20)

Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of Contract
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Construction law lecture 10
Construction law lecture 10Construction law lecture 10
Construction law lecture 10
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
 
VA Sup Ct Opinion 11232016
VA Sup Ct Opinion 11232016VA Sup Ct Opinion 11232016
VA Sup Ct Opinion 11232016
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 
Contract Law II Group Assignment Presentation
Contract Law II Group Assignment PresentationContract Law II Group Assignment Presentation
Contract Law II Group Assignment Presentation
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
L7 Rights to discharge and disolve contracts.pptx
L7 Rights to discharge and disolve contracts.pptxL7 Rights to discharge and disolve contracts.pptx
L7 Rights to discharge and disolve contracts.pptx
 
Defining Necessity: implied terms revisited
Defining Necessity: implied terms revisitedDefining Necessity: implied terms revisited
Defining Necessity: implied terms revisited
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
 
5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions5 a law and ethics discharge of contract, remedies and injunctions
5 a law and ethics discharge of contract, remedies and injunctions
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
Building contract introduction
Building contract  introductionBuilding contract  introduction
Building contract introduction
 
Chapter 21 – Performance of Sales Contracts
Chapter 21 – Performance of Sales Contracts Chapter 21 – Performance of Sales Contracts
Chapter 21 – Performance of Sales Contracts
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performance
 
The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019The Small Business Reorganization Act of 2019
The Small Business Reorganization Act of 2019
 

More from Hafizul Mukhlis

Fe practice 4 collaborative learning among msian students (1)
Fe practice 4 collaborative learning among msian students (1)Fe practice 4 collaborative learning among msian students (1)
Fe practice 4 collaborative learning among msian students (1)
Hafizul Mukhlis
 
Fe practice 3 social networking (1)
Fe practice 3 social networking (1)Fe practice 3 social networking (1)
Fe practice 3 social networking (1)
Hafizul Mukhlis
 
Fe practice 2 coping strat (1)
Fe practice 2 coping strat (1)Fe practice 2 coping strat (1)
Fe practice 2 coping strat (1)
Hafizul Mukhlis
 
Rp sample full text (lily)
Rp sample full text (lily)Rp sample full text (lily)
Rp sample full text (lily)
Hafizul Mukhlis
 
Arrrsa mid sem sample test anxiety
Arrrsa   mid sem sample test anxietyArrrsa   mid sem sample test anxiety
Arrrsa mid sem sample test anxiety
Hafizul Mukhlis
 
Subject verb agreement
Subject verb agreementSubject verb agreement
Subject verb agreement
Hafizul Mukhlis
 
Week 10 abstracts 2
Week 10   abstracts 2Week 10   abstracts 2
Week 10 abstracts 2
Hafizul Mukhlis
 
Week 10 conclusion grammar notes
Week 10 conclusion  grammar notesWeek 10 conclusion  grammar notes
Week 10 conclusion grammar notes
Hafizul Mukhlis
 
Week 10 the conclusion
Week 10 the conclusionWeek 10 the conclusion
Week 10 the conclusion
Hafizul Mukhlis
 
Week 9 writing discussion
Week 9 writing discussionWeek 9 writing discussion
Week 9 writing discussion
Hafizul Mukhlis
 
Week 8 presenting data in charts, graphs, and tables 2
Week 8 presenting data in charts, graphs, and tables 2Week 8 presenting data in charts, graphs, and tables 2
Week 8 presenting data in charts, graphs, and tables 2
Hafizul Mukhlis
 
Week8 writing the results
Week8  writing the resultsWeek8  writing the results
Week8 writing the results
Hafizul Mukhlis
 
Week6 7a- developing a questionnaire
Week6 7a- developing a questionnaireWeek6 7a- developing a questionnaire
Week6 7a- developing a questionnaire
Hafizul Mukhlis
 
Week 6 7c - language in procedures & method
Week 6 7c - language in procedures & methodWeek 6 7c - language in procedures & method
Week 6 7c - language in procedures & method
Hafizul Mukhlis
 
Week5b writing research questions
Week5b   writing research questionsWeek5b   writing research questions
Week5b writing research questions
Hafizul Mukhlis
 
Week5a writing statement of the problem & general purpose 2
Week5a   writing statement of the problem & general purpose 2Week5a   writing statement of the problem & general purpose 2
Week5a writing statement of the problem & general purpose 2
Hafizul Mukhlis
 
Week4g pptslides in text citation- quoting 4
Week4g pptslides   in text citation- quoting 4Week4g pptslides   in text citation- quoting 4
Week4g pptslides in text citation- quoting 4
Hafizul Mukhlis
 
Week4f pptslides in text citation - summarising
Week4f pptslides   in text citation - summarisingWeek4f pptslides   in text citation - summarising
Week4f pptslides in text citation - summarising
Hafizul Mukhlis
 
Week4e pptslides in text citation-synthesizing 2
Week4e pptslides   in text citation-synthesizing 2Week4e pptslides   in text citation-synthesizing 2
Week4e pptslides in text citation-synthesizing 2
Hafizul Mukhlis
 
Week4d pptslides writing with coherence
Week4d pptslides  writing with coherenceWeek4d pptslides  writing with coherence
Week4d pptslides writing with coherence
Hafizul Mukhlis
 

More from Hafizul Mukhlis (20)

Fe practice 4 collaborative learning among msian students (1)
Fe practice 4 collaborative learning among msian students (1)Fe practice 4 collaborative learning among msian students (1)
Fe practice 4 collaborative learning among msian students (1)
 
Fe practice 3 social networking (1)
Fe practice 3 social networking (1)Fe practice 3 social networking (1)
Fe practice 3 social networking (1)
 
Fe practice 2 coping strat (1)
Fe practice 2 coping strat (1)Fe practice 2 coping strat (1)
Fe practice 2 coping strat (1)
 
Rp sample full text (lily)
Rp sample full text (lily)Rp sample full text (lily)
Rp sample full text (lily)
 
Arrrsa mid sem sample test anxiety
Arrrsa   mid sem sample test anxietyArrrsa   mid sem sample test anxiety
Arrrsa mid sem sample test anxiety
 
Subject verb agreement
Subject verb agreementSubject verb agreement
Subject verb agreement
 
Week 10 abstracts 2
Week 10   abstracts 2Week 10   abstracts 2
Week 10 abstracts 2
 
Week 10 conclusion grammar notes
Week 10 conclusion  grammar notesWeek 10 conclusion  grammar notes
Week 10 conclusion grammar notes
 
Week 10 the conclusion
Week 10 the conclusionWeek 10 the conclusion
Week 10 the conclusion
 
Week 9 writing discussion
Week 9 writing discussionWeek 9 writing discussion
Week 9 writing discussion
 
Week 8 presenting data in charts, graphs, and tables 2
Week 8 presenting data in charts, graphs, and tables 2Week 8 presenting data in charts, graphs, and tables 2
Week 8 presenting data in charts, graphs, and tables 2
 
Week8 writing the results
Week8  writing the resultsWeek8  writing the results
Week8 writing the results
 
Week6 7a- developing a questionnaire
Week6 7a- developing a questionnaireWeek6 7a- developing a questionnaire
Week6 7a- developing a questionnaire
 
Week 6 7c - language in procedures & method
Week 6 7c - language in procedures & methodWeek 6 7c - language in procedures & method
Week 6 7c - language in procedures & method
 
Week5b writing research questions
Week5b   writing research questionsWeek5b   writing research questions
Week5b writing research questions
 
Week5a writing statement of the problem & general purpose 2
Week5a   writing statement of the problem & general purpose 2Week5a   writing statement of the problem & general purpose 2
Week5a writing statement of the problem & general purpose 2
 
Week4g pptslides in text citation- quoting 4
Week4g pptslides   in text citation- quoting 4Week4g pptslides   in text citation- quoting 4
Week4g pptslides in text citation- quoting 4
 
Week4f pptslides in text citation - summarising
Week4f pptslides   in text citation - summarisingWeek4f pptslides   in text citation - summarising
Week4f pptslides in text citation - summarising
 
Week4e pptslides in text citation-synthesizing 2
Week4e pptslides   in text citation-synthesizing 2Week4e pptslides   in text citation-synthesizing 2
Week4e pptslides in text citation-synthesizing 2
 
Week4d pptslides writing with coherence
Week4d pptslides  writing with coherenceWeek4d pptslides  writing with coherence
Week4d pptslides writing with coherence
 

Recently uploaded

Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Thomas (Tom) Jasper
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
Finlaw Consultancy Pvt Ltd
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptxPRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
OmGod1
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
BRELGOSIMAT
 
Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
Purushottam Jha
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
AHRP Law Firm
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
shweeta209
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
OmGod1
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
Wendy Couture
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
9ib5wiwt
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
SidharthKashyap5
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
9ib5wiwt
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
BridgeWest.eu
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
KHURRAMWALI
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 

Recently uploaded (20)

Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptxPRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptx
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
 
Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 

Determination of building_contracts

  • 2.  Determination by Employer  Determination by Contractor  Pre-mature determination
  • 3. Pre-mature determination  The main cause for pre-mature determination is frustration  Generally, a ct is frustrated when further performance has become illegal/impossible due to subsequent or supervening event which rendered the contract :  (i) illegal  (ii) impossible  (iii) commercial sterile
  • 4.  A frustration event must be of such a nature as to have been unforeseeable, irresistible and not due to fault of either contractual party.
  • 5. Goh Yew Chew & Anor v Soh Kian Tee The plf entered a ct with the def (contractor) for the construction of two storey shop houses in Malacca. The plf paid $5000 of earnest deposit. The def later discovered that the building could not be completed according to plan because of the proximity to an adjacent house. The plf claimed for the deposit.
  • 6. Federal court: The contractor claimed that the plf can not claim for the deposit as the ct has become frustrated. The ct was not a frustrated contract where a change of circumstances vitiated it, but one which rendered void by initial impossibility. There was no evidence that construction work on the buildings had actually started.
  • 7. Force-majeure  Another circumstances for pre mature determination.  The contract shall be determined if the force majeure event render the contract to become impossible or illegal to perform.  The scope of force majeure includes two other terms: (i) Act of God (ii) Vis major ( Refer to notes on EoT)
  • 8. Commercially Sterile  This circumstances occur when the essential commercial purpose of the contract has become frustrated Bush v Whitehaven Port & Town Trustees The contract was entered by the parties in summer. However, due to some fault of the employer, the performance of the contract was delayed. The delay resulted higher cost as the works had to be extended until winter. The contractor claimed for QM. Held: The contractor is entitled to the QM claim as if there had been frustrated.
  • 9. Determination by the Employer  Clause 25.0 PAM 2006  Cl 25.1-Grounds which give rights to the employer to determine the contract : (a) –(f)
  • 10. Duties of contractors upon of determination of contract by employer  Clause 25.4(a)-(d)
  • 11. Duties of employers upon determination of the contract by them  Clause 25.5-Records of works  Clause 25.6-Final account
  • 12. Determination by Contractors  Clause 26: Contractor may determine his own employment if the employer defaults in any of the following- cl 26.1 (a)- (d)
  • 13.  Duties of contractors - cl 26.4(a) - cl 26.5 - cl 26.6  Duties of employer-cl 26.4(b)
  • 14. Insolvency  Insolvency is a ground for determination of the contract: Insolvency of the contractor- employment of the contractor shall be automatically determine-cl 25.3 Insolvency of the employer- employment of the contractor shall be automatically determine- cl 26.3