The contractor submitted a final claim for a variation order totalling RM55,000 for excavating 100m3 of rock. The original bill of quantities stated 10m3 of rock excavation priced at RM50/m3. However, there was a mistake in the original pricing and the quantity was significantly understated. As such, the quantity surveyor can value the variation using fair market rates to compensate the contractor for additional expenses incurred due to the mistake and change in quantity, as allowed for under the contract terms.