Processplanning
Process planning is concerned with determining the sequence of individual
manufacturing operations needed to produce a given part or product.
The resulting operation sequence is documented on a form typically referred to as
operation sheet/route sheet. The operation sheet is a listing of the production
operations and associated machine tools for a work part or assembly.
Process planning is an important stage of product development since production
tooling like jigs, fixtures, special tools etc. can be designed only after the process is
finalized.
Definition
Process planning is that function within a manufacturing facility, that
establishes which machining process and process parameters are to be
used to convert a work material (blank) from its initial form (raw
material) to a final form defined by an engineering drawing Process.
The process planning activity can be divided into to following steps
• Selection of processes and tools
• Selection of machine tools
• Sequencing the operations
• Grouping of operations
• Selection of work piece holding devices and datum surfaces (Set ups)
• Selection of inspection instruments
• Determination of production tolerances
• Determination of the proper cutting conditions.
• Determination of the cutting times and non-machining Times (setting time, inspection time) for each
operation
Route sheet
Role of Process Planning in CAD/CAM Integration
Computer Aided Process Planning
• Process rationalization and standardisation
• Productivity improvement
• Product cost reduction
• Elimination of human error
• Reduction in time
• Reduced paper work
• Faster response
• Improved legibility
Approaches to CAPP
Types of Approaches
• Variant Approach - Computer search for existing or similar process
plans of similar part families using codes, retrieves and then edit
according to new process sequence.
• Generative Approach - Computer generates new process plan every
time when a new plan is needed.
• Hybrid Approach
Data Input to CAPP
• Generally the geometric model of the part is the input for the process planning
system.
• The input to the process planning system may be engineering drawing or CAD
model.
The other prerequisites for process planning are given below:
- Parts list
- Annual demand/batch size
- Accuracy and surface finish requirement (CAD Database)
- Equipment details (Work centre Database)
- Data on cutting fluids, tools, jigs & fixtures, gauges
- Standard stock sizes
- Machining data, data on handling and setup
Variant or Retrieval Approaches to CAPP
Part
Description GT Code Process Plan
Retrieve/Edit
New
Process Plan
Master Plans
Database
Variant or Retrieval CAPP system
Variant or Retrieval CAPP system
A variant process planning system uses the similarity among Components to retrieve the existing process plans.
A process plan that can be used by a family of components is called a Standard plan. A standard plan is stored
permanently with a family number as its key. A family is represented by a family matrix, which includes all
possible members. The variant process planning system has two operational stages: 1. preparatory stage 2.
Production stage. During the preparatory stage, existing components are coded, classified, and subsequently
grouped into families. The process begins by summarizing process plans already prepared for components in
the family. Standard plans are then stored in a database and indexed by family matrices. The production stage
occurs when the system is ready for production. An incoming part is first coded. The code is then input to a
part family search routine to find the family to which the component belongs. The family number is then used
to retrieve a standard plan. Some other functions, such as parameter selection and standard time calculations,
can also be added to make the system more complete. This system is used in a machine shop that produces a
variety of small components
Advantages of Variant type CAPP
• Once a standard plan has been written, a variety of components can be
planned.
• Comparatively simple programming and installation (compared with
generative systems) is required to implement a planning system.
• The system is understandable, and the planner has control of the final
plan.
• It is easy to learn, and easy to use.
Disadvantages of Variant type CAPP
• The components to be planned are limited to similar components
previously planned.
• Experienced process planners are still required to modify the
standard plan for the specific component.
• Variant planning cannot be used in an entirely automated
manufacturing system, without additional process planning.
Generative Approaches to CAPP
Part
Descriptive
System
New
Process Plan
Process Plan
Logic
Machine
Tool
Cutting
Tool
Jigs &
Fixtures Material
Manufacturing Database
Generative process planning is a system that synthesizes process Information in order to create a process plan
for a new Component automatically. In a generative planning system, process plans are created from
information available in manufacturing database without human intervention. Upon receiving the design
model, the system can generate the required operations and operation sequences for the component.
Knowledge of manufacturing must be captured and encoded into efficient software. By applying decision logic,
a process Planner’s decision making can be imitated. Other planning functions, such as machine selection, tool
selection, process optimization, and so on, can also be automated using generative planning techniques.
The generative planning has the following advantages:
1. It can generate consistent process plans rapidly.
2. New components can- be planned as easily as existing Components.
3. It can be interfaced with an automated manufacturing
Forward planning (Generative)
In generative process planning, when process plans are generated, the
system must define an initial state in order to reach the final state
(goal). The path taken represents the sequence of processes. For
example, the initial state is the raw material and the final state is the
component design. Then a planner works in modifying the raw work
piece until it takes on the final design qualities. This is called forward
planning.
Backward planning (Generative)
Backward planning uses a reverse procedure. Assuming that we have a
finished component, the goal is to go back to the unmachined work
piece. Each machining process is considered a filling process.
For forward planning, we must know the successor surface before
we select a process.
Backward planning eliminates this conditioning Problem since it
begins with the final surfaces and processes are selected to satisfy
the initial requirements.
A-3
Q1. With a neat sketch explain the methodology to be followed in for
developing a retrieval type CAPP system.
Q2.Briefly explain the need for computer aided process planning. Write
any five differences between variant and generative type of computer
aided process planning.

More Related Content

What's hot

COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.pptfahamkhan7
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Bhushan Tawade
 
Layout of FMS
Layout of FMSLayout of FMS
Layout of FMSsgrsoni45
 
Unit 1-automation of assembly lines
Unit 1-automation of assembly linesUnit 1-automation of assembly lines
Unit 1-automation of assembly linesjoemaxagu
 
Computer Integrated Manufacturing
Computer Integrated Manufacturing  Computer Integrated Manufacturing
Computer Integrated Manufacturing suraj_21
 
Group Technology, coding and cell design
Group Technology, coding and cell designGroup Technology, coding and cell design
Group Technology, coding and cell designNauman khan
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planningVenu Yadav
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)KRUNAL RAVAL
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systemschethan kumar
 

What's hot (20)

Group Technology
Group TechnologyGroup Technology
Group Technology
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Flexible manufacturing system
Flexible manufacturing systemFlexible manufacturing system
Flexible manufacturing system
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt
6 CHAPTER SIX - COMPUTER AIDED INSPECTION.ppt
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Capp
CappCapp
Capp
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
 
Computer Aided Process Planning
Computer Aided Process PlanningComputer Aided Process Planning
Computer Aided Process Planning
 
CAPP
CAPPCAPP
CAPP
 
Layout of FMS
Layout of FMSLayout of FMS
Layout of FMS
 
Unit 1-automation of assembly lines
Unit 1-automation of assembly linesUnit 1-automation of assembly lines
Unit 1-automation of assembly lines
 
Computer Integrated Manufacturing
Computer Integrated Manufacturing  Computer Integrated Manufacturing
Computer Integrated Manufacturing
 
Group Technology, coding and cell design
Group Technology, coding and cell designGroup Technology, coding and cell design
Group Technology, coding and cell design
 
Computer integrated production planning
Computer integrated production planningComputer integrated production planning
Computer integrated production planning
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systems
 
Unit 2.1 cim
Unit 2.1 cimUnit 2.1 cim
Unit 2.1 cim
 
Nc part programming
Nc part programmingNc part programming
Nc part programming
 
Cim ppt
Cim pptCim ppt
Cim ppt
 

Similar to Computer aided process planning

Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches chethan kumar
 
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSJyotiraman De
 
Computer Aided Process Planning Poster
Computer Aided Process Planning PosterComputer Aided Process Planning Poster
Computer Aided Process Planning PosterJyotiraman De
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)rajnitj19
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docxprabaharjeevanananda
 
notes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxnotes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxAshok Mannava
 
Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit twoZELALEMGIRMAW
 
introduction to process planning murugananthan
introduction to process planning murugananthanintroduction to process planning murugananthan
introduction to process planning murugananthanMurugananthan K
 
4th unit CADM important questions related to capp and fms etc design processs
4th unit CADM important questions related to capp and fms etc design processs4th unit CADM important questions related to capp and fms etc design processs
4th unit CADM important questions related to capp and fms etc design processsPrudhviRaj667957
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniquesMohamad Sahiedan
 
CAPP , JIT, FMS
CAPP , JIT, FMSCAPP , JIT, FMS
CAPP , JIT, FMSDenny John
 

Similar to Computer aided process planning (20)

Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches
 
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
 
M-2_CAPP.pptx
M-2_CAPP.pptxM-2_CAPP.pptx
M-2_CAPP.pptx
 
Computer Aided Process Planning Poster
Computer Aided Process Planning PosterComputer Aided Process Planning Poster
Computer Aided Process Planning Poster
 
CIM MODULE 2.pptx
CIM MODULE 2.pptxCIM MODULE 2.pptx
CIM MODULE 2.pptx
 
TEST 2.pptx
TEST 2.pptxTEST 2.pptx
TEST 2.pptx
 
TEST 2.pdf
TEST 2.pdfTEST 2.pdf
TEST 2.pdf
 
Unit 2 cim
Unit 2 cimUnit 2 cim
Unit 2 cim
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx
 
notes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxnotes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptx
 
CIM unit-2
CIM unit-2CIM unit-2
CIM unit-2
 
Unit 2
Unit 2Unit 2
Unit 2
 
Capp
CappCapp
Capp
 
Me6703 cim systems
Me6703 cim systemsMe6703 cim systems
Me6703 cim systems
 
Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit two
 
introduction to process planning murugananthan
introduction to process planning murugananthanintroduction to process planning murugananthan
introduction to process planning murugananthan
 
4th unit CADM important questions related to capp and fms etc design processs
4th unit CADM important questions related to capp and fms etc design processs4th unit CADM important questions related to capp and fms etc design processs
4th unit CADM important questions related to capp and fms etc design processs
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
 
CAPP , JIT, FMS
CAPP , JIT, FMSCAPP , JIT, FMS
CAPP , JIT, FMS
 

More from sushma chinta

programming for programs solving using C language
programming for  programs solving using C languageprogramming for  programs solving using C language
programming for programs solving using C languagesushma chinta
 
Programming languages
Programming languages Programming languages
Programming languages sushma chinta
 
Shear stresses in beams p
Shear stresses in beams pShear stresses in beams p
Shear stresses in beams psushma chinta
 
Overhanged Beam and Cantilever beam problems
Overhanged Beam and Cantilever beam problemsOverhanged Beam and Cantilever beam problems
Overhanged Beam and Cantilever beam problemssushma chinta
 
Problems on simply supported beams (udl , uvl and couple)
Problems on simply supported beams (udl , uvl and couple)Problems on simply supported beams (udl , uvl and couple)
Problems on simply supported beams (udl , uvl and couple)sushma chinta
 
Problems on simply supported beams
Problems on simply supported beamsProblems on simply supported beams
Problems on simply supported beamssushma chinta
 
Shear force and bending moment diagram for simply supported beam _1P
Shear force and bending moment diagram for simply supported beam _1PShear force and bending moment diagram for simply supported beam _1P
Shear force and bending moment diagram for simply supported beam _1Psushma chinta
 
Relation between load shear force and bending moment of beams
Relation between load shear force and bending moment of  beamsRelation between load shear force and bending moment of  beams
Relation between load shear force and bending moment of beamssushma chinta
 
Simple torsion equation
Simple torsion equationSimple torsion equation
Simple torsion equationsushma chinta
 
Problems on triaxial loading and stresses on inclined planes for uniaxial and...
Problems on triaxial loading and stresses on inclined planes for uniaxial and...Problems on triaxial loading and stresses on inclined planes for uniaxial and...
Problems on triaxial loading and stresses on inclined planes for uniaxial and...sushma chinta
 
Bars with variable cross sections subjected to axial loads 2
Bars with variable cross sections subjected to axial loads 2Bars with variable cross sections subjected to axial loads 2
Bars with variable cross sections subjected to axial loads 2sushma chinta
 
Bars with variable cross sections subjected to axial loads
Bars with variable cross sections subjected to axial loadsBars with variable cross sections subjected to axial loads
Bars with variable cross sections subjected to axial loadssushma chinta
 
Bars subjected to multiple loads
Bars subjected to multiple loadsBars subjected to multiple loads
Bars subjected to multiple loadssushma chinta
 
20 08 2020stress_straincurve_p
20 08 2020stress_straincurve_p20 08 2020stress_straincurve_p
20 08 2020stress_straincurve_psushma chinta
 
Stresses and strains p
Stresses and strains pStresses and strains p
Stresses and strains psushma chinta
 

More from sushma chinta (20)

programming for programs solving using C language
programming for  programs solving using C languageprogramming for  programs solving using C language
programming for programs solving using C language
 
Programming languages
Programming languages Programming languages
Programming languages
 
Thick cylinders
Thick cylinders Thick cylinders
Thick cylinders
 
Shear stresses in beams p
Shear stresses in beams pShear stresses in beams p
Shear stresses in beams p
 
Problems on Torsion
Problems on TorsionProblems on Torsion
Problems on Torsion
 
Overhanged Beam and Cantilever beam problems
Overhanged Beam and Cantilever beam problemsOverhanged Beam and Cantilever beam problems
Overhanged Beam and Cantilever beam problems
 
Problems on simply supported beams (udl , uvl and couple)
Problems on simply supported beams (udl , uvl and couple)Problems on simply supported beams (udl , uvl and couple)
Problems on simply supported beams (udl , uvl and couple)
 
Problems on simply supported beams
Problems on simply supported beamsProblems on simply supported beams
Problems on simply supported beams
 
Shear force and bending moment diagram for simply supported beam _1P
Shear force and bending moment diagram for simply supported beam _1PShear force and bending moment diagram for simply supported beam _1P
Shear force and bending moment diagram for simply supported beam _1P
 
Relation between load shear force and bending moment of beams
Relation between load shear force and bending moment of  beamsRelation between load shear force and bending moment of  beams
Relation between load shear force and bending moment of beams
 
Beams Introduction
Beams IntroductionBeams Introduction
Beams Introduction
 
Simple torsion equation
Simple torsion equationSimple torsion equation
Simple torsion equation
 
Problems on triaxial loading and stresses on inclined planes for uniaxial and...
Problems on triaxial loading and stresses on inclined planes for uniaxial and...Problems on triaxial loading and stresses on inclined planes for uniaxial and...
Problems on triaxial loading and stresses on inclined planes for uniaxial and...
 
Bars with variable cross sections subjected to axial loads 2
Bars with variable cross sections subjected to axial loads 2Bars with variable cross sections subjected to axial loads 2
Bars with variable cross sections subjected to axial loads 2
 
Bars with variable cross sections subjected to axial loads
Bars with variable cross sections subjected to axial loadsBars with variable cross sections subjected to axial loads
Bars with variable cross sections subjected to axial loads
 
Bars subjected to multiple loads
Bars subjected to multiple loadsBars subjected to multiple loads
Bars subjected to multiple loads
 
20 08 2020stress_straincurve_p
20 08 2020stress_straincurve_p20 08 2020stress_straincurve_p
20 08 2020stress_straincurve_p
 
Stresses and strains p
Stresses and strains pStresses and strains p
Stresses and strains p
 
Mom introduction p
Mom introduction pMom introduction p
Mom introduction p
 
Mechanical Members
Mechanical MembersMechanical Members
Mechanical Members
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 

Computer aided process planning

  • 2. Processplanning Process planning is concerned with determining the sequence of individual manufacturing operations needed to produce a given part or product. The resulting operation sequence is documented on a form typically referred to as operation sheet/route sheet. The operation sheet is a listing of the production operations and associated machine tools for a work part or assembly. Process planning is an important stage of product development since production tooling like jigs, fixtures, special tools etc. can be designed only after the process is finalized.
  • 3. Definition Process planning is that function within a manufacturing facility, that establishes which machining process and process parameters are to be used to convert a work material (blank) from its initial form (raw material) to a final form defined by an engineering drawing Process.
  • 4. The process planning activity can be divided into to following steps • Selection of processes and tools • Selection of machine tools • Sequencing the operations • Grouping of operations • Selection of work piece holding devices and datum surfaces (Set ups) • Selection of inspection instruments • Determination of production tolerances • Determination of the proper cutting conditions. • Determination of the cutting times and non-machining Times (setting time, inspection time) for each operation
  • 6. Role of Process Planning in CAD/CAM Integration
  • 7. Computer Aided Process Planning • Process rationalization and standardisation • Productivity improvement • Product cost reduction • Elimination of human error • Reduction in time • Reduced paper work • Faster response • Improved legibility
  • 8. Approaches to CAPP Types of Approaches • Variant Approach - Computer search for existing or similar process plans of similar part families using codes, retrieves and then edit according to new process sequence. • Generative Approach - Computer generates new process plan every time when a new plan is needed. • Hybrid Approach
  • 9. Data Input to CAPP • Generally the geometric model of the part is the input for the process planning system. • The input to the process planning system may be engineering drawing or CAD model. The other prerequisites for process planning are given below: - Parts list - Annual demand/batch size - Accuracy and surface finish requirement (CAD Database) - Equipment details (Work centre Database) - Data on cutting fluids, tools, jigs & fixtures, gauges - Standard stock sizes - Machining data, data on handling and setup
  • 10. Variant or Retrieval Approaches to CAPP Part Description GT Code Process Plan Retrieve/Edit New Process Plan Master Plans Database
  • 11. Variant or Retrieval CAPP system
  • 12. Variant or Retrieval CAPP system A variant process planning system uses the similarity among Components to retrieve the existing process plans. A process plan that can be used by a family of components is called a Standard plan. A standard plan is stored permanently with a family number as its key. A family is represented by a family matrix, which includes all possible members. The variant process planning system has two operational stages: 1. preparatory stage 2. Production stage. During the preparatory stage, existing components are coded, classified, and subsequently grouped into families. The process begins by summarizing process plans already prepared for components in the family. Standard plans are then stored in a database and indexed by family matrices. The production stage occurs when the system is ready for production. An incoming part is first coded. The code is then input to a part family search routine to find the family to which the component belongs. The family number is then used to retrieve a standard plan. Some other functions, such as parameter selection and standard time calculations, can also be added to make the system more complete. This system is used in a machine shop that produces a variety of small components
  • 13. Advantages of Variant type CAPP • Once a standard plan has been written, a variety of components can be planned. • Comparatively simple programming and installation (compared with generative systems) is required to implement a planning system. • The system is understandable, and the planner has control of the final plan. • It is easy to learn, and easy to use.
  • 14. Disadvantages of Variant type CAPP • The components to be planned are limited to similar components previously planned. • Experienced process planners are still required to modify the standard plan for the specific component. • Variant planning cannot be used in an entirely automated manufacturing system, without additional process planning.
  • 15. Generative Approaches to CAPP Part Descriptive System New Process Plan Process Plan Logic Machine Tool Cutting Tool Jigs & Fixtures Material Manufacturing Database
  • 16. Generative process planning is a system that synthesizes process Information in order to create a process plan for a new Component automatically. In a generative planning system, process plans are created from information available in manufacturing database without human intervention. Upon receiving the design model, the system can generate the required operations and operation sequences for the component. Knowledge of manufacturing must be captured and encoded into efficient software. By applying decision logic, a process Planner’s decision making can be imitated. Other planning functions, such as machine selection, tool selection, process optimization, and so on, can also be automated using generative planning techniques. The generative planning has the following advantages: 1. It can generate consistent process plans rapidly. 2. New components can- be planned as easily as existing Components. 3. It can be interfaced with an automated manufacturing
  • 17. Forward planning (Generative) In generative process planning, when process plans are generated, the system must define an initial state in order to reach the final state (goal). The path taken represents the sequence of processes. For example, the initial state is the raw material and the final state is the component design. Then a planner works in modifying the raw work piece until it takes on the final design qualities. This is called forward planning.
  • 18. Backward planning (Generative) Backward planning uses a reverse procedure. Assuming that we have a finished component, the goal is to go back to the unmachined work piece. Each machining process is considered a filling process.
  • 19. For forward planning, we must know the successor surface before we select a process. Backward planning eliminates this conditioning Problem since it begins with the final surfaces and processes are selected to satisfy the initial requirements.