SlideShare a Scribd company logo
1 of 51
PROCESS PLANNING
Process planning is defined as conversion of design data to
work instruction
Process planning is defined as systematic determination of methods by
which a product is to be manufactured economically and competitively.
It consists of
Devising (arrange),
Selecting
Specifying process
machine tools
to convert raw material to finished products
Process planning is also called:
manufacturing planning,
material processing,
machine routing.
PROCESS
PLAN
Process plan is also called
as operation sheet
route sheet
The detailed plan contains:
Route (printed sheet)
Processes (welding , drilling , milling , lathe operations,
etc.,) process parameters
machine and tool selections
(lathe, shaping m/c & drill bit, single point tool
etc.,) Fixtures (milling fixture , drilling fixture)
Machining time
Detail of how the plan is depends on the application.
Operation Plan sequence & Summary of a process plan.
PROCESS
PLANNING
Design Machine
Tool
Process
Planning
Scheduling and Production Control
Concept of Process Planning
Product design
(specifications, requirements)
Process,
Process planning machine
knowledge
Operation programming
(suitable process such as grinding , welding,
milling, heat treatment process)
Verification
(make buy decisions)
Scheduling
Scheduling
(Rout sheet)
knowledge
Execution
Detailed Process Plan
Process Planning Activities
Analyse (Part ,dimension requirements) [DRAWING INTERPRETATION]
Determine (operation sequence) [MATERIAL EVALUATION AND PROCESS SELECTION]
Select (equipment ) [SELECTION OF MACHINES . TOOLING and WORK HOLDING DEVICE]
Calculate (processing times ) [SETTING PROCESS PARAMETERS]
Select (QA/Inspection methods) [SELECTING QUALITY ASSURANCE METHOD]
Estimate (manufacturing cost) [COST ESTIMATING]
Document (Process Plan ) [PREPARING PROCESS PLANNING DOCUMENTATION]
Communicate (manufacturing Engineer with shop floor)
• Aim and Objectives
Identify appropriate
Supplementary
the drawing to aid the process
Identify and interpret dimensional information from
the drawing
Identify and interpret geometric information from the
drawing
Identify the critical processing factors for the
component from the dimensional and geometric
information from the drawing
tati
Information from
• Types of Drawing
Detail drawing
I. Single part drawing
II. Collective drawing
Assembly drawing
I. Single assembly drawing
II. Collective assembly drawing
Combined drawing
Ex: Single part drawing
 Single-part drawings are workshop drawings that
show the fabrication information for one part
(usually without welds).
 Single-part drawings usually use small sheet sizes.
Collective Drawings:
• A similar parts or assembly are collected together in
one common document.
 Each item or assembly will be given with drawing
number or code number for identification.
 Assembly drawings can be used to represent items
that consist of more than one component.
 Assembly drawings may include instructions, lists
of the component parts, reference numbers, and
references to detail drawings or shop drawings, and
specification information.
Assembly Drawing
Combined Drawing
• It is sometimes convenient to illustrate details with
their assembly drawing on the same sheet.
• It not only reduces the actual number of drawings
Part drawing
• Shape
FACTORS AFFECTING
PROCESS
PLAN SELECTION
• Tolerance
• Surface finish
• Size
• Material type
• Quantity
• Value of the product
• Urgency
• Manufacturing system itself
• etc.
MATERIAL EVALUATION
• IMPORTANT FACTORS
Product design must meet the specified need
Materials with appropriate properties must be
selected
 Suitable manufacturing process must be
selected the response of the material during
manufacture and its service
MATERIAL EVALUATION
AIM and OBJECTIVES
 Identify and specify common material used
for manufacture
 Identify and specify the main properties of the material
Identify and specify the common material selection
process
 Identify and specify the common process used
for manufacture
 Carryout an overall evaluation of the selection of
materials for manufacture in terms of processes
 Select the suitable process for given product based on
critical processing factors identified during the
drawing interpretation
MATERIAL EVALUATION
Type of material
MATERIAL EVALUATION
Material Properties
MATERIAL EVALUATION
Types of metal
PROCESS PLANNING APPROACHES
MANUAL
COMPUTER-AIDED
VARIANT (Retrieval/Recovery)
GT based
Computer aids for editing
Parameters selection
GENERATIVE (Reproductive)
Some kind of decision logic
Decision tree/table
Artificial Intelligence
Objective-Oriented
Still experience based
REQUIREMENTS IN MANUAL
PROCESS PLANNING
 Ability to interpret an engineering drawing.
• Familiar with manufacturing processes and practice.
• Familiar with tooling and fixtures.
• Know what resources are available in the shop.
• Know how to use reference books, such
as machinability data handbook.
• Able to do computations on machining time and cost.
• Familiar with the raw materials.
• Know the relative costs of processes, tooling,
and raw materials.
MANUAL PROCESS PLANNING STEPS
• Study the overall shape of the part.
• Use this information to classify the part and determine the
type of workstation needed.
• Thoroughly study the drawing. Try to identify every
manufacturing features and notes.
• If raw stock is not given, determine the best raw material
shape to use.
• Identify datum surfaces. Use information on datum
surfaces to determine the setups.
• Select machines for each setup.
• For each setup determine the rough sequence of
operations necessary to create all the features.
MANUAL PROCESS PLANNING STEPS
• Sequence the operations determined in the
previous step.
• Select tools for each operation.
• Try to use the same tool for several operations if it is
possible.
• Keep in mind the trade off on tool change time and
estimated machining time.
• Select or design fixtures for each setup.
• Evaluate the plan generate thus far and make
necessary modifications.
• Select cutting parameters for each operation.
• Prepare the final process plan document.
COMPUTER-AIDED
PROCESS PLANNING
ADVANTAGES
1. It can reduce the skill required of a planner.
2. It can reduce the process planning time.
3. It can reduce both process planning and
manufacturing cost.
4. It can create more consistent plans.
5. It can produce more accurate plans.
6. It can increase productivity.
Variant Process Planning
PROCESS
PLANNING
Design Machining features
 Workpiece Selection
 Process Selection
 Tool Selection
 Feed, Speed Selection
 Operation Sequencing Setup
 Planning Fixturing
 Planning Part Programming
PROBLEMS ASSOCIATED WITH
THE VARIANT APPROACH
1. The components to be planned are limited to similar
components previously planned.
2. Experienced process planners are still required to
modify the standard plan for the specific component.
3. Details of the plan cannot be generated.
4. Variant planning cannot be used in an entirely
automated manufacturing system, without additional
process planning.
ADVANTAGES OF THE
VARIANT APPROACH
1. Once a standard plan has been written, a variety
of components can be planned.
2. Comparatively simple programming and installation
(compared with generative systems) is required to
implement a planning system.
3. The system is understandable, and the planner has
control of the final plan.
4. It is easy to learn, and easy to use.
GENERATIVE APPROACH
A system which automatically synthesizes a process
Plan for a new component.
MAJOR COMPONENTS:
(i) part description
(ii) manufacturing databases
(iii) decision making logic and algorithms
ADVANTAGES OF THE
GENERATIVE APPROACH
1. Generate consistent process plans rapidly;
2. New components can be planned as easily
as existing components;
3. It has potential for integrating with an
automated manufacturing facility to provide
detailed control information.
Benefits of CAPP(Computer aided process planning)
1. Process rationalization and standardization:
 CAPP leads to more logical and consistent/Stable process
plans than manual process planning.
2. Productivity improvement:
 As a result of standard process plan, the productivity is
improved (due to more efficient utilization of resources such
as machines, tooling, stock material and labour).
3. Product cost reduction:
 Standard plans tend to result in lower manufacturing costs
and higher product quality.
4. Elimination of human error
General steps involved in CAPP
 Design input, Material selection,Process selection
 Process sequencing, Machine and tool selection
 Intermediate surface determination, Fixture selection
 Machining parameter selection,Cost/time estimation
 Plan preparation, Mc tape image generation
 These are the general steps involved in the computer aided
process planning
Dis Advantages
 While compared with manual process planning the CAPP
systems have few dis Advantages:
 The inability to show special manufacturing techniques.
 The initial cost of establishing a CAPP system
Is high while compared with manual process planning.
Review of CAPP
MATERIAL EVALUATION
 Selection of material has become complicated by the great
increase not only in the kinds of materials but also in the
various forms in which any one material may be available.
 Material should be of right quality and chemical composition
as per the product specifications.
 Shape and size of material should restrict the scrap (i.e.,
material removed for getting the product shape).
Bill of Material
 Bill of material is a means of determining, purchasing and
production order requirements.
 It should indicate if the part is to be manufactured or
purchased.
 The production control department uses the bill of material to
determine manufacturing and scheduling dates.
 Process engineering uses it as a checklist to complete their
work
The information usually required on the bill of material
1. The product name.
2. Product code identification.
3. Sheet number.
4. Use.
5. Date of preparation.
6. Name/initials of preparer.
7. Name/initials of checker.
8. Item numbers.
9. Make/purchase designations.
10. Subassembly part numbers and names.
11. Quantity requirements, and
12. Material used in each part.
Selection of “jigs, fixtures and other special attachments”
These supporting devices are necessary
• To give higher production rate.
• To reduce cost of production per piece.
Selection of “cutting tools and inspection gauges”
They, respectively, are necessary to
• Reduce production time.
• Inspect accurately and at a faster rate.
Tools, jigs and fixture requirements
The tools requirements is worked out considering the following:
1. Number of tools already available.
2. Number of new tools required.
3. Time required for designing the new tools.
4. Taking (make or buy) decision for new tools.
5. Finding out when the new tools will be ready for use.
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx

More Related Content

Similar to 1-unit(Introduction to process planning)-converted.docx

Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit twoZELALEMGIRMAW
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
notes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxnotes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxAshok Mannava
 
Product and process planning
Product and process planningProduct and process planning
Product and process planningzimbar
 
PPCE notes PPT (1).pdf
PPCE notes PPT (1).pdfPPCE notes PPT (1).pdf
PPCE notes PPT (1).pdfmani617576
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxmurugarajan001
 
Process Planning
Process PlanningProcess Planning
Process PlanningGuhan M
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches chethan kumar
 
Product service -profiling
Product service -profilingProduct service -profiling
Product service -profilingMeenakshi Singh
 
Product planning and product control
Product planning and product controlProduct planning and product control
Product planning and product controlMohanKirthik
 
Group Technology
Group TechnologyGroup Technology
Group Technologysgrsoni45
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................4PS19AU411SyedaSoubi
 

Similar to 1-unit(Introduction to process planning)-converted.docx (20)

Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit two
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
notes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptxnotes_9 Lec PP and CAPP.pptx
notes_9 Lec PP and CAPP.pptx
 
Product and process planning
Product and process planningProduct and process planning
Product and process planning
 
PPCE notes PPT (1).pdf
PPCE notes PPT (1).pdfPPCE notes PPT (1).pdf
PPCE notes PPT (1).pdf
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptx
 
Process Planning
Process PlanningProcess Planning
Process Planning
 
Unit 2 cim
Unit 2 cimUnit 2 cim
Unit 2 cim
 
Dfma
DfmaDfma
Dfma
 
Process planning
Process planningProcess planning
Process planning
 
Processs planning
Processs planningProcesss planning
Processs planning
 
UNIT 1 PPCE.ppt
UNIT 1 PPCE.pptUNIT 1 PPCE.ppt
UNIT 1 PPCE.ppt
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches
 
Product service -profiling
Product service -profilingProduct service -profiling
Product service -profiling
 
Product planning and product control
Product planning and product controlProduct planning and product control
Product planning and product control
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
CIM MODULE 2.pptx
CIM MODULE 2.pptxCIM MODULE 2.pptx
CIM MODULE 2.pptx
 
Process planning
Process planningProcess planning
Process planning
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................
 
Me6703 cim systems
Me6703 cim systemsMe6703 cim systems
Me6703 cim systems
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

1-unit(Introduction to process planning)-converted.docx

  • 1. PROCESS PLANNING Process planning is defined as conversion of design data to work instruction Process planning is defined as systematic determination of methods by which a product is to be manufactured economically and competitively. It consists of Devising (arrange), Selecting Specifying process machine tools to convert raw material to finished products Process planning is also called: manufacturing planning, material processing, machine routing.
  • 2. PROCESS PLAN Process plan is also called as operation sheet route sheet The detailed plan contains: Route (printed sheet) Processes (welding , drilling , milling , lathe operations, etc.,) process parameters machine and tool selections (lathe, shaping m/c & drill bit, single point tool etc.,) Fixtures (milling fixture , drilling fixture) Machining time Detail of how the plan is depends on the application. Operation Plan sequence & Summary of a process plan.
  • 4. Concept of Process Planning Product design (specifications, requirements) Process, Process planning machine knowledge Operation programming (suitable process such as grinding , welding, milling, heat treatment process) Verification (make buy decisions) Scheduling Scheduling (Rout sheet) knowledge Execution
  • 6. Process Planning Activities Analyse (Part ,dimension requirements) [DRAWING INTERPRETATION] Determine (operation sequence) [MATERIAL EVALUATION AND PROCESS SELECTION] Select (equipment ) [SELECTION OF MACHINES . TOOLING and WORK HOLDING DEVICE] Calculate (processing times ) [SETTING PROCESS PARAMETERS] Select (QA/Inspection methods) [SELECTING QUALITY ASSURANCE METHOD] Estimate (manufacturing cost) [COST ESTIMATING] Document (Process Plan ) [PREPARING PROCESS PLANNING DOCUMENTATION] Communicate (manufacturing Engineer with shop floor)
  • 7. • Aim and Objectives Identify appropriate Supplementary the drawing to aid the process Identify and interpret dimensional information from the drawing Identify and interpret geometric information from the drawing Identify the critical processing factors for the component from the dimensional and geometric information from the drawing tati Information from
  • 8. • Types of Drawing Detail drawing I. Single part drawing II. Collective drawing Assembly drawing I. Single assembly drawing II. Collective assembly drawing Combined drawing
  • 9. Ex: Single part drawing
  • 10.  Single-part drawings are workshop drawings that show the fabrication information for one part (usually without welds).  Single-part drawings usually use small sheet sizes.
  • 11. Collective Drawings: • A similar parts or assembly are collected together in one common document.  Each item or assembly will be given with drawing number or code number for identification.
  • 12.
  • 13.  Assembly drawings can be used to represent items that consist of more than one component.  Assembly drawings may include instructions, lists of the component parts, reference numbers, and references to detail drawings or shop drawings, and specification information.
  • 15. Combined Drawing • It is sometimes convenient to illustrate details with their assembly drawing on the same sheet. • It not only reduces the actual number of drawings
  • 17. • Shape FACTORS AFFECTING PROCESS PLAN SELECTION • Tolerance • Surface finish • Size • Material type • Quantity • Value of the product • Urgency • Manufacturing system itself • etc.
  • 18. MATERIAL EVALUATION • IMPORTANT FACTORS Product design must meet the specified need Materials with appropriate properties must be selected  Suitable manufacturing process must be selected the response of the material during manufacture and its service
  • 19. MATERIAL EVALUATION AIM and OBJECTIVES  Identify and specify common material used for manufacture  Identify and specify the main properties of the material Identify and specify the common material selection process  Identify and specify the common process used for manufacture  Carryout an overall evaluation of the selection of materials for manufacture in terms of processes  Select the suitable process for given product based on critical processing factors identified during the drawing interpretation
  • 23. PROCESS PLANNING APPROACHES MANUAL COMPUTER-AIDED VARIANT (Retrieval/Recovery) GT based Computer aids for editing Parameters selection GENERATIVE (Reproductive) Some kind of decision logic Decision tree/table Artificial Intelligence Objective-Oriented Still experience based
  • 24. REQUIREMENTS IN MANUAL PROCESS PLANNING  Ability to interpret an engineering drawing. • Familiar with manufacturing processes and practice. • Familiar with tooling and fixtures. • Know what resources are available in the shop. • Know how to use reference books, such as machinability data handbook. • Able to do computations on machining time and cost. • Familiar with the raw materials. • Know the relative costs of processes, tooling, and raw materials.
  • 25. MANUAL PROCESS PLANNING STEPS • Study the overall shape of the part. • Use this information to classify the part and determine the type of workstation needed. • Thoroughly study the drawing. Try to identify every manufacturing features and notes. • If raw stock is not given, determine the best raw material shape to use. • Identify datum surfaces. Use information on datum surfaces to determine the setups. • Select machines for each setup. • For each setup determine the rough sequence of operations necessary to create all the features.
  • 26. MANUAL PROCESS PLANNING STEPS • Sequence the operations determined in the previous step. • Select tools for each operation. • Try to use the same tool for several operations if it is possible. • Keep in mind the trade off on tool change time and estimated machining time. • Select or design fixtures for each setup. • Evaluate the plan generate thus far and make necessary modifications. • Select cutting parameters for each operation. • Prepare the final process plan document.
  • 27. COMPUTER-AIDED PROCESS PLANNING ADVANTAGES 1. It can reduce the skill required of a planner. 2. It can reduce the process planning time. 3. It can reduce both process planning and manufacturing cost. 4. It can create more consistent plans. 5. It can produce more accurate plans. 6. It can increase productivity.
  • 29. PROCESS PLANNING Design Machining features  Workpiece Selection  Process Selection  Tool Selection  Feed, Speed Selection  Operation Sequencing Setup  Planning Fixturing  Planning Part Programming
  • 30. PROBLEMS ASSOCIATED WITH THE VARIANT APPROACH 1. The components to be planned are limited to similar components previously planned. 2. Experienced process planners are still required to modify the standard plan for the specific component. 3. Details of the plan cannot be generated. 4. Variant planning cannot be used in an entirely automated manufacturing system, without additional process planning.
  • 31. ADVANTAGES OF THE VARIANT APPROACH 1. Once a standard plan has been written, a variety of components can be planned. 2. Comparatively simple programming and installation (compared with generative systems) is required to implement a planning system. 3. The system is understandable, and the planner has control of the final plan. 4. It is easy to learn, and easy to use.
  • 32. GENERATIVE APPROACH A system which automatically synthesizes a process Plan for a new component. MAJOR COMPONENTS: (i) part description (ii) manufacturing databases (iii) decision making logic and algorithms
  • 33. ADVANTAGES OF THE GENERATIVE APPROACH 1. Generate consistent process plans rapidly; 2. New components can be planned as easily as existing components; 3. It has potential for integrating with an automated manufacturing facility to provide detailed control information.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39. Benefits of CAPP(Computer aided process planning) 1. Process rationalization and standardization:  CAPP leads to more logical and consistent/Stable process plans than manual process planning. 2. Productivity improvement:  As a result of standard process plan, the productivity is improved (due to more efficient utilization of resources such as machines, tooling, stock material and labour). 3. Product cost reduction:  Standard plans tend to result in lower manufacturing costs and higher product quality. 4. Elimination of human error
  • 40.
  • 41. General steps involved in CAPP  Design input, Material selection,Process selection  Process sequencing, Machine and tool selection  Intermediate surface determination, Fixture selection  Machining parameter selection,Cost/time estimation  Plan preparation, Mc tape image generation  These are the general steps involved in the computer aided process planning
  • 42. Dis Advantages  While compared with manual process planning the CAPP systems have few dis Advantages:  The inability to show special manufacturing techniques.  The initial cost of establishing a CAPP system Is high while compared with manual process planning.
  • 44. MATERIAL EVALUATION  Selection of material has become complicated by the great increase not only in the kinds of materials but also in the various forms in which any one material may be available.  Material should be of right quality and chemical composition as per the product specifications.  Shape and size of material should restrict the scrap (i.e., material removed for getting the product shape).
  • 45. Bill of Material  Bill of material is a means of determining, purchasing and production order requirements.  It should indicate if the part is to be manufactured or purchased.  The production control department uses the bill of material to determine manufacturing and scheduling dates.  Process engineering uses it as a checklist to complete their work
  • 46. The information usually required on the bill of material 1. The product name. 2. Product code identification. 3. Sheet number. 4. Use. 5. Date of preparation. 6. Name/initials of preparer. 7. Name/initials of checker. 8. Item numbers. 9. Make/purchase designations. 10. Subassembly part numbers and names. 11. Quantity requirements, and 12. Material used in each part.
  • 47.
  • 48. Selection of “jigs, fixtures and other special attachments” These supporting devices are necessary • To give higher production rate. • To reduce cost of production per piece. Selection of “cutting tools and inspection gauges” They, respectively, are necessary to • Reduce production time. • Inspect accurately and at a faster rate.
  • 49. Tools, jigs and fixture requirements The tools requirements is worked out considering the following: 1. Number of tools already available. 2. Number of new tools required. 3. Time required for designing the new tools. 4. Taking (make or buy) decision for new tools. 5. Finding out when the new tools will be ready for use.