Well Foundations
( Caissons )
 Well foundations are being used in India from
very early days.
 Taj Mahal was built on such foundations.
 Wells are classified as deep foundations.
 The main difference between a well and a pile
foundation:
 Pile is flexible like a beam under horizontal
loads
 well undergoes rigid body movement under
such loads
Wells have different shapes and
accordingly they are named as
( According to shape in plan)
• Circular Wells
• Dumb bell
• Double-D Wells
• Double Octagonal Wells
• Single and Double Rectangular Wells
• Multiple Dredged Holed Wells
( According to Material Used for Construction)
• Wood
• Steel
• Reinforced Concrete
Classification according to shape in cross section
Classification according to cutting edge type
• Large diameter, can be extended up to large depths.
• Similar to piles, but shorter
• If large bearing capacity soil (rock) is between 3-7 m, it can be
very effective
• If loads are not too large, but the upper 3-7 m of the soil is not
appropriate, can be applied effectively
• Cost of Construction is relatively less on bed level or lower
side.
• Since the placing of concrete is done for concrete seal
under water, it may not be satisfactory.
• If any obstruction of boulders or logs are encountered,
then progress of work becomes slow.
• Through cleaning and inspection at the bottom of
caisson is very difficult and hence not possible.
• The help of divers may be required for excavation near
haunches at the cutting edges.
The various component of
a well foundations are
1. Cutting Edge
2. Well Curb
3. Bottom Plug
4. Steining
5. Top Plug
6. Well Cap
Open Caisson
Cutting Edge:
• Sharp edge which is provided at the lower end of the
well or open and pneumatic caisson for accelerating
sinking operation is called cutting edge. It is made up
steel or it is made in R.C.C. Its angle to vertical is 30 0
and normally slope of 1 horizontal to 2 vertical given
better result.
• In concrete caissons, the lower part of the cutting
edge is rigidly fastened with 12 mm steel plates.
• The cutting edge should be sharp so as to penetrate
into the soil and it should resist the various stresses
caused by blows, boulders, blasting, etc.
• A sharp vertical edge is generally provided to the
outside face of the caisson. Edge facilities the rate of
sinking.
Well Curbs
• It is made of concrete or brick.
• Cutting edge of well or caisson is attached to well
curb.
• During sinking operation well curb impart to the
well steining and facilities the formation of bottom
Bottom Plug
• After final grounding of
the well to the required
foundation level, a
concrete plug is provided.
• The bottom plug transfer the
entire load to the ground.
• The bottom plug functions
as an inverted dome
supported along the periphery
of the steining.
• As it is not feasible to
provide reinforcement at the
bottom, it is generally made
thick and a rich concrete
mix (M20) is used.
Sand Filling
The bottom plug concrete is
cured and after curing, the well is
filled with sand in saturated
condition. Sand filling provides
1. Stability to the bottom of the well.
2. Eliminate the tensile forces at the
base
3. Cancels hoop stresses steining
induced in
Steining
• Steining is constructed in concrete or
masonry work.
• Use of steining is to provide dead load
during sinking operation.
Topping
• Covering provided over the well or caisson
is called as topping.
• Sand is filled in between topping and
bottom plug. Topping also acts as a part of
shuttering for laying the well cap.
Top Plug• The top plug is provided
after the filling is
completed.
• Top plug helps in transferring
the load of the pier and
superstructure to the
steining.
• The thickness of the top
plug is generally kept
greater than 50 % of the smaller
dimension of the dredge hole.
• If sand filling is used, the top
plug is simply constructed using
PCC of 1:2:4 otherwise it is
reinforced with steel bars and
lean concrete of 1:3:6 is used.
Well Cap
• As the shape of the well pier and cap are different, the
well cap forms an interim (acting) layer to accommodate
the pier.
• The well cap is so designed that the base of the pier is
provided with aminimum all round offset.
• The centre of the well cap is made to
coincide with that of the pier and not with
that of the well.
• Such positioning nullifies the effect of the
minor shifts which might have occurred
during well sinking.
Construction
Sequences
Well foundation> construction sequences
A well foundation supporting a bridge pier is
subjected to vertical and horizontal forces. The
various forces acting on the well are
1. Self weight of the well and its superstructure
2. Live loads
3. Water currents and buoyancy
4. Temperature, wind and earth quake
5. Breaking and tracking forces
6. Resistance of the well walls
7. Base and skin friction
The IRC and IS 3955 publications recommend
the following procedure for design of well
foundations in sand deposits (for clay the
expressions should be suitably modified)
1 Check the stability of well under working
loads, assuming elastic theory
2. Find the factor of safety of the well against ultimate
failure using ultimate load theory
Design of wells basically involves finding
1. Depth of the well
2. Size of the well and
3. Design of the other components.
1. Non uniform bearing capacity
2. Obstruction on one side of the well
3. Sand blowing in wells during sinking. It will cause sudden
sinking of well
4. Method of sinking: Material should be removed from all sides
equally otherwise the well may experience tilt
5. Sudden sinking due to blasting may also cause tilting of well
6. Irregular casting of steining will cause less friction on one side
leads to chances of tilting of well.
Precautions to be taken to avoid tilts and shift
• The cutting edge of caisson must be thick and sharp
pointed
• The external surface of steining and caisson curb should be
smooth.
• Dredging should be done uniformly on all sides and in all
pockets of caisson.
• Caisson should be symmetrically placed.
• The diameter (D) of the curb must be placed from 40 mm to
80 mm or larger or more than external diameter of steining.
1. Eccentric grabbing
2. Eccentric loading
3. Water jetting
4. Arresting the cutting edge
5. Pulling the well
6. Strutting the well
7. Pushing the well by jacks
Pushing the caissons or well with jack:
Eccentric loading
Water jetting
Providing temporary obstacles below the cutting edge:
Pulling the well or caisson
Strutting the caissons or well
Caisson Diseases
In case of sinking process of pneumatic caisson, workers or
workmen have to work in working chamber under compressed
air. If the compressed air pressure is less than 0.35 N/mm 2 to
0.4 N/ mm 2, then workmen may suffer from the following
pains:
 Workmen may suffer from giddiness
 There is pains in ears of workmen
 There is breaking of ear drums of workmen
 There is bursting of blood vessels in the nose or ears of workmen
 The above mentioned pains are not that serious or fatal, but
workmen is actually suffering during decompression and effect
causing depression is called caisson disease.
Following are the caisson disease caused by decompression:
 Severe pains in joints leading to bends
 It may cause paralytic death
 Excessive oxygen get absorbed in the blood may cause bursting
of vessels.
 If bubbles are developed in joints it causes bends
 If the bubbles are developed in spinal cord, it causes paralysis
and if the bubble are developed in heart, it causes heart attack.
 Caisson diseases can be controlled by recompression followed
by slow decompression.

More Related Content

What's hot

DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
Asaru Champ
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
Riya Trivedi
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
Safiullah Khan
 
Caisson
CaissonCaisson
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
Aglaia Connect
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
Alauddin aziz khan
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
Rajesh Prasad
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
Latif Hyder Wadho
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
dhara dattani
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil samplingAna Debbarma
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
Chaitanya Raval
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
Dar Hilal
 
Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...
A Makwana
 
Jacketing
JacketingJacketing
Jacketing
SHAIKH ARSHAD
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
ramgsvhce
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
Sherchandra Shrestha
 
Grouting
Grouting Grouting
Grouting
Chaitanya Raval
 

What's hot (20)

DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 
Caisson
CaissonCaisson
Caisson
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil sampling
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...
 
Jacketing
JacketingJacketing
Jacketing
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Grouting
Grouting Grouting
Grouting
 

Similar to Chapter 4.3 well foundation-final-ppt

Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
DYPCET
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
KHUSHBU SHAH
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Andhra University
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
SantistebanCampos
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
kushpatel927805
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
bryankalindo888
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
ChinnuNinan
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
Types of pile according to their composition
Types of pile according to their compositionTypes of pile according to their composition
Types of pile according to their composition
MdDiluarHossain1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
VATSAL PATEL
 
Piles and drilled shaft - Deep Foundations
Piles and drilled shaft - Deep FoundationsPiles and drilled shaft - Deep Foundations
Piles and drilled shaft - Deep Foundations
WakarusaCo
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Aamir Farhan Sheikh
 
caissons.pptx
caissons.pptxcaissons.pptx
caissons.pptx
PavanNadgouda2
 
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pratik Solanki
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptx
NisthaPathak2
 
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 

Similar to Chapter 4.3 well foundation-final-ppt (20)

Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
Types of pile according to their composition
Types of pile according to their compositionTypes of pile according to their composition
Types of pile according to their composition
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 
Piles and drilled shaft - Deep Foundations
Piles and drilled shaft - Deep FoundationsPiles and drilled shaft - Deep Foundations
Piles and drilled shaft - Deep Foundations
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
caissons.pptx
caissons.pptxcaissons.pptx
caissons.pptx
 
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptx
 
Form Work
Form Work Form Work
Form Work
 

More from DYPCET

Design of concrete structures-I- Design Steps
Design of concrete structures-I- Design StepsDesign of concrete structures-I- Design Steps
Design of concrete structures-I- Design Steps
DYPCET
 
Chapter 6 earth pressure
Chapter 6 earth pressureChapter 6 earth pressure
Chapter 6 earth pressure
DYPCET
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidation
DYPCET
 
Modern trends in optimization techniques
Modern trends in optimization techniquesModern trends in optimization techniques
Modern trends in optimization techniques
DYPCET
 
Productivity tools for students
Productivity tools for studentsProductivity tools for students
Productivity tools for students
DYPCET
 
Emotional intelligence at glance
Emotional intelligence at glanceEmotional intelligence at glance
Emotional intelligence at glance
DYPCET
 
Unit 2 building planning-final
Unit 2 building planning-finalUnit 2 building planning-final
Unit 2 building planning-final
DYPCET
 
Unit 1-introduction to civil engg final
Unit 1-introduction to civil engg finalUnit 1-introduction to civil engg final
Unit 1-introduction to civil engg final
DYPCET
 
BCE assignments
BCE assignmentsBCE assignments
BCE assignments
DYPCET
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
DYPCET
 
Assignments 1 to 8
Assignments 1 to 8Assignments 1 to 8
Assignments 1 to 8
DYPCET
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
DYPCET
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
DYPCET
 
Chapter 1.0 soil exploration
Chapter 1.0   soil explorationChapter 1.0   soil exploration
Chapter 1.0 soil exploration
DYPCET
 
Section 2-gte-i
Section  2-gte-iSection  2-gte-i
Section 2-gte-i
DYPCET
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
DYPCET
 

More from DYPCET (16)

Design of concrete structures-I- Design Steps
Design of concrete structures-I- Design StepsDesign of concrete structures-I- Design Steps
Design of concrete structures-I- Design Steps
 
Chapter 6 earth pressure
Chapter 6 earth pressureChapter 6 earth pressure
Chapter 6 earth pressure
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidation
 
Modern trends in optimization techniques
Modern trends in optimization techniquesModern trends in optimization techniques
Modern trends in optimization techniques
 
Productivity tools for students
Productivity tools for studentsProductivity tools for students
Productivity tools for students
 
Emotional intelligence at glance
Emotional intelligence at glanceEmotional intelligence at glance
Emotional intelligence at glance
 
Unit 2 building planning-final
Unit 2 building planning-finalUnit 2 building planning-final
Unit 2 building planning-final
 
Unit 1-introduction to civil engg final
Unit 1-introduction to civil engg finalUnit 1-introduction to civil engg final
Unit 1-introduction to civil engg final
 
BCE assignments
BCE assignmentsBCE assignments
BCE assignments
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Assignments 1 to 8
Assignments 1 to 8Assignments 1 to 8
Assignments 1 to 8
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
 
Chapter 1.0 soil exploration
Chapter 1.0   soil explorationChapter 1.0   soil exploration
Chapter 1.0 soil exploration
 
Section 2-gte-i
Section  2-gte-iSection  2-gte-i
Section 2-gte-i
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
 

Recently uploaded

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 

Recently uploaded (20)

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

Chapter 4.3 well foundation-final-ppt

  • 2.  Well foundations are being used in India from very early days.  Taj Mahal was built on such foundations.  Wells are classified as deep foundations.  The main difference between a well and a pile foundation:  Pile is flexible like a beam under horizontal loads  well undergoes rigid body movement under such loads
  • 3.
  • 4. Wells have different shapes and accordingly they are named as ( According to shape in plan) • Circular Wells • Dumb bell • Double-D Wells • Double Octagonal Wells • Single and Double Rectangular Wells • Multiple Dredged Holed Wells ( According to Material Used for Construction) • Wood • Steel • Reinforced Concrete
  • 5.
  • 6.
  • 7. Classification according to shape in cross section Classification according to cutting edge type
  • 8. • Large diameter, can be extended up to large depths. • Similar to piles, but shorter • If large bearing capacity soil (rock) is between 3-7 m, it can be very effective • If loads are not too large, but the upper 3-7 m of the soil is not appropriate, can be applied effectively • Cost of Construction is relatively less on bed level or lower side.
  • 9. • Since the placing of concrete is done for concrete seal under water, it may not be satisfactory. • If any obstruction of boulders or logs are encountered, then progress of work becomes slow. • Through cleaning and inspection at the bottom of caisson is very difficult and hence not possible. • The help of divers may be required for excavation near haunches at the cutting edges.
  • 10.
  • 11. The various component of a well foundations are 1. Cutting Edge 2. Well Curb 3. Bottom Plug 4. Steining 5. Top Plug 6. Well Cap
  • 12.
  • 14. Cutting Edge: • Sharp edge which is provided at the lower end of the well or open and pneumatic caisson for accelerating sinking operation is called cutting edge. It is made up steel or it is made in R.C.C. Its angle to vertical is 30 0 and normally slope of 1 horizontal to 2 vertical given better result. • In concrete caissons, the lower part of the cutting edge is rigidly fastened with 12 mm steel plates. • The cutting edge should be sharp so as to penetrate into the soil and it should resist the various stresses caused by blows, boulders, blasting, etc. • A sharp vertical edge is generally provided to the outside face of the caisson. Edge facilities the rate of sinking.
  • 15. Well Curbs • It is made of concrete or brick. • Cutting edge of well or caisson is attached to well curb. • During sinking operation well curb impart to the well steining and facilities the formation of bottom
  • 16. Bottom Plug • After final grounding of the well to the required foundation level, a concrete plug is provided. • The bottom plug transfer the entire load to the ground. • The bottom plug functions as an inverted dome supported along the periphery of the steining. • As it is not feasible to provide reinforcement at the bottom, it is generally made thick and a rich concrete mix (M20) is used.
  • 17. Sand Filling The bottom plug concrete is cured and after curing, the well is filled with sand in saturated condition. Sand filling provides 1. Stability to the bottom of the well. 2. Eliminate the tensile forces at the base 3. Cancels hoop stresses steining induced in
  • 18. Steining • Steining is constructed in concrete or masonry work. • Use of steining is to provide dead load during sinking operation. Topping • Covering provided over the well or caisson is called as topping. • Sand is filled in between topping and bottom plug. Topping also acts as a part of shuttering for laying the well cap.
  • 19. Top Plug• The top plug is provided after the filling is completed. • Top plug helps in transferring the load of the pier and superstructure to the steining. • The thickness of the top plug is generally kept greater than 50 % of the smaller dimension of the dredge hole. • If sand filling is used, the top plug is simply constructed using PCC of 1:2:4 otherwise it is reinforced with steel bars and lean concrete of 1:3:6 is used.
  • 20. Well Cap • As the shape of the well pier and cap are different, the well cap forms an interim (acting) layer to accommodate the pier. • The well cap is so designed that the base of the pier is provided with aminimum all round offset. • The centre of the well cap is made to coincide with that of the pier and not with that of the well. • Such positioning nullifies the effect of the minor shifts which might have occurred during well sinking.
  • 23.
  • 24. A well foundation supporting a bridge pier is subjected to vertical and horizontal forces. The various forces acting on the well are 1. Self weight of the well and its superstructure 2. Live loads 3. Water currents and buoyancy 4. Temperature, wind and earth quake 5. Breaking and tracking forces 6. Resistance of the well walls 7. Base and skin friction
  • 25. The IRC and IS 3955 publications recommend the following procedure for design of well foundations in sand deposits (for clay the expressions should be suitably modified) 1 Check the stability of well under working loads, assuming elastic theory 2. Find the factor of safety of the well against ultimate failure using ultimate load theory
  • 26. Design of wells basically involves finding 1. Depth of the well 2. Size of the well and 3. Design of the other components.
  • 27.
  • 28. 1. Non uniform bearing capacity 2. Obstruction on one side of the well 3. Sand blowing in wells during sinking. It will cause sudden sinking of well 4. Method of sinking: Material should be removed from all sides equally otherwise the well may experience tilt 5. Sudden sinking due to blasting may also cause tilting of well 6. Irregular casting of steining will cause less friction on one side leads to chances of tilting of well.
  • 29.
  • 30. Precautions to be taken to avoid tilts and shift • The cutting edge of caisson must be thick and sharp pointed • The external surface of steining and caisson curb should be smooth. • Dredging should be done uniformly on all sides and in all pockets of caisson. • Caisson should be symmetrically placed. • The diameter (D) of the curb must be placed from 40 mm to 80 mm or larger or more than external diameter of steining.
  • 31. 1. Eccentric grabbing 2. Eccentric loading 3. Water jetting 4. Arresting the cutting edge 5. Pulling the well 6. Strutting the well 7. Pushing the well by jacks
  • 32. Pushing the caissons or well with jack:
  • 35.
  • 36. Providing temporary obstacles below the cutting edge:
  • 37. Pulling the well or caisson
  • 40. In case of sinking process of pneumatic caisson, workers or workmen have to work in working chamber under compressed air. If the compressed air pressure is less than 0.35 N/mm 2 to 0.4 N/ mm 2, then workmen may suffer from the following pains:  Workmen may suffer from giddiness  There is pains in ears of workmen  There is breaking of ear drums of workmen  There is bursting of blood vessels in the nose or ears of workmen  The above mentioned pains are not that serious or fatal, but workmen is actually suffering during decompression and effect causing depression is called caisson disease.
  • 41. Following are the caisson disease caused by decompression:  Severe pains in joints leading to bends  It may cause paralytic death  Excessive oxygen get absorbed in the blood may cause bursting of vessels.  If bubbles are developed in joints it causes bends  If the bubbles are developed in spinal cord, it causes paralysis and if the bubble are developed in heart, it causes heart attack.  Caisson diseases can be controlled by recompression followed by slow decompression.