SlideShare a Scribd company logo
Contract Costing
CONTRACT
COSTING
๏‚ž Contract costing also known as terminal
costing, is a variant of job costing. In this
method of job costing , each contract is a
cost unit and a account is opened for each
contract in the book of contractor to ascertain
profit/loss thereon.
๏‚ž Contract costing is used in: Building
construction, Road construction, Bridge
construction, other civil engineering works,
ship building etc.
Contract costing and job
costing -Distinction
๏‚ž Main points of distinction as follows:
1- The no. of jobs undertaken at a time are
usually large as compared to no. of
contracts because contracts are
generally much bigger in size.
2- In contract costing , most of the costs
are chargeable direct to contract
account. Under job costing direct
allocation to such an extent is not
possible.
Con..
3- Allocation and apportionment of overhead
costs is simpler in contract costing as
compared to job costing .
4- contract is generally big while job is a small.
It is well said , โ€œ a job is small contract and
contract is big jobโ€
5- jobs are usually carried in factory premises
while contract work is done at site.
Features of contract costing
1- contracts are generally takes more than one
year to complete .
2- contracts are generally of large size and
therefore, a contractor usually carries out small
number of contracts in the course of one year.
3- work on contracts is carried out at the site of
contracts and not in factory premises .
4-Each contract under taken is treated as a cost
unit.
5-A separate contract account is prepared for each
contract in the books of the contractor to
ascertain profit and loss on each contract.
Recording Cost Contract or Costing Procedure
In contract costing, costs are allocated, collected and accumulated
according to the contract works.
Each contract is treated as a separate entity in which each contract
account may be maintained separately
or in general ledger itself for the purpose of costing and cost control. The
following are the costing
procedure for different costs relating to the important expenses :
(1) Materials:
(A) Contract Account is debited with the following transactions relating to
materials :
(I) Bulk of materials are purchased for a specific contract from suppliers.
(2) Materials obtained from contractor's central stores through the
requisition slips.
(3) Materials transferred from one contract to another contract.
(4) Value of materials remaining unutilized on site during the accounting
year.
.
(B) Contract Account is credited with the
following transactions relating to materials:
(1) Materials returned under Materials Return
Note.
(2) Sale of materials at site on account of some
extraneous reasons.
(3) Materials transferred to other contracts.
(4) Materials stolen or destroyed by fire.
(5) On completion, if a part of materials received
from the stores are returned
(C) Any profit or loss on materials account is transferred to the
Profu and Loss Account:
(I) Sale price is different from the cost price.
(2) Resulting from the sale of materials at site.
(3) Resulting from the materials stolen or destroyed by fire.
(2) Labour: In the case of contract costing, all labours engaged
at site and the salaries and wages paid to the labour and
workers are treated as direct labour cost is debited to Contract
Account.
(3) Direct Expenses: Most of the expenses like electricity,
insurance telephone, postage, sub-contracts, Architect's fees
etc. can also be treated as direct cost is debited to Contract
Account.
(4) Overhead Cost: In the case of contract costing overheads
incurred only an insignificant part of the total cost of contract
account. The nature office and administrative expenses of a
particular contract may be apportioned on suitable basis.
(5) Plant and Machinery: For use of plant and machinery in a
particular contract, the treatment of plant costs in any of the two
ways:
(a) Where a plant has been specially purchased for a particular
contract and will be exhausted at site Contract Account
should be debited with the cost of the plant. On completion
of the contract the residual or written down value as shown
by the Plant Ledger will be credited "to the Contract Account.
(b) When the plant and machinery are required to the contract
site only for a shorter period, the contract account should be
debited with the notional amount of depreciation based on some
estimates be charged to Contract Account.
Sub-Contracts: Sub-Contracts refer to some portions of the
specified work connected with the main contract, to be done by
the sub-contractor. For example, the work of painting, special
flooring, steel work etc. may be given to the sub-contractors.
Usually sub-contract has been undertaken on cost-plus basis
and the cost of such sub-contract should be treated as a direct
charge and is debited to Contract Account.
(7) Work Certified: In the case of the small contracts which are
completed within the shorter period, the contractor pays the
contract price on the completion of the contract. In the case of
contracts of long duration. the contract agreement provides
interim payment to the contractor. It is done on the basis of
certificates issued
by the contractee's Surveyor, Architect or Engineer. At the same
time Contractee usually does not pay to the full value of the
work certified. A portion of amount say 20% or 30% thereof shall
be retained by the Contractee.
The money so retained is called as "Retention Money." This
retention money is intented to ensure that the contractor to
complete the work as scheduled and according to
specifications. Money retained could also be used for imposing
penalties for faulty or delayed work. This amount will be settled
on completion of the contract.
(8) Work Uncertified : If the progress of a work is
unsatisfactory or the work has not reached the stipulated
stage, though certain work is completed, such work does
not qualify for a certificate by the Contractee's Architect
or Surveyor is termed as "Work Uncertified." It is valued
at cost and credited to Contract
Account and debited to Work in Progress Account.
(9) Work in Progress: Work in progress includes the
amount of work .certified and the amount of work
uncertified. The work in progress account will appear on
the asset side of the balance sheet. The amount of cash
received from the contractee and reserve for
contingencies will be deducted out of this amount.
Treatment of Profits or Loss on Contracts Alc.
The accounting treatment of profits or loss of
contracts in the following stages :
(A) Profit or Loss on incomplete contracts
(B) Profits or Loss on completed contracts
(A) Profit or Loss on Incomplete Contracts
To determine the profits to be taken to Profit and Loss
Account. in the case of incomplete contracts,
the following situations may arise :
(i) Completion of Contract is Less than 25% : In this case no
profit should be taken to Profit and Loss Account.
(ii) Completion of Contract is upto 25% or more but Less than
50% : In this case one-third of the notional profit, reduced in
the ratio of cash received to work certified, should be
transferred to Profit and Loss Account. It can be expressed as:
1/3 x Notional Profitx Cash Received/ Work Certified
(iii) Completion of Contract is upto 50% or more but Less
than 90% : In this case two-third of the notional profit
reduced by proportion of cash received to work certified
is transferred to Profit and Loss Account. The equation is
2/3xNotionalProfitxCashReceived/Work Certified
(iv) Completion of Contract is upto 90% or more than 90%, i.e., it is
nearing completion: In this case the profit to be taken to Profit and
Loss Account is determined by determining the estimated profit and
using anyone of the following formula :
(a)Estimated Profit x Work Certified/ Contract Price
(b) Estimated Profit x Cash Received / Contract Price
(c) Estimated Profit x Cost of Work to Date/ Estimated total cost
(d) Estimated Profit X Cost of Work to Date/ Estimated
Total Cost x Cash Received / Work Certified
(e) Notional Profit X Work Certified /Contract Price
Escalation Clause: This clause is often provided in contracts
as safeguard against any likely changes in price or utilization
of material and labour. Such a clause in a contract would
provide that in the event of a specified contingency
happening, the contract price would be suitably enhanced by
an agreed formula or factor.
This clause is particularly necessary where the prices of a
certain raw material are likely to rise. where labour rates are
anticipated to increase, or where the quantity of material and
labour hours cannot be assessed properly or estimated
unless the job has progressed sufficiently.
Cost-Plus Contract: These contracts provide for
the payment by the contractee of the actual cost of
manufacturing plus a stipulated profit. The profit to
be added to the cost may be a fixed amount or it
may be a stipulated percentage of cost. These
contracts are generally entered into when at the time
of undertaking of a work, it is not possible to
estimate it's cost with reasonable accuracy due to
unstable condition of material. labour etc. or when
the work is spread over a long period of time and
prices of materials. rates of labour etc. are liable to
fluctuate.
(B) Profits or Loss on Completed Contracts :
When a contract is completed, the overall profit or loss on the
contract is transferred to the Profit and Loss Account.
The following are the expenses on a contract which commences
on 1st Jan. 2003
Materials purchased 1.00.000
Materials on hand 5.000
Direct wages 1.50.000
Plant issued 50.000
Direct expenses 80000
The contract price was Rs. 15.00.000 and the same was duly
received when the contract was completed in
August 2003. Charge indirect expenses at 15% on wages.
provide Rs. 10.000 for depreciation on plant and prepare the
contract account and the contractee's account.
CONTRACT ACCOUNT
PARTICULARS Rs.
PARTICULARS Rs
To Materials Purchased 1.00.000 By Materials on hand
5.000
To Direct Wages 1.50.000 By Plant on hand
To Direct Expenses 80.000 (Rs.50.000 -
10.000) 40.000
To Indirect Expenses } By Contractor's Alc
(15% on wages) 22.500 (Contract Price)
15.00.000
To Depreciation on Plant 10.000
To Profit & Loss Alc 11.82.500
15,45,000
15,45,000
Contractee's Account
Particulars Rs. Particulars
Rs.
To contract a/c 1500000 By Bank a/c
1500000
1500000
1500000
References/Sources
๏‚ž Accounting for Managers by Dr. Sakshi Vasudeva Galgotia
Publishing Company Chapter 25 Contract Costing page no. 867
๏‚ž Cost Accounting by S.P jain K.L Naran Part 4 Chapter 1 Job Batch
and Contract costing page no. 1.5
Thank U

More Related Content

What's hot

Ind as 16
Ind as 16Ind as 16
Ind as 16
SHASHIKANT VARSHNEY
ย 
Plant & equipment depreciation and intangible assets
Plant & equipment depreciation and intangible assetsPlant & equipment depreciation and intangible assets
Plant & equipment depreciation and intangible assets
Ramila Anwar
ย 
Ind as 19
Ind as 19Ind as 19
Ind as 19
Mohit Goyal
ย 
Contract costing
Contract costingContract costing
Contract costing
Shubham Verma
ย 
Bailment and Pledge
Bailment and PledgeBailment and Pledge
Bailment and Pledge
Galaxy4u Legal Consulting Pune
ย 
Contract costing
Contract costingContract costing
Contract costing
Mahesh Chandra Sharma
ย 
Ias 11
Ias 11Ias 11
Rights of an unpaid seller
Rights of an unpaid sellerRights of an unpaid seller
Rights of an unpaid seller
Sweetp999
ย 
Cost overhead
Cost overheadCost overhead
Cost overhead
Mohit Singhal
ย 
IFRS 15 Revenue from contracts with customers
IFRS 15 Revenue from contracts with customers IFRS 15 Revenue from contracts with customers
IFRS 15 Revenue from contracts with customers
Nadir Malik
ย 
Scrap waste spoilage in costing
Scrap waste spoilage in costingScrap waste spoilage in costing
Scrap waste spoilage in costing
N A M COLLEGE KALLIKKANDY
ย 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
uktaxandaccounts.com
ย 
Capital expenditure & Revenue expenditure
Capital expenditure & Revenue expenditureCapital expenditure & Revenue expenditure
Capital expenditure & Revenue expenditure
Mudassir Raza
ย 
Final accounts of banks & companies
Final accounts of banks & companiesFinal accounts of banks & companies
Final accounts of banks & companies
Babasab Patil
ย 
IFRS 4
IFRS 4IFRS 4
IFRS 4
KLAX RUKATO
ย 
IFRS 15/ Ind AS 115
IFRS 15/ Ind AS 115IFRS 15/ Ind AS 115
IFRS 15/ Ind AS 115
Talati and Talati Group
ย 
Cost Allocation powerpoint presentation
Cost Allocation powerpoint presentationCost Allocation powerpoint presentation
Cost Allocation powerpoint presentation
Shibani123
ย 
optimal capital structure
optimal capital structureoptimal capital structure
optimal capital structure
Shree Bhargava and Associate
ย 
As 19
As 19As 19
As 19
Praveen Kumar
ย 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accounts
Mahesh Chandra Sharma
ย 

What's hot (20)

Ind as 16
Ind as 16Ind as 16
Ind as 16
ย 
Plant & equipment depreciation and intangible assets
Plant & equipment depreciation and intangible assetsPlant & equipment depreciation and intangible assets
Plant & equipment depreciation and intangible assets
ย 
Ind as 19
Ind as 19Ind as 19
Ind as 19
ย 
Contract costing
Contract costingContract costing
Contract costing
ย 
Bailment and Pledge
Bailment and PledgeBailment and Pledge
Bailment and Pledge
ย 
Contract costing
Contract costingContract costing
Contract costing
ย 
Ias 11
Ias 11Ias 11
Ias 11
ย 
Rights of an unpaid seller
Rights of an unpaid sellerRights of an unpaid seller
Rights of an unpaid seller
ย 
Cost overhead
Cost overheadCost overhead
Cost overhead
ย 
IFRS 15 Revenue from contracts with customers
IFRS 15 Revenue from contracts with customers IFRS 15 Revenue from contracts with customers
IFRS 15 Revenue from contracts with customers
ย 
Scrap waste spoilage in costing
Scrap waste spoilage in costingScrap waste spoilage in costing
Scrap waste spoilage in costing
ย 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
ย 
Capital expenditure & Revenue expenditure
Capital expenditure & Revenue expenditureCapital expenditure & Revenue expenditure
Capital expenditure & Revenue expenditure
ย 
Final accounts of banks & companies
Final accounts of banks & companiesFinal accounts of banks & companies
Final accounts of banks & companies
ย 
IFRS 4
IFRS 4IFRS 4
IFRS 4
ย 
IFRS 15/ Ind AS 115
IFRS 15/ Ind AS 115IFRS 15/ Ind AS 115
IFRS 15/ Ind AS 115
ย 
Cost Allocation powerpoint presentation
Cost Allocation powerpoint presentationCost Allocation powerpoint presentation
Cost Allocation powerpoint presentation
ย 
optimal capital structure
optimal capital structureoptimal capital structure
optimal capital structure
ย 
As 19
As 19As 19
As 19
ย 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accounts
ย 

Viewers also liked

Cost accounting bba 3rd
Cost accounting bba 3rdCost accounting bba 3rd
Cost accounting bba 3rd
ahsanullah mohsen
ย 
Contract costing
Contract costingContract costing
Contract costing
Shubham Verma
ย 
Batch costing
Batch costingBatch costing
Batch costing
SUJOY KR PAUL
ย 
METHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTINGMETHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTING
Naveen Khubchandani
ย 
Tally. erp9
Tally. erp9Tally. erp9
Tally. erp9
Kulbeer Bumrah
ย 
Construction contract
Construction contractConstruction contract
Construction contract
Aqsa Shafique
ย 
Workshop on tally- Cost Centre
Workshop on tally- Cost CentreWorkshop on tally- Cost Centre
Workshop on tally- Cost Centre
Anchit Agrawal
ย 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
Megha Shah
ย 
Standard Costing
Standard CostingStandard Costing
Standard Costing
Aurus Network
ย 
Fma10
Fma10Fma10
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
rcaldwell002
ย 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing h
MitikaAnjel
ย 
Cost accounting bba fri
Cost accounting bba friCost accounting bba fri
Cost accounting bba fri
Arslan Mehmood
ย 
Standard costing
Standard costingStandard costing
Standard costing
Vikash Kumar-IB
ย 
Standard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsStandard Costing - Uses & Limitations
Standard Costing - Uses & Limitations
M Ravish Malgi
ย 
Process costing
Process costingProcess costing
Process costing
grvthakkar
ย 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
Augustin Bangalore
ย 
ICT Initiatives in Higher Education Department, GOK
ICT Initiatives in  Higher Education Department, GOKICT Initiatives in  Higher Education Department, GOK
ICT Initiatives in Higher Education Department, GOK
eGov Magazine
ย 
Standard Costing
Standard Costing Standard Costing
Standard Costing
Nitin Parbhakar
ย 
Standard costing
Standard costingStandard costing
Standard costing
abner domingo
ย 

Viewers also liked (20)

Cost accounting bba 3rd
Cost accounting bba 3rdCost accounting bba 3rd
Cost accounting bba 3rd
ย 
Contract costing
Contract costingContract costing
Contract costing
ย 
Batch costing
Batch costingBatch costing
Batch costing
ย 
METHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTINGMETHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTING
ย 
Tally. erp9
Tally. erp9Tally. erp9
Tally. erp9
ย 
Construction contract
Construction contractConstruction contract
Construction contract
ย 
Workshop on tally- Cost Centre
Workshop on tally- Cost CentreWorkshop on tally- Cost Centre
Workshop on tally- Cost Centre
ย 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
ย 
Standard Costing
Standard CostingStandard Costing
Standard Costing
ย 
Fma10
Fma10Fma10
Fma10
ย 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
ย 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing h
ย 
Cost accounting bba fri
Cost accounting bba friCost accounting bba fri
Cost accounting bba fri
ย 
Standard costing
Standard costingStandard costing
Standard costing
ย 
Standard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsStandard Costing - Uses & Limitations
Standard Costing - Uses & Limitations
ย 
Process costing
Process costingProcess costing
Process costing
ย 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
ย 
ICT Initiatives in Higher Education Department, GOK
ICT Initiatives in  Higher Education Department, GOKICT Initiatives in  Higher Education Department, GOK
ICT Initiatives in Higher Education Department, GOK
ย 
Standard Costing
Standard Costing Standard Costing
Standard Costing
ย 
Standard costing
Standard costingStandard costing
Standard costing
ย 

Similar to Bba ii cost and management accounting u 3.3 contract costing

AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
Prakhar Jain
ย 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
Collen Mahambo
ย 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
SreedeviPMenon
ย 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
mianmohsinmumtazshb
ย 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
MANNU KUMAR
ย 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
ChelDems
ย 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
Saqib Imran
ย 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
NithyaPotterhead
ย 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
sulevrunda
ย 
ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
TAXPERT PROFESSIONALS
ย 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
Nikhil Kumar
ย 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
Tulsi Pokhrel
ย 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
AC&C Consulting Co., Ltd.
ย 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
mayuray
ย 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
ย 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
ย 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion Costs
The Vertex Companies, LLC
ย 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
MohammedAlfayad2
ย 
Job costing
Job costing Job costing
Job costing
Joseph Mary
ย 
Construction practices
Construction practicesConstruction practices
Construction practices
Arun Kurali
ย 

Similar to Bba ii cost and management accounting u 3.3 contract costing (20)

AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
ย 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
ย 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
ย 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
ย 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
ย 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
ย 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
ย 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
ย 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
ย 
ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
ย 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
ย 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
ย 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
ย 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
ย 
Construction contract
Construction contractConstruction contract
Construction contract
ย 
Construction contract
Construction contractConstruction contract
Construction contract
ย 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion Costs
ย 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
ย 
Job costing
Job costing Job costing
Job costing
ย 
Construction practices
Construction practicesConstruction practices
Construction practices
ย 

More from Rai University

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
Rai University
ย 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
Rai University
ย 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
Rai University
ย 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
Rai University
ย 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
Rai University
ย 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
Rai University
ย 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
Rai University
ย 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
Rai University
ย 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
Rai University
ย 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
Rai University
ย 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
Rai University
ย 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Rai University
ย 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Rai University
ย 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
Rai University
ย 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
Rai University
ย 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
Rai University
ย 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
Rai University
ย 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
Rai University
ย 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
Rai University
ย 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
Rai University
ย 

More from Rai University (20)

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
ย 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
ย 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
ย 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
ย 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
ย 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
ย 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
ย 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
ย 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
ย 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
ย 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
ย 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
ย 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
ย 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
ย 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
ย 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
ย 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
ย 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
ย 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
ย 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
ย 

Recently uploaded

Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
nitinpv4ai
ย 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
ย 
Stack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 MicroprocessorStack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 Microprocessor
JomonJoseph58
ย 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
deepaannamalai16
ย 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
Prof. Dr. K. Adisesha
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
ย 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
MysoreMuleSoftMeetup
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
David Douglas School District
ย 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
Iris Thiele Isip-Tan
ย 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
MJDuyan
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
Celine George
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
Mohammad Al-Dhahabi
ย 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
ย 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
ย 
How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17
Celine George
ย 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
ย 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
nitinpv4ai
ย 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
ย 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Henry Hollis
ย 

Recently uploaded (20)

Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
ย 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
ย 
Stack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 MicroprocessorStack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 Microprocessor
ย 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
ย 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
ย 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
ย 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
ย 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
ย 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
ย 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
ย 
How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17How Barcodes Can Be Leveraged Within Odoo 17
How Barcodes Can Be Leveraged Within Odoo 17
ย 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
ย 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
ย 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
ย 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
ย 

Bba ii cost and management accounting u 3.3 contract costing

  • 2. CONTRACT COSTING ๏‚ž Contract costing also known as terminal costing, is a variant of job costing. In this method of job costing , each contract is a cost unit and a account is opened for each contract in the book of contractor to ascertain profit/loss thereon. ๏‚ž Contract costing is used in: Building construction, Road construction, Bridge construction, other civil engineering works, ship building etc.
  • 3. Contract costing and job costing -Distinction ๏‚ž Main points of distinction as follows: 1- The no. of jobs undertaken at a time are usually large as compared to no. of contracts because contracts are generally much bigger in size. 2- In contract costing , most of the costs are chargeable direct to contract account. Under job costing direct allocation to such an extent is not possible.
  • 4. Con.. 3- Allocation and apportionment of overhead costs is simpler in contract costing as compared to job costing . 4- contract is generally big while job is a small. It is well said , โ€œ a job is small contract and contract is big jobโ€ 5- jobs are usually carried in factory premises while contract work is done at site.
  • 5. Features of contract costing 1- contracts are generally takes more than one year to complete . 2- contracts are generally of large size and therefore, a contractor usually carries out small number of contracts in the course of one year. 3- work on contracts is carried out at the site of contracts and not in factory premises . 4-Each contract under taken is treated as a cost unit. 5-A separate contract account is prepared for each contract in the books of the contractor to ascertain profit and loss on each contract.
  • 6. Recording Cost Contract or Costing Procedure In contract costing, costs are allocated, collected and accumulated according to the contract works. Each contract is treated as a separate entity in which each contract account may be maintained separately or in general ledger itself for the purpose of costing and cost control. The following are the costing procedure for different costs relating to the important expenses : (1) Materials: (A) Contract Account is debited with the following transactions relating to materials : (I) Bulk of materials are purchased for a specific contract from suppliers. (2) Materials obtained from contractor's central stores through the requisition slips. (3) Materials transferred from one contract to another contract. (4) Value of materials remaining unutilized on site during the accounting year. .
  • 7. (B) Contract Account is credited with the following transactions relating to materials: (1) Materials returned under Materials Return Note. (2) Sale of materials at site on account of some extraneous reasons. (3) Materials transferred to other contracts. (4) Materials stolen or destroyed by fire. (5) On completion, if a part of materials received from the stores are returned
  • 8. (C) Any profit or loss on materials account is transferred to the Profu and Loss Account: (I) Sale price is different from the cost price. (2) Resulting from the sale of materials at site. (3) Resulting from the materials stolen or destroyed by fire. (2) Labour: In the case of contract costing, all labours engaged at site and the salaries and wages paid to the labour and workers are treated as direct labour cost is debited to Contract Account. (3) Direct Expenses: Most of the expenses like electricity, insurance telephone, postage, sub-contracts, Architect's fees etc. can also be treated as direct cost is debited to Contract Account. (4) Overhead Cost: In the case of contract costing overheads incurred only an insignificant part of the total cost of contract account. The nature office and administrative expenses of a particular contract may be apportioned on suitable basis.
  • 9. (5) Plant and Machinery: For use of plant and machinery in a particular contract, the treatment of plant costs in any of the two ways: (a) Where a plant has been specially purchased for a particular contract and will be exhausted at site Contract Account should be debited with the cost of the plant. On completion of the contract the residual or written down value as shown by the Plant Ledger will be credited "to the Contract Account. (b) When the plant and machinery are required to the contract site only for a shorter period, the contract account should be debited with the notional amount of depreciation based on some estimates be charged to Contract Account.
  • 10. Sub-Contracts: Sub-Contracts refer to some portions of the specified work connected with the main contract, to be done by the sub-contractor. For example, the work of painting, special flooring, steel work etc. may be given to the sub-contractors. Usually sub-contract has been undertaken on cost-plus basis and the cost of such sub-contract should be treated as a direct charge and is debited to Contract Account.
  • 11. (7) Work Certified: In the case of the small contracts which are completed within the shorter period, the contractor pays the contract price on the completion of the contract. In the case of contracts of long duration. the contract agreement provides interim payment to the contractor. It is done on the basis of certificates issued by the contractee's Surveyor, Architect or Engineer. At the same time Contractee usually does not pay to the full value of the work certified. A portion of amount say 20% or 30% thereof shall be retained by the Contractee. The money so retained is called as "Retention Money." This retention money is intented to ensure that the contractor to complete the work as scheduled and according to specifications. Money retained could also be used for imposing penalties for faulty or delayed work. This amount will be settled on completion of the contract.
  • 12. (8) Work Uncertified : If the progress of a work is unsatisfactory or the work has not reached the stipulated stage, though certain work is completed, such work does not qualify for a certificate by the Contractee's Architect or Surveyor is termed as "Work Uncertified." It is valued at cost and credited to Contract Account and debited to Work in Progress Account. (9) Work in Progress: Work in progress includes the amount of work .certified and the amount of work uncertified. The work in progress account will appear on the asset side of the balance sheet. The amount of cash received from the contractee and reserve for contingencies will be deducted out of this amount.
  • 13. Treatment of Profits or Loss on Contracts Alc. The accounting treatment of profits or loss of contracts in the following stages : (A) Profit or Loss on incomplete contracts (B) Profits or Loss on completed contracts
  • 14. (A) Profit or Loss on Incomplete Contracts To determine the profits to be taken to Profit and Loss Account. in the case of incomplete contracts, the following situations may arise : (i) Completion of Contract is Less than 25% : In this case no profit should be taken to Profit and Loss Account. (ii) Completion of Contract is upto 25% or more but Less than 50% : In this case one-third of the notional profit, reduced in the ratio of cash received to work certified, should be transferred to Profit and Loss Account. It can be expressed as: 1/3 x Notional Profitx Cash Received/ Work Certified
  • 15. (iii) Completion of Contract is upto 50% or more but Less than 90% : In this case two-third of the notional profit reduced by proportion of cash received to work certified is transferred to Profit and Loss Account. The equation is 2/3xNotionalProfitxCashReceived/Work Certified
  • 16. (iv) Completion of Contract is upto 90% or more than 90%, i.e., it is nearing completion: In this case the profit to be taken to Profit and Loss Account is determined by determining the estimated profit and using anyone of the following formula : (a)Estimated Profit x Work Certified/ Contract Price (b) Estimated Profit x Cash Received / Contract Price (c) Estimated Profit x Cost of Work to Date/ Estimated total cost
  • 17. (d) Estimated Profit X Cost of Work to Date/ Estimated Total Cost x Cash Received / Work Certified (e) Notional Profit X Work Certified /Contract Price
  • 18. Escalation Clause: This clause is often provided in contracts as safeguard against any likely changes in price or utilization of material and labour. Such a clause in a contract would provide that in the event of a specified contingency happening, the contract price would be suitably enhanced by an agreed formula or factor. This clause is particularly necessary where the prices of a certain raw material are likely to rise. where labour rates are anticipated to increase, or where the quantity of material and labour hours cannot be assessed properly or estimated unless the job has progressed sufficiently.
  • 19. Cost-Plus Contract: These contracts provide for the payment by the contractee of the actual cost of manufacturing plus a stipulated profit. The profit to be added to the cost may be a fixed amount or it may be a stipulated percentage of cost. These contracts are generally entered into when at the time of undertaking of a work, it is not possible to estimate it's cost with reasonable accuracy due to unstable condition of material. labour etc. or when the work is spread over a long period of time and prices of materials. rates of labour etc. are liable to fluctuate.
  • 20. (B) Profits or Loss on Completed Contracts : When a contract is completed, the overall profit or loss on the contract is transferred to the Profit and Loss Account.
  • 21. The following are the expenses on a contract which commences on 1st Jan. 2003 Materials purchased 1.00.000 Materials on hand 5.000 Direct wages 1.50.000 Plant issued 50.000 Direct expenses 80000 The contract price was Rs. 15.00.000 and the same was duly received when the contract was completed in August 2003. Charge indirect expenses at 15% on wages. provide Rs. 10.000 for depreciation on plant and prepare the contract account and the contractee's account.
  • 22. CONTRACT ACCOUNT PARTICULARS Rs. PARTICULARS Rs To Materials Purchased 1.00.000 By Materials on hand 5.000 To Direct Wages 1.50.000 By Plant on hand To Direct Expenses 80.000 (Rs.50.000 - 10.000) 40.000 To Indirect Expenses } By Contractor's Alc (15% on wages) 22.500 (Contract Price) 15.00.000 To Depreciation on Plant 10.000 To Profit & Loss Alc 11.82.500 15,45,000 15,45,000
  • 23. Contractee's Account Particulars Rs. Particulars Rs. To contract a/c 1500000 By Bank a/c 1500000 1500000 1500000
  • 24. References/Sources ๏‚ž Accounting for Managers by Dr. Sakshi Vasudeva Galgotia Publishing Company Chapter 25 Contract Costing page no. 867 ๏‚ž Cost Accounting by S.P jain K.L Naran Part 4 Chapter 1 Job Batch and Contract costing page no. 1.5