SlideShare a Scribd company logo
1 of 62
PeopleSoft Cost
Management
A Layman’s Perspective
2
Outline
• Introduction – Who is this guy?
• What is Standard Cost?
• What is Actual Cost?
• What are the different Actual Cost Methods?
• Is it better?
• How would I change from Standard to
Actual Costing?
3
Introduction Ron Caldwell
• Former practicing CPA with 4 years experience in “Big 5”
Public Accounting
• 2 years Private Sector Accounting for US Defense
Contractor
• Beta tested PeopleSoft Cost Management version 5.0
• 9+ years working “hands-on” with PeopleSoft SCM and
Financial Applications the last 4 years in private practice.
• Help setup Cost Management for DMUG member Honda of
America.
• Reengineered setup of Cost Management 8.8 for DMUG
member: Monster Cable Products and Combe, Inc
4
What is Standard Cost?
• Standard Cost is a predefined calculation of the
costs to produce a good under specified “standard”
working conditions.
• It is built up from an assessment of the value of
cost elements and correlates technical
specifications and the quantification of materials,
labor and other costs expected during the period in
which the standard cost is intended to be used.
• Its main purposes are to provide bases for control
through variance accounting, for the valuation of
work in progress and for fixing selling prices.
5
What the heck did that mean?
• Standard cost is a singular frozen estimate
of production costs based on a singular set
of assumptions used to evaluate production
efficiency through variance analysis.
• Standard cost predetermined and intended
for a finite period of time.
6
What are Assumptions are used?
• The Source Code (Make or Buy) of the Final
Product
• The Primary Bill of Material (BOM) and the
Source Codes (Make, Buy, Floor Stock*,
Expensed*) and Standard Costs of the BOM
Components
• The Primary Production Routing which includes
decisions about which Work Centers, what Crews,
how many per Crew, how much Operating Time
per Crew member, and whether or not any of the
production steps are Subcontracted.
*Not included in the Standard Cost of the Assembly
7
Standard Cost - Illustrated
8
Fin Goods Production “Make” Cost
9
Typical Lower Level for Fin Goods
 These items are comprised of Raw Material
items on it’s Bill of Material. So the Cost
Elements typical of Raw Material items will
comprise the Lower Level cost of the
Finished Goods item. These are as follows:
 100 – Material – Vendor or Transfer Price
 300 – Freight – Inbound Freight Cost
 400 – Duty – Inbound Duty Cost
 700 – Overhead – Purchasing Overhead
10
Rolling up Lower Level Costs
Item 200
Cost Element 100 $8.00
Cost Element 300 $1.50
Cost Element 400 $1.25
Cost Element 700 $1.75
Item 140
Cost Element 100 $1.75
Cost Element 400 $0.75
Cost Element 700 $0.25
Item 160
Cost Element 100 $3.75
Cost Element 300 $1.00
Cost Element 400 $0.50
Cost Element 700 $0.25
Item 180
Cost Element 100 $2.50
Cost Element 300 $0.50
Cost Element 700 $1.25
Cost Elements are retained in the Lower Level Cost as they roll up from Raw
Materials to assembled Finished Goods.
11
Bill of Material for a Make Item
Sum of the
Component cost
$6.0419
12
Typical This Level for Fin Goods
The cost associated with assembling the
Raw Material items into Finished
Goods items are the This Level cost for
the Finished Goods Item:
200 – Labor – Production Labor
500 – Overhead – Production Overhead
600 – Outside Processing – Subcontracted
Production Cost
13
Routing Summary for a Make Item
The Routing displays the Work Centers
used to assemble the Make Item.
14
Operation Times for a Make Item
Note Costing Labor
Run is 4 Minutes
15
Crew Size for a Make Item
Note Crew Size is 1
Employee
16
Labor Rate for the Work Center
The Labor Rate is $19.80/Hr.
$19.80 X 1 X (4/60) = $1.3200
17
Overhead Rate for the Work Center
The Overhead Rate is 77% of the
Labor Amount.
$1.3200 X 77% = $1.0164
18
Establishing a Standard Cost
• When using Standard Costing establishing a
cost standard for each item is a prerequisite
for transacting the item for Inventory or
Production purposes.
• The standard are set after running these two
processes:
– Cost Rollup
– Cost Update
19
Cost Rollup Process
20
Cost Update Process
21
Actual Costing for Production Items
• Okay, now it’s about to get interesting.
• One of the things that production operations
will like is that Actual costing doesn’t
require a pre-established standard cost before
the item can be transacted.
• With Actual Costing the Cost Rollup and
Cost Update process is not required.
22
What is Actual Costing?
• Actual Costing values inventory based on the “best
available” actual cost information at the time
including purchase order price or matched vendor
invoice price, and actual production labor and
machine time.
• The release of PeopleSoft 8.8 Cost Management
made available the use of Actual and Average
Costing Methods for production inventories.
• Prior to 8.8 Standard Costing was the only cost
method available for production inventories
23
Actual Costing emphasizes Material Cost
• Standard cost accounting methods were
developed about 100 years ago, when labor
comprised the most important cost in
manufactured goods. The emphasis on
measuring production labor efficiency in one
of the prime sources of criticism by Eliyahu
“theory of constraints” Goldratt.
• Actual Costing endeavors to reflect the
actual vendor cost for the material
component of production inventories.
24
Actual Costing for “Buy” Items
• Purchased goods are initially valued based on the
Purchase Order Price at the time of Receipt.
• The value of purchased goods is adjusted for any
difference between the Purchase Order price and
the Vendor Invoice price after the related voucher
is MATCHED, POSTED, and EXTRACTED via
the Landed Cost Extract Process.
• The adjusted cost of the purchased goods flow into
Work-in-Process cost based upon the Costing
Method selected.
25
Landed Cost Extract Process
26
Actual Costing Methods for Outputs
• The Actual Costing methods include:
– FIFO (First-in, First-out)
– LIFO (Last-in, First-out)
• The Weighted Average Costing Methods include:
– Periodic – calculated at month-end – all depletions use
the same average.
– Perpetual – calculated throughout period based on
information available at the time of the depletions
– Retroactive – similar to perpetual except that depletions
are revalued retroactively at month end for all for AP
match and post activity during the month
27
Costing Methods on Cost Profile Page
28
Calculating Labor and Machine Cost
• Labor and Machine Cost can be added to
material cost based on following selections
on the Cost Profile-Manufacturing Page:
– Not Applicable
– Standard Time-Conversion Rate
– Actual Time-Conversion Rate
– Actual Time-Actual Rate (Labor Only)
29
Cost Profile Mfg Labor Cost
30
Labor and Machine Cost Inputs
31
Crew Rates
32
Actual costing eliminates variances
• You can chose to eliminate Purchase Price
Variance Expense for inventory purchases. Any
difference between purchase order and invoice
price updates the basis of the good, even if it has
been consumed into work-in-process and the
assembly had been shipped to a customer.
• You will not have Material, Conversion or Rework
Variances, or Subcontract PPV Expense for
production work orders because these costs are
added to the basis of the assemblies produced.
33
Is it better?
• Actual costing is flexible. Each production
transaction is valued exactly in the manner in which
it is produced for those who might use alternate
sourcing, Bill of Material or Routing.
• It is especially beneficial to those who extensively
use Product Configurator in Production
• Actual Costing ultimately provides the most
accurate inventory information for evaluating
production costs and gross margin.
• Yes, it’s better! Period!
34
Actual Costing Caveats
• You should develop a reasonable means for Current
Purchase Cost for Bill of Material (BOM)
components and Default Actual Cost for All Actual
Cost items.
• Current Purchase Cost (or Last Price Paid) is
used to cost components when no cost is available
such as when inventory of the component is
negative.
• Default Actual Cost is used cost any “Increase”
adjustment transaction like Cycle Count and User
adjustments. It is also used to value RMA
transactions as well
35
One more Caveat
• When running the Cost Accounting
Creation process it is very important to run
using the Mid-Period Mode during the
month and Regular Mode on the last day of
the month especially when using an Average
Costing Method.
36
Cost Accounting Creation Process
37
Migrating from Standard to Actual Cost
• Oracle does not have a certified upgrade
methodology for migrating from standard
cost to an actual or average costing method.
• There will not be a one size fits all solution
for migration.
• At Combe we will develop a methodology
for migrating from Standard to Actual
Costing where the initial Actual Cost of
Inventory will be equal to the Standard Cost.
38
End Presentation
39
Appendix - More Standard Cost Info
40
Standard Cost is predicated on the
creation and analysis of variances.
Variances are created on most
purchase and production
transactions.
41
Standard Purchase Price Variance
There are two instances where PPV
may apply:
The Purchase Order Price differs from the
Standard Cost for an Item (PPV 1).
The Voucher Price MATCHED and
POSTED differs from the Purchase Order
Price (PPV2). This variance is extracted
from Accounts Payable using the Landed
Cost Extract process
42
Standard Cost Production Variances
Material Variance – to account for
deviations from the Primary Bill of
Material (BOM)
Conversion Variance – to account for
deviations from the Primary Production
Routing
Rework Expense – to account for the
additional material and processing cost
associated with rework production.
43
Walkthrough of the Cost Rollup of
“Buy Items.
44
Cost Elements for Raw Material Items
Cost Elements typically used:
100 – Material – Vendor or Transfer Price
300 – Freight – Inbound Freight Cost
400 – Duty – Inbound Duty Cost
700 – Overhead – Purchasing Overhead
Cost Elements NEVER used:
200 – Labor – Production Labor
500 – Overhead – Production Overhead
600 – Outside Processing – Subcontracted
Production Cost
45
Material Standard Cost for “Buy” Items
• The material cost for these items are primarily
comprised of purchased cost. The standards for
these items can be derived from one of these
sources:
– Current Cost
– Average Cost
– Last Price Paid
– Forecasted Purchase Price
• Despite by names like “Current” and “Last Price”
the material standards remain frozen (unchanged)
between Standard Cost Updates.
46
Material standard basis can vary
47
Raw Material Item
Raw Material items only have cost
at This Level because they do not
have a Bill of Material.
48
Raw Item Current Purchase Cost
The Material Cost should equal
the Current Purchase Cost for each
unit.
49
Raw Item Vendor-Item Set-up
The Vendor Price on PO’s will be
compared to ONLY CE 100 to
determine PPV.
50
Raw Item Freight-In Cost
3.9% X $3.48 =
$0.1357
51
Raw Item Duty-In Cost
5.8% X $3.48 =
$0.2018
52
Raw Item Purchasing Overhead Cost
5.1% X $3.48 =
$0.1775
53
Cost Elements for FG “Buy” Items
Cost Elements typically used:
100 – Material – Vendor or Transfer Price
300 – Freight – Inbound Freight Cost
400 – Duty – Inbound Duty Cost
700 – Overhead – Purchasing Overhead
Cost Elements NEVER used:
200 – Labor – Production Labor
500 – Overhead – Production Overhead
600 – Outside Processing – Subcontracted
Production Cost
54
Finished Goods “Buy” Item
Finished Goods Buy items are
similar to Raw items in that they
only have This Level cost.
55
Now it gets exciting because we’re
going to illustrate the Accounting
Debit and Credits for a few typical
transactions.
56
Buying a Raw Material Item
DR 1200-Inventory-Raw Stk 3.9950
CR 2100-Accrued Liabilities-
Inventory
3.4800
CR 5159-Applied-Ocean
Freight In
0.1357
CR 5169-Applied-Customs-
Duty
0.2018
CR 5999-COGSI-Overhead
Absorption
0.1775
57
Issuing Material to a PID
DR 1300 – Inventory WIP 6.0419
CR 1200 – Inventory Raw
Stk
6.0419
58
Applying Labor to a PID
DR 1300 – Inventory WIP 1.3200
CR 5149– COGSD-Direct
Labor Absorption
1.3200
59
Applying Overhead to a PID
DR 1300 – Inventory WIP 1.0164
CR 5999 – COGSI-
Overhead Absorption
1.0164
60
Closing a Production Order (PID)
DR 1400 – Inventory
Finished
8.3783
CR 1300 – Inventory WIP 8.3783
61
Issuing Material to a Customer
DR 5000 – COGSD-
Taxable
8.3783
CR 1400 – Inventory
Finished Goods
8.3783
62
Contact Information
If you have any questions please feel free to
contact me at:
Rondal A Caldwell, CPA
Caldwell + Associates
1900 West 42nd
Street
Austin, TX 78704
832-741-7427

More Related Content

What's hot

What's hot (19)

Material Ledger Product costing
Material Ledger Product costingMaterial Ledger Product costing
Material Ledger Product costing
 
Traditional & Abc
Traditional & AbcTraditional & Abc
Traditional & Abc
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
Job order costing
Job order costingJob order costing
Job order costing
 
Job Order and Process Costin Accounting
Job Order and Process Costin AccountingJob Order and Process Costin Accounting
Job Order and Process Costin Accounting
 
Product costing system
Product costing systemProduct costing system
Product costing system
 
Job order costing and Process costing
Job order costing and Process costingJob order costing and Process costing
Job order costing and Process costing
 
Job costing power point show
Job costing power point showJob costing power point show
Job costing power point show
 
Manufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba financeManufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba finance
 
Job order costing
Job order costingJob order costing
Job order costing
 
Process Costing
Process CostingProcess Costing
Process Costing
 
Chapter 4 : Analysis For Decision Making
Chapter 4 : Analysis For Decision MakingChapter 4 : Analysis For Decision Making
Chapter 4 : Analysis For Decision Making
 
Cost allocation
Cost allocationCost allocation
Cost allocation
 
Chapter 9 study guide
Chapter 9 study guideChapter 9 study guide
Chapter 9 study guide
 
55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap55811936 product-costing-cost-estimation-in-sap
55811936 product-costing-cost-estimation-in-sap
 
Job order costing
Job order costingJob order costing
Job order costing
 
Just in Time Cost
Just in Time CostJust in Time Cost
Just in Time Cost
 
Abc costig
Abc costigAbc costig
Abc costig
 
Costing of Formal Shirt
Costing of Formal ShirtCosting of Formal Shirt
Costing of Formal Shirt
 

Viewers also liked

Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
Megha Shah
 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing h
MitikaAnjel
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
Rai University
 
Process costing
Process costingProcess costing
Process costing
Prem Chand
 

Viewers also liked (20)

Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
 
Fma10
Fma10Fma10
Fma10
 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing h
 
Standard costing
Standard costingStandard costing
Standard costing
 
Process costing
Process costingProcess costing
Process costing
 
Standard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsStandard Costing - Uses & Limitations
Standard Costing - Uses & Limitations
 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Process Costing- Chapter Four
Process Costing- Chapter FourProcess Costing- Chapter Four
Process Costing- Chapter Four
 
Standard & labour costing
Standard & labour costingStandard & labour costing
Standard & labour costing
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Process costing
Process costingProcess costing
Process costing
 
Process costing
Process costingProcess costing
Process costing
 
Standard Costing & Variances
Standard Costing & VariancesStandard Costing & Variances
Standard Costing & Variances
 
Process costing explained
Process costing explainedProcess costing explained
Process costing explained
 
Standard costing and its types
Standard costing and its typesStandard costing and its types
Standard costing and its types
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 

Similar to People Soft Standard Costing Dmug

Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Kenesha Marshall
 
cost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service designcost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service design
BeaDelaPenia1
 
activity_based_costing power point presentation
activity_based_costing power point presentationactivity_based_costing power point presentation
activity_based_costing power point presentation
ChamodiBandara1
 

Similar to People Soft Standard Costing Dmug (20)

Standard costing
Standard costingStandard costing
Standard costing
 
Cost accounting By CA Ankush Gupta
Cost accounting By CA Ankush GuptaCost accounting By CA Ankush Gupta
Cost accounting By CA Ankush Gupta
 
Cost Accounting
Cost AccountingCost Accounting
Cost Accounting
 
UNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTINGUNIT IV COST ACCOUNTING
UNIT IV COST ACCOUNTING
 
Innovative Inventory and Production Management Techniques
Innovative Inventory and  Production Management TechniquesInnovative Inventory and  Production Management Techniques
Innovative Inventory and Production Management Techniques
 
Process costing (1)
Process costing (1)Process costing (1)
Process costing (1)
 
Case Study_SAP Material Ledger
Case Study_SAP Material LedgerCase Study_SAP Material Ledger
Case Study_SAP Material Ledger
 
Case study in implementing sap material ledger
Case study in implementing sap material ledgerCase study in implementing sap material ledger
Case study in implementing sap material ledger
 
Chapter 3 : Overhead Analysis
Chapter 3 : Overhead AnalysisChapter 3 : Overhead Analysis
Chapter 3 : Overhead Analysis
 
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
 
cost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service designcost accounting chapter 6, fundamentals of product and service design
cost accounting chapter 6, fundamentals of product and service design
 
Unit 3
Unit 3Unit 3
Unit 3
 
ERP 101: Tracking Costs Using ERP
ERP 101: Tracking Costs Using ERPERP 101: Tracking Costs Using ERP
ERP 101: Tracking Costs Using ERP
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptx
 
job oder cost system part one.pptx
job oder cost system part one.pptxjob oder cost system part one.pptx
job oder cost system part one.pptx
 
Process Costing
Process CostingProcess Costing
Process Costing
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
As 2 inventories valuation
As   2 inventories valuationAs   2 inventories valuation
As 2 inventories valuation
 
activity_based_costing power point presentation
activity_based_costing power point presentationactivity_based_costing power point presentation
activity_based_costing power point presentation
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 

People Soft Standard Costing Dmug

  • 2. 2 Outline • Introduction – Who is this guy? • What is Standard Cost? • What is Actual Cost? • What are the different Actual Cost Methods? • Is it better? • How would I change from Standard to Actual Costing?
  • 3. 3 Introduction Ron Caldwell • Former practicing CPA with 4 years experience in “Big 5” Public Accounting • 2 years Private Sector Accounting for US Defense Contractor • Beta tested PeopleSoft Cost Management version 5.0 • 9+ years working “hands-on” with PeopleSoft SCM and Financial Applications the last 4 years in private practice. • Help setup Cost Management for DMUG member Honda of America. • Reengineered setup of Cost Management 8.8 for DMUG member: Monster Cable Products and Combe, Inc
  • 4. 4 What is Standard Cost? • Standard Cost is a predefined calculation of the costs to produce a good under specified “standard” working conditions. • It is built up from an assessment of the value of cost elements and correlates technical specifications and the quantification of materials, labor and other costs expected during the period in which the standard cost is intended to be used. • Its main purposes are to provide bases for control through variance accounting, for the valuation of work in progress and for fixing selling prices.
  • 5. 5 What the heck did that mean? • Standard cost is a singular frozen estimate of production costs based on a singular set of assumptions used to evaluate production efficiency through variance analysis. • Standard cost predetermined and intended for a finite period of time.
  • 6. 6 What are Assumptions are used? • The Source Code (Make or Buy) of the Final Product • The Primary Bill of Material (BOM) and the Source Codes (Make, Buy, Floor Stock*, Expensed*) and Standard Costs of the BOM Components • The Primary Production Routing which includes decisions about which Work Centers, what Crews, how many per Crew, how much Operating Time per Crew member, and whether or not any of the production steps are Subcontracted. *Not included in the Standard Cost of the Assembly
  • 7. 7 Standard Cost - Illustrated
  • 8. 8 Fin Goods Production “Make” Cost
  • 9. 9 Typical Lower Level for Fin Goods  These items are comprised of Raw Material items on it’s Bill of Material. So the Cost Elements typical of Raw Material items will comprise the Lower Level cost of the Finished Goods item. These are as follows:  100 – Material – Vendor or Transfer Price  300 – Freight – Inbound Freight Cost  400 – Duty – Inbound Duty Cost  700 – Overhead – Purchasing Overhead
  • 10. 10 Rolling up Lower Level Costs Item 200 Cost Element 100 $8.00 Cost Element 300 $1.50 Cost Element 400 $1.25 Cost Element 700 $1.75 Item 140 Cost Element 100 $1.75 Cost Element 400 $0.75 Cost Element 700 $0.25 Item 160 Cost Element 100 $3.75 Cost Element 300 $1.00 Cost Element 400 $0.50 Cost Element 700 $0.25 Item 180 Cost Element 100 $2.50 Cost Element 300 $0.50 Cost Element 700 $1.25 Cost Elements are retained in the Lower Level Cost as they roll up from Raw Materials to assembled Finished Goods.
  • 11. 11 Bill of Material for a Make Item Sum of the Component cost $6.0419
  • 12. 12 Typical This Level for Fin Goods The cost associated with assembling the Raw Material items into Finished Goods items are the This Level cost for the Finished Goods Item: 200 – Labor – Production Labor 500 – Overhead – Production Overhead 600 – Outside Processing – Subcontracted Production Cost
  • 13. 13 Routing Summary for a Make Item The Routing displays the Work Centers used to assemble the Make Item.
  • 14. 14 Operation Times for a Make Item Note Costing Labor Run is 4 Minutes
  • 15. 15 Crew Size for a Make Item Note Crew Size is 1 Employee
  • 16. 16 Labor Rate for the Work Center The Labor Rate is $19.80/Hr. $19.80 X 1 X (4/60) = $1.3200
  • 17. 17 Overhead Rate for the Work Center The Overhead Rate is 77% of the Labor Amount. $1.3200 X 77% = $1.0164
  • 18. 18 Establishing a Standard Cost • When using Standard Costing establishing a cost standard for each item is a prerequisite for transacting the item for Inventory or Production purposes. • The standard are set after running these two processes: – Cost Rollup – Cost Update
  • 21. 21 Actual Costing for Production Items • Okay, now it’s about to get interesting. • One of the things that production operations will like is that Actual costing doesn’t require a pre-established standard cost before the item can be transacted. • With Actual Costing the Cost Rollup and Cost Update process is not required.
  • 22. 22 What is Actual Costing? • Actual Costing values inventory based on the “best available” actual cost information at the time including purchase order price or matched vendor invoice price, and actual production labor and machine time. • The release of PeopleSoft 8.8 Cost Management made available the use of Actual and Average Costing Methods for production inventories. • Prior to 8.8 Standard Costing was the only cost method available for production inventories
  • 23. 23 Actual Costing emphasizes Material Cost • Standard cost accounting methods were developed about 100 years ago, when labor comprised the most important cost in manufactured goods. The emphasis on measuring production labor efficiency in one of the prime sources of criticism by Eliyahu “theory of constraints” Goldratt. • Actual Costing endeavors to reflect the actual vendor cost for the material component of production inventories.
  • 24. 24 Actual Costing for “Buy” Items • Purchased goods are initially valued based on the Purchase Order Price at the time of Receipt. • The value of purchased goods is adjusted for any difference between the Purchase Order price and the Vendor Invoice price after the related voucher is MATCHED, POSTED, and EXTRACTED via the Landed Cost Extract Process. • The adjusted cost of the purchased goods flow into Work-in-Process cost based upon the Costing Method selected.
  • 26. 26 Actual Costing Methods for Outputs • The Actual Costing methods include: – FIFO (First-in, First-out) – LIFO (Last-in, First-out) • The Weighted Average Costing Methods include: – Periodic – calculated at month-end – all depletions use the same average. – Perpetual – calculated throughout period based on information available at the time of the depletions – Retroactive – similar to perpetual except that depletions are revalued retroactively at month end for all for AP match and post activity during the month
  • 27. 27 Costing Methods on Cost Profile Page
  • 28. 28 Calculating Labor and Machine Cost • Labor and Machine Cost can be added to material cost based on following selections on the Cost Profile-Manufacturing Page: – Not Applicable – Standard Time-Conversion Rate – Actual Time-Conversion Rate – Actual Time-Actual Rate (Labor Only)
  • 29. 29 Cost Profile Mfg Labor Cost
  • 30. 30 Labor and Machine Cost Inputs
  • 32. 32 Actual costing eliminates variances • You can chose to eliminate Purchase Price Variance Expense for inventory purchases. Any difference between purchase order and invoice price updates the basis of the good, even if it has been consumed into work-in-process and the assembly had been shipped to a customer. • You will not have Material, Conversion or Rework Variances, or Subcontract PPV Expense for production work orders because these costs are added to the basis of the assemblies produced.
  • 33. 33 Is it better? • Actual costing is flexible. Each production transaction is valued exactly in the manner in which it is produced for those who might use alternate sourcing, Bill of Material or Routing. • It is especially beneficial to those who extensively use Product Configurator in Production • Actual Costing ultimately provides the most accurate inventory information for evaluating production costs and gross margin. • Yes, it’s better! Period!
  • 34. 34 Actual Costing Caveats • You should develop a reasonable means for Current Purchase Cost for Bill of Material (BOM) components and Default Actual Cost for All Actual Cost items. • Current Purchase Cost (or Last Price Paid) is used to cost components when no cost is available such as when inventory of the component is negative. • Default Actual Cost is used cost any “Increase” adjustment transaction like Cycle Count and User adjustments. It is also used to value RMA transactions as well
  • 35. 35 One more Caveat • When running the Cost Accounting Creation process it is very important to run using the Mid-Period Mode during the month and Regular Mode on the last day of the month especially when using an Average Costing Method.
  • 37. 37 Migrating from Standard to Actual Cost • Oracle does not have a certified upgrade methodology for migrating from standard cost to an actual or average costing method. • There will not be a one size fits all solution for migration. • At Combe we will develop a methodology for migrating from Standard to Actual Costing where the initial Actual Cost of Inventory will be equal to the Standard Cost.
  • 39. 39 Appendix - More Standard Cost Info
  • 40. 40 Standard Cost is predicated on the creation and analysis of variances. Variances are created on most purchase and production transactions.
  • 41. 41 Standard Purchase Price Variance There are two instances where PPV may apply: The Purchase Order Price differs from the Standard Cost for an Item (PPV 1). The Voucher Price MATCHED and POSTED differs from the Purchase Order Price (PPV2). This variance is extracted from Accounts Payable using the Landed Cost Extract process
  • 42. 42 Standard Cost Production Variances Material Variance – to account for deviations from the Primary Bill of Material (BOM) Conversion Variance – to account for deviations from the Primary Production Routing Rework Expense – to account for the additional material and processing cost associated with rework production.
  • 43. 43 Walkthrough of the Cost Rollup of “Buy Items.
  • 44. 44 Cost Elements for Raw Material Items Cost Elements typically used: 100 – Material – Vendor or Transfer Price 300 – Freight – Inbound Freight Cost 400 – Duty – Inbound Duty Cost 700 – Overhead – Purchasing Overhead Cost Elements NEVER used: 200 – Labor – Production Labor 500 – Overhead – Production Overhead 600 – Outside Processing – Subcontracted Production Cost
  • 45. 45 Material Standard Cost for “Buy” Items • The material cost for these items are primarily comprised of purchased cost. The standards for these items can be derived from one of these sources: – Current Cost – Average Cost – Last Price Paid – Forecasted Purchase Price • Despite by names like “Current” and “Last Price” the material standards remain frozen (unchanged) between Standard Cost Updates.
  • 47. 47 Raw Material Item Raw Material items only have cost at This Level because they do not have a Bill of Material.
  • 48. 48 Raw Item Current Purchase Cost The Material Cost should equal the Current Purchase Cost for each unit.
  • 49. 49 Raw Item Vendor-Item Set-up The Vendor Price on PO’s will be compared to ONLY CE 100 to determine PPV.
  • 50. 50 Raw Item Freight-In Cost 3.9% X $3.48 = $0.1357
  • 51. 51 Raw Item Duty-In Cost 5.8% X $3.48 = $0.2018
  • 52. 52 Raw Item Purchasing Overhead Cost 5.1% X $3.48 = $0.1775
  • 53. 53 Cost Elements for FG “Buy” Items Cost Elements typically used: 100 – Material – Vendor or Transfer Price 300 – Freight – Inbound Freight Cost 400 – Duty – Inbound Duty Cost 700 – Overhead – Purchasing Overhead Cost Elements NEVER used: 200 – Labor – Production Labor 500 – Overhead – Production Overhead 600 – Outside Processing – Subcontracted Production Cost
  • 54. 54 Finished Goods “Buy” Item Finished Goods Buy items are similar to Raw items in that they only have This Level cost.
  • 55. 55 Now it gets exciting because we’re going to illustrate the Accounting Debit and Credits for a few typical transactions.
  • 56. 56 Buying a Raw Material Item DR 1200-Inventory-Raw Stk 3.9950 CR 2100-Accrued Liabilities- Inventory 3.4800 CR 5159-Applied-Ocean Freight In 0.1357 CR 5169-Applied-Customs- Duty 0.2018 CR 5999-COGSI-Overhead Absorption 0.1775
  • 57. 57 Issuing Material to a PID DR 1300 – Inventory WIP 6.0419 CR 1200 – Inventory Raw Stk 6.0419
  • 58. 58 Applying Labor to a PID DR 1300 – Inventory WIP 1.3200 CR 5149– COGSD-Direct Labor Absorption 1.3200
  • 59. 59 Applying Overhead to a PID DR 1300 – Inventory WIP 1.0164 CR 5999 – COGSI- Overhead Absorption 1.0164
  • 60. 60 Closing a Production Order (PID) DR 1400 – Inventory Finished 8.3783 CR 1300 – Inventory WIP 8.3783
  • 61. 61 Issuing Material to a Customer DR 5000 – COGSD- Taxable 8.3783 CR 1400 – Inventory Finished Goods 8.3783
  • 62. 62 Contact Information If you have any questions please feel free to contact me at: Rondal A Caldwell, CPA Caldwell + Associates 1900 West 42nd Street Austin, TX 78704 832-741-7427