Embed presentation








The document discusses the forward and backward pass technique used to find the critical path in a project schedule network diagram. The forward pass is used to determine the early start and finish times by calculating the early finish as the early start plus duration minus one. The backward pass then calculates the late start and finish times by setting the late finish to be the highest early finish and calculating late start as late finish minus duration plus one. Float is defined as the difference between late start and early start, and the critical path is the path with zero float.







