PROJECT SCHEDULING
The tool that communicates what work needs to be performed,
which resources of the organization will perform the work and
the timeframes in which that work needs to be performed.
The project schedule should reflect all of the work associated
with delivering the project on time. Without a full and
complete schedule, the project manager will be unable to
communicate the complete effort, in terms of cost and
resources, necessary to deliver the project.
For making a schedule, a TIME-SCALED NETWORK ANALYSIS
is used .
COMMON TYPES OF PROJECT SCHEDULING:
GANTT CHART with S-Curve
PERT - Program Evaluation and Review Technique
CPM - Critical Path MethOd
PDM- Precedence diagram method
GANTT CHART
 A tool used for planning and scheduling project
activities and to monitor progress over time by
comparing planned and actual progress
 A display of cumulative costs, progress or other
quantities plotted against time. The name derives
from the S-like shape of the curve, flatter at the
beginning and end and steeper in the middle,
which is typical of most projects. The beginning
represents a slow, deliberate but accelerating
start, while the end represents a deceleration as
the work runs out.
S- CURVE
PERT was Developed as a result of looking
for an improved method of planning and
evaluating progress of a large scale research
and development program.
Designed to provide the management a
periodic reporting of current status and an
outlook for the future on meeting approved
plans and schedules
PERT - Program Evaluation and
Review Technique
CPM - Critical Path Method
Designed as a tool for planning, scheduling
and control of construction work
Its emphasis was on the work or activities to
be managed
COMPARISON : PERT VS CPM
PERT CPM
PERT is a project management
technique, used to manage uncertain
activities of a project.
CPM is a statistical technique of project
management that manages well defined
activities of a project.
A technique of planning and control of
time.
A method to control cost and time.
Event-oriented Activity-oriented
Evolved as Research & Development
project
Evolved as Construction project
Probabilistic Model Deterministic Model
Time Time-cost trade-off
Unpredictable Activities Predictable activities
Research and Development Project Non-research projects like civil
construction, ship building etc.
PERT/CPM
PERT AND CPM combined, is a control tool for defining
the parts of construction job and then putting them
together in a NETWORK form.
It serves as an aid to the construction manager but it
does not make decision for him nor it does guarantee go
od management. It only serves the project manager to
see the whole picture of the entire job.
It encourages periodic re-evaluation and providing an
accurate measure of progress. Thus, a person in charge
of each work and the project manager knows WHAT is
supposed to happen and WHEN it is supposed to
happen.
PERT/CPM
PRESIDENTIAL DECREE (PD) 1594
Prescribing Policies, Guidelines, Rules and
Regulations for Government Infrastructure
Contract
PERT/CPM
The project manager can easily obtain
 Graphical display of project activities
 Estimate of how long will the project last
 Determine which activities are the most
critical to timely project completion
 Determine how long any activity can be
delayed without lengthening the project
THREE PHASES OF PERT/CPM
 PLANNING
 SCHEDULING
 CONTROLLING AND MONITORING
THREE PHASES OF PERT/CPM
PLANNING
 Defined as determining the relationship
between the work operation and the
sequence in which they are to be
performed
THREE PHASES OF PERT/CPM
PLANNING
1. Dividing the project into distinct activities.
2. Estimating time requirement for each activity.
3. Establishing precedence relationship among
activities.
4. Construction of the arrow diagram (network)
PLANNING PHASE
 FIVE INPUTS THAT CAN BE OBTAINED
1. A network diagram defining the
activities in the project
2. Duration of activities
3. Cost estimates of the activities for
monitoring cost, cash flow requirements
4. Resource estimates
5. Trade indicators (responsibility) for
activity grouping
THREE PHASES OF PERT/CPM
SCHEDULING
 Defined as the process of translating the
arrow diagram into time table of calendar
days. Determines the start and end time of
every activity.
SCHEDULE PHASE
FOUR OUTPUT THAT CAN BE OBTAINED
1. Schedule of activities in the network
diagram (critical activities, earliest start,
earliest finish, latest start, latest finish,
float)
2. Bar Chart or a Time-Scaled Network
3. Resource Analysis
4. Cash Requirement
THREE PHASES OF PERT/CPM
CONTROLLING AND MONITORING
 Flexibility and updated re-computations
brought about by changing conditions is
the key to a successful network
programming, wherein, this must be
updated periodically.
CONTROLLING AND MONITORING
PHASE
THE OUTPUT PHASE:
1. Time Status Report
2. Revised Schedules
3. Revised Bar Charts/Arrow Diagram/
Network
4. Revised resource Analysis
5. Revised Cash Flow analysis
CONTROLLING AND MONITORING
PHASE
USES ACTUAL DATAS INCLUDING:
1. Additions to the project
2. Deletion from the project
3. Changes as to duration, description, trade
indicators, cost and resource estimates
4. Actual Starting Dates
5. Actual Finishing Dates.
NETWORK or ARROW
DIAGRAM
A project consists of interrelated activities which are to
be executed in a certain order before the entire task is
completed.
The activities are interrelated in a logical sequence
which is known as Precedence relationship.
Project is represented in the form of network for the
purpose of analytical treatment to get solutions for
scheduling and controlling its activities.
A Network diagram are composed mainly of a number
of Arrows (Activity) and Nodes (Events)
ELEMENTS OF NETWORK DIAGRAMMING
Activity (Arrows) - is the work
operations required to complete a task
or the actual work between events.
Events (Nodes) – Point in time
signifying the beginning or end of one
or more activities.
Dummy Activity- an arrow with
imaginary activity on a network
showing the precedence relationship
between two activities. Duration = 0
Duration – the time it takes an activity
to be finished.
Path- a sequence of activities that
leads from the starting node to the
finishing node.
NETWORK FUNDAMENTALS
Conventions:
1. Activity on Arrow
2. Activity on Node
Principles :
1. Everything on the
Diagram must have
meaning.
2. An activity has a single
definite starting point (tail
event) and a single ending
point (head event)
3. The network does not
describe time relationship
but rather dependency
relationship
4. The network is hardly
ever done by a single
person.
THE NETWORK DIAGRAM
Critical Path - Is the longest
route in the network of a project
representing a project. The sum
of the activities duration along
this path will be the DURATION
OF THE PROJECT, any delays
within these activities may result
to delay on the entire project.
Two Phases:
1. Forward Pass – determining
the Earliest Start (ES) Event
1. Backward Pass-
Determining the Latest
Finish (LF) Event
THE NETWORK DIAGRAM
Earliest Event – earliest occurrence of
an event and numerically equal to the
longest path of activities in series from
the project start to finish.
ES – Earliest Start Event
ES(n) =MAX { EF(n-1) + D(n)}
EF- Earliest Finish Event
EF(n) =ES(n-1)+ D(n)
Latest Events - latest time the event
may occur without delaying project
completion.
LS – Latest Start Event
LS(n) =LF(n+1) - D(n)
LF- Latest Finish Event
LF(n) =MIN { LF(n+1) - D(n)}
THE NETWORK DIAGRAM
Conditions for Critical Path:
1. Based on Earliest Start and Latest
Finish:
ES(1) = LF(1)
ES(n) = LF(n)
ES(n) - ES(1) = LF(n) - LF(1) = D(n)
1. Based on Total Float and Free
Float:
TF(n) = FF(n) =0
THE NETWORK DIAGRAM
Total Float (TF) - the span of time
an activity can be delayed after its
earliest start time without delaying
the project completion.
TF (n) =LF(n)- EF(n)
TF (n) =LF(n)- ES(n-1)- D(n)
Free Float (FF) – the span of time
that the activity completion time
can be delayed without affecting the
Earliest Start Time of immediate
successor activities in the network.
FF (n) =ES(n)- ES(n-1)- D(n)
1. The starting event and
ending event of an activity
are also called tail event
and head event respectively.
2. The network should have a
unique starting node (tail
event).
3. The network should have a
unique completion node
(head event).
4. No activity should be
represented more than one
activity in the network.
5. No two activities should
have the same starting
node and the same ending
node.
6. Duration of a dummy
activity is zero
Guidelines for Network
Construction
Example:
ACTIVITY PREDECESSOR(S)
DURATION
(WEEKS)
A - 2
B - 5
C - 4
D B 5
E A 7
F A 3
G B 3
H C,D 6
I C,D 2
J E 5
K F,G,H 4
L F,G,H 3
M I 12
N J,K 8
1. Construct the Network
diagram for this data from a
project:
2. Determine the Critical Path
and Determine the total
duration of the Project
3. Compute the Total Float and
Free Float
Seatwork:
ACTIVITY PREDECESSOR(S)
DURATION
(WEEKS)
A - 6
B - 3
C - 4
D A 2
E B 3
F C 5
G C 3
H E,F 5
I D 5
J HG 3
1. Construct the Network
diagram for this data from a
project:
2. Determine the Critical Path
and Determine the total
duration of the Project
1. Construct the Network
diagram for this data from a
project:
2. Determine the Critical Path
and Determine the total
duration of the Project
3. Compute the Total Float and
Free Float
REMINDERS: BSCE 4A
Reporting- Printed Output – last submission Friday, March22,
2019
FINAL EXAM - Tuesday, MARCH 28, 2019 6-9PM
Coverage: Chapters 3-9
PIT (Assignment) – Printed Output submitted
on/before April 01, 2019.
Output: Project Drawings, Program of
Works, Gantt Chart with S-Curve and
PERT/CPM network diagram
REMINDERS: BSCE 4C
Reporting- Printed Output – last submission Friday, March22,
2019
FINAL EXAM - Tuesday, MARCH 26, 2019 6-9PM
Coverage: Chapters 1-9
PIT (Assignment) – Printed Output submitted
on/before April 01, 2019.
Output: Project Drawings, Program of
Works, Gantt Chart with S-Curve and
PERT/CPM network diagram

More Related Content

What's hot

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Anand Subramaniam
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
NR Computer Learning Center
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and control
Dr.R. SELVAM
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
VARSHA RUSTAGI
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Carla Fair-Wright
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Alecsis Roe Frasco
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
Insaf Ali Soomro PMP
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
Farhana Rehman
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
Institute of Rural Management
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
Project management planning
Project management planningProject management planning
Project management planning
Alvin Niere
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
Agus Suhanto
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
Vikram Thadeshvar
 

What's hot (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and control
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project management planning
Project management planningProject management planning
Project management planning
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
06 project time management
06  project time management06  project time management
06 project time management
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 

Similar to PROJECT-SCHEDULING-pptx.pptx

project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
abdelazizfarag1
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
AynetuTerefe2
 
Pert and gantt chart.pptx
Pert and gantt chart.pptxPert and gantt chart.pptx
Pert and gantt chart.pptx
ABHIJEETKUMAR992494
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
RajnikantPatel45
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
HarSimaranSinghBhamr
 
porject management
porject managementporject management
porject management
BANDJO Chabrel
 
06 pert cpm (1)
06 pert cpm (1)06 pert cpm (1)
06 pert cpm (1)
NAGENDRAKUMARS
 
Pert
PertPert
Pert
corvinno
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
ssusere57332
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
Siddanna Balapgol
 

Similar to PROJECT-SCHEDULING-pptx.pptx (20)

project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Pert and gantt chart.pptx
Pert and gantt chart.pptxPert and gantt chart.pptx
Pert and gantt chart.pptx
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
porject management
porject managementporject management
porject management
 
06 pert cpm (1)
06 pert cpm (1)06 pert cpm (1)
06 pert cpm (1)
 
Pert
PertPert
Pert
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 

More from TecnicoItca

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
TecnicoItca
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
TecnicoItca
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
TecnicoItca
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
TecnicoItca
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
TecnicoItca
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
TecnicoItca
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
TecnicoItca
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
TecnicoItca
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
TecnicoItca
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
TecnicoItca
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
TecnicoItca
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
TecnicoItca
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
TecnicoItca
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
TecnicoItca
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
TecnicoItca
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
TecnicoItca
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
TecnicoItca
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
TecnicoItca
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
TecnicoItca
 

More from TecnicoItca (20)

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 

Recently uploaded

Online fraud prediction and prevention.pptx
Online fraud prediction and prevention.pptxOnline fraud prediction and prevention.pptx
Online fraud prediction and prevention.pptx
madihasultana209
 
Vernier Caliper and How to use Vernier Caliper.ppsx
Vernier Caliper and How to use Vernier Caliper.ppsxVernier Caliper and How to use Vernier Caliper.ppsx
Vernier Caliper and How to use Vernier Caliper.ppsx
Tool and Die Tech
 
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
YanKing2
 
Introduction to IP address concept - Computer Networking
Introduction to IP address concept - Computer NetworkingIntroduction to IP address concept - Computer Networking
Introduction to IP address concept - Computer Networking
Md.Shohel Rana ( M.Sc in CSE Khulna University of Engineering & Technology (KUET))
 
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptxIE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
BehairyAhmed2
 
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
PradeepKumarSK3
 
libro de modelado de diseño-part-1[160-250].pdf
libro de modelado de diseño-part-1[160-250].pdflibro de modelado de diseño-part-1[160-250].pdf
libro de modelado de diseño-part-1[160-250].pdf
celiosilva66
 
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
amzhoxvzidbke
 
Online airline reservation system project report.pdf
Online airline reservation system project report.pdfOnline airline reservation system project report.pdf
Online airline reservation system project report.pdf
Kamal Acharya
 
Quadcopter Dynamics, Stability and Control
Quadcopter Dynamics, Stability and ControlQuadcopter Dynamics, Stability and Control
Quadcopter Dynamics, Stability and Control
Blesson Easo Varghese
 
Disaster Management and Mitigation presentation
Disaster Management and Mitigation presentationDisaster Management and Mitigation presentation
Disaster Management and Mitigation presentation
RajaRamannaTarigoppu
 
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY pptCONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
ASHOK KUMAR SINGH
 
Adv. Digital Signal Processing LAB MANUAL.pdf
Adv. Digital Signal Processing LAB MANUAL.pdfAdv. Digital Signal Processing LAB MANUAL.pdf
Adv. Digital Signal Processing LAB MANUAL.pdf
T.D. Shashikala
 
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
IJAEMSJORNAL
 
Top EPC companies in India - Best EPC Contractor
Top EPC companies in India - Best EPC  ContractorTop EPC companies in India - Best EPC  Contractor
Top EPC companies in India - Best EPC Contractor
MangeshK6
 
Rockets and missiles notes engineering ppt
Rockets and missiles notes engineering pptRockets and missiles notes engineering ppt
Rockets and missiles notes engineering ppt
archithaero
 
readers writers Problem in operating system
readers writers Problem in operating systemreaders writers Problem in operating system
readers writers Problem in operating system
VADAPALLYPRAVEENKUMA1
 
printing of ic circuits.pdf
printing       of        ic     circuits.pdfprinting       of        ic     circuits.pdf
printing of ic circuits.pdf
chidambaramnatarajar
 
Evento anual Splunk .conf24 Highlights recap
Evento anual Splunk .conf24 Highlights recapEvento anual Splunk .conf24 Highlights recap
Evento anual Splunk .conf24 Highlights recap
Rafael Santos
 
ARITMETICO.pdf xxxxxxxxxxxxxxxxxxxxxxxx
ARITMETICO.pdf  xxxxxxxxxxxxxxxxxxxxxxxxARITMETICO.pdf  xxxxxxxxxxxxxxxxxxxxxxxx
ARITMETICO.pdf xxxxxxxxxxxxxxxxxxxxxxxx
alemaro1123
 

Recently uploaded (20)

Online fraud prediction and prevention.pptx
Online fraud prediction and prevention.pptxOnline fraud prediction and prevention.pptx
Online fraud prediction and prevention.pptx
 
Vernier Caliper and How to use Vernier Caliper.ppsx
Vernier Caliper and How to use Vernier Caliper.ppsxVernier Caliper and How to use Vernier Caliper.ppsx
Vernier Caliper and How to use Vernier Caliper.ppsx
 
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
Natural Is The Best: Model-Agnostic Code Simplification for Pre-trained Large...
 
Introduction to IP address concept - Computer Networking
Introduction to IP address concept - Computer NetworkingIntroduction to IP address concept - Computer Networking
Introduction to IP address concept - Computer Networking
 
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptxIE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
IE-469-Lecture-Notes-3IE-469-Lecture-Notes-3.pptx
 
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
21EC63_Module1B.pptx VLSI design 21ec63 MOS TRANSISTOR THEORY
 
libro de modelado de diseño-part-1[160-250].pdf
libro de modelado de diseño-part-1[160-250].pdflibro de modelado de diseño-part-1[160-250].pdf
libro de modelado de diseño-part-1[160-250].pdf
 
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
李易峰祝绪丹做爱视频流出【网芷:ht28.co】可爱学生妹>>>[网趾:ht28.co】]<<<
 
Online airline reservation system project report.pdf
Online airline reservation system project report.pdfOnline airline reservation system project report.pdf
Online airline reservation system project report.pdf
 
Quadcopter Dynamics, Stability and Control
Quadcopter Dynamics, Stability and ControlQuadcopter Dynamics, Stability and Control
Quadcopter Dynamics, Stability and Control
 
Disaster Management and Mitigation presentation
Disaster Management and Mitigation presentationDisaster Management and Mitigation presentation
Disaster Management and Mitigation presentation
 
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY pptCONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
CONFINED SPACE ENTRY TRAINING FOR OIL INDUSTRY ppt
 
Adv. Digital Signal Processing LAB MANUAL.pdf
Adv. Digital Signal Processing LAB MANUAL.pdfAdv. Digital Signal Processing LAB MANUAL.pdf
Adv. Digital Signal Processing LAB MANUAL.pdf
 
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
Best Practices of Clothing Businesses in Talavera, Nueva Ecija, A Foundation ...
 
Top EPC companies in India - Best EPC Contractor
Top EPC companies in India - Best EPC  ContractorTop EPC companies in India - Best EPC  Contractor
Top EPC companies in India - Best EPC Contractor
 
Rockets and missiles notes engineering ppt
Rockets and missiles notes engineering pptRockets and missiles notes engineering ppt
Rockets and missiles notes engineering ppt
 
readers writers Problem in operating system
readers writers Problem in operating systemreaders writers Problem in operating system
readers writers Problem in operating system
 
printing of ic circuits.pdf
printing       of        ic     circuits.pdfprinting       of        ic     circuits.pdf
printing of ic circuits.pdf
 
Evento anual Splunk .conf24 Highlights recap
Evento anual Splunk .conf24 Highlights recapEvento anual Splunk .conf24 Highlights recap
Evento anual Splunk .conf24 Highlights recap
 
ARITMETICO.pdf xxxxxxxxxxxxxxxxxxxxxxxx
ARITMETICO.pdf  xxxxxxxxxxxxxxxxxxxxxxxxARITMETICO.pdf  xxxxxxxxxxxxxxxxxxxxxxxx
ARITMETICO.pdf xxxxxxxxxxxxxxxxxxxxxxxx
 

PROJECT-SCHEDULING-pptx.pptx

  • 1. PROJECT SCHEDULING The tool that communicates what work needs to be performed, which resources of the organization will perform the work and the timeframes in which that work needs to be performed. The project schedule should reflect all of the work associated with delivering the project on time. Without a full and complete schedule, the project manager will be unable to communicate the complete effort, in terms of cost and resources, necessary to deliver the project. For making a schedule, a TIME-SCALED NETWORK ANALYSIS is used .
  • 2. COMMON TYPES OF PROJECT SCHEDULING: GANTT CHART with S-Curve PERT - Program Evaluation and Review Technique CPM - Critical Path MethOd PDM- Precedence diagram method
  • 3. GANTT CHART  A tool used for planning and scheduling project activities and to monitor progress over time by comparing planned and actual progress  A display of cumulative costs, progress or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, which is typical of most projects. The beginning represents a slow, deliberate but accelerating start, while the end represents a deceleration as the work runs out. S- CURVE
  • 4. PERT was Developed as a result of looking for an improved method of planning and evaluating progress of a large scale research and development program. Designed to provide the management a periodic reporting of current status and an outlook for the future on meeting approved plans and schedules PERT - Program Evaluation and Review Technique
  • 5. CPM - Critical Path Method Designed as a tool for planning, scheduling and control of construction work Its emphasis was on the work or activities to be managed
  • 6. COMPARISON : PERT VS CPM PERT CPM PERT is a project management technique, used to manage uncertain activities of a project. CPM is a statistical technique of project management that manages well defined activities of a project. A technique of planning and control of time. A method to control cost and time. Event-oriented Activity-oriented Evolved as Research & Development project Evolved as Construction project Probabilistic Model Deterministic Model Time Time-cost trade-off Unpredictable Activities Predictable activities Research and Development Project Non-research projects like civil construction, ship building etc.
  • 7. PERT/CPM PERT AND CPM combined, is a control tool for defining the parts of construction job and then putting them together in a NETWORK form. It serves as an aid to the construction manager but it does not make decision for him nor it does guarantee go od management. It only serves the project manager to see the whole picture of the entire job. It encourages periodic re-evaluation and providing an accurate measure of progress. Thus, a person in charge of each work and the project manager knows WHAT is supposed to happen and WHEN it is supposed to happen.
  • 8. PERT/CPM PRESIDENTIAL DECREE (PD) 1594 Prescribing Policies, Guidelines, Rules and Regulations for Government Infrastructure Contract
  • 9. PERT/CPM The project manager can easily obtain  Graphical display of project activities  Estimate of how long will the project last  Determine which activities are the most critical to timely project completion  Determine how long any activity can be delayed without lengthening the project
  • 10. THREE PHASES OF PERT/CPM  PLANNING  SCHEDULING  CONTROLLING AND MONITORING
  • 11. THREE PHASES OF PERT/CPM PLANNING  Defined as determining the relationship between the work operation and the sequence in which they are to be performed
  • 12. THREE PHASES OF PERT/CPM PLANNING 1. Dividing the project into distinct activities. 2. Estimating time requirement for each activity. 3. Establishing precedence relationship among activities. 4. Construction of the arrow diagram (network)
  • 13. PLANNING PHASE  FIVE INPUTS THAT CAN BE OBTAINED 1. A network diagram defining the activities in the project 2. Duration of activities 3. Cost estimates of the activities for monitoring cost, cash flow requirements 4. Resource estimates 5. Trade indicators (responsibility) for activity grouping
  • 14. THREE PHASES OF PERT/CPM SCHEDULING  Defined as the process of translating the arrow diagram into time table of calendar days. Determines the start and end time of every activity.
  • 15. SCHEDULE PHASE FOUR OUTPUT THAT CAN BE OBTAINED 1. Schedule of activities in the network diagram (critical activities, earliest start, earliest finish, latest start, latest finish, float) 2. Bar Chart or a Time-Scaled Network 3. Resource Analysis 4. Cash Requirement
  • 16. THREE PHASES OF PERT/CPM CONTROLLING AND MONITORING  Flexibility and updated re-computations brought about by changing conditions is the key to a successful network programming, wherein, this must be updated periodically.
  • 17. CONTROLLING AND MONITORING PHASE THE OUTPUT PHASE: 1. Time Status Report 2. Revised Schedules 3. Revised Bar Charts/Arrow Diagram/ Network 4. Revised resource Analysis 5. Revised Cash Flow analysis
  • 18. CONTROLLING AND MONITORING PHASE USES ACTUAL DATAS INCLUDING: 1. Additions to the project 2. Deletion from the project 3. Changes as to duration, description, trade indicators, cost and resource estimates 4. Actual Starting Dates 5. Actual Finishing Dates.
  • 19. NETWORK or ARROW DIAGRAM A project consists of interrelated activities which are to be executed in a certain order before the entire task is completed. The activities are interrelated in a logical sequence which is known as Precedence relationship. Project is represented in the form of network for the purpose of analytical treatment to get solutions for scheduling and controlling its activities. A Network diagram are composed mainly of a number of Arrows (Activity) and Nodes (Events)
  • 20. ELEMENTS OF NETWORK DIAGRAMMING Activity (Arrows) - is the work operations required to complete a task or the actual work between events. Events (Nodes) – Point in time signifying the beginning or end of one or more activities. Dummy Activity- an arrow with imaginary activity on a network showing the precedence relationship between two activities. Duration = 0 Duration – the time it takes an activity to be finished. Path- a sequence of activities that leads from the starting node to the finishing node.
  • 21. NETWORK FUNDAMENTALS Conventions: 1. Activity on Arrow 2. Activity on Node Principles : 1. Everything on the Diagram must have meaning. 2. An activity has a single definite starting point (tail event) and a single ending point (head event) 3. The network does not describe time relationship but rather dependency relationship 4. The network is hardly ever done by a single person.
  • 22. THE NETWORK DIAGRAM Critical Path - Is the longest route in the network of a project representing a project. The sum of the activities duration along this path will be the DURATION OF THE PROJECT, any delays within these activities may result to delay on the entire project. Two Phases: 1. Forward Pass – determining the Earliest Start (ES) Event 1. Backward Pass- Determining the Latest Finish (LF) Event
  • 23. THE NETWORK DIAGRAM Earliest Event – earliest occurrence of an event and numerically equal to the longest path of activities in series from the project start to finish. ES – Earliest Start Event ES(n) =MAX { EF(n-1) + D(n)} EF- Earliest Finish Event EF(n) =ES(n-1)+ D(n) Latest Events - latest time the event may occur without delaying project completion. LS – Latest Start Event LS(n) =LF(n+1) - D(n) LF- Latest Finish Event LF(n) =MIN { LF(n+1) - D(n)}
  • 24. THE NETWORK DIAGRAM Conditions for Critical Path: 1. Based on Earliest Start and Latest Finish: ES(1) = LF(1) ES(n) = LF(n) ES(n) - ES(1) = LF(n) - LF(1) = D(n) 1. Based on Total Float and Free Float: TF(n) = FF(n) =0
  • 25. THE NETWORK DIAGRAM Total Float (TF) - the span of time an activity can be delayed after its earliest start time without delaying the project completion. TF (n) =LF(n)- EF(n) TF (n) =LF(n)- ES(n-1)- D(n) Free Float (FF) – the span of time that the activity completion time can be delayed without affecting the Earliest Start Time of immediate successor activities in the network. FF (n) =ES(n)- ES(n-1)- D(n)
  • 26. 1. The starting event and ending event of an activity are also called tail event and head event respectively. 2. The network should have a unique starting node (tail event). 3. The network should have a unique completion node (head event). 4. No activity should be represented more than one activity in the network. 5. No two activities should have the same starting node and the same ending node. 6. Duration of a dummy activity is zero Guidelines for Network Construction
  • 27. Example: ACTIVITY PREDECESSOR(S) DURATION (WEEKS) A - 2 B - 5 C - 4 D B 5 E A 7 F A 3 G B 3 H C,D 6 I C,D 2 J E 5 K F,G,H 4 L F,G,H 3 M I 12 N J,K 8 1. Construct the Network diagram for this data from a project: 2. Determine the Critical Path and Determine the total duration of the Project 3. Compute the Total Float and Free Float
  • 28. Seatwork: ACTIVITY PREDECESSOR(S) DURATION (WEEKS) A - 6 B - 3 C - 4 D A 2 E B 3 F C 5 G C 3 H E,F 5 I D 5 J HG 3 1. Construct the Network diagram for this data from a project: 2. Determine the Critical Path and Determine the total duration of the Project 1. Construct the Network diagram for this data from a project: 2. Determine the Critical Path and Determine the total duration of the Project 3. Compute the Total Float and Free Float
  • 29. REMINDERS: BSCE 4A Reporting- Printed Output – last submission Friday, March22, 2019 FINAL EXAM - Tuesday, MARCH 28, 2019 6-9PM Coverage: Chapters 3-9 PIT (Assignment) – Printed Output submitted on/before April 01, 2019. Output: Project Drawings, Program of Works, Gantt Chart with S-Curve and PERT/CPM network diagram
  • 30. REMINDERS: BSCE 4C Reporting- Printed Output – last submission Friday, March22, 2019 FINAL EXAM - Tuesday, MARCH 26, 2019 6-9PM Coverage: Chapters 1-9 PIT (Assignment) – Printed Output submitted on/before April 01, 2019. Output: Project Drawings, Program of Works, Gantt Chart with S-Curve and PERT/CPM network diagram