SlideShare a Scribd company logo
Plan Scope
Management
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group
Monitoring and Controlling Process
Group
Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project
Management Plan
4.3 Direct and Manage Project
Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or
Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost
Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project
Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk
Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement
Management
12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders
13.2 Plan Stakeholder
Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Plan Scope Management
Coincides with PMBOK 5.1
What is it?
Plan Scope Management is the process of creating a scope
management plan that documents how the project and product scope
will be defined, validated, and controlled.
Why do we do it?
The key benefit of this process is that it provides guidance and
direction on how scope will be managed throughout the project.
Plan Scope Management
Coincides with PMBOK 5.1
Overview
The development of the scope management plan and the
detailing of the project scope begin with the analysis of
information contained in the project charter, the latest
approved subsidiary plans of the project management plan,
historical information contained in the organizational process
assets, and any other relevant enterprise environmental
factors.
Plan Scope Management
Coincides with PMBOK 5.1
Plan Scope Management
Coincides with PMBOK 5.1
Inputs, Tools & Techniques and Outputs
Inputs Tools & Techniques Outputs
1. Project Charter
2. Project Management Plan
• Quality Management Plan
• Project life cycle description
• Development approach
3. Enterprise Environmental
Factors
4. Organisational Process Assets
1. Expert judgment
2. Data Analysis
• Alternatives analysis
3. Meetings
1. Scope Management Plan
2. Requirements
Management Plan
Plan Scope Management
Coincides with PMBOK 5.1
5.1
Plan Scope
Management
Project
Management
Plan
Enterprise
Environmental
Factors
Organisational
Process Assets
Quality
Management
Plan
Development
ApproachProject Life
Cycle
Description
Project
Management Plan
4.1 Develop
Project Charter
Scope
Management
Plan
Benefits
Management
Plan
Plan Scope Management - Inputs
Coincides with PMBOK 5.1
Project Charter
The project charter documents the:
• Project purpose
• High-level project description
• Assumptions
• Constraints
• High-level requirements that the project is intended to satisfy.
Plan Scope Management - Inputs
Coincides with PMBOK 5.1
Project Management Plan
Project Management Plan components include:
• Quality Management Plan
• Project Life Cycle Description
• Development Approach
Plan Scope Management - Inputs
Coincides with PMBOK 5.1
Enterprise Environmental Factors
• Organization’s culture
• Infrastructure
• Personnel Administration
• Marketplace conditions
Things that can affect Project Management Plan:
Plan Scope Management - Inputs
Coincides with PMBOK 5.1
Organisational Process Assets
• Policies and Procedures
• Historical information and lessons learned
repository
Things that can influence the Project Scope Management Process:
Plan Scope Management – Tools & Techniques
Coincides with PMBOK 5.1
Expert Judgment
• Previous Similar Projects
• Information in the industry, discipline and application
area
Expertise should be considered from individuals or groups with
specialized knowledge of or training in the following topics:
Plan Scope Management – Tools & Techniques
Coincides with PMBOK 5.1
Data Analysis
• Alternatives Analysis
Use for the various ways of:
• Collecting Requirements
• Elaborating the project and product scope
• Validating the scope
• Controlling the scope
Plan Scope Management – Tools & Techniques
Coincides with PMBOK 5.1
Meetings
Project teams may attend project meetings to develop
the scope management plan, held with key stakeholders:
• Project Manager
• Project Sponsor
• Project Team Members
• Selected Stakeholders
• Anyone responsible for any of the scope management
processes.
Plan Scope Management – Outputs
Coincides with PMBOK 5.1
Scope Management Plan
The scope management plan is a component of the project management plan that
describes how the scope will be defined, developed, monitored, controlled, and
validated. Components include:
• Process for preparing a project scope statement
• Process that enables the creation of the WBS from the detailed
project scope statement
• Process that establishes how the scope baseline will be
approved and maintained
• Process that specifies how formal acceptance of the completed
project deliverables will be obtained.
Plan Scope Management – Outputs
Coincides with PMBOK 5.1
Requirements Management Plan
Part of the Project Management Plan:
The requirements management plan describes how project and product
requirements will be analysed, documented, and managed. Could also be called a
Business Analysis Plan.
• How requirements activities will be planned, tracked, and reported
• Configuration management activities
• Requirements prioritization process
• Metrics that will be used and the rationale for using them
• Traceability structure that reflects the requirement attributes captured on the
traceability matrix.

More Related Content

What's hot

11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
DavidMcLachlan1
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
Ahmed Alageed
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
Amit Gupta
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
DavidMcLachlan1
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
DavidMcLachlan1
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
DavidMcLachlan1
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
DavidMcLachlan1
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
DavidMcLachlan1
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
DavidMcLachlan1
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
Oleksiy Rudenko
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
Shamil Habet
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge Area
Joshua Render
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
GlobalSkillup
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
DavidMcLachlan1
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1reddvise
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
DavidMcLachlan1
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
DavidMcLachlan1
 

What's hot (20)

11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
 
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...PMP Chapter 6 of 6  closing process group (1- Process) (Based on PMBOK 6th ed...
PMP Chapter 6 of 6 closing process group (1- Process) (Based on PMBOK 6th ed...
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge Area
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 

Similar to 5.1 Plan Scope Management

05 project scope management
05 project scope management05 project scope management
05 project scope management
Omer Alsayed PhD,MBA, PMP®
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
Arlene Smith
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
Mohamed Loey
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
DavidMcLachlan1
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource Management
DavidMcLachlan1
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
MohamadAGhareb
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
Hisham Ali,PMP
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
Joshua Render
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
Nawzad Bilal
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
DavidMcLachlan1
 
49ProcessesPMI
49ProcessesPMI49ProcessesPMI
49ProcessesPMI
KareemBullard1
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
AbdiqadirOsman
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
Zaur Ahmadov, PMP
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
Abdullah Ahmed, PMP, RMP
 
File 3 extra slide 2
File 3 extra slide 2File 3 extra slide 2
File 3 extra slide 2test prod1
 
Nine Things-in-the-PMBoK
Nine Things-in-the-PMBoKNine Things-in-the-PMBoK
Nine Things-in-the-PMBoK
masilamani ramasamy
 

Similar to 5.1 Plan Scope Management (20)

05 project scope management
05 project scope management05 project scope management
05 project scope management
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource Management
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
49ProcessesPMI
49ProcessesPMI49ProcessesPMI
49ProcessesPMI
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Itto pmbok guide 6th edition
Itto   pmbok guide 6th editionItto   pmbok guide 6th edition
Itto pmbok guide 6th edition
 
File 3 extra slide 2
File 3 extra slide 2File 3 extra slide 2
File 3 extra slide 2
 
Nine Things-in-the-PMBoK
Nine Things-in-the-PMBoKNine Things-in-the-PMBoK
Nine Things-in-the-PMBoK
 

More from DavidMcLachlan1

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
DavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
DavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
DavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
DavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
DavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
DavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
DavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
DavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
DavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
DavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
DavidMcLachlan1
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
DavidMcLachlan1
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
DavidMcLachlan1
 

More from DavidMcLachlan1 (15)

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 

Recently uploaded

Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Reflective and Evaluative Practice PowerPoint
Reflective and Evaluative Practice PowerPointReflective and Evaluative Practice PowerPoint
Reflective and Evaluative Practice PowerPoint
amberjdewit93
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
kitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptxkitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptx
datarid22
 
Fresher’s Quiz 2023 at GMC Nizamabad.pptx
Fresher’s Quiz 2023 at GMC Nizamabad.pptxFresher’s Quiz 2023 at GMC Nizamabad.pptx
Fresher’s Quiz 2023 at GMC Nizamabad.pptx
SriSurya50
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
NelTorrente
 
What is the purpose of studying mathematics.pptx
What is the purpose of studying mathematics.pptxWhat is the purpose of studying mathematics.pptx
What is the purpose of studying mathematics.pptx
christianmathematics
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
goswamiyash170123
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Reflective and Evaluative Practice PowerPoint
Reflective and Evaluative Practice PowerPointReflective and Evaluative Practice PowerPoint
Reflective and Evaluative Practice PowerPoint
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
kitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptxkitab khulasah nurul yaqin jilid 1 - 2.pptx
kitab khulasah nurul yaqin jilid 1 - 2.pptx
 
Fresher’s Quiz 2023 at GMC Nizamabad.pptx
Fresher’s Quiz 2023 at GMC Nizamabad.pptxFresher’s Quiz 2023 at GMC Nizamabad.pptx
Fresher’s Quiz 2023 at GMC Nizamabad.pptx
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
 
What is the purpose of studying mathematics.pptx
What is the purpose of studying mathematics.pptxWhat is the purpose of studying mathematics.pptx
What is the purpose of studying mathematics.pptx
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 

5.1 Plan Scope Management

  • 2. Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement Plan Scope Management Coincides with PMBOK 5.1
  • 3. What is it? Plan Scope Management is the process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled. Why do we do it? The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project. Plan Scope Management Coincides with PMBOK 5.1
  • 4. Overview The development of the scope management plan and the detailing of the project scope begin with the analysis of information contained in the project charter, the latest approved subsidiary plans of the project management plan, historical information contained in the organizational process assets, and any other relevant enterprise environmental factors. Plan Scope Management Coincides with PMBOK 5.1
  • 5. Plan Scope Management Coincides with PMBOK 5.1 Inputs, Tools & Techniques and Outputs Inputs Tools & Techniques Outputs 1. Project Charter 2. Project Management Plan • Quality Management Plan • Project life cycle description • Development approach 3. Enterprise Environmental Factors 4. Organisational Process Assets 1. Expert judgment 2. Data Analysis • Alternatives analysis 3. Meetings 1. Scope Management Plan 2. Requirements Management Plan
  • 6. Plan Scope Management Coincides with PMBOK 5.1 5.1 Plan Scope Management Project Management Plan Enterprise Environmental Factors Organisational Process Assets Quality Management Plan Development ApproachProject Life Cycle Description Project Management Plan 4.1 Develop Project Charter Scope Management Plan Benefits Management Plan
  • 7. Plan Scope Management - Inputs Coincides with PMBOK 5.1 Project Charter The project charter documents the: • Project purpose • High-level project description • Assumptions • Constraints • High-level requirements that the project is intended to satisfy.
  • 8. Plan Scope Management - Inputs Coincides with PMBOK 5.1 Project Management Plan Project Management Plan components include: • Quality Management Plan • Project Life Cycle Description • Development Approach
  • 9. Plan Scope Management - Inputs Coincides with PMBOK 5.1 Enterprise Environmental Factors • Organization’s culture • Infrastructure • Personnel Administration • Marketplace conditions Things that can affect Project Management Plan:
  • 10. Plan Scope Management - Inputs Coincides with PMBOK 5.1 Organisational Process Assets • Policies and Procedures • Historical information and lessons learned repository Things that can influence the Project Scope Management Process:
  • 11. Plan Scope Management – Tools & Techniques Coincides with PMBOK 5.1 Expert Judgment • Previous Similar Projects • Information in the industry, discipline and application area Expertise should be considered from individuals or groups with specialized knowledge of or training in the following topics:
  • 12. Plan Scope Management – Tools & Techniques Coincides with PMBOK 5.1 Data Analysis • Alternatives Analysis Use for the various ways of: • Collecting Requirements • Elaborating the project and product scope • Validating the scope • Controlling the scope
  • 13. Plan Scope Management – Tools & Techniques Coincides with PMBOK 5.1 Meetings Project teams may attend project meetings to develop the scope management plan, held with key stakeholders: • Project Manager • Project Sponsor • Project Team Members • Selected Stakeholders • Anyone responsible for any of the scope management processes.
  • 14. Plan Scope Management – Outputs Coincides with PMBOK 5.1 Scope Management Plan The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. Components include: • Process for preparing a project scope statement • Process that enables the creation of the WBS from the detailed project scope statement • Process that establishes how the scope baseline will be approved and maintained • Process that specifies how formal acceptance of the completed project deliverables will be obtained.
  • 15. Plan Scope Management – Outputs Coincides with PMBOK 5.1 Requirements Management Plan Part of the Project Management Plan: The requirements management plan describes how project and product requirements will be analysed, documented, and managed. Could also be called a Business Analysis Plan. • How requirements activities will be planned, tracked, and reported • Configuration management activities • Requirements prioritization process • Metrics that will be used and the rationale for using them • Traceability structure that reflects the requirement attributes captured on the traceability matrix.

Editor's Notes

  1. This process is performed throughout the project.
  2. Quality management plan. The way the project and product scope will be managed can be influenced by how the organization’s quality policy, methodologies, and standards are implemented on the project. Project life cycle description. The project life cycle determines the series of phases that a project passes through from its inception to the end of the project. Development approach. The development approach defines whether waterfall, iterative, adaptive, agile, or a hybrid development approach will be used.
  3. The scope management plan can be formal or informal, broadly framed or highly detailed, based on the needs of the project.
  4. Some organizations refer to it as a business analysis plan Configuration management activities : how changes will be initiated; how impacts will be analysed; how they will be traced, tracked, and reported; as well as the authorization levels required to approve these changes