SlideShare a Scribd company logo
Activity Planning
Objectives, Project Schedule, Network
Planning Model, Time Dimension,
Identifying Critical Path
Unit - 6
Activity Planning in Software Project Management
Activity planning is a critical component of software project
management, ensuring that the project is completed on time
and within budget while meeting the specified requirements.
This involves defining activities, establishing a project
schedule, and using various models to manage and optimize
project timelines.
Objectives
The primary objectives of activity planning in software project
management include:
Defining Activities: Breaking down the project into manageable
tasks and activities.
Sequencing Activities: Determining the order of activities based
on dependencies and project requirements.
Estimating Resources: Identifying the resources required for each
activity, including personnel, tools, and time.
Allocating Time: Assigning start and end times to each activity
to ensure a logical flow and efficient use of resources.
Setting Milestones: Establishing significant points in the
project timeline to measure progress and ensure alignment
with goals.
Project Schedule
A project schedule is a detailed plan that outlines all activities, their
durations, and the sequence in which they will be performed. Key
components include:
Task List: A comprehensive list of all tasks and activities required to
complete the project.
Dependencies: Relationships between tasks that dictate the order in which
they must be completed.
Duration Estimates: The amount of time each task is expected to take.
Milestones: Significant events or achievements in the project timeline.
Gantt Chart: A visual representation of the project schedule, showing tasks,
durations, and dependencies.
Network Planning Model
Network planning models are used to represent the sequence and
interdependencies of project activities. The most commonly used models
are:
Program Evaluation and Review Technique (PERT): Uses probabilistic time
estimates to account for uncertainty in activity durations. It helps in
identifying the minimum time needed to complete a project by calculating
the expected time for each activity.
Critical Path Method (CPM): Focuses on identifying the longest sequence of
dependent tasks (the critical path) that determines the minimum project
duration. CPM uses deterministic time estimates and is ideal for projects
with well-defined tasks and timelines.
Time Dimension
The time dimension in project management refers to the scheduling
aspect, which includes:
Start and Finish Times: The specific times when each task begins and
ends.
Float/Slack Time: The amount of time a task can be delayed without
affecting the overall project completion date.
Lead and Lag Time: Lead time allows for tasks to overlap, while lag
time inserts delays between tasks.
Identifying Critical Path
The critical path is the sequence of activities that determines the
shortest possible duration to complete a project. Identifying the critical
path involves:
Listing Activities: Identifying all tasks involved in the project.
Determining Dependencies: Establishing the relationships and
dependencies between tasks.
Estimating Duration: Assigning time estimates to each task.
Constructing the Network Diagram: Creating a visual representation of
the task sequence and dependencies.
Calculating the Critical Path: Using algorithms to determine the
longest path through the network diagram, which represents the
critical path. This includes:
• Forward Pass: Calculating the earliest start and finish times for each
task.
• Backward Pass: Determining the latest start and finish times that will
not delay the project.
• Identifying Float: Calculating the float for each task to understand
flexibility.
The critical path has zero float, meaning any delay in these tasks
directly impacts the project completion date. Effective management of
the critical path ensures timely project delivery.
Conclusion
Activity planning in software project management is essential for
successful project execution. By defining objectives, creating a detailed
project schedule, utilizing network planning models, understanding the
time dimension, and identifying the critical path, project managers can
effectively plan, execute, and monitor software projects to ensure they
meet their goals within the constraints of time and resources.
Sample Questions
1. What are the primary objectives of activity planning in software project management?
2. How do you define activities in the context of a software project?
3. What techniques can be used to sequence activities in a software project?
4. How do you estimate resources required for project activities?
5. What is the importance of setting milestones in activity planning?
6. Can you explain the process of breaking down a project into manageable tasks?
7. What are the key components of a project schedule?
8. How do you create a task list for a software project?
9. What methods can be used to determine task dependencies?
10. How do you estimate the duration of tasks in a project schedule?
11. What is a Gantt chart and how is it used in project scheduling?
12. How do you manage and adjust a project schedule when unexpected delays occur?
1. What are the differences between PERT and CPM in network planning?
2. How does the PERT model account for uncertainty in project scheduling?
3. What steps are involved in creating a network diagram for a software project?
4. How do you identify and manage the critical path in CPM?
5. What are the advantages and disadvantages of using network planning models in
software project management?
6. How do network planning models help in optimizing resource allocation?
7. What is the time dimension in project management?
8. How do start and finish times impact project scheduling?
9. What is float/slack time and how is it calculated?
10. How can lead and lag times be used to optimize project schedules?
11. What strategies can be employed to manage the time dimension in large projects?
12. How do you balance the time dimension with other project constraints like cost and
scope?
Sample Questions

More Related Content

What's hot

Software estimation
Software estimationSoftware estimation
Software estimation
Md Shakir
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
MSharmilaDeviITDEPT
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.ppt
AnupamaSharma80
 
Software Process Models
Software Process ModelsSoftware Process Models
Software Process Models
Atul Karmyal
 
Design concept -Software Engineering
Design concept -Software EngineeringDesign concept -Software Engineering
Design concept -Software Engineering
Varsha Ajith
 
Artifacts
ArtifactsArtifacts
Artifacts
Mayuresh Wadekar
 
Control Flow Testing
Control Flow TestingControl Flow Testing
Control Flow Testing
Hirra Sultan
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
Kathirvel Ayyaswamy
 
Importance & Principles of Modeling from UML Designing
Importance & Principles of Modeling from UML DesigningImportance & Principles of Modeling from UML Designing
Importance & Principles of Modeling from UML Designing
ABHISHEK KUMAR
 
A Role of Lexical Analyzer
A Role of Lexical AnalyzerA Role of Lexical Analyzer
A Role of Lexical Analyzer
Archana Gopinath
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process Improvement
Bilal Shah
 
Compiler Design Basics
Compiler Design BasicsCompiler Design Basics
Compiler Design Basics
Akhil Kaushik
 
Analysis modeling
Analysis modelingAnalysis modeling
Analysis modeling
Inocentshuja Ahmad
 
Target language in compiler design
Target language in compiler designTarget language in compiler design
Target language in compiler design
Muhammad Haroon
 
Media Access Control
Media Access ControlMedia Access Control
Media Access Control
VijayaLakshmi514
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
Baskarkncet
 
Software architecture
Software architectureSoftware architecture
Software architecture
Ahmad Raza Aslam
 
Google App Engine
Google App EngineGoogle App Engine
Google App Engine
Urmi510
 
source code metrics and other maintenance tools and techniques
source code metrics and other maintenance tools and techniquessource code metrics and other maintenance tools and techniques
source code metrics and other maintenance tools and techniques
Siva Priya
 
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
IrtazaAfzal3
 

What's hot (20)

Software estimation
Software estimationSoftware estimation
Software estimation
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.ppt
 
Software Process Models
Software Process ModelsSoftware Process Models
Software Process Models
 
Design concept -Software Engineering
Design concept -Software EngineeringDesign concept -Software Engineering
Design concept -Software Engineering
 
Artifacts
ArtifactsArtifacts
Artifacts
 
Control Flow Testing
Control Flow TestingControl Flow Testing
Control Flow Testing
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Importance & Principles of Modeling from UML Designing
Importance & Principles of Modeling from UML DesigningImportance & Principles of Modeling from UML Designing
Importance & Principles of Modeling from UML Designing
 
A Role of Lexical Analyzer
A Role of Lexical AnalyzerA Role of Lexical Analyzer
A Role of Lexical Analyzer
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process Improvement
 
Compiler Design Basics
Compiler Design BasicsCompiler Design Basics
Compiler Design Basics
 
Analysis modeling
Analysis modelingAnalysis modeling
Analysis modeling
 
Target language in compiler design
Target language in compiler designTarget language in compiler design
Target language in compiler design
 
Media Access Control
Media Access ControlMedia Access Control
Media Access Control
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Software architecture
Software architectureSoftware architecture
Software architecture
 
Google App Engine
Google App EngineGoogle App Engine
Google App Engine
 
source code metrics and other maintenance tools and techniques
source code metrics and other maintenance tools and techniquessource code metrics and other maintenance tools and techniques
source code metrics and other maintenance tools and techniques
 
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
 

Similar to Activity Planning: Objectives, Project Schedule, Network Planning Model. Time Dimension. Identifying Critical Path.

Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
rielaantonio
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
preetidamakale
 
223417 Diploma_Sem4_software_engg-chap-05.ppt
223417 Diploma_Sem4_software_engg-chap-05.ppt223417 Diploma_Sem4_software_engg-chap-05.ppt
223417 Diploma_Sem4_software_engg-chap-05.ppt
Deepgaichor1
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
ShudipPal
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
guestc8140fe
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
POOJA UDAYAN
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Jaafer Saeed
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
GBPUA&T, Pantnagar
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
PedadaSaikumar
 
Primavara
PrimavaraPrimavara
Primavara
danabl
 
Control techniques
Control techniquesControl techniques
Control techniques
Adnan Shakir
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project scheduling
lokareminakshi
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
ghulam MUSTAFA
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
Somashekar S.M
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptx
MAHASREEM
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 

Similar to Activity Planning: Objectives, Project Schedule, Network Planning Model. Time Dimension. Identifying Critical Path. (20)

Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
223417 Diploma_Sem4_software_engg-chap-05.ppt
223417 Diploma_Sem4_software_engg-chap-05.ppt223417 Diploma_Sem4_software_engg-chap-05.ppt
223417 Diploma_Sem4_software_engg-chap-05.ppt
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Primavara
PrimavaraPrimavara
Primavara
 
Control techniques
Control techniquesControl techniques
Control techniques
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project scheduling
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptx
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 

More from Lovely Professional University

Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
Lovely Professional University
 
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
Lovely Professional University
 
Programme Management & Project Evaluation
Programme Management & Project EvaluationProgramme Management & Project Evaluation
Programme Management & Project Evaluation
Lovely Professional University
 
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
Lovely Professional University
 
Introduction to Software Project Management:
Introduction to Software Project Management:Introduction to Software Project Management:
Introduction to Software Project Management:
Lovely Professional University
 
The HyperText Markup Language or HTML is the standard markup language
The HyperText Markup Language or HTML is the standard markup languageThe HyperText Markup Language or HTML is the standard markup language
The HyperText Markup Language or HTML is the standard markup language
Lovely Professional University
 
Working with JSON
Working with JSONWorking with JSON
Yargs Module
Yargs ModuleYargs Module
NODEMON Module
NODEMON ModuleNODEMON Module
Getting Input from User
Getting Input from UserGetting Input from User
Getting Input from User
Lovely Professional University
 
fs Module.pptx
fs Module.pptxfs Module.pptx
Transaction Processing in DBMS.pptx
Transaction Processing in DBMS.pptxTransaction Processing in DBMS.pptx
Transaction Processing in DBMS.pptx
Lovely Professional University
 
web_server_browser.ppt
web_server_browser.pptweb_server_browser.ppt
web_server_browser.ppt
Lovely Professional University
 
Web Server.pptx
Web Server.pptxWeb Server.pptx
Number System.pptx
Number System.pptxNumber System.pptx
Number System.pptx
Lovely Professional University
 
Programming Language.ppt
Programming Language.pptProgramming Language.ppt
Programming Language.ppt
Lovely Professional University
 
Information System.pptx
Information System.pptxInformation System.pptx
Information System.pptx
Lovely Professional University
 
Applications of Computer Science in Pharmacy-1.pptx
Applications of Computer Science in Pharmacy-1.pptxApplications of Computer Science in Pharmacy-1.pptx
Applications of Computer Science in Pharmacy-1.pptx
Lovely Professional University
 
Application of Computers in Pharmacy.pptx
Application of Computers in Pharmacy.pptxApplication of Computers in Pharmacy.pptx
Application of Computers in Pharmacy.pptx
Lovely Professional University
 
Deploying your app.pptx
Deploying your app.pptxDeploying your app.pptx
Deploying your app.pptx
Lovely Professional University
 

More from Lovely Professional University (20)

Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
Effort Estimation: Meaning, Problems with Estimation, Basis, Estimation Techn...
 
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
Project Approach: Intro. Technical Plan, Choice of Process Models: Waterfall,...
 
Programme Management & Project Evaluation
Programme Management & Project EvaluationProgramme Management & Project Evaluation
Programme Management & Project Evaluation
 
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
Step Wise Project Planning: Project Scope, Objectives, Infrastructure, Charac...
 
Introduction to Software Project Management:
Introduction to Software Project Management:Introduction to Software Project Management:
Introduction to Software Project Management:
 
The HyperText Markup Language or HTML is the standard markup language
The HyperText Markup Language or HTML is the standard markup languageThe HyperText Markup Language or HTML is the standard markup language
The HyperText Markup Language or HTML is the standard markup language
 
Working with JSON
Working with JSONWorking with JSON
Working with JSON
 
Yargs Module
Yargs ModuleYargs Module
Yargs Module
 
NODEMON Module
NODEMON ModuleNODEMON Module
NODEMON Module
 
Getting Input from User
Getting Input from UserGetting Input from User
Getting Input from User
 
fs Module.pptx
fs Module.pptxfs Module.pptx
fs Module.pptx
 
Transaction Processing in DBMS.pptx
Transaction Processing in DBMS.pptxTransaction Processing in DBMS.pptx
Transaction Processing in DBMS.pptx
 
web_server_browser.ppt
web_server_browser.pptweb_server_browser.ppt
web_server_browser.ppt
 
Web Server.pptx
Web Server.pptxWeb Server.pptx
Web Server.pptx
 
Number System.pptx
Number System.pptxNumber System.pptx
Number System.pptx
 
Programming Language.ppt
Programming Language.pptProgramming Language.ppt
Programming Language.ppt
 
Information System.pptx
Information System.pptxInformation System.pptx
Information System.pptx
 
Applications of Computer Science in Pharmacy-1.pptx
Applications of Computer Science in Pharmacy-1.pptxApplications of Computer Science in Pharmacy-1.pptx
Applications of Computer Science in Pharmacy-1.pptx
 
Application of Computers in Pharmacy.pptx
Application of Computers in Pharmacy.pptxApplication of Computers in Pharmacy.pptx
Application of Computers in Pharmacy.pptx
 
Deploying your app.pptx
Deploying your app.pptxDeploying your app.pptx
Deploying your app.pptx
 

Recently uploaded

Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
amsjournal
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
shivani5543
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 

Recently uploaded (20)

Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 

Activity Planning: Objectives, Project Schedule, Network Planning Model. Time Dimension. Identifying Critical Path.

  • 1. Activity Planning Objectives, Project Schedule, Network Planning Model, Time Dimension, Identifying Critical Path Unit - 6
  • 2. Activity Planning in Software Project Management Activity planning is a critical component of software project management, ensuring that the project is completed on time and within budget while meeting the specified requirements. This involves defining activities, establishing a project schedule, and using various models to manage and optimize project timelines.
  • 3. Objectives The primary objectives of activity planning in software project management include: Defining Activities: Breaking down the project into manageable tasks and activities. Sequencing Activities: Determining the order of activities based on dependencies and project requirements. Estimating Resources: Identifying the resources required for each activity, including personnel, tools, and time.
  • 4. Allocating Time: Assigning start and end times to each activity to ensure a logical flow and efficient use of resources. Setting Milestones: Establishing significant points in the project timeline to measure progress and ensure alignment with goals.
  • 5. Project Schedule A project schedule is a detailed plan that outlines all activities, their durations, and the sequence in which they will be performed. Key components include: Task List: A comprehensive list of all tasks and activities required to complete the project. Dependencies: Relationships between tasks that dictate the order in which they must be completed. Duration Estimates: The amount of time each task is expected to take. Milestones: Significant events or achievements in the project timeline. Gantt Chart: A visual representation of the project schedule, showing tasks, durations, and dependencies.
  • 6. Network Planning Model Network planning models are used to represent the sequence and interdependencies of project activities. The most commonly used models are: Program Evaluation and Review Technique (PERT): Uses probabilistic time estimates to account for uncertainty in activity durations. It helps in identifying the minimum time needed to complete a project by calculating the expected time for each activity. Critical Path Method (CPM): Focuses on identifying the longest sequence of dependent tasks (the critical path) that determines the minimum project duration. CPM uses deterministic time estimates and is ideal for projects with well-defined tasks and timelines.
  • 7. Time Dimension The time dimension in project management refers to the scheduling aspect, which includes: Start and Finish Times: The specific times when each task begins and ends. Float/Slack Time: The amount of time a task can be delayed without affecting the overall project completion date. Lead and Lag Time: Lead time allows for tasks to overlap, while lag time inserts delays between tasks.
  • 8. Identifying Critical Path The critical path is the sequence of activities that determines the shortest possible duration to complete a project. Identifying the critical path involves: Listing Activities: Identifying all tasks involved in the project. Determining Dependencies: Establishing the relationships and dependencies between tasks. Estimating Duration: Assigning time estimates to each task. Constructing the Network Diagram: Creating a visual representation of the task sequence and dependencies.
  • 9. Calculating the Critical Path: Using algorithms to determine the longest path through the network diagram, which represents the critical path. This includes: • Forward Pass: Calculating the earliest start and finish times for each task. • Backward Pass: Determining the latest start and finish times that will not delay the project. • Identifying Float: Calculating the float for each task to understand flexibility. The critical path has zero float, meaning any delay in these tasks directly impacts the project completion date. Effective management of the critical path ensures timely project delivery.
  • 10. Conclusion Activity planning in software project management is essential for successful project execution. By defining objectives, creating a detailed project schedule, utilizing network planning models, understanding the time dimension, and identifying the critical path, project managers can effectively plan, execute, and monitor software projects to ensure they meet their goals within the constraints of time and resources.
  • 11. Sample Questions 1. What are the primary objectives of activity planning in software project management? 2. How do you define activities in the context of a software project? 3. What techniques can be used to sequence activities in a software project? 4. How do you estimate resources required for project activities? 5. What is the importance of setting milestones in activity planning? 6. Can you explain the process of breaking down a project into manageable tasks? 7. What are the key components of a project schedule? 8. How do you create a task list for a software project? 9. What methods can be used to determine task dependencies? 10. How do you estimate the duration of tasks in a project schedule? 11. What is a Gantt chart and how is it used in project scheduling? 12. How do you manage and adjust a project schedule when unexpected delays occur?
  • 12. 1. What are the differences between PERT and CPM in network planning? 2. How does the PERT model account for uncertainty in project scheduling? 3. What steps are involved in creating a network diagram for a software project? 4. How do you identify and manage the critical path in CPM? 5. What are the advantages and disadvantages of using network planning models in software project management? 6. How do network planning models help in optimizing resource allocation? 7. What is the time dimension in project management? 8. How do start and finish times impact project scheduling? 9. What is float/slack time and how is it calculated? 10. How can lead and lag times be used to optimize project schedules? 11. What strategies can be employed to manage the time dimension in large projects? 12. How do you balance the time dimension with other project constraints like cost and scope? Sample Questions