 The purpose of this presentation is the
description of the process for Project Controls
(covering engineering, procurement and
construction) for the execution small size
projects
 The tools are developed as database systems,
with a clear separation between datasets and
reports.
 Excel was used for simplicity, but for more
data integrity it is advisable to use RDMS (
Like MS Access )
 The approach used in this presentation :
 There is no real time integration or one system to
manage the different process.
 instead every process is managed using a separate
tool, the integration is done using well defined
interface.
 The data generated from different process is
integrated in one place to generate Reports, curves,
and dashboards.
 All the stakeholder must agree before the start of
the project on the interfaces and the level of the
details and integration between the different
process.
 WBS : Work Breakdown structure.
 CBS : Cost Breakdown structure.
 AREA : a geographic division of the plant.
 Workpackage is a group of deliverables.
- Construction: Group of items ( building, piperack).
- Engineering : Group of drawing.
- Procurement : Group of equipment, material etc.
 Task_Code is a standard activity with efficiency and
physical quantity
 SCOPE_ID is the business rule primary key
It is a concatenation of Area, Task_Code and
Workpackage
 Steps is further detail of Task_code to basic activities
 L1 : the project.
 L2 : Phase (General, Engineering, Procurement,
Construction, Precommissioning,
Commissioning, Start-up, Handover.
 L4 : Milestones, Management
 L5 :
- Milestones are split between contractual
Milestones and Project Milestones.
- Management is split between the different
Department output for the project.
 L4 : Disciplines
 L5 : Work Packages
 L4 : Subcontract, Long lead items, Disciplines (
auxiliary, Civil ) and Bulk Materials.
 L5 : Work Packages ( group of equipment)
 L4 : Zone
 L5 : Area
 L6 : Work Packages
 L4 : systems
 SCOPE: provide The whole scope of work(EPC),
including manhours and quantities
 Schedule: Time Management ( Planning software)
 PRT : Progress reporting and tracking, excel
tool to managed update progress and reporting
 Time_Sheet: The manhours spent in Construction.
 Job Card : detailed Progress report at level 5
 DPR : Document Progress Register.
 PSR : Procurement status report.
 Cost : Cost Control is managed by Separate tool.
Task_Code Descipline Task Class Unique identifier
Level L1 L2 L3
XXXXXX XX XX XX
Example CV1020 CV 10 20
Civil Concrete Works Foundation Civil Works
CV1060 CV 10 60
Civil Concrete Works Pipe support Civil Works
 Task_Code : is a unique six digit Code.
 It is the concatenation of Discipline, Task Class
and a unique identifier
 The efficiency per Task_Code is a based on a
historical data of the company.
 SCOPE is a live List incorporating all new
update to the scope of works (EPC).
 The integration between the planning software
and SCOPE is using SCOPE_ID.
 When there is a significant change in Scope of
Work, the Planning software is update from
SCOPE
SCOPE_ID
SCOPE ( Budget manhours, Quantities, weightage to
the client as by the contract revenue)
Construction
ITEM List
Document
Progress
Register
Procurement
Status Report
SCOPE_ID
SCOPE_ID
Construction
Productivity
database
Master Schedule Level 4
SCOPE_ID
Contract
Value
 The data in the PRT is mapped at the activity
level in The Planning software, basically it is
the same schedule but handled in a separate
spreadsheet.
 It is easier to record period performance in
excel then in a planning software.
 Anyone with basic Excel skills, can update the
progress and produce reports without the need
to operate a Planning software.
PRT (Progress Reporting and Tracking)
Weekly
Planning software (Weekly, Or Monthly)
Progress
report
S
Curve
Invoice
SCOPE_ID
Time
sheet
Productivity
Internal Report
Cost
Dates by
CBS
WBS
Job Card
Procurement
register
Engineering
Register
 Planning software is used only to manage time, by using the CPM
calculation.
 In the initial baseline, load the physical quantities to level your
production output.
 A hammock can be used to split an Activity assigned to
SCOPE_ID
 The Frequency of updating the schedule, depend if you want to
generate a Forecast curve, Weekly or Monthly.
 The actual start, actual finish ( the facts) are imported from PRT.
 There is no magic formula to generate remaining duration, talk to
the guy doing the work, he is the best one to provide this
information.
 After scheduling, the new forecast dates are exported to PRT, to
generate the forecast data.
 Any planning tool can be used (MS Project, Primavera, etc).
 Never Ever input dates directly in Excel !!!!!
 For the sake of simplification the spent hours in
the site will be recorded only by subcontractor,
but in order to have a more accurate
Productivity analysis, the hours should be at
least recorded at the Subcontractor/ discipline
level.
 The data is recorded in a daily basis, the
productivity factor in a weekly basis.
 The time sheet records the roles by direct and
indirect.
 Cost control is a separate process.
 The cost breakdown structure is implemented
using the activity codes in the planning software.
 The spread of cost by cost account is done using
the dates from the schedule.
 PRT generate progress report by CBS, it should be
considered as an approximation, as progress based
on cost weight and revenue weight are little bit
different.
 It is important to avoid the use the “best guess method”
in distributing cost data.
 The more CBS is detailed the more the distribution
is accurate.
 Engineering and construction the budget is in
manhours.
 Procurement the budget is the cost.
 The revenue Factor
Revenue = Budget X Factor
 The overall Progress (EPC) is based on the
contract Value.
 The Primary Progress reports for the client are
based on the WBS.
 For different audience, there is a different
reports.
1. By Contractor.
2. By discipline.
3. By Work Package
4. By systems.
 Separate datasets from the reports.
 Never Hard Code a report
 Understand your Primary key.
 Use codes, standardize your codifications.
 Always prepare and generate data as database.
 Pivot table in Excel is very powerful reporting
utility.
 Automatize your workflow, manual data entry
is a waste of time.
 Use both WBS and activity codes for maximum
flexibility in reporting.
 Two Approaches
1- Keep two revision of PRT.
 Stable Revision issued to the client, the budget
is frozen.
 An internal live revision incorporating the
latest changes from SCOPE.
2- update the current schedule with the latest data
from SCOPE ( without adding weightage)
 The period performance ( % complete) does not
change, as it is calculated in the JOB CARD
using always the latest update from
Construction ITEM LIST
 PS :
 I added a new Excel file Project dashboard, it is
much easier to use, and all the calculation are
automated

More Related Content

What's hot

S curves
S curvesS curves
S curves
Sagar Rana
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
Amit Kumar Senapati, PMP®
 
3.1 the usage of bar chart
3.1 the usage of bar chart3.1 the usage of bar chart
3.1 the usage of bar chart
Natalie Ulza
 
4.1 planning schedulling
4.1 planning schedulling4.1 planning schedulling
4.1 planning schedulling
Natalie Ulza
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg
Meet Shah
 
Gantt chart
Gantt chartGantt chart
Gantt chart
charnjeet kaur
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
Intaver Insititute
 
Gantt and PERT chart
Gantt and PERT chartGantt and PERT chart
Gantt and PERT chart
Krishna Mohan Mishra
 
SAP CPM-BW Solution Overview
SAP CPM-BW Solution OverviewSAP CPM-BW Solution Overview
SAP CPM-BW Solution Overview
Naresh Raghavan
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
Future Managers
 
Gantt
GanttGantt
Gantt
Balaji P
 
Gantt chart
Gantt chartGantt chart
Gantt chart
Tanoj Patidar
 
CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016
Maryann Cooper
 
Ghant chart
Ghant chartGhant chart
Ghant chart
Vinod Singh
 
Project management
Project managementProject management
Project management
Jubayer Alam Shoikat
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
PMA Consultants
 
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
p6academy
 
Brief tutorial on gantt charts
Brief tutorial on gantt chartsBrief tutorial on gantt charts
Brief tutorial on gantt charts
Dr Ghaiath Hussein
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpm
Mimin Adam
 
William Canning Portfolio Annotated
William Canning Portfolio AnnotatedWilliam Canning Portfolio Annotated
William Canning Portfolio Annotated
canningw
 

What's hot (20)

S curves
S curvesS curves
S curves
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
3.1 the usage of bar chart
3.1 the usage of bar chart3.1 the usage of bar chart
3.1 the usage of bar chart
 
4.1 planning schedulling
4.1 planning schedulling4.1 planning schedulling
4.1 planning schedulling
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Gantt and PERT chart
Gantt and PERT chartGantt and PERT chart
Gantt and PERT chart
 
SAP CPM-BW Solution Overview
SAP CPM-BW Solution OverviewSAP CPM-BW Solution Overview
SAP CPM-BW Solution Overview
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
Gantt
GanttGantt
Gantt
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016
 
Ghant chart
Ghant chartGhant chart
Ghant chart
 
Project management
Project managementProject management
Project management
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
 
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
 
Brief tutorial on gantt charts
Brief tutorial on gantt chartsBrief tutorial on gantt charts
Brief tutorial on gantt charts
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpm
 
William Canning Portfolio Annotated
William Canning Portfolio AnnotatedWilliam Canning Portfolio Annotated
William Canning Portfolio Annotated
 

Viewers also liked

International Approach to Predicting Construction Labour Hours
International Approach to Predicting Construction Labour HoursInternational Approach to Predicting Construction Labour Hours
International Approach to Predicting Construction Labour Hours
forths
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Energy Construction Forum
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digital
Zoe MacDonald
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
p6academy
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Energy Construction Forum
 
Curve of influence mar 2014
Curve of influence mar 2014Curve of influence mar 2014
Curve of influence mar 2014
Niall M Reynolds
 
Contracts & Cost Breakdown Structure
Contracts & Cost Breakdown StructureContracts & Cost Breakdown Structure
Contracts & Cost Breakdown Structure
Steven Eady
 
Work breakdown structurep
Work breakdown structurepWork breakdown structurep
Work breakdown structurep
Ravi Malik
 

Viewers also liked (8)

International Approach to Predicting Construction Labour Hours
International Approach to Predicting Construction Labour HoursInternational Approach to Predicting Construction Labour Hours
International Approach to Predicting Construction Labour Hours
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digital
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 
Curve of influence mar 2014
Curve of influence mar 2014Curve of influence mar 2014
Curve of influence mar 2014
 
Contracts & Cost Breakdown Structure
Contracts & Cost Breakdown StructureContracts & Cost Breakdown Structure
Contracts & Cost Breakdown Structure
 
Work breakdown structurep
Work breakdown structurepWork breakdown structurep
Work breakdown structurep
 

Similar to 00 project control tools

00 project control tools
00 project control tools00 project control tools
00 project control tools
shrn4u
 
Chaitanya_updated resume
Chaitanya_updated resumeChaitanya_updated resume
Chaitanya_updated resume
Chaitanya Lakshmi
 
Chaitanya_updated resume
Chaitanya_updated resumeChaitanya_updated resume
Chaitanya_updated resume
Chaitanya Lakshmi
 
Decomposition technique In Software Engineering
Decomposition technique In Software Engineering Decomposition technique In Software Engineering
Decomposition technique In Software Engineering
Bilal Hassan
 
Tableau Portfolio
Tableau PortfolioTableau Portfolio
Tableau Portfolio
Bjorn Andersson
 
Companion by Minitab - Desktop App
Companion by Minitab - Desktop AppCompanion by Minitab - Desktop App
Companion by Minitab - Desktop App
GMSL S.r.l.
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
carolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
donaldp2
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
PMA Consultants
 
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdfintegrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
AngusMacleod20
 
Project Planning Board Overview_SAP PS.pptx
Project Planning Board Overview_SAP PS.pptxProject Planning Board Overview_SAP PS.pptx
Project Planning Board Overview_SAP PS.pptx
NCHKRISHNATEJA
 
Project management
Project managementProject management
Project management
Ahmed Said
 
Project Share Feature List - MS Project Services
Project Share Feature List - MS Project ServicesProject Share Feature List - MS Project Services
Project Share Feature List - MS Project Services
mahyars
 
Resume_Vellaiyan
Resume_VellaiyanResume_Vellaiyan
Resume_Vellaiyan
vellaiyan lakshmanan
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
varun maheshwari
 
Primavara
PrimavaraPrimavara
Primavara
danabl
 
Project management
Project managementProject management
Project management
ervinod
 
battery pa report.docx
battery pa report.docxbattery pa report.docx
battery pa report.docx
deependerdeshwal
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
Resource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environmentsResource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environments
Geert Vanhove
 

Similar to 00 project control tools (20)

00 project control tools
00 project control tools00 project control tools
00 project control tools
 
Chaitanya_updated resume
Chaitanya_updated resumeChaitanya_updated resume
Chaitanya_updated resume
 
Chaitanya_updated resume
Chaitanya_updated resumeChaitanya_updated resume
Chaitanya_updated resume
 
Decomposition technique In Software Engineering
Decomposition technique In Software Engineering Decomposition technique In Software Engineering
Decomposition technique In Software Engineering
 
Tableau Portfolio
Tableau PortfolioTableau Portfolio
Tableau Portfolio
 
Companion by Minitab - Desktop App
Companion by Minitab - Desktop AppCompanion by Minitab - Desktop App
Companion by Minitab - Desktop App
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
 
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdfintegrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
 
Project Planning Board Overview_SAP PS.pptx
Project Planning Board Overview_SAP PS.pptxProject Planning Board Overview_SAP PS.pptx
Project Planning Board Overview_SAP PS.pptx
 
Project management
Project managementProject management
Project management
 
Project Share Feature List - MS Project Services
Project Share Feature List - MS Project ServicesProject Share Feature List - MS Project Services
Project Share Feature List - MS Project Services
 
Resume_Vellaiyan
Resume_VellaiyanResume_Vellaiyan
Resume_Vellaiyan
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
 
Primavara
PrimavaraPrimavara
Primavara
 
Project management
Project managementProject management
Project management
 
battery pa report.docx
battery pa report.docxbattery pa report.docx
battery pa report.docx
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Resource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environmentsResource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environments
 

More from AHMED NADIM JILANI

Scaffolding by vn prabhu source facebook group survey & engineering de...
Scaffolding  by  vn prabhu source facebook group survey  & engineering de...Scaffolding  by  vn prabhu source facebook group survey  & engineering de...
Scaffolding by vn prabhu source facebook group survey & engineering de...
AHMED NADIM JILANI
 
Nanotechnology in civil engineering0
Nanotechnology in civil engineering0Nanotechnology in civil engineering0
Nanotechnology in civil engineering0
AHMED NADIM JILANI
 
Staadpresentation1 159
Staadpresentation1 159Staadpresentation1 159
Staadpresentation1 159
AHMED NADIM JILANI
 
Pres staadpro
Pres staadproPres staadpro
Pres staadpro
AHMED NADIM JILANI
 
Corenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materialsCorenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materials
AHMED NADIM JILANI
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
AHMED NADIM JILANI
 
Ccna day5
Ccna day5Ccna day5
Ccna day4
Ccna day4Ccna day4
Ccna day3
Ccna day3Ccna day3
Ccna day2
Ccna day2Ccna day2
Ccna day1
Ccna day1Ccna day1
What is nanotechnology
What is nanotechnologyWhat is nanotechnology
What is nanotechnology
AHMED NADIM JILANI
 
Nanotechnology in civil engineering by shahid
Nanotechnology in  civil engineering by shahidNanotechnology in  civil engineering by shahid
Nanotechnology in civil engineering by shahid
AHMED NADIM JILANI
 
What is nanotechnology
What is nanotechnologyWhat is nanotechnology
What is nanotechnology
AHMED NADIM JILANI
 
Nanotechnology in civil engineering by shahid
Nanotechnology in  civil engineering by shahidNanotechnology in  civil engineering by shahid
Nanotechnology in civil engineering by shahid
AHMED NADIM JILANI
 
Corenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materialsCorenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materials
AHMED NADIM JILANI
 
Carbon nanotubes
Carbon nanotubesCarbon nanotubes
Carbon nanotubes
AHMED NADIM JILANI
 
Nanotechnology in civil engineering
Nanotechnology in civil engineeringNanotechnology in civil engineering
Nanotechnology in civil engineering
AHMED NADIM JILANI
 
electrical engineering
electrical engineeringelectrical engineering
electrical engineering
AHMED NADIM JILANI
 
Water balance & management
Water balance & managementWater balance & management
Water balance & management
AHMED NADIM JILANI
 

More from AHMED NADIM JILANI (20)

Scaffolding by vn prabhu source facebook group survey & engineering de...
Scaffolding  by  vn prabhu source facebook group survey  & engineering de...Scaffolding  by  vn prabhu source facebook group survey  & engineering de...
Scaffolding by vn prabhu source facebook group survey & engineering de...
 
Nanotechnology in civil engineering0
Nanotechnology in civil engineering0Nanotechnology in civil engineering0
Nanotechnology in civil engineering0
 
Staadpresentation1 159
Staadpresentation1 159Staadpresentation1 159
Staadpresentation1 159
 
Pres staadpro
Pres staadproPres staadpro
Pres staadpro
 
Corenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materialsCorenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materials
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Ccna day5
Ccna day5Ccna day5
Ccna day5
 
Ccna day4
Ccna day4Ccna day4
Ccna day4
 
Ccna day3
Ccna day3Ccna day3
Ccna day3
 
Ccna day2
Ccna day2Ccna day2
Ccna day2
 
Ccna day1
Ccna day1Ccna day1
Ccna day1
 
What is nanotechnology
What is nanotechnologyWhat is nanotechnology
What is nanotechnology
 
Nanotechnology in civil engineering by shahid
Nanotechnology in  civil engineering by shahidNanotechnology in  civil engineering by shahid
Nanotechnology in civil engineering by shahid
 
What is nanotechnology
What is nanotechnologyWhat is nanotechnology
What is nanotechnology
 
Nanotechnology in civil engineering by shahid
Nanotechnology in  civil engineering by shahidNanotechnology in  civil engineering by shahid
Nanotechnology in civil engineering by shahid
 
Corenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materialsCorenet montreal 2_13_08_nanotech_materials
Corenet montreal 2_13_08_nanotech_materials
 
Carbon nanotubes
Carbon nanotubesCarbon nanotubes
Carbon nanotubes
 
Nanotechnology in civil engineering
Nanotechnology in civil engineeringNanotechnology in civil engineering
Nanotechnology in civil engineering
 
electrical engineering
electrical engineeringelectrical engineering
electrical engineering
 
Water balance & management
Water balance & managementWater balance & management
Water balance & management
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
gaafergoudaay7aga
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 

00 project control tools

  • 2.  The purpose of this presentation is the description of the process for Project Controls (covering engineering, procurement and construction) for the execution small size projects  The tools are developed as database systems, with a clear separation between datasets and reports.  Excel was used for simplicity, but for more data integrity it is advisable to use RDMS ( Like MS Access )
  • 3.  The approach used in this presentation :  There is no real time integration or one system to manage the different process.  instead every process is managed using a separate tool, the integration is done using well defined interface.  The data generated from different process is integrated in one place to generate Reports, curves, and dashboards.  All the stakeholder must agree before the start of the project on the interfaces and the level of the details and integration between the different process.
  • 4.  WBS : Work Breakdown structure.  CBS : Cost Breakdown structure.  AREA : a geographic division of the plant.  Workpackage is a group of deliverables. - Construction: Group of items ( building, piperack). - Engineering : Group of drawing. - Procurement : Group of equipment, material etc.  Task_Code is a standard activity with efficiency and physical quantity  SCOPE_ID is the business rule primary key It is a concatenation of Area, Task_Code and Workpackage  Steps is further detail of Task_code to basic activities
  • 5.
  • 6.  L1 : the project.  L2 : Phase (General, Engineering, Procurement, Construction, Precommissioning, Commissioning, Start-up, Handover.
  • 7.  L4 : Milestones, Management  L5 : - Milestones are split between contractual Milestones and Project Milestones. - Management is split between the different Department output for the project.
  • 8.  L4 : Disciplines  L5 : Work Packages
  • 9.  L4 : Subcontract, Long lead items, Disciplines ( auxiliary, Civil ) and Bulk Materials.  L5 : Work Packages ( group of equipment)
  • 10.  L4 : Zone  L5 : Area  L6 : Work Packages
  • 11.  L4 : systems
  • 12.  SCOPE: provide The whole scope of work(EPC), including manhours and quantities  Schedule: Time Management ( Planning software)  PRT : Progress reporting and tracking, excel tool to managed update progress and reporting  Time_Sheet: The manhours spent in Construction.  Job Card : detailed Progress report at level 5  DPR : Document Progress Register.  PSR : Procurement status report.  Cost : Cost Control is managed by Separate tool.
  • 13. Task_Code Descipline Task Class Unique identifier Level L1 L2 L3 XXXXXX XX XX XX Example CV1020 CV 10 20 Civil Concrete Works Foundation Civil Works CV1060 CV 10 60 Civil Concrete Works Pipe support Civil Works  Task_Code : is a unique six digit Code.  It is the concatenation of Discipline, Task Class and a unique identifier  The efficiency per Task_Code is a based on a historical data of the company.
  • 14.  SCOPE is a live List incorporating all new update to the scope of works (EPC).  The integration between the planning software and SCOPE is using SCOPE_ID.  When there is a significant change in Scope of Work, the Planning software is update from SCOPE
  • 15. SCOPE_ID SCOPE ( Budget manhours, Quantities, weightage to the client as by the contract revenue) Construction ITEM List Document Progress Register Procurement Status Report SCOPE_ID SCOPE_ID Construction Productivity database Master Schedule Level 4 SCOPE_ID Contract Value
  • 16.  The data in the PRT is mapped at the activity level in The Planning software, basically it is the same schedule but handled in a separate spreadsheet.  It is easier to record period performance in excel then in a planning software.  Anyone with basic Excel skills, can update the progress and produce reports without the need to operate a Planning software.
  • 17. PRT (Progress Reporting and Tracking) Weekly Planning software (Weekly, Or Monthly) Progress report S Curve Invoice SCOPE_ID Time sheet Productivity Internal Report Cost Dates by CBS WBS Job Card Procurement register Engineering Register
  • 18.  Planning software is used only to manage time, by using the CPM calculation.  In the initial baseline, load the physical quantities to level your production output.  A hammock can be used to split an Activity assigned to SCOPE_ID  The Frequency of updating the schedule, depend if you want to generate a Forecast curve, Weekly or Monthly.  The actual start, actual finish ( the facts) are imported from PRT.  There is no magic formula to generate remaining duration, talk to the guy doing the work, he is the best one to provide this information.  After scheduling, the new forecast dates are exported to PRT, to generate the forecast data.  Any planning tool can be used (MS Project, Primavera, etc).  Never Ever input dates directly in Excel !!!!!
  • 19.  For the sake of simplification the spent hours in the site will be recorded only by subcontractor, but in order to have a more accurate Productivity analysis, the hours should be at least recorded at the Subcontractor/ discipline level.  The data is recorded in a daily basis, the productivity factor in a weekly basis.  The time sheet records the roles by direct and indirect.
  • 20.  Cost control is a separate process.  The cost breakdown structure is implemented using the activity codes in the planning software.  The spread of cost by cost account is done using the dates from the schedule.  PRT generate progress report by CBS, it should be considered as an approximation, as progress based on cost weight and revenue weight are little bit different.  It is important to avoid the use the “best guess method” in distributing cost data.  The more CBS is detailed the more the distribution is accurate.
  • 21.  Engineering and construction the budget is in manhours.  Procurement the budget is the cost.  The revenue Factor Revenue = Budget X Factor  The overall Progress (EPC) is based on the contract Value.
  • 22.  The Primary Progress reports for the client are based on the WBS.  For different audience, there is a different reports. 1. By Contractor. 2. By discipline. 3. By Work Package 4. By systems.
  • 23.  Separate datasets from the reports.  Never Hard Code a report  Understand your Primary key.  Use codes, standardize your codifications.  Always prepare and generate data as database.  Pivot table in Excel is very powerful reporting utility.  Automatize your workflow, manual data entry is a waste of time.  Use both WBS and activity codes for maximum flexibility in reporting.
  • 24.  Two Approaches 1- Keep two revision of PRT.  Stable Revision issued to the client, the budget is frozen.  An internal live revision incorporating the latest changes from SCOPE. 2- update the current schedule with the latest data from SCOPE ( without adding weightage)  The period performance ( % complete) does not change, as it is calculated in the JOB CARD using always the latest update from Construction ITEM LIST
  • 25.  PS :  I added a new Excel file Project dashboard, it is much easier to use, and all the calculation are automated