1. Day 1 03 05 10 15 20 25 30 35 40 42 45
GHANTT CHART--
A Gantt chart is a graphical depiction of a project schedule. A Gantt
chart is a type of bar chart that shows the start and finish dates of
several elements of a project that include resources, milestones,
tasks and dependencies.
Henry Gantt, an American mechanical engineer, designed the Gantt
chart
2. Day 1 03 05 10 15 20 25 30 35 40 42 45NO. OF DAYS
05
days
FEASIBILITY STUDY
08
days
SRS
08
days
DESIGN 03
days
05
days
FLOW CHART
ER DIAGRAM
USE CASE ,ACTIVITY
DIAGRAM
10
days
08
days
IMPLEMENTATION
TESTING
GANTT CHART
3. PERT CHART --
A PERT chart is a project management tool that provides
a graphical representation of a project's timeline. PERT,
or Program Evaluation Review Technique, allows the
tasks in a particular project to be analyzed. Although
PERT charts are preferable to Gantt charts because they
more clearly identify task dependencies, PERT charts are
often more difficult to interpret.