http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com
International Journal of Civil Engineering and Technology (IJCIET)
Volume 10, Issue 03, March 2019, pp. 31-40, Article ID: IJCIET_10_03_003
Available online at http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=10&IType=03
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
© IAEME Publication Scopus Indexed
TIME AND COST OVERRUN IN DELIVERY OF
GOVERNMENT BUILDINGS IN UTTAR
PRADESH: THE INVISIBLE CAUSES
Asthana Kamla Kant
Research Scholar, AK Technical University, Lucknow
Jagbir Singh
Professor, Director, School of Architecture and Planning, Amity University, Lucknow
ABSTRACT
Causes of time and cost overrun in delivery of government buildings in Uttar
Pradesh are quite complex. These causes may be divided into two categories. One
type of causes or factors affects the general efficiency of construction agency which in
turn results in to delay in the delivery and increase in the cost of the buildings. Other
factors have direct impact on time and cost overrun.
Both types of causes are important as each of them ultimately causes time and
cost overrun. Attempt has been made to identify the invisible and indirect factors
affecting general efficiency of the construction agencies by critically reviewing the
building delivery process in Uttar Pradesh. The roles and responsibilities of various
stake holders involved at various stages of this process has also been analysed.
Format of study has been kept as informal discussions along with unstructured
and semi structured interviews with stake holders and people involved at various
stages of the process to explore the ground realities.
Keywords: Causes Efficiency Invisible Overrun Stakeholder
Cite this Article: Asthana Kamla Kant and Jagbir Singh, Time and Cost Overrun in
Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes.,
International Journal of Civil Engineering and Technology, 10(03), 2019, pp. 31–40
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=03
1. THE BACKGROUND
The phenomena of time and cost overrun in the delivery of government buildings in Uttar
Pradesh is so common that it has almost been accepted as the integral part of the delivery
process of these buildings. There is hardly any government project that is finished within
time and cost limits. Delay in the process is no more taken as the failure and increase in cost
is not taken as breach of promise.
Asthana Kamla Kant and Jagbir Singh
http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com
Though the phenomena of time and cost overrun is universal in nature and there are
significant cases of time and cost overrun in the delivery of the projects across the globe,
especially in the infrastructure related mega projects, but according to specialists the causes
of delay and cost overrun are not same in all the cases. Some scholars have a view that
applying the same principles and using same tools of management may not give similar
results in every case.
Every geographical region and cultural as well as socio political entity has its own set of
problems and their specific solutions. Uttar Pradesh might also be having its unique set of
problems and equally unique solutions to those problems. It is therefore very important to
establish the exact reasons that affect the time schedule and cause the cost overrun in these
buildings.
Various studies have been done in the past to know the exact reasons of this problem.
Most of these studies are based on projects set in the western world. Recently Indian
researchers have also started paying attention to this problem. Many studies and researches
have been published by them in last couple of years. These studies are focused on the Indian
conditions and portray more realistic picture of the problem in Indian perspective.
This study intends to explore the present scenario of the delivery of government buildings
in Uttar Pradesh to know the ground realities. Feedback from stakeholders and participants of
the process has been taken to establish these causes of time and cost overrun.
Causes of time and cost overrun may be broadly divided in two categories. One type of
causes affects the general efficiency of the construction agency which in turn results in to
delay in the delivery and increase in the cost of the buildings. Other causes have direct impact
on time and cost increase.
2. SCOPE OF STUDY
Present study is limited to the causes having direct impact on the efficiency of the
construction agency which in turn results into time and cost overrun. These causes are so
common in nature that researchers and decision makers usually tend to take them for granted
and ignore them. Present study shows that these invisible causes have tremendous effect on
the delivery process and cause significant delay in delivery and cost of the project.
“Identifying the reason is the first step while addressing a problem, then only the corrective
measures can be taken” (Chang2002, in T. Subramani2014)
3. METHODOLOGY FOR STUDY
Methodology for the study includes extensive literature survey, especially researches done by
scholars in Indian settings, along with investigation of delivery process of government
buildings. Causes of time and cost overrun were narrowed down through literature survey.
Semi structured interviews of major stakeholders were conducted to have feedback on these
narrowed down causes. The two major stakeholders include client or administrative
departments of the government and the construction agency. Construction agency is
represented by its project manager. Another major player of the process is the monitoring
system of the construction agency which controls the entire delivery process.
4. LITERATURE SURVEY
Literature survey shows that most of the scholars have focused only on the factors having
direct impact on time and cost overrun. The factors having indirect impact on general
efficiency of the construction agencies were not given much importance by them. These
Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible
Causes
http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com
factors were noted down. Unstructured as well as semi structured interviews of some of the
stakeholders were taken to know the ground reality of these factors.
5. ANALYSIS OF BUILDING DELIVERY PROCESS IN UTTAR
PRADESH
State government buildings are constructed by one of the State Government owned
construction agencies. The process of building delivery starts with the initiative by the client
or administrative department. The client department prepares a report highlighting the need
of the building along with the expected expenditure and submits it for approval from the
government
Administrative departments are usually not well equipped to prepare such proposals.
Normally no construction agency or no other specialist is involved till this stage of the work
due to lack of funds. Fund is allotted only after approval of the project. At this point, the
administrative department engages a construction agency for delivery of the building on
Design and Build system.
5.1. Working of Construction Agency
Working of the government owned construction agencies has great impact on the efficiency
of its officials which indirectly results into time and cost overrun of the project. Construction
agencies work in a system, where the material is procured by the construction agency itself
and execution is done by labor contractors or petty contractors in supervision of the technical
staff of the construction agency.
The „design and build‟ delivery system is supposed to be the fastest delivery system as
the construction starts even before all the working drawings are prepared. Still the projects
are not completed on time. It indicates that there are some serious reasons behind this delay
and cost overrun that follows it.
One of the apparent reasons is „no risk‟ status of the construction agency in the delivery
process. The construction agency gets certain percent of the cost of the project as centage
charges for establishment, overhead expenses and its profit. The profit is paid over and above
the actual cost incurred on construction. Construction agency has no risk, even if the cost of
building increases. Rather its profit increases with the increased cost. That is one big reason
of casual attitude of construction agencies towards time and cost overrun.
5.2. Selection of Construction Agency for the project
The other reason of casual approach of the construction agency is its selection process.
Selection of construction agency by state government is purely on arbitrary basis.
Government allots the work to one of its construction agencies without any competitive
bidding. Criteria for selection of construction agency is not defined. Due to lack of
competition, the construction agencies tend to take the work casually. Lack of professional
approach is prevalent at every stage.
6. FEEDBACK FROM STAKEHOLDERS
Twenty Project managers and monitoring personnel from one of the construction agencies
and five officers from administrative or client department were interviewed in detail. Format
of interview was kept open ended and semi structured as the purpose was to explore and find
out their version of the problem.
Asthana Kamla Kant and Jagbir Singh
http://www.iaeme.com/IJCIET/index.asp 34 editor@iaeme.com
Most significant factors affecting the general efficiency of the construction agency,
derived from literature survey and critical analysis of building delivery process were
shortlisted. A survey in the form of semi structured discussions with stakeholders was
conducted to verify the significance of these shortlisted causes. Table given below shows the
feedback from stakeholders
Feedback from Stakeholders on factors affecting efficiency of construction unit
Not Significant-0, slightly significante-1, moderate-2, very significant-3, externally
significant-4
S.N. Factors
Response in Percentage
0 1 2 3 4
1- Inadequate staff strength at site & & 10 15 75
2- Large Number of projects with the construction unit.
& & 20 60 20
3- Under qualified technical staff & & 40 40 20
4-
Lack of basic training of construction management
& 20 40 40 &
5-
Lack of ongoing training/refresher courses to update
the knowledge & & 40 40 20
6-
Staff‟s involvement in non-productive work of other
government schemes. & 10 40 40 10
7-
Too much of monitoring by bureaucracy at district
as well as higher level. & & 20 40 40
8- Political and other interference & & 25 50 25
9- Clash of interest and Corruption & 25 50 25 &
9-1
Vested interests of insiders in the construction
agency & 10 40 40 10
9-2
Vested interests of influential out siders.
& 10 40 40 10
10-
Lack of technical expertise with client department
resulting in to poor coordination. & & 60 40 &
11- Slow decision making process in government & & 40 30 30
12-
Late allotment of work to construction agency.
& & 20 40 40
13-
Difficulty in getting the project sanctioned from the
government & & 60 20 20
14- Difficulty in getting the funds released. & 10 50 30 10
15-
Transfer of Project Manager during the construction
process. & & 60 20 20
16-
Lack of accountability for bad work
& 10 20 50 20
Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible
Causes
http://www.iaeme.com/IJCIET/index.asp 35 editor@iaeme.com
17-
Lack of incentive for timely and within budget
completion of work & 10 20 50 20
6.1 Inadequate Staff Strength with Construction Units: Most of the construction
agencies suffer from acute shortage of technical as well as nontechnical staff owing to the
policy of economy drive of the state government. Lack of adequate technical staff at lower
level adversely affects the actual construction work at site on daily basis. 75 percent of
project managers have endorsed this problem as the most severe cause affecting the
efficiency of the unit.
6.2 Large Number of Projects with Construction Units: Most of the units of
construction agencies have unmanageably large number of projects at any given time. The
projects are usually spread in a couple of adjoining districts. Construction units find it
difficult to manage the quality of construction as well as schedule of these projects due to
long distances between various project sites. This eventually results in to cost overrun also.
Large number of projects adversely affects the general efficiency of the construction unit.
6.3 Under Qualified Technical Staff: Due to defective policies of the government as
well as construction agencies, under qualified staff gets promoted to the key positions. Even a
diploma holder engineer, appointed on the post of junior engineer, rises to the level of project
manager without obtaining the required knowledge of civil engineering and construction
management.
6.4 Lack of Basic Training of Management and Construction Management: A fresh
engineering degree holder is appointed on the post of Assistant Engineer. The diploma
engineer appointed on the post of junior engineer also gets promoted to this post after certain
years of experience. These promoted officers hardly get any opportunity for enhancing their
qualification. They are neither taught during their college time, nor trained later for the
important task of project management. Both these engineers are further promoted to more
important position of project manager
6.5 Lack of Training and Refresher Courses to update the Knowledge: There has
been tremendous development in the field of materials as well as construction techniques in
last couple of decades. Construction agencies hardly have regular program for upgrading
skills of their personnel. This has emerged as one of the basic reasons for poor performance
of the construction agencies.
6.6 Involvement of staff in non-productive works: Staff of construction units, including
the project manager, are kept engaged for considerable duration by District Administration in
nonprofit making social schemes of state government. General election is also one such affair
in which staff of construction units is deployed quite often and for long durations. The
working of entire unit gets paralyzed during this period. Work of election commission goes
on round the year and there are so many elections of various level. This factor has never been
acknowledged.
6.7 Too much of Review and Monitoring: There are periodical reviews by district
administration for various government schemes being run in the district. Representatives of
all the departments including construction agencies are called for quick problem solving. A
project manager, having projects in more than one district, attends these review meetings in
all those districts.
Similar meetings are held at commissioner level also. Heads of client departments also
have review meetings for the works of their department. Then there are special reviews by
ministers and other public representatives. There is thrust on submitting reports in various
prescribed formats for which site staff is not properly trained. These meetings consume
Asthana Kamla Kant and Jagbir Singh
http://www.iaeme.com/IJCIET/index.asp 36 editor@iaeme.com
significant amount of productive time. This exercise of ensuring the efficiency of
construction unit, in fact has adverse effect on its performance.
6.8 Political Interference: There is always a direct or indirect pressure to accommodate
the undeserving people in the process. Project manager has no option but to yield to the
pressure, compromising with the quality in the works undertaken by these unwanted and
undeserving people. Project manager loses its control over these people resulting in to loss of
control over the entire building delivery process. This is one factor that is not even
acknowledged by the decision makers at higher level.
6.9 Clash of Interests and Corruption
6.9.1 Vested interests of insiders in the construction agency: There may be vested
interests of one or more of the responsible people in the construction agency itself, who may
deliberately delay the process at any stage. Delaying the payment of material supplier or
labor contractor without any specific reason is always viewed as the extortion techniques. It
certainly affects the efficiency of the construction unit at site. This has become a common
practice and has direct impact on the efficiency of the construction agency.
6.9.2 Vested interest of others, involved in the process: There may be people outside
the construction agency, capable of influencing the process of building delivery with their
agenda to implement. Holding back one of the required approvals or delaying the process of
fund release may put extra pressure on the implementing team and may fetch them some
favor in terms of money. This not only hampers the progress of work but has financial impact
on the cost of the project.
6.10 Lack of Technical Knowhow with Client Department: Client or administrative
department is generally dependant on construction agency itself for the technical advice, as
there is normally no technical person working with them. Working out the requirements,
acquisition of land and preparation of preliminary proposal requires specific knowledge of
planning and quantity surveying. Administrative or client department manages to get the
preliminary proposal prepared either with the help of one of the construction agencies itself
or any other entity. Accuracy of the estimate prepared as obligatory work is always doubtful.
Administrative department is supposed to monitor the progress of the work during
construction and to forward the utilization certificate produced by the construction agency to
the government. Administrative department is also required to take over the building from the
construction agency. Due to lack of technical personnel working with them, it becomes very
difficult for the administrative department to monitor the progress of construction at site and
to take the possession of the building after technical scrutiny. This hampers the progress at
site and becomes a significant cause of time and cost overrun.
6.11 Slow Decision-making in Government: It sometimes takes years altogether to get
the project approved from the maze of government rules, regulations and procedures. By the
time project is sanctioned the preliminary estimate becomes redundant. The rates of PWD
schedule itself get escalated and revised by the time the project gets approved from the
government. To avoid further delay, the construction agency starts the work at site in
anticipation of getting the estimate revised in due course of time. Same story is repeated in
the sanctioning of revised estimate also. Cost is already escalated by the time the estimate is
sanctioned. This process is repeated for several rounds till the project is completed with many
fold cost escalation and enormous delay in schedule.
6.12 Late Engagement of Construction Agency: Construction agency comes into the
picture when the preliminary proposal is already prepared without proper input from experts
and approval by the government is already granted. The first step of construction agency thus
Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible
Causes
http://www.iaeme.com/IJCIET/index.asp 37 editor@iaeme.com
becomes to rationalize the requirements as well as specifications and revise the estimate
accordingly. This revision has become an integral part of the delivery process due to the
system.
This estimate after first revision with input from experts must be regarded as the
preliminary estimate for all the purposes and cost escalation should be counted against this
estimate only. It would be advisable to develop a system that ensures input of experts from
the very beginning.
6.13 Difficulty in Getting the Revised Estimate Approved: The whole process of
project approval is repeated once again in getting the revised estimate processed through the
labyrinth of official procedures and finally getting it approved from the government. It takes
even more time in getting the revised estimate finally approved. This causes delay in the
starting of the project leading to further delay and cost overrun.
6.14 Difficulty in Getting Funds Released: Getting the funds released for the project is
another art supposed to be mastered by the project managers of the construction agency in
Uttar Pradesh. It takes considerably long time and efforts as well as sources and resources to
get the fund released for the project. Though there are no documented evidences, but the
financial involvement of many responsible entities in the process of building delivery is an
open secrete. Financial involvement of responsible persons at various levels of process gives
the project manager sort of moral courage to take the work casually.
6.15 Transfer of Project Manager during Execution of Work: The work of project
delivery is quite complex. A mistake committed at an initial stage may have its affect in later
part of execution of the project. Continuity of the team deployed for the project is very
important for accountability. It has been observed that the key persons are transferred during
the execution stage. It adversely affects the progress of the work and efficiency of the
construction unit.
6.16 Lack of Accountability for Delay and Cost Overrun: Normally it is the joint
responsibility of the team comprising of the project in charge and other engineers of various
levels posted at the site to complete the project diligently, within the time and cost limits.
Though the roles and responsibility of each and every personnel are clearly defined yet by
and large these responsibilities are overlapping. There has been hardly any action against any
officer for time and cost overrun within the construction agency.
6.17 Lack of incentive for timely and within budget completion of work: No incentive
of any sort is given to the officers of construction agency for their excellent performance in
terms of completing the project within time and cost limits.
6.18 Defective Monitoring System / Pressure for Turnover: Since the construction
agencies are commercial organizations, they are required to earn for the salary of their
employees. Project manager, being the key person in the field, is always pressurized for
procurement of work and turnover. Monitoring is focused on turnover instead of progress of
the work. Project managers develop a tendency to spend the money on whatever item they
can, just to increase the turnover. With the result a huge inventory is created and money gets
blocked in the items which are not immediately required and actual construction at times
suffers due to shortage of funds, causing unnecessary delay in completion of work. As the
work gets held up it causes cost overrun also.
6.19 Factors beyond control: There are certain factors which are beyond control of
every one, like natural calamities or disruption of work due to political reasons. Some of
these factors are listed below.
Asthana Kamla Kant and Jagbir Singh
http://www.iaeme.com/IJCIET/index.asp 38 editor@iaeme.com
 Inadequate supply of building materials from time to time due to reasons beyond
control of every one.
 Wastage of building materials purchased in advance due to lack of proper storage.
 Lack of mechanization due to availability of cheap labor. It results in to time
overrun which ultimately results in to cost overrun also.
7. INFERENCES
There are certain invisible factors which affect the general efficiency of the construction
units. Impact on efficiency of construction unit reflects in time and cost overrun. These
factors are generally not noticed by the researchers as the significant and direct factors
causing time and cost overrun, but they have significant effect.
Time and cost overrun in the delivery of government buildings can be checked up to a
considerable level by increasing the working efficiency of the construction units. Efficiency
of the construction units may be increased by improving the general working conditions at
site. These factors have been identified in the present study. The corrective measures
immerged in this study will not only check the time and cost overrun but shall improve the
quality of work also.
8. LIMITATIONS OF THE STUDY
The purpose of this study was to underline the invisible or normally ignored causes which
directly affect the general efficiency of the construction agency and have indirect. Impact on
time schedule and budget of the building. Since the sample size was very small, the
percentage of response was not highlighted in the discussion. Only the presence of those
causes was underlined. This study may be used for hypothesis formation for further
investigations.
9. RECOMMENDATIONS
9.1 The study shows that most of the causes affecting the general efficiency of the
construction unit are very common in nature and may be tackled very easily. Here are some
recommendations which may improve the efficiency of construction units and may be useful
in having check on time and cost overrun in the delivery of government buildings.
9.2 Delivery process of government buildings must be redefined to ensure input of
experts from the very beginning. Funds for preparation of preliminary proposal may be made
available to the administrative or client department so that a realistic project report based on
accurate estimate of various expenditures may be prepared.
9.3 Selection process of construction agencies must be made more transparent and
competitive. Construction agencies to be made more accountable towards quality of
construction, cost limit and time schedule for construction.
9.4 Adequate staff should be provided to the construction unit according to work load or
work load should be restricted according to availability of the staff with the unit.
9.5 Serious thought should be given to define the area to be covered by a construction
unit. A separate unit for each district may be deployed.
9.6 Minimum qualification for responsible positions should be reviewed. Constant
refresher courses and quality improvement programs should be organized for staff as well as
officers of the construction unit.
Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible
Causes
http://www.iaeme.com/IJCIET/index.asp 39 editor@iaeme.com
9.7 There should be professional approach for construction management. Detailed
planning for material and manpower management should be prepared and execution should
be carried out accordingly.
9.8 The responsibilities of project manager may be divided between two officers. One
officer may look after the planning and may liaison with various authorities while the other
one may be made responsible for actual execution at site.
9.9 Public Works Department or some other organization may be made technical advisor
to all the administrative departments. This entity may work for and on behalf of the
administrative departments in all the matters related with construction of buildings.
9.10 Joint periodical inspection of construction site by administrative department,
advising entity, consultants and personnel from construction agency should be made
mandatory. All of them should bear proportionate responsibility for time and cost overrun.
9.11 Responsible officers of construction unit, especially the project manager should not
be changed during construction of the building. Project manager should be accountable for
success or failure of the project.
9.12 Incentive for successful completion of the work and punishment for failure should be
there.
REFERENCES
[1] Anant Narayan Shete and Vaibhav Durwas Kothawade, An Analysis of Cost Overrun and
Time Overrun of Construction Projects in India, International Journal of engineering
Trends and Technology (IJETT), Volume-41, Number-1, 2016, pp 33-36
[2] Anupam Dutta & Probol Dutta, Causes of Time and Cost Overrun in Transportation
Sector Projects in Bangladesh, SSRG-IJEMS, Vol. 2, Issue 4, 2015
[3] Ashwini Arun Salunkhe, Rahul S. Patil, Statistical Methods for Construction Delay
Analysis, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Vol. 9,
2013, pp58-62
[4] Borvorn Israngkura Na Ayudhya, Evaluation of Common Delay Causes of Construction
Projects in Singapore, Journal of Civil Engineering and Architecture, Vol.5, No. 11
(Serial no. 48), 2011, pp1027-1034
[5] Desai Megha, Dr Bhatt Rajeev, A Methodology for Ranking of Causes of Delay for
Residential Construction Projects in Indian Context, International Journal Emerging
Technology and Advanced Engineering, Vol. 3, Issue 3, 2013
[6] K.Muthu Venkata Sekar and M.Mahalakshmi, Evaluating Reasons for Cost Overrun in A
Low Cost Construction Project, International Journal of Civil Engineering and
Technology, 9(4), 2018, pp. 690–696.
[7] Dinesh Kumar R, Causes and Effects of Delays in Indian Construction Projects,
International Research Journal of engineering and Technology (IRJET), Vol 3, Issue 4,
2016, pp1831-1837
[8] Divya R. & Ramya S., Causes Effects and Minimization of Delays in Construction
Projects, National Conference on Research Advances in Communication, Computation,
Electrical Science and Structures (NCRACCESS), 2015, pp 51-52
[9] Muhammad Akram, TauhaHussain Ali, Nafees Ahmed Memon and Shabir Hussain
Khahro Causal Attributes of Cost Overrun In Construction Projects of Pakistan.
International Journal of Civil Engineering and Technology, 8(6), 2017, pp. 477–483.
[10] K. Mukilan and R. Jayanthi, Severity Rating of Time And Cost Overruns In Construction
Projects, International Journal of Science and Engineering Research (IJOSER), Vol.3
Issue 5, 2015,
Asthana Kamla Kant and Jagbir Singh
http://www.iaeme.com/IJCIET/index.asp 40 editor@iaeme.com
[11] Kaming, P.F., Olomolaiye, P.O., Holt, G.D. & Harris, F.C., Factors influencing
construction time and cost overruns on high-rise projects in Indonesia, Construction
Management Economics, 15(1), pp 83-94
[12] M.S.Ramabodu and JJP Verster, Factors Contributing to cost Overruns of Construction
Projects, Proceedings 5th Built Environment Conference, Durban South Africa, 2010, pp
131-143
[13] Siddesh Pai, Bijayanand Patnaik, Dr. Ankur Mittal and Dr. Neeraj Anand, Identification
of Risks Causing Time and Cost Overrun in Roads and Highway Projects in India,
International Journal of Civil Engineering and Technology, 9(3), 2018, pp. 683–697.
[14] Asthana Kamla Kant, Bottlenecks in the Delivery Process of Government Buildings in
Uttar Pradesh (India) Causing Time and Cost Overrun, International Journal of Civil
Engineering and Technology, 9(2), 2018, pp. 693–704.
[15] Naveen Kumar.G.V. and Prabhu.V, Factors Influencing Time and Cost Overruns in
Construction Projects, International Journal of Innovative Research in Science,
Engineering and Technology (IJIRSET), Vol.5, Issue 4, 20016, pp 6468-6473
[16] Salim S. Mulla and Ashish P. Wagmare, A Study of Factors Caused for Time and Cost
Overrun in Construction Projects and their Remedial Measures, International Journal of
Engineering Research and Application (IJERA), Vol.5, Issue 1(Part-6),2015, pp 48-53
[17] Santosh Kumar Prajapati, Rakesh Gupta and Mukesh Pande, Causes and Effects of Cost
Overrun on Construction Projects in Madhya Pradesh, International Journal of
Engineering Development and Research (IJEDR), Vol 4, Issue 2, 2016, pp 1346-1350
[18] T. Subramani, PS Sruthi and M. Kavitha, Causes of Cost Overrun in Construction,
International Organization of Scientific Research Journal of Engineering (IOSRJEN), Vol
4, Issue 6, 2014, (V3) pp 1-7

More Related Content

What's hot

IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET Journal
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268HASHIM HANIF
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysiseSAT Publishing House
 

What's hot (18)

IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Time overruns
Time overrunsTime overruns
Time overruns
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysis
 

Similar to TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: THE INVISIBLE CAUSES

IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction worksvivatechijri
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...ijtsrd
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxsaeedahmed433704
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
 
FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS
   FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS   FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS
FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTSIAEME Publication
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 

Similar to TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: THE INVISIBLE CAUSES (20)

IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS
   FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS   FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS
FACTORS EFFECTING THE FAILURE ANALYSIS OF CONSTRUCTION PROJECTS
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 

More from IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSIAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSIAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSIAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSIAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOIAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYIAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEIAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTIAEME Publication
 

More from IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Recently uploaded

electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.benjamincojr
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationEmaan Sharma
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfragupathi90
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxKarpagam Institute of Teechnology
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentationsj9399037128
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Toolssoginsider
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..MaherOthman7
 
Insurance management system project report.pdf
Insurance management system project report.pdfInsurance management system project report.pdf
Insurance management system project report.pdfKamal Acharya
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Stationsiddharthteach18
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualBalamuruganV28
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...Amil baba
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024EMMANUELLEFRANCEHELI
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1T.D. Shashikala
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUankushspencer015
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...IJECEIAES
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfssuser5c9d4b1
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfJNTUA
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New HorizonMorshed Ahmed Rahath
 

Recently uploaded (20)

electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & Modernization
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdf
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentation
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
 
Insurance management system project report.pdf
Insurance management system project report.pdfInsurance management system project report.pdf
Insurance management system project report.pdf
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdf
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 

TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: THE INVISIBLE CAUSES

  • 1. http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 03, March 2019, pp. 31-40, Article ID: IJCIET_10_03_003 Available online at http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=10&IType=03 ISSN Print: 0976-6308 and ISSN Online: 0976-6316 © IAEME Publication Scopus Indexed TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: THE INVISIBLE CAUSES Asthana Kamla Kant Research Scholar, AK Technical University, Lucknow Jagbir Singh Professor, Director, School of Architecture and Planning, Amity University, Lucknow ABSTRACT Causes of time and cost overrun in delivery of government buildings in Uttar Pradesh are quite complex. These causes may be divided into two categories. One type of causes or factors affects the general efficiency of construction agency which in turn results in to delay in the delivery and increase in the cost of the buildings. Other factors have direct impact on time and cost overrun. Both types of causes are important as each of them ultimately causes time and cost overrun. Attempt has been made to identify the invisible and indirect factors affecting general efficiency of the construction agencies by critically reviewing the building delivery process in Uttar Pradesh. The roles and responsibilities of various stake holders involved at various stages of this process has also been analysed. Format of study has been kept as informal discussions along with unstructured and semi structured interviews with stake holders and people involved at various stages of the process to explore the ground realities. Keywords: Causes Efficiency Invisible Overrun Stakeholder Cite this Article: Asthana Kamla Kant and Jagbir Singh, Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes., International Journal of Civil Engineering and Technology, 10(03), 2019, pp. 31–40 http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=03 1. THE BACKGROUND The phenomena of time and cost overrun in the delivery of government buildings in Uttar Pradesh is so common that it has almost been accepted as the integral part of the delivery process of these buildings. There is hardly any government project that is finished within time and cost limits. Delay in the process is no more taken as the failure and increase in cost is not taken as breach of promise.
  • 2. Asthana Kamla Kant and Jagbir Singh http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com Though the phenomena of time and cost overrun is universal in nature and there are significant cases of time and cost overrun in the delivery of the projects across the globe, especially in the infrastructure related mega projects, but according to specialists the causes of delay and cost overrun are not same in all the cases. Some scholars have a view that applying the same principles and using same tools of management may not give similar results in every case. Every geographical region and cultural as well as socio political entity has its own set of problems and their specific solutions. Uttar Pradesh might also be having its unique set of problems and equally unique solutions to those problems. It is therefore very important to establish the exact reasons that affect the time schedule and cause the cost overrun in these buildings. Various studies have been done in the past to know the exact reasons of this problem. Most of these studies are based on projects set in the western world. Recently Indian researchers have also started paying attention to this problem. Many studies and researches have been published by them in last couple of years. These studies are focused on the Indian conditions and portray more realistic picture of the problem in Indian perspective. This study intends to explore the present scenario of the delivery of government buildings in Uttar Pradesh to know the ground realities. Feedback from stakeholders and participants of the process has been taken to establish these causes of time and cost overrun. Causes of time and cost overrun may be broadly divided in two categories. One type of causes affects the general efficiency of the construction agency which in turn results in to delay in the delivery and increase in the cost of the buildings. Other causes have direct impact on time and cost increase. 2. SCOPE OF STUDY Present study is limited to the causes having direct impact on the efficiency of the construction agency which in turn results into time and cost overrun. These causes are so common in nature that researchers and decision makers usually tend to take them for granted and ignore them. Present study shows that these invisible causes have tremendous effect on the delivery process and cause significant delay in delivery and cost of the project. “Identifying the reason is the first step while addressing a problem, then only the corrective measures can be taken” (Chang2002, in T. Subramani2014) 3. METHODOLOGY FOR STUDY Methodology for the study includes extensive literature survey, especially researches done by scholars in Indian settings, along with investigation of delivery process of government buildings. Causes of time and cost overrun were narrowed down through literature survey. Semi structured interviews of major stakeholders were conducted to have feedback on these narrowed down causes. The two major stakeholders include client or administrative departments of the government and the construction agency. Construction agency is represented by its project manager. Another major player of the process is the monitoring system of the construction agency which controls the entire delivery process. 4. LITERATURE SURVEY Literature survey shows that most of the scholars have focused only on the factors having direct impact on time and cost overrun. The factors having indirect impact on general efficiency of the construction agencies were not given much importance by them. These
  • 3. Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com factors were noted down. Unstructured as well as semi structured interviews of some of the stakeholders were taken to know the ground reality of these factors. 5. ANALYSIS OF BUILDING DELIVERY PROCESS IN UTTAR PRADESH State government buildings are constructed by one of the State Government owned construction agencies. The process of building delivery starts with the initiative by the client or administrative department. The client department prepares a report highlighting the need of the building along with the expected expenditure and submits it for approval from the government Administrative departments are usually not well equipped to prepare such proposals. Normally no construction agency or no other specialist is involved till this stage of the work due to lack of funds. Fund is allotted only after approval of the project. At this point, the administrative department engages a construction agency for delivery of the building on Design and Build system. 5.1. Working of Construction Agency Working of the government owned construction agencies has great impact on the efficiency of its officials which indirectly results into time and cost overrun of the project. Construction agencies work in a system, where the material is procured by the construction agency itself and execution is done by labor contractors or petty contractors in supervision of the technical staff of the construction agency. The „design and build‟ delivery system is supposed to be the fastest delivery system as the construction starts even before all the working drawings are prepared. Still the projects are not completed on time. It indicates that there are some serious reasons behind this delay and cost overrun that follows it. One of the apparent reasons is „no risk‟ status of the construction agency in the delivery process. The construction agency gets certain percent of the cost of the project as centage charges for establishment, overhead expenses and its profit. The profit is paid over and above the actual cost incurred on construction. Construction agency has no risk, even if the cost of building increases. Rather its profit increases with the increased cost. That is one big reason of casual attitude of construction agencies towards time and cost overrun. 5.2. Selection of Construction Agency for the project The other reason of casual approach of the construction agency is its selection process. Selection of construction agency by state government is purely on arbitrary basis. Government allots the work to one of its construction agencies without any competitive bidding. Criteria for selection of construction agency is not defined. Due to lack of competition, the construction agencies tend to take the work casually. Lack of professional approach is prevalent at every stage. 6. FEEDBACK FROM STAKEHOLDERS Twenty Project managers and monitoring personnel from one of the construction agencies and five officers from administrative or client department were interviewed in detail. Format of interview was kept open ended and semi structured as the purpose was to explore and find out their version of the problem.
  • 4. Asthana Kamla Kant and Jagbir Singh http://www.iaeme.com/IJCIET/index.asp 34 editor@iaeme.com Most significant factors affecting the general efficiency of the construction agency, derived from literature survey and critical analysis of building delivery process were shortlisted. A survey in the form of semi structured discussions with stakeholders was conducted to verify the significance of these shortlisted causes. Table given below shows the feedback from stakeholders Feedback from Stakeholders on factors affecting efficiency of construction unit Not Significant-0, slightly significante-1, moderate-2, very significant-3, externally significant-4 S.N. Factors Response in Percentage 0 1 2 3 4 1- Inadequate staff strength at site & & 10 15 75 2- Large Number of projects with the construction unit. & & 20 60 20 3- Under qualified technical staff & & 40 40 20 4- Lack of basic training of construction management & 20 40 40 & 5- Lack of ongoing training/refresher courses to update the knowledge & & 40 40 20 6- Staff‟s involvement in non-productive work of other government schemes. & 10 40 40 10 7- Too much of monitoring by bureaucracy at district as well as higher level. & & 20 40 40 8- Political and other interference & & 25 50 25 9- Clash of interest and Corruption & 25 50 25 & 9-1 Vested interests of insiders in the construction agency & 10 40 40 10 9-2 Vested interests of influential out siders. & 10 40 40 10 10- Lack of technical expertise with client department resulting in to poor coordination. & & 60 40 & 11- Slow decision making process in government & & 40 30 30 12- Late allotment of work to construction agency. & & 20 40 40 13- Difficulty in getting the project sanctioned from the government & & 60 20 20 14- Difficulty in getting the funds released. & 10 50 30 10 15- Transfer of Project Manager during the construction process. & & 60 20 20 16- Lack of accountability for bad work & 10 20 50 20
  • 5. Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes http://www.iaeme.com/IJCIET/index.asp 35 editor@iaeme.com 17- Lack of incentive for timely and within budget completion of work & 10 20 50 20 6.1 Inadequate Staff Strength with Construction Units: Most of the construction agencies suffer from acute shortage of technical as well as nontechnical staff owing to the policy of economy drive of the state government. Lack of adequate technical staff at lower level adversely affects the actual construction work at site on daily basis. 75 percent of project managers have endorsed this problem as the most severe cause affecting the efficiency of the unit. 6.2 Large Number of Projects with Construction Units: Most of the units of construction agencies have unmanageably large number of projects at any given time. The projects are usually spread in a couple of adjoining districts. Construction units find it difficult to manage the quality of construction as well as schedule of these projects due to long distances between various project sites. This eventually results in to cost overrun also. Large number of projects adversely affects the general efficiency of the construction unit. 6.3 Under Qualified Technical Staff: Due to defective policies of the government as well as construction agencies, under qualified staff gets promoted to the key positions. Even a diploma holder engineer, appointed on the post of junior engineer, rises to the level of project manager without obtaining the required knowledge of civil engineering and construction management. 6.4 Lack of Basic Training of Management and Construction Management: A fresh engineering degree holder is appointed on the post of Assistant Engineer. The diploma engineer appointed on the post of junior engineer also gets promoted to this post after certain years of experience. These promoted officers hardly get any opportunity for enhancing their qualification. They are neither taught during their college time, nor trained later for the important task of project management. Both these engineers are further promoted to more important position of project manager 6.5 Lack of Training and Refresher Courses to update the Knowledge: There has been tremendous development in the field of materials as well as construction techniques in last couple of decades. Construction agencies hardly have regular program for upgrading skills of their personnel. This has emerged as one of the basic reasons for poor performance of the construction agencies. 6.6 Involvement of staff in non-productive works: Staff of construction units, including the project manager, are kept engaged for considerable duration by District Administration in nonprofit making social schemes of state government. General election is also one such affair in which staff of construction units is deployed quite often and for long durations. The working of entire unit gets paralyzed during this period. Work of election commission goes on round the year and there are so many elections of various level. This factor has never been acknowledged. 6.7 Too much of Review and Monitoring: There are periodical reviews by district administration for various government schemes being run in the district. Representatives of all the departments including construction agencies are called for quick problem solving. A project manager, having projects in more than one district, attends these review meetings in all those districts. Similar meetings are held at commissioner level also. Heads of client departments also have review meetings for the works of their department. Then there are special reviews by ministers and other public representatives. There is thrust on submitting reports in various prescribed formats for which site staff is not properly trained. These meetings consume
  • 6. Asthana Kamla Kant and Jagbir Singh http://www.iaeme.com/IJCIET/index.asp 36 editor@iaeme.com significant amount of productive time. This exercise of ensuring the efficiency of construction unit, in fact has adverse effect on its performance. 6.8 Political Interference: There is always a direct or indirect pressure to accommodate the undeserving people in the process. Project manager has no option but to yield to the pressure, compromising with the quality in the works undertaken by these unwanted and undeserving people. Project manager loses its control over these people resulting in to loss of control over the entire building delivery process. This is one factor that is not even acknowledged by the decision makers at higher level. 6.9 Clash of Interests and Corruption 6.9.1 Vested interests of insiders in the construction agency: There may be vested interests of one or more of the responsible people in the construction agency itself, who may deliberately delay the process at any stage. Delaying the payment of material supplier or labor contractor without any specific reason is always viewed as the extortion techniques. It certainly affects the efficiency of the construction unit at site. This has become a common practice and has direct impact on the efficiency of the construction agency. 6.9.2 Vested interest of others, involved in the process: There may be people outside the construction agency, capable of influencing the process of building delivery with their agenda to implement. Holding back one of the required approvals or delaying the process of fund release may put extra pressure on the implementing team and may fetch them some favor in terms of money. This not only hampers the progress of work but has financial impact on the cost of the project. 6.10 Lack of Technical Knowhow with Client Department: Client or administrative department is generally dependant on construction agency itself for the technical advice, as there is normally no technical person working with them. Working out the requirements, acquisition of land and preparation of preliminary proposal requires specific knowledge of planning and quantity surveying. Administrative or client department manages to get the preliminary proposal prepared either with the help of one of the construction agencies itself or any other entity. Accuracy of the estimate prepared as obligatory work is always doubtful. Administrative department is supposed to monitor the progress of the work during construction and to forward the utilization certificate produced by the construction agency to the government. Administrative department is also required to take over the building from the construction agency. Due to lack of technical personnel working with them, it becomes very difficult for the administrative department to monitor the progress of construction at site and to take the possession of the building after technical scrutiny. This hampers the progress at site and becomes a significant cause of time and cost overrun. 6.11 Slow Decision-making in Government: It sometimes takes years altogether to get the project approved from the maze of government rules, regulations and procedures. By the time project is sanctioned the preliminary estimate becomes redundant. The rates of PWD schedule itself get escalated and revised by the time the project gets approved from the government. To avoid further delay, the construction agency starts the work at site in anticipation of getting the estimate revised in due course of time. Same story is repeated in the sanctioning of revised estimate also. Cost is already escalated by the time the estimate is sanctioned. This process is repeated for several rounds till the project is completed with many fold cost escalation and enormous delay in schedule. 6.12 Late Engagement of Construction Agency: Construction agency comes into the picture when the preliminary proposal is already prepared without proper input from experts and approval by the government is already granted. The first step of construction agency thus
  • 7. Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes http://www.iaeme.com/IJCIET/index.asp 37 editor@iaeme.com becomes to rationalize the requirements as well as specifications and revise the estimate accordingly. This revision has become an integral part of the delivery process due to the system. This estimate after first revision with input from experts must be regarded as the preliminary estimate for all the purposes and cost escalation should be counted against this estimate only. It would be advisable to develop a system that ensures input of experts from the very beginning. 6.13 Difficulty in Getting the Revised Estimate Approved: The whole process of project approval is repeated once again in getting the revised estimate processed through the labyrinth of official procedures and finally getting it approved from the government. It takes even more time in getting the revised estimate finally approved. This causes delay in the starting of the project leading to further delay and cost overrun. 6.14 Difficulty in Getting Funds Released: Getting the funds released for the project is another art supposed to be mastered by the project managers of the construction agency in Uttar Pradesh. It takes considerably long time and efforts as well as sources and resources to get the fund released for the project. Though there are no documented evidences, but the financial involvement of many responsible entities in the process of building delivery is an open secrete. Financial involvement of responsible persons at various levels of process gives the project manager sort of moral courage to take the work casually. 6.15 Transfer of Project Manager during Execution of Work: The work of project delivery is quite complex. A mistake committed at an initial stage may have its affect in later part of execution of the project. Continuity of the team deployed for the project is very important for accountability. It has been observed that the key persons are transferred during the execution stage. It adversely affects the progress of the work and efficiency of the construction unit. 6.16 Lack of Accountability for Delay and Cost Overrun: Normally it is the joint responsibility of the team comprising of the project in charge and other engineers of various levels posted at the site to complete the project diligently, within the time and cost limits. Though the roles and responsibility of each and every personnel are clearly defined yet by and large these responsibilities are overlapping. There has been hardly any action against any officer for time and cost overrun within the construction agency. 6.17 Lack of incentive for timely and within budget completion of work: No incentive of any sort is given to the officers of construction agency for their excellent performance in terms of completing the project within time and cost limits. 6.18 Defective Monitoring System / Pressure for Turnover: Since the construction agencies are commercial organizations, they are required to earn for the salary of their employees. Project manager, being the key person in the field, is always pressurized for procurement of work and turnover. Monitoring is focused on turnover instead of progress of the work. Project managers develop a tendency to spend the money on whatever item they can, just to increase the turnover. With the result a huge inventory is created and money gets blocked in the items which are not immediately required and actual construction at times suffers due to shortage of funds, causing unnecessary delay in completion of work. As the work gets held up it causes cost overrun also. 6.19 Factors beyond control: There are certain factors which are beyond control of every one, like natural calamities or disruption of work due to political reasons. Some of these factors are listed below.
  • 8. Asthana Kamla Kant and Jagbir Singh http://www.iaeme.com/IJCIET/index.asp 38 editor@iaeme.com  Inadequate supply of building materials from time to time due to reasons beyond control of every one.  Wastage of building materials purchased in advance due to lack of proper storage.  Lack of mechanization due to availability of cheap labor. It results in to time overrun which ultimately results in to cost overrun also. 7. INFERENCES There are certain invisible factors which affect the general efficiency of the construction units. Impact on efficiency of construction unit reflects in time and cost overrun. These factors are generally not noticed by the researchers as the significant and direct factors causing time and cost overrun, but they have significant effect. Time and cost overrun in the delivery of government buildings can be checked up to a considerable level by increasing the working efficiency of the construction units. Efficiency of the construction units may be increased by improving the general working conditions at site. These factors have been identified in the present study. The corrective measures immerged in this study will not only check the time and cost overrun but shall improve the quality of work also. 8. LIMITATIONS OF THE STUDY The purpose of this study was to underline the invisible or normally ignored causes which directly affect the general efficiency of the construction agency and have indirect. Impact on time schedule and budget of the building. Since the sample size was very small, the percentage of response was not highlighted in the discussion. Only the presence of those causes was underlined. This study may be used for hypothesis formation for further investigations. 9. RECOMMENDATIONS 9.1 The study shows that most of the causes affecting the general efficiency of the construction unit are very common in nature and may be tackled very easily. Here are some recommendations which may improve the efficiency of construction units and may be useful in having check on time and cost overrun in the delivery of government buildings. 9.2 Delivery process of government buildings must be redefined to ensure input of experts from the very beginning. Funds for preparation of preliminary proposal may be made available to the administrative or client department so that a realistic project report based on accurate estimate of various expenditures may be prepared. 9.3 Selection process of construction agencies must be made more transparent and competitive. Construction agencies to be made more accountable towards quality of construction, cost limit and time schedule for construction. 9.4 Adequate staff should be provided to the construction unit according to work load or work load should be restricted according to availability of the staff with the unit. 9.5 Serious thought should be given to define the area to be covered by a construction unit. A separate unit for each district may be deployed. 9.6 Minimum qualification for responsible positions should be reviewed. Constant refresher courses and quality improvement programs should be organized for staff as well as officers of the construction unit.
  • 9. Time and Cost Overrun in Delivery of Government Buildings in Uttar Pradesh: the Invisible Causes http://www.iaeme.com/IJCIET/index.asp 39 editor@iaeme.com 9.7 There should be professional approach for construction management. Detailed planning for material and manpower management should be prepared and execution should be carried out accordingly. 9.8 The responsibilities of project manager may be divided between two officers. One officer may look after the planning and may liaison with various authorities while the other one may be made responsible for actual execution at site. 9.9 Public Works Department or some other organization may be made technical advisor to all the administrative departments. This entity may work for and on behalf of the administrative departments in all the matters related with construction of buildings. 9.10 Joint periodical inspection of construction site by administrative department, advising entity, consultants and personnel from construction agency should be made mandatory. All of them should bear proportionate responsibility for time and cost overrun. 9.11 Responsible officers of construction unit, especially the project manager should not be changed during construction of the building. Project manager should be accountable for success or failure of the project. 9.12 Incentive for successful completion of the work and punishment for failure should be there. REFERENCES [1] Anant Narayan Shete and Vaibhav Durwas Kothawade, An Analysis of Cost Overrun and Time Overrun of Construction Projects in India, International Journal of engineering Trends and Technology (IJETT), Volume-41, Number-1, 2016, pp 33-36 [2] Anupam Dutta & Probol Dutta, Causes of Time and Cost Overrun in Transportation Sector Projects in Bangladesh, SSRG-IJEMS, Vol. 2, Issue 4, 2015 [3] Ashwini Arun Salunkhe, Rahul S. Patil, Statistical Methods for Construction Delay Analysis, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Vol. 9, 2013, pp58-62 [4] Borvorn Israngkura Na Ayudhya, Evaluation of Common Delay Causes of Construction Projects in Singapore, Journal of Civil Engineering and Architecture, Vol.5, No. 11 (Serial no. 48), 2011, pp1027-1034 [5] Desai Megha, Dr Bhatt Rajeev, A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context, International Journal Emerging Technology and Advanced Engineering, Vol. 3, Issue 3, 2013 [6] K.Muthu Venkata Sekar and M.Mahalakshmi, Evaluating Reasons for Cost Overrun in A Low Cost Construction Project, International Journal of Civil Engineering and Technology, 9(4), 2018, pp. 690–696. [7] Dinesh Kumar R, Causes and Effects of Delays in Indian Construction Projects, International Research Journal of engineering and Technology (IRJET), Vol 3, Issue 4, 2016, pp1831-1837 [8] Divya R. & Ramya S., Causes Effects and Minimization of Delays in Construction Projects, National Conference on Research Advances in Communication, Computation, Electrical Science and Structures (NCRACCESS), 2015, pp 51-52 [9] Muhammad Akram, TauhaHussain Ali, Nafees Ahmed Memon and Shabir Hussain Khahro Causal Attributes of Cost Overrun In Construction Projects of Pakistan. International Journal of Civil Engineering and Technology, 8(6), 2017, pp. 477–483. [10] K. Mukilan and R. Jayanthi, Severity Rating of Time And Cost Overruns In Construction Projects, International Journal of Science and Engineering Research (IJOSER), Vol.3 Issue 5, 2015,
  • 10. Asthana Kamla Kant and Jagbir Singh http://www.iaeme.com/IJCIET/index.asp 40 editor@iaeme.com [11] Kaming, P.F., Olomolaiye, P.O., Holt, G.D. & Harris, F.C., Factors influencing construction time and cost overruns on high-rise projects in Indonesia, Construction Management Economics, 15(1), pp 83-94 [12] M.S.Ramabodu and JJP Verster, Factors Contributing to cost Overruns of Construction Projects, Proceedings 5th Built Environment Conference, Durban South Africa, 2010, pp 131-143 [13] Siddesh Pai, Bijayanand Patnaik, Dr. Ankur Mittal and Dr. Neeraj Anand, Identification of Risks Causing Time and Cost Overrun in Roads and Highway Projects in India, International Journal of Civil Engineering and Technology, 9(3), 2018, pp. 683–697. [14] Asthana Kamla Kant, Bottlenecks in the Delivery Process of Government Buildings in Uttar Pradesh (India) Causing Time and Cost Overrun, International Journal of Civil Engineering and Technology, 9(2), 2018, pp. 693–704. [15] Naveen Kumar.G.V. and Prabhu.V, Factors Influencing Time and Cost Overruns in Construction Projects, International Journal of Innovative Research in Science, Engineering and Technology (IJIRSET), Vol.5, Issue 4, 20016, pp 6468-6473 [16] Salim S. Mulla and Ashish P. Wagmare, A Study of Factors Caused for Time and Cost Overrun in Construction Projects and their Remedial Measures, International Journal of Engineering Research and Application (IJERA), Vol.5, Issue 1(Part-6),2015, pp 48-53 [17] Santosh Kumar Prajapati, Rakesh Gupta and Mukesh Pande, Causes and Effects of Cost Overrun on Construction Projects in Madhya Pradesh, International Journal of Engineering Development and Research (IJEDR), Vol 4, Issue 2, 2016, pp 1346-1350 [18] T. Subramani, PS Sruthi and M. Kavitha, Causes of Cost Overrun in Construction, International Organization of Scientific Research Journal of Engineering (IOSRJEN), Vol 4, Issue 6, 2014, (V3) pp 1-7