SlideShare a Scribd company logo
http://www.iaeme.com/IJCIET/index.asp 28 editor@iaeme.com
International Journal of Civil Engineering and Technology (IJCIET)
Volume 8, Issue 2, February 2017, pp. 28–33 Article ID: IJCIET_08_02_005
Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=2
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
© IAEME Publication Scopus Indexed
A STUDY OF VARIOUS FACTORS AFFECTING
CONTRACTOR’S PERFORMANCE IN LOWEST BID
AWARD CONSTRUCTION PROJECTS
Shumank Deep
A.M.ASCE, Assistant Professor, Department of Civil Engineering,
Integral University, Lucknow, Uttar Pradesh, India
Mohd Bilal Khan
Assistant Professor, Department of Civil Engineering,
Integral University, Lucknow, Uttar Pradesh, India
Sabih Ahmad
Associate Professor, Department of Civil Engineering,
Integral University, Lucknow, Uttar Pradesh, India
Adeeba Saeed
Assistant Professor, Department of Civil Engineering,
Ambalika Institute of Technology and Management, Lucknow, Uttar Pradesh, India
ABSTRACT
Real estate sector in present scenario is going through a lean patch, many organisations
are either running in loss or with a marginal profits. As in state government and central
government departments contractors are facing huge problems that are in turn tending to
decrease in contractor profits. The present study focuses on study of various factors that affect
contractor’s performance who have been awarded projects on the basis of lowest bid awards.
The study analyses various factors and their impacts on the basis of responses collected form a
survey. On the basis of overall index and relative importance index factor causing a major
impact on contractor’s efficiency have been identified.
Key words: contract management; contractor performance; subletting; lowest bid awards;
contractor efficiency
Cite this Article: Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed, A
Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award
Construction Projects. International Journal of Civil Engineering and Technology, 8(2), 2017,
pp. 28–33.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=2
Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed
http://www.iaeme.com/IJCIET/index.asp 29 editor@iaeme.com
1. INTRODUCTION
Lowest bidder approach is a common method applied for contractor selection of construction projects
in India. As per studies available efficiency of contract in lowest bidder award projects is
comparatively low. Major reasons being inflation, extension of duration, price escalation (S Deep et
al). The major flow of lowest bid award method is work awards could be made on the basis of
submission of deliberate and unrealistic bid by a contractor. This practice has led to a series of
disputes and caused several stereotypes in work progress resulting in increased prices. One of vital
tasks faced by a client willing for a success project outcome is to select an efficient c contractor
(Plebankiewicz, 2010). Globally prequalification criteria are altered to select competent contractors.
Once prequalification is completed, the client can then give work award to the contractor to start
project. The literature available identifies several prequalification criterion that can be applied in the
selection process; the most common of which are: management capability, technical ability, financial
capacity, and occupational health and safety (Hatush and Skitmore, 1997; Plebankiewicz, 2009;
Huang et al. 2014). Different evaluations are conducted for each criterion; however, the evaluations
methods used for some processes are ambiguous or highly subjective (Hosny et al. 2013).But as
current practice in Indian scenario lowest bidder award are highly practiced, though, prequalification
is done using aforesaid criterions, yet work award is made to lowest bidder. To encounter this issue,
many countries have adopted average-bid method and award t contract to a contractor whose price is
closest to the average-bid and evaluates its merits in a similar way to the low-bid method (Ioannou et
al, 1993). The prime advantage this method is that it protects owner’s interest in case of unrealistic bid
submissions (Ioannou et al, 1993).It has also been observed that this method also aids in removal of
discrepancies in submitted bids.The disadvantage of the average-bid method is, it does not essentially
promotes price competition, which is at times not beneficial for client. Many studies conducted
concluded that average bidding method results in significantly higher profits for the contractors in
projects (Irtishad, 1993).It has been observed that contractor has to face a series of constraints while
execution of projects awards on the basis of lowest bid award methods. Presently in case of public
sector projects in case of state government an overhead 10% of overall project cost exists in which
contractor appoints a of the design team, the existing agreement between the client and the design
team ceases and a new contractual agreement is implemented between the design team and the
contractor for project completion (Doloi, 2008).Construction sector of many countries have recently
undergone transformation, and projects are now subcontracted more frequently than in the past.
Subcontractors are specialists in the execution of a specific job, and may supply personnel, materials,
equipment, tools, and designs (Shimizu and Cardoso 2002). It can further remarked that a contractor
has to face a series of constraints in case of lowest bid awarded projects. Some of them have been tried
to be identified in this paper.
2. RESEARCH HYPOTHESIS
The study is aimed to identify the various causes that lead to decrease in efficiency of contractors in
construction projects. It has been observed that the increase in overall duration in a construction is a
persistent issue in case of lowest bid (S. Deep et al, 2016). An increase in duration of a construction
projects has a widespread impact on overall cost of construction project. In current scenario retail
inflation rate in case of construction materials is very high, similarly other factor like quality of
equipment used, supervision from consultant side are some of common issues to be evaluated as part
of this study.
3. RESEARCH METHODOLOGY
Two types of questionnaires were developed for diverse groups i.e. construction organizations and
public organizations. Contractors, Sub contractors, Consultants, Architects and Engineers were
included in the first group. The second group was comprised of public agencies and state/central
A Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award Construction Projects
http://www.iaeme.com/IJCIET/index.asp 30 editor@iaeme.com
government departments. The responses obtained from questionnaire survey were analyzed to identify
the trends and practices in bid and procurement in UP state government and central government
owned construction projects. Questionnaires were also used to analyze the major difficulties faced by
contractors that tend to decrease the efficiencies of contractors.
4. QUESTIONNAIRES RESPONSE RATE
A total of 275 questionnaires, 149 to construction organizations (contractors and consultants) and 126
to public organizations were distributed. Table 1 shows the summary of number of rate of responses
by major stockholders.
Table 1 Summary of number and response rate by participants.
S.No.
Professional cadre of
Respondents
No. of respondents Percentage of responses
1 Consultants 24 8.73
2 Public Sector Organisation 126 45.82
3 Contractors 125 45.5
Total 275 100
Figure 1 percentage share of responses
5. MAJOR DIFFICULTIES ENCOUNTERED DURING THE CONSTRUCTION
PROCESS
As part of study assessment has been made to account for the major constraints encountered during the
project. Material shortage, equipment shortage, cash shortage, man power shortage, employer
interference, design/drawing related and supervision related problems were short listed by the
researcher. Other prominent factors such as unexpected weather condition and security related
problems were also discovered through the survey. Table 2 below summarizes the major difficulties
encountered.
Material shortage (15 projects) and equipment shortage (11 projects) are the major problems
encountered. Manpower shortage (7 projects) and cash shortage (6 projects) are the second most
serious problems while design/drawing interference (2 projects) and supervision related (1
project) were non-significant problems while client interference has no affect.
Consultants
9%
Public Sector
Organisation
46%
Contractors
45%
No. of respondents
Consultants PublicSector Organisation Contractors
Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed
http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com
Table 2 Summary of major difficulties encountered
Constraint types
Response rates
Yes No Unknown
Material shortage 15 10 3
Equipment shortage 11 9 7
Cash shortage 6 6 10
Manpower shortage 7 20 5
Client interference 0 14 8
Design/drawing related 2 15 8
Supervision related 1 17 4
Other’s 6 1 15
6. EVALUATION OF CONTRACTORS PERFORMANCE
The surveyed owners, consultants, managers, engineers, and contractors ranked the ‘‘inadequate
project management assistance factor as the most important factor affecting efficiency of contractor in
construction projects in India at this category, with an Overall Index equal to 66.17%. The major
factors that affect contractor efficiency to a great extent are listed in table 3.
Table 3 Major factors constraining performance of contractors from different category
Cat.no. Category ID Factor Overall Index (OI %)
1 Consultant 19 Inadequate project management
assistance
66.17
2 Contractor 10 Inadequate contractor experience 70.23
3 Design 28 Misunderstanding of owner’s
requirements by design engineer
72.03
4 Equipment 37 low efficiency of equipment 66.07
5 External 43 Delay in obtaining permits from
municipality
72.30
6 Labour 59 Shortage of labourer 72.30
7 Material 67 Damage of sorted materials 66.83
8 Owner 78 Delay in progress payments (Funding
problems)
67.03
9 Project 94 Complexity of project (project type,
project scale, etc.)
67.51
It might be noted that all these factors are originated either by the consultant related factors
category, contractor related factors category, design related factors category, equipment related factors
category, external related factors category, labour related factors category, material related factors
category, owner related factors category, or project related factors category. This is expected since
each party is trying to blame the other for causing delays. Researcher desires to compare the strength
or the importance of each category; the weighted average value of the causes composing this category
was calculated. The results are tabulated in Table 4 by using priority rule formula as shown in the
following equation:
ERIIj (%) =
∑ ( )
∑ ( )
(1)
where ERIIj (%) is the Equivalent weighted average percentage of Relative Importance Index per
category; ORIIn (%) is the Overall weighted average percentage of Relative Importance Index per
factor of specific category, which is calculated based upon total years of experiences of all
respondents; n is the number represents the factor number in the related category (from first factor of
A Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award Construction Projects
http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com
category n= 1 to from last factor of category n = N); and Pn is the priority weight of the studied
factor.It is clear that the results of the nine categories were almost consistent, where the categories are
ranked from top to bottom as shown in Table 4.
Table 4 Equivalent average Relative Importance Index of Category
Rank Category Item Equivalent average Relative
Importance Index Eq. (1)
01 Contractor Related Factors category 64.62
02 Project Related Factors category 63.82
03 Labourer Related Factors category 62.46
04 Design Related Factors category 62.28
05 Owner Related Factors category 60.28
06 Consultant Related Factors category 60.26
07 External Related Factors category 60.25
08 Equipment Related Factors category 59.61
09 Material Related Factors category 59.31
According to Tables, showing the rank and impact of the grouped factors and the ranking of the
groups as shown in Table 4.8, three most contributing factors for each group to delay were mentioned
as follows: Contractor (EARII =64.62%): The contractor related group of factors affecting
performance of contractors was the most important group causing delays. Second important group was
the project related group, having the most significant factors as ‘‘Complexity of project (project type,
project scale, etc.) (OI = 67.51%),’’ third Laborer (EARII =62.46%): After the Laborer, the design
related group of factors affecting performance of contractorstook place as the Fourth most important
group. The significant factors were ‘‘Misunderstanding of owner’s requirements by design engineer”
(RII = 72.03%),Owner (EARII =60.28%): Following the owner, the Consultant related group of
factors affecting performance of contractors’ ranks as the Sixth most important group.
7. CONCLUSION
Lowest bid awards a most common practice for awarding work charge in India whether its public or
private sector. The study tried to investigate the various factors affecting efficiency of contractors in
case of lowest bid award projects. The noticeable factors were inadequate project management
assistance) (OI = 66.17%), external (EARII =60.25%): eighth important group was the Equipment
related group. The prominent factors were ‘‘low efficiency of equipment (OI = 66.07%),’’ (9) Material
(EARII =59.31%). On basis of findings it could be concluded that though lowest bid award is not a
primarily a good practice due to firstly the contractor’s profit margins are low which contractor is not
able to sublet much and tends to employ low efficiency equipment and poor quality materials.
Secondly projects management practices should be popularized amongst contractor working in small
scale projects this can help them in understanding client’s need and hence increasing efficiency, which
could in turn benefit the contractor.
REFERENCES
[1] Deep, S., Singh, D.and Ahmad, S.A. (2017) A Review of Contract Awards to Lowest Bidder in
Indian Construction Projects via Case Based Approach. Open Journal of Business and Management
, 5, 159-168.http://dx.doi.org/10.4236/ojbm.2017.51015
[2] Hancher, D. E., & Lambert, S. E. (2002). Quality-based prequalification of contractors.
Transportation Research Record: Journal of the Transportation Research Board, 1813(1), 260-
274.
Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed
http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com
[3] Harker, P.T., & Vargas, L.G. (1990). Reply to remarks on the analytic hierarchy process.
Management Science, 36,269-73.
[4] Hatush, Z., & Skitmore, M. (1997). Criteria for contractor selection. Construction Management &
Economics, 15, 19-38.
[5] Hosny, O., Nassar, K., & Esmail, Y. (2013). Prequalification of Egyptian construction contractors
using fuzzy-AHP models. Engineering, Construction and Architectural Management, 20(4), 381-
405
[6] Huang, X. (2011). An analysis of the selection of project contractor in the construction management
process. International Journal of Business and Management, 6,184.
[7] M. Chittaranjan and K. N. Prasad, A Rational Approach for Assessing the Competitive Bidding of
Infrastructure Projects of Indian Railways, International Journal of Civil Engineering and
Technology, 7(3), 2016, pp. 145–162.
[8] Irtishad Ahmed P.E (Dr.), Alternative Bid-Evaluation and Contract-Award Systems: Department of
Construction Management College of Engineering and Design, Florida International University,
Miami, Florida, 1993
[9] Photois G.Ioannou, Average-Bid Method-Competitive Bidding Strategy: Journal of Construction
Engineering and Management, Vol. 119, No. 1, March, 1993.
[10] Pinto, J.K., Slevin, D.P., & English, B. (2009). Trust in projects: an empirical assessment of
owner/contractor relationships. International Journal of Project Management, 27, 638-648.
[11] Plebankiewicz, E. (2009). Contractor prequalification model using fuzzy sets. Journal of Civil
Engineering and Management, 15, 377-385.
[12] Plebankiewicz, E. (2010). Construction contractor prequalification from Polish clients’ perspective.
Journal of Civil Engineering and Management, 16(1), 57-64.
[13] J. Kiran Kumar. A Study on Key Factors Influencing Bid/No-Bid Decisions for Different
Construction Projects in India. International Journal of Civil Engineering and Technology, 7(6),
2016, pp. 732–737.
[14] Xiao, H., & Proverbs, D. (2003). Factors influencing contractor performance: an international
investigation. Engineering, Construction and Architectural Management, 10, 322-332.
[15] Yang, C. L., Chuang, S. P., & Huang, R. H. (2009). Manufacturing evaluation system based on
AHP/ANP approach for wafer fabricating industry. Expert Systems with Applications, 36, 11369–
11377.

More Related Content

What's hot

A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET Journal
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
Vamsi Kovalam
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
eSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
Rifan Fhazi
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
IAEME Publication
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
Fredy Kurniawan
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
IRJET Journal
 
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET Journal
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET Journal
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
IAEME Publication
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
civej
 

What's hot (17)

A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 

Viewers also liked

A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
IAEME Publication
 
CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
 CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ... CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
IAEME Publication
 
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
IAEME Publication
 
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
IAEME Publication
 
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
IAEME Publication
 
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORKTRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
IAEME Publication
 
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
iosrjce
 
Vibration induced stresses from equipment tools in a school workshop as a fac...
Vibration induced stresses from equipment tools in a school workshop as a fac...Vibration induced stresses from equipment tools in a school workshop as a fac...
Vibration induced stresses from equipment tools in a school workshop as a fac...
Alexander Decker
 
FACTORS AFFECTING STUDENTS’ ENROLMENT
FACTORS AFFECTING STUDENTS’ ENROLMENTFACTORS AFFECTING STUDENTS’ ENROLMENT
FACTORS AFFECTING STUDENTS’ ENROLMENT
Reason Masengu
 
Stg6 pdh unit outline from net
Stg6 pdh unit outline from netStg6 pdh unit outline from net
Stg6 pdh unit outline from net
mphillips89
 
Factors affecting performance appraisal
Factors affecting performance appraisalFactors affecting performance appraisal
Factors affecting performance appraisal
marianelson0292
 
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
IAEME Publication
 
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
IAEME Publication
 
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINESCOMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
IAEME Publication
 
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
IAEME Publication
 
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINECOMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
IAEME Publication
 
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
IAEME Publication
 
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
IAEME Publication
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
IAEME Publication
 
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINESCOMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
IAEME Publication
 

Viewers also liked (20)

A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
A STUDY ON PEER TO PEER NETWORK IN CURRENT NETWORKING
 
CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
 CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ... CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
CRITICAL ANALYSIS OF THE METHODOLOGY ADOPTED BY CERTAIN CAMEROONIAN STUDIES ...
 
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
DETERMINATION OF NET FLOWS INTO ALMATTI RESERVOIR FROM CWC GAUGE DATA AND RES...
 
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
EXPERIMENTAL VERIFICATION OF MULTIPLE CORRELATIONS BETWEEN THE SOIL YOUNG MOD...
 
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
STUDY OF FEASIBILITY FOR ADOPTING TOUCHLESS FAUCETS, LOW FLOW AERATORS AND SE...
 
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORKTRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
TRUST MANAGEMENT FOR DELAY TOLERANT NETWORK
 
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
Study of Biomass Briquettes, Factors Affecting Its Performance and Technologi...
 
Vibration induced stresses from equipment tools in a school workshop as a fac...
Vibration induced stresses from equipment tools in a school workshop as a fac...Vibration induced stresses from equipment tools in a school workshop as a fac...
Vibration induced stresses from equipment tools in a school workshop as a fac...
 
FACTORS AFFECTING STUDENTS’ ENROLMENT
FACTORS AFFECTING STUDENTS’ ENROLMENTFACTORS AFFECTING STUDENTS’ ENROLMENT
FACTORS AFFECTING STUDENTS’ ENROLMENT
 
Stg6 pdh unit outline from net
Stg6 pdh unit outline from netStg6 pdh unit outline from net
Stg6 pdh unit outline from net
 
Factors affecting performance appraisal
Factors affecting performance appraisalFactors affecting performance appraisal
Factors affecting performance appraisal
 
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
ANALYTICAL TOOL FOR ANALYSING SLAGGING CHARACTERISTIC OF HIGH ASH COALS IN UT...
 
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
PERFORMANCE OF 3-D POLAR WEAVE CARBON-CARBON COMPOSITES IN HIGH THERMAL EROSI...
 
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINESCOMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
 
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
EFFECT OF SURFACE ROUGHNESS ON CHARACTERISTICS OF SQUEEZE FILM BETWEEN POROUS...
 
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINECOMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
COMBUSTION MONITORING THROUGH VIBRATIONAL DATA IN A TURBOCHARGED CITY CAR ENGINE
 
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
DESIGN AND DEVELOPMENT OF SPECIAL PURPOSE MACHINE USING HYDROPNEUMATIC CYLIND...
 
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
COMPRESSIVE STRENGTH AND CARBONATION OF SEA WATER CURED BLENDED CONCRETE
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
 
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINESCOMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
COMPARATIVE EMISSION ANALYSIS OF CNG AND OCTANE IN RETROFITTED CAR ENGINES
 

Similar to A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID AWARD CONSTRUCTION PROJECTS

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
saeedahmed433704
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
IRJET Journal
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
Harish Rajmane
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
IRJET Journal
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
D012261521
D012261521D012261521
D012261521
IOSR Journals
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
IOSR Journals
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
ijsrd.com
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
vivatechijri
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
civejjour
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
IJERA Editor
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
IAEME Publication
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
IAEME Publication
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
Abhishek Shah
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
IRJET Journal
 

Similar to A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID AWARD CONSTRUCTION PROJECTS (20)

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
D012261521
D012261521D012261521
D012261521
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 

More from IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
IAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
IAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
IAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
IAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
IAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
IAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
IAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
IAEME Publication
 

More from IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Recently uploaded

DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 

Recently uploaded (20)

DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 

A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID AWARD CONSTRUCTION PROJECTS

  • 1. http://www.iaeme.com/IJCIET/index.asp 28 editor@iaeme.com International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 2, February 2017, pp. 28–33 Article ID: IJCIET_08_02_005 Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=2 ISSN Print: 0976-6308 and ISSN Online: 0976-6316 © IAEME Publication Scopus Indexed A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID AWARD CONSTRUCTION PROJECTS Shumank Deep A.M.ASCE, Assistant Professor, Department of Civil Engineering, Integral University, Lucknow, Uttar Pradesh, India Mohd Bilal Khan Assistant Professor, Department of Civil Engineering, Integral University, Lucknow, Uttar Pradesh, India Sabih Ahmad Associate Professor, Department of Civil Engineering, Integral University, Lucknow, Uttar Pradesh, India Adeeba Saeed Assistant Professor, Department of Civil Engineering, Ambalika Institute of Technology and Management, Lucknow, Uttar Pradesh, India ABSTRACT Real estate sector in present scenario is going through a lean patch, many organisations are either running in loss or with a marginal profits. As in state government and central government departments contractors are facing huge problems that are in turn tending to decrease in contractor profits. The present study focuses on study of various factors that affect contractor’s performance who have been awarded projects on the basis of lowest bid awards. The study analyses various factors and their impacts on the basis of responses collected form a survey. On the basis of overall index and relative importance index factor causing a major impact on contractor’s efficiency have been identified. Key words: contract management; contractor performance; subletting; lowest bid awards; contractor efficiency Cite this Article: Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed, A Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award Construction Projects. International Journal of Civil Engineering and Technology, 8(2), 2017, pp. 28–33. http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=2
  • 2. Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed http://www.iaeme.com/IJCIET/index.asp 29 editor@iaeme.com 1. INTRODUCTION Lowest bidder approach is a common method applied for contractor selection of construction projects in India. As per studies available efficiency of contract in lowest bidder award projects is comparatively low. Major reasons being inflation, extension of duration, price escalation (S Deep et al). The major flow of lowest bid award method is work awards could be made on the basis of submission of deliberate and unrealistic bid by a contractor. This practice has led to a series of disputes and caused several stereotypes in work progress resulting in increased prices. One of vital tasks faced by a client willing for a success project outcome is to select an efficient c contractor (Plebankiewicz, 2010). Globally prequalification criteria are altered to select competent contractors. Once prequalification is completed, the client can then give work award to the contractor to start project. The literature available identifies several prequalification criterion that can be applied in the selection process; the most common of which are: management capability, technical ability, financial capacity, and occupational health and safety (Hatush and Skitmore, 1997; Plebankiewicz, 2009; Huang et al. 2014). Different evaluations are conducted for each criterion; however, the evaluations methods used for some processes are ambiguous or highly subjective (Hosny et al. 2013).But as current practice in Indian scenario lowest bidder award are highly practiced, though, prequalification is done using aforesaid criterions, yet work award is made to lowest bidder. To encounter this issue, many countries have adopted average-bid method and award t contract to a contractor whose price is closest to the average-bid and evaluates its merits in a similar way to the low-bid method (Ioannou et al, 1993). The prime advantage this method is that it protects owner’s interest in case of unrealistic bid submissions (Ioannou et al, 1993).It has also been observed that this method also aids in removal of discrepancies in submitted bids.The disadvantage of the average-bid method is, it does not essentially promotes price competition, which is at times not beneficial for client. Many studies conducted concluded that average bidding method results in significantly higher profits for the contractors in projects (Irtishad, 1993).It has been observed that contractor has to face a series of constraints while execution of projects awards on the basis of lowest bid award methods. Presently in case of public sector projects in case of state government an overhead 10% of overall project cost exists in which contractor appoints a of the design team, the existing agreement between the client and the design team ceases and a new contractual agreement is implemented between the design team and the contractor for project completion (Doloi, 2008).Construction sector of many countries have recently undergone transformation, and projects are now subcontracted more frequently than in the past. Subcontractors are specialists in the execution of a specific job, and may supply personnel, materials, equipment, tools, and designs (Shimizu and Cardoso 2002). It can further remarked that a contractor has to face a series of constraints in case of lowest bid awarded projects. Some of them have been tried to be identified in this paper. 2. RESEARCH HYPOTHESIS The study is aimed to identify the various causes that lead to decrease in efficiency of contractors in construction projects. It has been observed that the increase in overall duration in a construction is a persistent issue in case of lowest bid (S. Deep et al, 2016). An increase in duration of a construction projects has a widespread impact on overall cost of construction project. In current scenario retail inflation rate in case of construction materials is very high, similarly other factor like quality of equipment used, supervision from consultant side are some of common issues to be evaluated as part of this study. 3. RESEARCH METHODOLOGY Two types of questionnaires were developed for diverse groups i.e. construction organizations and public organizations. Contractors, Sub contractors, Consultants, Architects and Engineers were included in the first group. The second group was comprised of public agencies and state/central
  • 3. A Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award Construction Projects http://www.iaeme.com/IJCIET/index.asp 30 editor@iaeme.com government departments. The responses obtained from questionnaire survey were analyzed to identify the trends and practices in bid and procurement in UP state government and central government owned construction projects. Questionnaires were also used to analyze the major difficulties faced by contractors that tend to decrease the efficiencies of contractors. 4. QUESTIONNAIRES RESPONSE RATE A total of 275 questionnaires, 149 to construction organizations (contractors and consultants) and 126 to public organizations were distributed. Table 1 shows the summary of number of rate of responses by major stockholders. Table 1 Summary of number and response rate by participants. S.No. Professional cadre of Respondents No. of respondents Percentage of responses 1 Consultants 24 8.73 2 Public Sector Organisation 126 45.82 3 Contractors 125 45.5 Total 275 100 Figure 1 percentage share of responses 5. MAJOR DIFFICULTIES ENCOUNTERED DURING THE CONSTRUCTION PROCESS As part of study assessment has been made to account for the major constraints encountered during the project. Material shortage, equipment shortage, cash shortage, man power shortage, employer interference, design/drawing related and supervision related problems were short listed by the researcher. Other prominent factors such as unexpected weather condition and security related problems were also discovered through the survey. Table 2 below summarizes the major difficulties encountered. Material shortage (15 projects) and equipment shortage (11 projects) are the major problems encountered. Manpower shortage (7 projects) and cash shortage (6 projects) are the second most serious problems while design/drawing interference (2 projects) and supervision related (1 project) were non-significant problems while client interference has no affect. Consultants 9% Public Sector Organisation 46% Contractors 45% No. of respondents Consultants PublicSector Organisation Contractors
  • 4. Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com Table 2 Summary of major difficulties encountered Constraint types Response rates Yes No Unknown Material shortage 15 10 3 Equipment shortage 11 9 7 Cash shortage 6 6 10 Manpower shortage 7 20 5 Client interference 0 14 8 Design/drawing related 2 15 8 Supervision related 1 17 4 Other’s 6 1 15 6. EVALUATION OF CONTRACTORS PERFORMANCE The surveyed owners, consultants, managers, engineers, and contractors ranked the ‘‘inadequate project management assistance factor as the most important factor affecting efficiency of contractor in construction projects in India at this category, with an Overall Index equal to 66.17%. The major factors that affect contractor efficiency to a great extent are listed in table 3. Table 3 Major factors constraining performance of contractors from different category Cat.no. Category ID Factor Overall Index (OI %) 1 Consultant 19 Inadequate project management assistance 66.17 2 Contractor 10 Inadequate contractor experience 70.23 3 Design 28 Misunderstanding of owner’s requirements by design engineer 72.03 4 Equipment 37 low efficiency of equipment 66.07 5 External 43 Delay in obtaining permits from municipality 72.30 6 Labour 59 Shortage of labourer 72.30 7 Material 67 Damage of sorted materials 66.83 8 Owner 78 Delay in progress payments (Funding problems) 67.03 9 Project 94 Complexity of project (project type, project scale, etc.) 67.51 It might be noted that all these factors are originated either by the consultant related factors category, contractor related factors category, design related factors category, equipment related factors category, external related factors category, labour related factors category, material related factors category, owner related factors category, or project related factors category. This is expected since each party is trying to blame the other for causing delays. Researcher desires to compare the strength or the importance of each category; the weighted average value of the causes composing this category was calculated. The results are tabulated in Table 4 by using priority rule formula as shown in the following equation: ERIIj (%) = ∑ ( ) ∑ ( ) (1) where ERIIj (%) is the Equivalent weighted average percentage of Relative Importance Index per category; ORIIn (%) is the Overall weighted average percentage of Relative Importance Index per factor of specific category, which is calculated based upon total years of experiences of all respondents; n is the number represents the factor number in the related category (from first factor of
  • 5. A Study of Various Factors Affecting Contractor’s Performance in Lowest Bid Award Construction Projects http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com category n= 1 to from last factor of category n = N); and Pn is the priority weight of the studied factor.It is clear that the results of the nine categories were almost consistent, where the categories are ranked from top to bottom as shown in Table 4. Table 4 Equivalent average Relative Importance Index of Category Rank Category Item Equivalent average Relative Importance Index Eq. (1) 01 Contractor Related Factors category 64.62 02 Project Related Factors category 63.82 03 Labourer Related Factors category 62.46 04 Design Related Factors category 62.28 05 Owner Related Factors category 60.28 06 Consultant Related Factors category 60.26 07 External Related Factors category 60.25 08 Equipment Related Factors category 59.61 09 Material Related Factors category 59.31 According to Tables, showing the rank and impact of the grouped factors and the ranking of the groups as shown in Table 4.8, three most contributing factors for each group to delay were mentioned as follows: Contractor (EARII =64.62%): The contractor related group of factors affecting performance of contractors was the most important group causing delays. Second important group was the project related group, having the most significant factors as ‘‘Complexity of project (project type, project scale, etc.) (OI = 67.51%),’’ third Laborer (EARII =62.46%): After the Laborer, the design related group of factors affecting performance of contractorstook place as the Fourth most important group. The significant factors were ‘‘Misunderstanding of owner’s requirements by design engineer” (RII = 72.03%),Owner (EARII =60.28%): Following the owner, the Consultant related group of factors affecting performance of contractors’ ranks as the Sixth most important group. 7. CONCLUSION Lowest bid awards a most common practice for awarding work charge in India whether its public or private sector. The study tried to investigate the various factors affecting efficiency of contractors in case of lowest bid award projects. The noticeable factors were inadequate project management assistance) (OI = 66.17%), external (EARII =60.25%): eighth important group was the Equipment related group. The prominent factors were ‘‘low efficiency of equipment (OI = 66.07%),’’ (9) Material (EARII =59.31%). On basis of findings it could be concluded that though lowest bid award is not a primarily a good practice due to firstly the contractor’s profit margins are low which contractor is not able to sublet much and tends to employ low efficiency equipment and poor quality materials. Secondly projects management practices should be popularized amongst contractor working in small scale projects this can help them in understanding client’s need and hence increasing efficiency, which could in turn benefit the contractor. REFERENCES [1] Deep, S., Singh, D.and Ahmad, S.A. (2017) A Review of Contract Awards to Lowest Bidder in Indian Construction Projects via Case Based Approach. Open Journal of Business and Management , 5, 159-168.http://dx.doi.org/10.4236/ojbm.2017.51015 [2] Hancher, D. E., & Lambert, S. E. (2002). Quality-based prequalification of contractors. Transportation Research Record: Journal of the Transportation Research Board, 1813(1), 260- 274.
  • 6. Shumank Deep, Mohd Bilal Khan, Sabih Ahmad and Adeeba Saeed http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com [3] Harker, P.T., & Vargas, L.G. (1990). Reply to remarks on the analytic hierarchy process. Management Science, 36,269-73. [4] Hatush, Z., & Skitmore, M. (1997). Criteria for contractor selection. Construction Management & Economics, 15, 19-38. [5] Hosny, O., Nassar, K., & Esmail, Y. (2013). Prequalification of Egyptian construction contractors using fuzzy-AHP models. Engineering, Construction and Architectural Management, 20(4), 381- 405 [6] Huang, X. (2011). An analysis of the selection of project contractor in the construction management process. International Journal of Business and Management, 6,184. [7] M. Chittaranjan and K. N. Prasad, A Rational Approach for Assessing the Competitive Bidding of Infrastructure Projects of Indian Railways, International Journal of Civil Engineering and Technology, 7(3), 2016, pp. 145–162. [8] Irtishad Ahmed P.E (Dr.), Alternative Bid-Evaluation and Contract-Award Systems: Department of Construction Management College of Engineering and Design, Florida International University, Miami, Florida, 1993 [9] Photois G.Ioannou, Average-Bid Method-Competitive Bidding Strategy: Journal of Construction Engineering and Management, Vol. 119, No. 1, March, 1993. [10] Pinto, J.K., Slevin, D.P., & English, B. (2009). Trust in projects: an empirical assessment of owner/contractor relationships. International Journal of Project Management, 27, 638-648. [11] Plebankiewicz, E. (2009). Contractor prequalification model using fuzzy sets. Journal of Civil Engineering and Management, 15, 377-385. [12] Plebankiewicz, E. (2010). Construction contractor prequalification from Polish clients’ perspective. Journal of Civil Engineering and Management, 16(1), 57-64. [13] J. Kiran Kumar. A Study on Key Factors Influencing Bid/No-Bid Decisions for Different Construction Projects in India. International Journal of Civil Engineering and Technology, 7(6), 2016, pp. 732–737. [14] Xiao, H., & Proverbs, D. (2003). Factors influencing contractor performance: an international investigation. Engineering, Construction and Architectural Management, 10, 322-332. [15] Yang, C. L., Chuang, S. P., & Huang, R. H. (2009). Manufacturing evaluation system based on AHP/ANP approach for wafer fabricating industry. Expert Systems with Applications, 36, 11369– 11377.